This is a federal solicitation amendment for a dredging project in the New York Harbor, Sandy Hook Channel. The primary work includes dredging approximately 124,075 cubic yards of material from Area A to the Sea Bright Offshore Borrow Area (SBOBA), with optional dredging for Areas B (30,080 cubic yards) and C (64,565 cubic yards). The contract includes additional line items for mobilization, a Black Box Monitoring Unit, and a Northeastern Beach Tiger Beetles Survey. The bid response date has been extended to 05 September 2025, with the contractor required to complete the basic work within 51 calendar days of receiving the Notice to Proceed. The pricing arrangement is firm fixed price, and the government may exercise options within 35 calendar days of the Notice to Proceed, subject to fund availability. Option CLINs have specific constraints, with CLIN 0006 (Area C) only executable after CLIN 0005 (Area B) is exercised.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section 00 00 00 - Procurement and Contracting Requirements

The following changes have been made:

INFORMATION FROM TO

Response Due Date 25 Aug 2025 05 Sep 2025

Miscellaneous text in this section has been added to:

Bid Schedule:

- Line items have been reverted to prior to Amendment 0001.

- Notes have been reverted to prior to Amendment 0001

Plans:

- Stockpile Placement information has been removed from the set of plans.

- Please refer to "Plans_AM0003".

- Any remaining references to the stockpile placement within "Plans_AM0003" are not relevant to the scope of work and are not enforceable.

Technical Specification:

- Stockpile Placement information has been removed from the technical specifications.

- Please refer to "Specifications_AM0003".

- The fully executed NPS Special Use Permit in Section 00 90 01 is included in "Specifications_AM0003".

- Any remaining references to the stockpile placement within "Specifications_AM0003" are not relevant to the scope of work and are not enforceable.

Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price Amount

Mobilization and Demobilization

Transfer of all required plant and equipment to and off site.

Pricing Arrangement: Firm Fixed Price

1 Job

Basic Work - Dredging Area A Dredging, Transportation and Placement of Dredged Material

Dredging of material except ledge rock to -35 feet mean lower low water (MLLW) + 2-foot allowable overdepth from the New York Harbor, Sandy Hook Channel with Transportation and Placement of the dredged material at the Sea Bright Offshore Borrow Area (SBOBA) placement area identified in the plan drawing. ESTIMATED QUANTITY.

Pricing Arrangement: Firm Fixed Price

124,075 Cubic Yard

Black Box Monitoring Unit

See specifications Section 35 20 23.10 18.

Pricing Arrangement: Firm Fixed Price

1 Job

Northeastern Beach Tiger Beetles Survey and Translocation Efforts

See specifications Section 01 11 00.

Pricing Arrangement: Firm Fixed Price

1 Job

Option Line Item

Option - Dredging Area B Dredging, Transportation and Placement of Dredged Material

Dredging of material except ledge rock to -35 feet mean lower low water (MLLW) + 2-foot allowable overdepth from the New York Harbor, Sandy Hook Channel with Transportation and Placement of the dredged material at the Sea Bright Offshore Borrow Area (SBOBA) placement area identified in the plan drawing. ESTIMATED

QUANTITY.

30,080 Cubic Yard

W912DS25BA0090003

The Government may exercise Option - Dredging Area B within thirty-five (35) calendar days of receipt by the contractor of the Notice to Proceed.

Pricing Arrangement: Firm Fixed Price

Option Line Item

Option - Dredging Area C Dredging, Transportation and Placement of Dredged Material

Dredging of material except ledge rock to -35 feet mean lower low water (MLLW) + 2 foot allowable overdepth from the New York Harbor, Sandy Hook Channel with Transportation and Placement of the dredged material at the Sea Bright Offshore Borrow Area (SBOBA) placement area identified in the plan drawing. ESTIMATED

QUANTITY.

The Government may exercise Option - Dredging Area C within thirty-five (35) calendar days of receipt by the contractor of the Notice to Proceed. CLIN 0006 cannot be exercised without the exercise of CLIN 0005.

Pricing Arrangement: Firm Fixed Price

64,565 Cubic Yard

Section 00 20 00 - Instructions for Procurements

TOTAL

TOTAL BASE BID (CLINS 0001 THRU 0004) $___________________

TOTAL OPTION BID (CLINS 0005 THRU 0006) $___________________

TOTAL BID (CLINS 0001 THRU 0006) $___________________

NOTES TO BIDDERS:

NOTE 1: Bidders must bid on all items. Failure to bid on all work will be cause for rejection of the bid as nonresponsive.

NOTE 2: Award of contract will be based on the responsible and responsive bidder with the lowest total price for the total of the CLINs 0001 through 0006.

NOTE 3: The unit price for CLINS 0002, 0005, and 0006 represent the cost per cubic yard for the removal of the estimated quantities of dredged material (all material except ledge rock above the plane of -35 feet Mean Lower Low Water, plus the respective allowable over-depth of 2 foot).

NOTE 4: All bidders are hereby advised that the execution of Options is subject to the availability of funds.

NOTE 5: Execution of an option is at the discretion of the Government, if exercised at all. If exercised at all, the options listed above shall be exercised in the order that is listed. CLIN 0006 cannot be exercised without the exercise of CLIN 0005. If an option is exercised, its period of performance will be consecutive to that of the Basic Work. Any option may be exercised within thirty-five (35) calendar days of receipt by the contractor of the Notice of Proceed.

NOTE 6: All bidders are hereby advised that the estimated dredge quantities for placement in the price schedule are estimated and based on the survey data collected on 23, 24, and 26 September 2024.

NOTE 7: The Government may reject a bid as non-responsive if the prices bid are materially unbalanced between line items and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low bid.

NOTE 8: Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions or attachments made by the bidder himself may render the proposal non-responsive and may be cause for its rejection.

NOTE 9: It is the contractor's responsibility to comply with all conditions and requirements of the SBOBA and stockpile placement.

NOTE 10: All bidders are hereby advised that the contractor is to complete the entire basic work ready for use, not later than fifty-one (51) calendar days after the date the Contractor receives the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

Solicitation Amendment W912DS25BA0090003 SF 30(1).pdf
Solicitation Amendment - W912DS25BA0090003(2).pdf
Solicitation Amendment - W912DS25BA0090003(2).pdf
Solicitation Amendment - W912DS25BA0090003(2).pdf
IDCode: J
Page: 1
Pages: 5
AmendNo: 0003
EffDate: 28 AUG 2025
ReqNo:
ProjNo: N/A
IssCode: W912DS
AdmCode:
IssuedBy: W2SD ENDIST NEW YORK

KO CONTRACTING DIVISION, 26 FEDERAL PLAZA ROOM 16 300

NEW YORK, NY 10278-0004

UNITED STATES

ADRIAN STAFFORD-BROWNE, EMAIL: ADRIAN.J.STAFFORD-BROWNE@USACE.ARMY.MIL TELEPHONE: 917-790-8087 AdminBy:

SCD: PAS:

ContractorNameAdd:
SolNo: W912DS25BA009
SolChg: 1
SolDate: 25 JUL 2025
AwardChg: Off
AwardNo:
Code:
FacCode:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: THE PURPOSE OF THIS AMENDMENT 0003 IS TO REMOVE CLIN 0005 OPTION - STOCKPILE PLACEMENT AND REVERT THE SCOPE OF WORK TO PRIOR TO AMENDMENT 0001. THE SCOPE OF WORK WILL ONLY CONSIST OF MAINTENANCE DREDGING OF THE SANDY HOOK CHANNEL WITH SUBSEQUENT PLACEMENT AT SBOBA. ANY REMAINING REFERENCES TO THE STOCKPILE PLACEMENT WITHIN THE SOLICITATION ARE NOT RELEVANT TO THE SCOPE OF WORK AND ARE NOT ENFORCEABLE. ALL RFI RESPONSES IN RELATIONS TO THE MAINTENANCE DREDGING OF SANDY HOOK CHANNEL AND SBOBA PLACEMENT REMAINS ACCURATE AND RELEVANT.

BID OPENING HAS BEEN EXTENDED TO 05 SEPTEMBER 2025. NO RFIS SHALL BE ACCEPTED AFTER THIS POSTING OF AMENDMENT 0003.