Package 1 - Thule Landfill - RFP.pdf

PDF 25 MB Posted

Attached to
FY24 Shoreline Stabilization and Landfill Capping Pituffik Space Base, Greenland
Solicitation number
W912DS24R0007
Issued by

About this file

This document provides details regarding a solicitation for landfill closure and shoreline stabilization work at Pituffik Space Base in Greenland. The U.S. Army Corps of Engineers intends to issue a solicitation seeking a firm fixed price contract for cleanup and stabilization of coastal faces at four sections of closed landfills along the northwest shoreline at Pituffik Space Base. The work includes extensive excavation and debris removal along sections ranging from 122 to 304 meters in length and up to 4.5 meters in height, followed by geotextile placement and blasted rock coverage. The project cost is estimated between $5-10 million and work is anticipated to take approximately two years to complete, with an expected award in the second quarter of fiscal year 2024. The solicitation will be restricted to Danish and Greenlandic firms only. A point of contact is provided for any questions.

View the file

Other files

File Type Posted
W912DS24R0007 Amend 0001.pdf PDF
W912DS24R0007.pdf PDF
W912DS24R0007.pdf PDF
Package 2 - Thule Landfill - Appendecies.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers

DESIGN-BUILD REQUEST

FOR PROPOSAL (RFP)

Final Submission August 11, 2023

Landfill Closure and Shoreline Stabilization Project Thule Air Base, Greenland

Landfill Closure and Shoreline Stabilization Thule Air Base, Greenland

This page left intentionally blank.

Landfill Closure and Shoreline Stabilization 11 August 2023 Thule AB, Greenland Final Submission

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 00 01 01/18 COVER SHEET

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 14 00 11/11, CHG 14: 02/22 WORK RESTRICTIONS

01 30 00 11/20, CHG 1: 08/21 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 02/15 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 16.00 10 05/16 DESIGN DATA (DESIGN AFTER AWARD)

01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 42 15 02/14 METRIC MEASUREMENTS

01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL

01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 50 00 11/20, CHG 1: 08/21 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 11/15, CHG 5: 08/21 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 08/19, CHG 4: 05/22 PROJECT IDENTIFICATION

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

THIS PAGE INTENTIONALLY LEFT BLANK

PROJECT TABLE OF CONTENTS Page 2

SECTION 00 00 01

COVER SHEET

01/18

PART 1 GENERAL

NEW YORK DISTRICT

CORPS OF ENGINEERS

NEW YORK, NEW YORK 10278-0090

REQUEST FOR PROPOSAL

FOR

Landfill Closure Thule Air Base , Greenland

1. Attached is Request for Proposal (RFP) NO. W912DS-24-R-000 7

2. RFP MUST BE SET FORTH full, accurate, and complete information as required by this RFP, including attachments. The penalty for making false statements in bids is prescribed under Title 18, United States Code, Section 1001.

3. SUBMISSION OF PROPOSAL: Complete details concerning proper submission of bids are contained in the INSTRUCTIONS TO PROPOSER (Section 00 21 16

4. REPRESENTATIONS AND CERTIFICATIONS - SECTION 00 45 00 Bidders and Offerors are required to complete the REPRESENTATIONS AND CERTIFICATIONS and submit them with their bids.

5. CONDITIONS OF CONTRACT - SECTION 00 70 00 , note in particular the PROHIBITION SEGREGATED FACILITIES. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000.

6. Please review all bonds and accompanying documents required to be submitted. Bonds, Powers of Attorney, statements of authenticity and continuing validity, and all related documents MUST NOT bear computer printer-generated signatures and/or seals. Documents bearing signatures and/or seals generated as part of a document, as opposed to being affixed to the document after its generation, will not be accepted. Submission of such documents may render the bid or offer non-responsive and ineligible for award.

7. Sections indicated in the cover page are part of the Solicitation.

DOCUMENT 00 00 01 Page 1

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 00 01 Page 2

SECTION 01 11 00

SUMMARY OF WORK

08/15, CHG 2: 08/21

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 1-300-02 (2014, with Change 3, 2021) Unified Facilities Guide Specifications (UFGS) Format Standard

1.2 PRE-CONSTRUCTION SURVEY

Pre-Construction Survey: Contractor to conduct pre-construction survey of site to verify existing conditions and provide basis for design.

Contractor to retain a professional surveyor to perform or supervise the surveying necessary to model existing conditions. Survey information must include the ties to the construction survey control points. Survey grid points must be at 6 m maximum intervals and must include all breaklines for top and toe of slopes, centerlines of ditches, edges and centerlines of roadways, and inverts of culverts.

1.3 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

a. The Contractor must (i) commence work under this contract within five

(5) calendar days after the date the Contractor receives the Notice to Proceed (NTP), (ii) prosecute the work diligently, and (iii) complete the entire work ready for use, within 365 calendar days after NTP.

The date stated for completion must include final cleanup of the premises. (FAR 52.212-3)

b. The completion date is based on the assumption that the successful offeror will receive the NTP by 31 October 2024. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the NTP, except to the extent that the delay in issuance of the NTP results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

c. All work must be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.

d. As set forth in UFC 1-300-02 , Change 3, 18 May 2021, 2-3.1, in project specifications directed to the Contractor, replace the word "shall" with the word "must."

SECTION 01 11 00 Page 1

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.4.1 Project Description

The project includes the work associated with shoreline stabilization, landfill closure, and stormwater ditch restoration. The project is divided into a Base Bid scope of work and five optional bid items. The following description includes the entire scope of work, including work in the base bid and five optional bid items.

Prepare design/build construction documents and provide construction for cleanup and stabilization of the coastal faces of the closed landfills located at four (4) sections on the northwest (NW) shoreline of Thule Air Base, Greenland. The NW shoreline requires clean up, geotextile, and blasted rock coverage. The first and second sections have lengths of approximately 122 meters and 159 meters, respectively, and vary from zero

(0) to approximately 4.5 m in height. The third section is approximately 304 meters in length and varies from zero (0) to approximately 3 meters in height. The fourth section is 170 m in length and is bounded to the north by the end of Section 3 and to the south by the 2011 revetment. All sections require thorough and extensive excavation, cleanup, and removal of half-buried scrap and debris, as well as a subsequent rehabilitation.

Prepare design/build construction documents and provide construction for landfill closure work which includes a necessary measure to provide adequate landfill cover for the areas identified in the documentation provided. The work includes stabilization of the two (2) seasonal stormwater ditches, one (1) at the north end of the landfill and one (1) on the southern part of the landfill. The area should be cleared from any metal debris that could cause issues or propagate thru freeze thaw.

1.4.2 Location

The site of work is located at Thule AB, Greenland. The site of the work is on a military installation and all rules and regulations issued by the Commanding Officer covering general safety, security, and sanitary requirements, etc., must be observed by the Contractor.

1.4.3 Base Bid Scope

The base bid scope of work includes 1) Design for the entire project, including all optional bid items, and 2) Shoreline Construction for Sections 1, 2 and 3 Revetment, as follows:

1.4.3.1 Base Bid Design

a. Shoreline Sections 1, 2, 3 and 4 Revetment Design: The proposed revetment design consists of two rock layers, an armor and an underlayer, with a main slope of 1:2 (vertical: horizontal). The armor rock sizing was calculated using Van der Meer’s formula et al. (1995) method from the Rock Manual, CIRIA (2007) with the design parameters as detailed in the Basis of Design Report, Section 2.4.1.1. The armor and underlayer have a layer thickness equal to two times the nominal stone diameter. The median weight of the underlayer stone (W50) is calculated as 1/10 of the primary armor stone mass. The stability between the armor and underlayer was assessed using the guidance provided in CIRIA (2007) to determine suitability of sub-layers against stability, permeability, and segregation criteria. Where the filter rules between the underlayer and core by CIRIA (2007) cannot be

SECTION 01 11 00 Page 2 met, the installation of a geotextile must be considered. The stability of the toe rubble mound will be estimated based on methods from the Rock Manual, CIRIA (2007).

The rock sizing calculations were performed for a 100-year return period and a design water level of 1.9 m MSL which includes 0.3 m of Sea Level Rise. A design wave height of 2.1 m and peak wave period of

10.0 sec was considered for the preliminary design. The design return period for overtopping is the 100-year return period wave event and no allowable overtopping under operational conditions. The design life of the shoreline protection must be 30 years. The concept of a design life assumes that regular inspections and minor maintenance, but not major repairs or rebuilding, will take place throughout the design life, unless damage occurs from a storm event in excess of the design criteria.

b. Revetment Geotextile Design: The geotextile design must be based upon the methods presented in CIRIA (2007), with the use of supplementary standards if necessary. The required tensile strength from armor layer, underlayer and wave loading have been calculated and design parameters for the geotextile preliminary design are detailed in the Basis of Design Report, Jacobs, Section 2.4.1.5.

c. Alternative Design: If the Contractor decides on an alternative revetment crest design, overtopping rate/volumes must be considered.

The proposed revetment crest can be made wider in place of using the gravel strip behind the crest. It is up to the Contractor to adequately evaluate overtopping conditions and ensure the maximum allowable overtopping rate/volume is not exceeded. The proposed berm was designed to match the previous 2011 shoreline protection. If the Contractor decides to widen the berm for construction purposes that is acceptable, however the berm width cannot be decreased from a minimum of 4 meters.

d. Ditch restoration design (cross section): If the Contractor decides on an alternative ditch cross section design than what is shown on the conceptual design documents, storm flows from snow and ice melt must be considered. The proposed stream must be able to carry the flow from a full upstream culvert (existing 610 mm (24") at the north stream and existing 1,070 mm (42") at the south stream) with appropriate freeboard.

e. Landfill closure design: Cover design must conform to standards in US Department of Defense Environmental Final Governing Standards Greenland. Existing cover thickness varies. Final cover thickness minimums will be measured from prepared subgrade to finished grade per the design standard. Final cover material must be compatible with existing cover material and able to achieve specified compaction.

f. Prior to detail design Bathymetric and Topographic survey: Prior to detail design Contractor must conduct a site topographic and bathymetric survey of the project site to verify existing conditions and provide basis for detail design. Survey extent should include the full footprint of proposed shoreline and landfill works. Elevations shall be provided at 0.5 m intervals and cover up to the -3.0 m contour line.

SECTION 01 11 00 Page 3

1.4.3.2 Base Bid Construction

Shoreline Stabilization Sections 1, 2, and 3 Revetment Construction:

a. Revetment Stone Material: The preliminary design assumes stone material will be sourced from the North Basalt Quarry located at North Mountain. The armor and underlayer stone must be hard, close grained, free of cracks, seams or other imperfections which might adversely affect its durability when exposed to weathering and wave action of the inlet environment. All stones must be roughly angular in shape, with at least dimension of any stone no less than one-third of its greater dimension. Flat stones will not be accepted. The inclusion of objectionable quantities of dirt, sand, clay and rock fines will not be permitted. Armor and underlayer stone must be tested for gradation. A gradation test must consist of weighing every stone in a representative sample to determine the amount of each stone between the various specified weights. The weights thus obtained are accumulated and expressed as a percent by weight of the total sample lighter than the various specified stone weight.

b. Revetment Construction Tolerances: Variation in slope lines and grades from the indicated slope lines and grades must be within the tolerances specified in CIRIA 2007 (CIRIA/CUR C683 Chapter 9, Table 9.7), which is +.6m to -0.4m for the armor layer and +0.3m to -0.2m for the underlayer. The above provided tolerances are for average difference between design profiles to actual profile (i.e. mean actual profile) over 15 m length along the structure’s axis. The tolerances on two consecutive mean actual profiles must not be negative.

Notwithstanding any accumulation of positive tolerances on the underlayer, the thickness of layer must not be less than 80% of the nominal thickness when calculated using mean actual profiles. The intention is that the work must be built generally to the required elevations, slope and grade and that the outer surfaces must be even and present a neat appearance. Placed material not meeting these limits must be removed or reworked.

c. Revetment Installation Preparation: Remove and dispose of miscellaneous debris (riprap, vegetation, metal debris, etc.), within the limits of the proposed revetment as required to properly install the revetment. Contractor must take all necessary precautions to prevent premature and/or uncontrolled collapse of any portion of the upland landfill. If uncovered debris at the landfill face is within the footprint of the proposed revetment but is mostly contained within the landfill, it is up to the Contractor whether to remove the full extent of the debris or cut and remove only the portion of the debris within the proposed revetment footprint. All riprap removed from the existing shoreline may potentially be reused in the construction of the proposed revetment if the Contractor deems the stone to be in good condition and riprap is within the proposed design grading or could be broken up to achieve the required gradation. Any stone considered unsalvageable must be removed and disposed of in a disposal area.

Flat stones must be removed and disposed of in a disposal area and cannot be reused for the proposed revetment.

Note: disposal locations of debris may vary and are dependent on debris classification. Hazardous waste will trigger appropriate disposal requirements, scrap metal must be cut into 1-meter (m) by 1-m pieces and taken to the DLA yard located on-base for disposal and sorted accordingly. All other debris is to be transported to active

SECTION 01 11 00 Page 4 base landfill for disposal.

d. Check Surveys and Final As-Builts: Surveys conducted by the Contractor must be performed after the sub grade is prepared prior to laying of any rock material, after the underlayer has been placed, and after the armor stone has been placed to determine that the materials are acceptably placed in the work. Make checks as the work progresses to verify lines, grades and thicknesses established for completed work.

As-built and check survey plan at 0.5 m elevation intervals of all components of the revetment, from back toe, crest, slope, and toe crest, and toe for underlayer and armor layer. The same scale for the as-built and check survey cross sections must be used as in the Contract Drawings. The cross-section profile must be digitally captured. The final as-built cross sections and the theoretical design templates must be superimposed over the original cross sections. Cross sections must be taken on 5 m intervals. All stations, ranges, and elevation points taken from field books must be clearly lettered as the profiles. A final survey covering all aspects of work including optional scope items constructed will be provided at 0.5 m elevations.

All digital survey files will be provided.

e. Revetment Geotextile Placement: Areas on which geotextile is to be placed must be graded and/or dressed to conform to the proposed design cross sections. Where such areas are below the allowable minus tolerance limit, they must be brought to grade by fill stone and compacted to a density equal to the adjacent in place material. For elevations above MSL and the areas below the allowable design minus tolerance limit will be brought to grade with structural backfill.

Subaqueous areas on which geotextile and stone/backfill are to be placed, shall be graded and/or dressed to conform to design cross sections. Installation of geotextile must be performed as directed by the product manufacturer.

f. Underlayer and Armor layer Placement: Underlayer Stone must be placed only after the base of the relocated slope is prepared and geotextile placement has been approved. The underlayer stone must be spread uniformly on the prepared base in a satisfactory manner to the indicated lines starting from the bottom of the area to be covered and continue up slope. Armor Stone must be placed only after the upper underlayer stone has been approved to be within design tolerances.

Armor stone shall be placed on the upper underlayer stone in such a manner as to produce a well-graded mass of stone with minimum voids.

g. Tugboat Launch Access: The existing tugboat launch and access road located in Section 3 must remain operational at all times. The Contractor must design the access route of the existing tugboat launch through the proposed revetment. At a minimum, a width of 30 m is required for the tugboat access road.

h. Access Road and Turnaround: The Contractor must maintain the existing access road and turnaround adjacent to the northern ditch.

i. Contractor to provide an O&M plan prior to construction completion.

O&M plan to outline revetment maintenance activities required, such as inspections after storm events, periodic inspections and maintenance requirements, and the methods needed to repair the revetment if inspection warrants repairs.

SECTION 01 11 00 Page 5

1.4.4 Optional Bid Item Scope

In addition to the base bid scope this project has contract Optional Bid Items No. 1-5 as follows:

1.4.4.1 Option 1: Shoreline Stabilization Section 4 Revetment Construction

Option 1 is for construction only and does not include design. Design for the Shoreline Stabilization Section 4 Revetment is included in the base bid and as such the final design for Section 4 is to be completed by the Contractor under the base contract and must tie in with the final design of Shoreline Sections 1, 2, and 3 Revetment.

Option 1 scope of work is as follows:

a. Construction for Option 1 Shoreline Stabilization Section 4 Revetment must adhere to requirements for design/construction of shoreline Sections 1, 2, and 3 as described in the base bid scope of work, including the requirement for the O&M manual.

b. Provide revetment construction for Section 4 which is 170 m in length and is bounded to the north by the end of Section 3 and to the south by the 2011 revetment. There is exposed debris throughout this section.

1.4.4.2 Option 2: North and South Stormwater Ditch Restoration

Option 2 scope of work is as follows:

a. Ditch Restoration: Install a continuous ditch cross section from east (existing culvert at road crossing) to west, discharging into the bay.

Culverts under the landfill limit east roadway are to remain in place.

Ditch restoration to include bottom and sideslope grading, separation geotextile, and rock. Import material needed to create continual stream cross section and fill in local ponding areas prior to geotextile installation. Design rock revetment within ditch to withstand full flow through ditch cross section. The Contractor must design the culmination of the restored ditch through the proposed shoreline stabilization revetment. Coordinate with the Shoreline Stabilization Contractor.

b. Culvert Removal: Remove existing washed out 1,070 mm (42") culvert within the south ditch as it is no longer required. Realign the south ditch to bypass the existing washed-out curve in the ditch.

c. Contractor to provide an O&M Plan prior to construction completion.

O&M Plan to outline drainage ditch maintenance activities required, such as inspections after storm events, periodic inspections and maintenance requirements, and the methods needed to repair the ditch to original condition if inspection warrants repairs.

1.4.4.3 Option 3, 4, and 5: Landfill Cover Sections A, B, and C

Options 3, 4, and 5 are the scope of work for construction/placement of the Landfill Cover. The landfill closure has a total of 21 hectares to be stabilized and has been divided into three sections, with an identical scope of work for each section. Option 3 is for Section A of the landfill closure. Option 4 is for Section B of the landfill closure. Option 5 is for Section C of the landfill closure.

SECTION 01 11 00 Page 6

The scope of work is as follows:

a. Landfill Closure Preparation: Remove and dispose miscellaneous exposed debris (metal, wire, plastic, asphalt, wood, etc.) that has breached the existing cover, within the limits of the landfill as required to properly achieve final cover thicknesses. Contractor must take all necessary precautions to prevent premature and/or uncontrolled collapse of any portion of the landfill. All stones removed from the existing landfill may potentially be reused in the construction of the proposed stream restoration if the Contractor deems the stone to be in good condition and are within the proposed design grading. Any stone considered unsalvageable must be removed and disposed of in an approved offsite disposal area. Flat stones must be removed and disposed of in an approved offsite disposal area and cannot be reused for the project. Prepare subgrade for cover installation by creating a firm, unyielding surface. Remove any vegetation prior to cover installation and fill in low spots and sink holes to grade to drain.

Please note disposal locations of debris may vary dependent on debris classification. Hazardous waste will trigger appropriate disposal requirements. Scrap metal must be cut into 1-meter (m) by 1-m pieces and taken to the DLA yard located on-base for disposal and sorted accordingly. All other debris is to be transported to active base landfill for disposal.

b. Landfill Grading: Install cover material over landfill to grade in an east to west fashion at a minimum 2 percent slope. Install shallow surface water drainage swale with erosion control measures along the interface of the landfill final cover eastern boundary and existing site grade (along east final cover boundary limit in all landfill options).

c. Compaction Testing: Contractor must perform compaction testing on in place final cover material to ensure final cover placement to required specifications.

d. As-built Survey: Contractor must conduct a post-construction survey of the landfill for record. Contractor to retain a professional surveyor to perform or supervise the surveying necessary to model final conditions. Survey information must include the ties to the construction survey control points. Survey grid points must be at 6 m maximum intervals and must include all breaklines for top and toe of slopes, centerlines of ditches, edges and centerlines of roadways, and inverts of culverts.

e. Landfill O&M Plan: Contractor to provide an O&M plan prior to construction completion. O&M plan to outline cover maintenance activities required, such as inspections after storm events, periodic inspections and maintenance requirements for settlement, and the methods needed to repair the cover if inspection warrants repairs.

1.5 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

This project is estimated between $10,000,000.00 and $25,000,000.00.

1.6 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING

Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may

SECTION 01 11 00 Page 7 make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy must be provided to the Contracting Officer. The Contractor must hold and save the Government, its officers, and agents free from liability arising from trespassing or damage occasioned by his operations.

1.7 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

c. The Contractor must be responsible for the repair, restoration, or for all cost of damage resulting therefrom. If the Contractor elects to have alterations made to any existing structure, utility, dune, road, or other improvements, contractor must make arrangements with the owner of the facility for such alteration and the arrangements must be approved by the Contracting Officer prior to making alterations.

Repair and restoration must comply with contract requirements and must also be approved by the Contracting Officer

1.8 LOCATION OF UNDERGROUND UTILITIES

Obtain a properly executed AF Form 103, Base Civil Engineering Work Clearance Request coordinated through the Contracting Officer and signed by the Base Civil Engineer prior to excavating to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.8.1 Notification Prior to Excavation

No excavation can be performed until site utilities have been field located. The Contractor must take the necessary precautions to ensure no damage occurs to existing structures and utilities. Damage to existing structures and utilities resulting from the Contractor's operations must be repaired at no additional cost to the Government. Utilities encountered that were not previously shown or otherwise located must not be disturbed

SECTION 01 11 00 Page 8 without written approval from the CCI. Notify the Contracting Officer at least 15 days prior to starting excavation work.

1.9 CRITERIA AND REGULATIONS APPLICABLE TO THIS WORK AT THULE AB

The regulations listed below take precedence over the requirements of the specification.

Refer to the links below:

a. Design of construction sites and similar workplaces in Greenland https://at.gl/da/regler/bekendtgoerelser/1348-indretning-af-byggepladser/

b. Executive Order for Greenland on substances and materials https://www.at.gl/da/regler/bekendtgoerelser/396-stoffer-og-materialer/

c. Executive Order for Greenland on the design of the workplace https://www.at.gl/da/regler/bekendtgoerelser/399-arbejdsstedets-indretning/

d. Executive Order for Greenland on the execution of the work https://www.at.gl/da/regler/bekendtgoerelser/395-arbejdets-udfoerelse/

e. Executive Order for Greenland on transportable containers for compressed, liquefied or pressurized gases https://at.gl/da/regler/bekendtgoerelser/149-transportable-beholdere/#afs7

f. Executive Order on the design of technical aids in Greenland https://www.at.gl/da/regler/bekendtgoerelser/656-anvendelse-af-tekniske-hjaelpemidler/

g. Executive Order on the use of technical aids in Greenland https://www.at.gl/da/regler/bekendtgoerelser/656-anvendelse-af-tekniske-hjaelpemidler/

h. Safety and health work at companies in Greenland https://at.gl/da/regler/bekendtgoerelser/1346-sikkerheds-og-sundhedsarbejde/

i. The client's duties in Greenland https://at.gl/da/regler/bekendtgoerelser/1344-bygherrens-pligter/

j. The Greenland Working Environment Act No.1048 of 26 October 2005 subsequently amended,and the US Department of Defense Environmental Final Governing Standards (FGS), Greenland 2022.

SECTION 01 11 00 Page 9

1. 10 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

a. The Government will furnish to the Contractor the property identified below. When the property is provided, the Contractor must verify its quantity and condition and acknowledge receipt in writing to the Contracting Officer. The Contractor must also report in writing to the Contracting officer within 72 hours of delivery damage to or shortage of the property as received. This property smust be installed or incorporated into the work at the expense of the Contractor, unless otherwise indicated in this contract.

b. Each item of property to be furnished under this clause must be identified in the Schedule by Quantity, item and description.

(FAR-52.245-3)

Item No.

Description Quantity

1. POL Products Arctic Diesel Fuel Mogas Lubricant Oil SAE 1OW30 Gear oil Hydraulic oil HDO, 10 & 30 Antifreeze

2. Arctic Parkas See ARCTIC PARKA paragraph

3. Arctic Gear, other than parkas Provided by Contractor. See ARCTIC PARKA paragraph

4. Aggregate for concrete work Provide by Contractor

Non Frost Susceptible (NFS) material

See NON FROST SUSCEPTIBLE (NFS) MATERIAL paragraph.

1. 10.1 Arctic Parkas

The Government will not furnish parkas to the Contractor. Contractors are responsible for providing their workforce with proper arctic gear.

SECTION 01 11 00 Page 10

1. 10.2 Non Frost Susceptible (NFS) Material

Non Frost Susceptible (NFS) material is available at Pituffik Space Base.

The material is free; however, the Contractor must process the material to achieve the proper gradation as required by the specifications.

1. 11 MARKINGS ON GOVERNMENT AND CONTRACTOR EQUIPMENT AND PROPERTY

The Contractor shall comply with the following equipment marking requirements:

a. Government-Owned: All items of Government-furnished construction plant, including but not limited to mobile vehicles, tractors, cranes;

secondary equipment such as trailers, trailer-mounted heavy stationary equipment, such as batch plants, crusher plants, etc., shall have the following marking conspicuously placed and maintained on both sides of each such vehicle or equipment:

GOVERNMENT OWNED (VEHICLE) (EQUIPMENT)

OPERATED BY

(NAME OF CONTRACTOR)

The marking shall be in legible and easily visible letters at least two inches high. The markings may be accomplished by stencils, using durable outdoor type paint or by firmly secured plaques or decals.

Uniformity of markings is required.

b. Contractor-Owned: All Contractor-owned or Contractor-furnished construction plant including but not limited to the same categories of such items as listed in sub-paragraph (a) above, shall have the same marking as prescribed in subparagraph (a) above for Government-owned construction-plant except that the word "Contractor" shall be substituted in place of the word "Government" in said prescribed marking.

c. Prior to the return by the Contractor of Government-furnished construction plant equipment, the Contractor shall neatly remove the name of the Contractor.

1.1 2 GOVERNMENT FURNISHED SERVICES

The Government will make available to the Contractor for the duration of the contract the following services, free of charge, or at the rates noted below, subject to the regulations set forth by the Pituffik Space Base Installation Commander

a. Billeting/Quarters

(1) Work Force. Contractor personnel will be billeted in available facilities, usually transient quarters furnished with beds, closets and lights, Individual maid service is not available. Once per week the Contractor shall arrange to bring soiled linen to the Linen Exchange and receive clean replacement linen. Contractor's own personnel shall clean assigned billets. Personnel paying short visits (14 days or less) will be billeted in transient quarters at prevailing rates.

SECTION 01 11 00 Page 11

(2) Contract Managerial Personnel, such as the Project Manager, who may be billeted in VOQ (Visiting Officers, Quarters), when available, will be charged $185.00 per night inclusive of maid service and weekly linen exchange. Actual rate may differ based on when projects are awarded.

b. Food Service: The Contractor employees are able to buy meals at Dundas Base Restaurant where the current daily rate for three meals is US dollars. The Contractor shall arrange the work schedule so that employees can eat during existing dining hall schedules. The dining hall is located at the Main Base.

Meal Daily

Breakfast 0500 - 0800

Lunch 1100 - 1300

Dinner 1700 - 1900

Messing for transient personnel (14 days or less) will be on a cash basis at prevailing rates. Present FY24 rates are $4.00 for breakfast and $6.46 for lunch or dinner with subject to 3.4% increase for subsequent years. The Contractor's personnel will not be issued free meal cards.

The Contractor is responsible for damage to messing facilities as caused by personnel tracking asphalt, tar, oil, grease, mud, etc., and will be charged any costs incurred for the repair or replacement of Government property.

c. Transportation: Contractor personnel may use the regularly scheduled Base bus system to go from one place to another on the Base.

d. Laundry and Dry Cleaning Services are available at prevailing rates, on a weekly basis. Rates and service times are posted in Building #100 (North Star Inn) and at the pick up point, Building #252.

e. Recreation Facilities including gymnasium, Motion Picture Theater, access to the Top of the World Club, and Base Exchange are subject to the regulations as set forth by the Pituffik Space Base Installation Commander. Approval for establishing Contractor's Clubs and rules for their operations must be obtained from the Installation Commander.

Individual users must pay the prevailing rates.

f. Vehicle and Equipment Maintenance: Maintenance and repair of Contractor-owned vehicles and equipment used in the performance of this contract will be the responsibility of the Contractor. Base maintenance shops may be made available to the Contractor for emergency repairs.

in the performance of this Contractor will be sold by the U.S.

Government at cost to the Contractor. Fuel products, oil and lubricants provided for Contractor-owned vehicles and equipment will be limited to such types as are readily available at the base and

SECTION 01 11 00 Page 12

Landfill Closure and Shoreline Stabilization 11 August 2023 Thule AB, Greenland Final Submission

g. POL: Fuel products, oil and lubricants as required for Governme --furnished equipment and Contractor- owned vehicles and equipment use shall be purchased through base supply. Special products, not available at the base, shall be furnished by the Contractor at his own expense. The following POL products can be made available to the Contractor: DFA and Mogas. These will be issued to the Contractor using an approved Serv-O-Plate (AF Form 1252A) issued by Vehicle Maintenance. Information regarding this contract, including contract number, expiration date, as well as identification of vehicles and equipment must be provided to the Base O&M contractors. The current Diesel Fuel Rate can be found in Appendix S.

h. Utilities: Water and electricity will be provided within allotted building work-spaces from existing sources and outlets. No electrical power or outlets will be made available for work to be performed away from buildings. The Contractor shall furnish a generator, as necessary, to power any equipment or machines utilized to produce the aggregate stockpiles. The U.S. Government will not furnish electrical power for use in connection with production of aggregate. POL will be available on a cost reimbursable basis per subparagraph h above.

1.1 3 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 10 miles of the construction site.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

1.1 4 SALVAGE AREA

Salvaged, non-hazardous materials or equipment must be identified to the Contracting Officer and must be returned to the Government as requested.

All salvaged items must be properly documented and signed by the Contracting Officer in compliance with Base regulations. Returned materials must be delivered to the landfill shown on the drawings or the DRMO yard at the Contractor's expense. No materials must be placed within the landfills without prior approval.

All recyclable materials must be cut into manageable pieces, one meter by three meters and neatly stacked in a pile at the DRMO yard. The contractor must be responsible for coordination of all demolition activities with the Contracting Officer and Pituffik Space Base BCE Office.

The contractor must adhere to the regulations as outlined in the respective management plans included in the Appendix. (Solid Waste Management Plan, Spill Prevention and Response Plan, Asbestos Management Plan, Slug (Wastewater) Management Plan, Hazardous Waste Management Plan, Pollution Prevention Management Plan)

1.1 5 CRITERIA AND REGULATIONS APPLICABLE TO THIS WORK AT PITUFFIK SPACE

BASE

Refer to Appendices, work shall be executed in strict accordance with the following:

SECTION 01 11 00 Page 13

" Conservation Mgmt Plan Final -

" Hazardous Waste Management Plan -

" Installation HAZMAT Management Plan -

" Spill Prevention-Response Plan -

" Pollution Prevention Management Plan -

" Solid Waste Management Plan -

" Storm Water Mgmt Plan -

" Asbestos Management Plan -

" Affirmative Proc Plan -

" Slug Mgmt Plan -

" Final Governing Standards for Environmental Protection by United States Forces in Greenland (FGS-GL) -

" Consolidated Act of Working Environment No. 268 of 18 March 2005 as subsequently amended issued by "Danish Working Environment Authority". Document may be obtained from the Danish Working Environment Authority, available on website https://amid.dk/en

" The Greenland Executive Order on design of construction sites and similar workplaces in Greenland, no 1348 of 15th December 2005.

Document may be obtained from the Greenland Working Environment Authority, available on website

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

SECTION 01 11 00 Page 14

SECTION 01 14 00

WORK RESTRICTIONS

11/11, CHG 14: 02/22

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.2.1.1 Identification Of Employees

The Contractor must be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. All prescribed identification must immediately be delivered to the Contracting officer for cancellation upon the release of employees. When required by the Contracting Officer, the Contractor must obtain and submit fingerprints of all persons employed or to be employed on the project.

(DOD FAR Supplement 52.236-7007)

1.2.1.2 Geographic Limitations

The work under this contract may be severely influenced by inherent geographical and climatic constraints. Exterior construction season is typically from 15 May to 15 September. Access to Thule AB for materials, equipment, and personnel is limited to an annual sealift. Military airlift may be available, depending on the availability of cargo space, but is very costly and at the Contractor's expense. The annual Military Sea Transportation Service operation is limited to summer months only.

Due to total daylight at Thule during this period, the Contractor can schedule continuous construction work. Acquisition of building materials at airlift is normally restricted to personnel and critical equipment only.

SECTION 01 14 00 Page 1

1.2.1.3 Rock Drilling and Blasting

Rock blasting operations to be coordinated with Contracting Officer.

Contractor to provide own equipment. Drilling equipment is not available from the Base Maintenance Contractor (BMC). The base's current supply of explosives is expired and no longer usable. Contractor to provide all drilling equipment, explosives, and detonators, and coordinate transfer and storage of explosives at least 2-3 months in advance of shipment through the COR. See Blasting Manual and map with base explosive storage location at the end of this section for more information. Maximum storage capacity for explosives at Building 1050 is 5,000 kg (5 ton).

1.2.1.4 Sea Transport

Thule Air Base is remotely located. The annual military sea transportation service operation is limited to a 60-day period, normally the second week of July through the first week of September. For planning purposes, the Pacer Goose ship typically arrives at Thule from the United States at the end of June. The first ship from Denmark usually arrives at Thule the 1st week of July, and the 2nd ship from Denmark arrives in mid-August. Please refer to the bid schedule notes for more information on coordination with the embassy on all shipping items.

1.2.1.5 Early Site Arrival

It is a requirement of this contract that the contractor or his representative must arrive at Thule AB at least 10 calendar days in advance of the arrival of equipment, materials or laborers. The Contractor and the Contracting Officer (or Contracting Officer Representative) will review the Contractor's CPM schedule project logistics, and Thule AB regulations.

1.2.1.6 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.2.1.7 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.2.2 Working Hours

Regular working hours will be established by the Contracting Officer, and should be coordinated with the BMC. Minimum 40 hours/week, except for weeks that contain a holiday, see 1.3.4 below.

1.2.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving

SECTION 01 14 00 Page 2 the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.

1.2.4 Exclusionary Period

Holidays observed at Thule AB by USAF and BMC (BASE MAINTENANCE

CONTRACTOR):

- 01 January (New Year's Day)

- Third Monday in January (Birthday of Martin Luther King Jr.)

- Third Monday in February (President's Day)

- Last Monday in May (Memorial Day)

- Third Monday in June (Juneneeth Day)

- 04 July (Independence Day)

- First Monday in September (Labor Day)

- Second Monday in October (Columbus Day)

- 11 November (Veteran's Day)

- Fourth Thursday in November (Thanksgiving Day)

- 25 December (Christmas Day)

Holidays which fall on the weekends are normally observed on the following Monday. Danish holidays are not observed at Thule AB. Holidays which fall on a Saturday will normally be observed by BMC that same day, but by USAF the following Monday.

1.3 RESPONSIBILITY FOR PHYSICAL SECURITY

Prior to mobilization, the Contractor must submit his proposed means of providing project security as defined below.

1. For the purpose of this clause, the term "physical security" is defined as that part of security concerned with the physical measures designed to safeguard personnel, to prevent unauthorized access to equipment, facilities, materials and documents, and to safeguard them against espionage, sabotage, damage, and theft.

2. Under the general supervision of the Contracting Officer, the Contractor must be responsible for physical security of all materials, supplies, and equipment of every description, including property which may be Government-furnished or owned, and all work performed, and also of areas occupied jointly by the Contractor and the Government. The Contractor agrees to furnish to the Contracting Officer just prior to physical completion of all work under this contract, a consolidated inventory of all excess supplies, materials and equipment imported, duty free, for use under the terms of this contract.

3. The continued employment of a person in connection with this contract, or subcontract there under whose conduct is determined to be prejudicial to the interests of the Government of Denmark, Ministry of Greenland or the Corps of Engineers must be terminated and that person must be immediately removed from the work upon request of the Contracting Officer at no cost to the Government. Compliance with the foregoing provisions of this paragraph by subcontractors must be the responsibility of the Contractor.

4. The Contractor represents that the contract price herein include an

SECTION 01 14 00 Page 3 amount sufficient to cover reasonable security measures based on local conditions. These measures must be subject to approval by the Contracting Officer. There must be no compensation for upgrading deficient security measures that are substandard due to an initial oversight in the security program.

5. The Contracting officer reserves the right at all times to issue instructions pertaining to the Contractor's jurisdiction and general conduct of guard forces including the extent, to which the Contracting Officer will desire the Contractor to initiate and maintain such liaison with other law enforcement agencies, and must have the right to examine procedures, methods, records and facilities utilized by the Contractor in complying with the requirements of the Contracting Officer.

6. Examination of the Contractor's security methods, records, and facilities must not be permitted by a person, agency or sources outside the Contractor's organization, other than the Government of Denmark, or the Contracting Officer, without the prior and express consent of the Contracting Officer.

1.4 SAFEGUARDING OF INFORMATION

The personnel employed on this contract may, in the performance of their assigned duties, have access to data and information pertaining to location of goods, supplies, parts, equipment, vehicles, and explosives.

Knowledge of this nature is considered restricted security information.

This information must be protected and safeguarded against disclosure to any unauthorized person or party and must be furnished or used on an official "need to know, basis only. Safeguarding of information is extended to dependents and guests of employees, who may in any manner, obtain knowledge of the Government of United States of America military capacity.

1.5 SECURITY CLEARANCES

Contractor employees will be subject to Security Clearance procedures by the Ministry of Greenland for Danish Nationals and United States Air-Force for American citizens.

This is the start of the file's text. The full file is on GovTribe.