This amendment to solicitation W912DS23B0020 from the Department of the Army Corps of Engineers provides revisions to the requirements for the North Dock Repair Project at the West Point Army Garrison. The amendment revises the bid schedule to incorporate a fixed price line item for hauling and disposal of contaminated materials. It also revises drawings to update the design of the east revetment, slope dimensions, and elevations. Bidders must acknowledge receipt of the amendment by the date specified to have their bids considered, and the bid opening date of September 12, 2023 at 2:00 PM EST remains unchanged. The amendment communicates important changes to the scope of work that bidders must account for in their responses to properly address the project requirements.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912DS23B0020
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of Amenmdent 0002:
1) Bid opening remains 12-September-2023 at 2:00 P.M. EST
2) Incorporate revised Bid Schedule.
3) Draw ings have been revised and reissued. Please see continuation page and attachments.
4) Incorporate draw ing RM303.
NOTE: Bidders must acknow ledge receipt of this amendment by date specif ied in the bid (or as amended) by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THELATE BID, LATE MODIFICATION OF BID, OR LATE
WITHDRAWAL OF BID (FAR 14.304
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-Aug-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS23B0020
X 9B. DATED (SEE ITEM 11)
09-Aug-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Aug-2023
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0002
North Dock Repairs US Army Garrison West Point DPW, New York
Amendment 0002
Amendmended Bid Schedule:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job All work associated with the attached
FFP
contract documents, including: mobilization and demobilization, demolition, bulkhead construction, revetment construction, parking lot restoration, including the bulk price of all excavation, and hauling and disposal of non-contaminated material excluding CLIN 0002.
FOB: Destination
PSC CD: Y1KZ
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 6,665 Short Ton
The bulk price of hauling and disposal
FFP
(excluding excavation which is included in CLIN 0001) of contaminated material including fill, sediment, construction debris and/or soil that is removed from the project area. All other hauling and disposal of other non-contaminated material is included in CLIN 0001. (ESTIMATED QUANTITY) FOB: Destination
PSC CD: Y1KZ
NET AMT
TOTAL BID
TOTAL BID
(CLINs 0001 thru 0002):
NOTES TO BIDDERS
(1) Total Bid shall include all costs associated with each item number including all bonding, overhead and profit.
(2) Please refer to the Scope of Work section 01 11 00 for a description of the CLINs.
(3) Offeror must submit a price for every CLIN. Failure to do so may result in Offer being unacceptable.
(4) Bids are to be valid for 120 calendar days from proposal due date.
(5) Period of performance (PoP - total contract duration) for the base bid scope is 540 days from NTP (Notice to Proceed).
(6) NOTE: The Government may reject a bid as non–responsive if the prices bid are materially unbalanced between line items and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low bid.
(7) NOTE: Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions or attachments made by the bidder himself may render the proposal non-responsive and may be cause for its rejection.
TO BIDDERS:
The following changes shall be made to the drawings and specifications.
DRAWINGS:
1. The following DRAWINGS have been REVISED and REISSUED:
Site / Civil:
• CS101 - outline of east revetment (IVO CS101/A1/C8) revised. Crest rear slope width of western revetment revised.
• CG101 - outline of east revetment (IVO CG101/A1/C8) revised, note added to reference revetment drawings. Crest rear slope width of western revetment revised.
• CG102 - outline of east revetment (IVO CG102/A1/C8) revised. Crest rear slope width of western revetment revised.
Structural:
• S-101 - outline of east revetment (IVO CS101/B10) revised. Crest rear slope width of western revetment revised.
• S-102 - outline of east revetment (IVO CS101/A1/C8) revised. Crest rear slope width of western revetment revised.
Marine:
• RM101 –
o Design of east revetment (RM101/2/B9) revised. Crest rear slope width of western revetment revised.
o The slope length of the East Revetment in Detail 2 has been revised, and the approximate elevation at the end of the slope has been added.
o Note added to the transition from revetment to new sheet pile wall bulkhead in Detail 1 (i.e., Note 5).
o Top of the revetment elevation added at the corner of revetment connection to the new sheet pile wall.
o Elevation at the toe of the slope changed to 0.00 ft in Detail 2 o Note 5 added to the face of the sheet pile wall in Detail 1 o Section G moved further northwest. A 1:33.3 (V: H) slope gradient is added, showing the crest elevation of 7 ft at Section G sloping down to +5 in front of the sheet pile wall over a Length of
66.7 ft
2. The following DRAWINGS have been REVISED but NOT REISSUED:
None
3. The following DRAWINGS have been ADDED:
RM303 – This drawing was inadvertently omitted from the advertised set.
4. The following DRAWINGS have been DELETED:
SPECIFICATIONS:
(End of Summary of Changes)