This amendment to a solicitation provides additional details for the maintenance dredging of the Shrewsbury River in New Jersey. The work includes dredging of the federal navigation project to authorized depths and placement of dredged material on a nearby beach. Bidders must acknowledge this amendment by the specified date and time. The amendment addresses environmental protections for shellfish beds and submerged aquatic vegetation both within and outside the dredging area. It also provides an extended performance period of 56 calendar days from notice to proceed to allow for increased mobilization and demobilization due to the dredging and pipeline distances.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Answ er questions to prospective bidders for informational purposes only.

NOTE: Bidders must acknow ledge receipt of this amendment by the date specif ied in the solicitation (or as amended) by one of the follow ing methods: In the space provided on the SF1442, by separate letter, or by signing the block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE DATE BID, LATE

MODIFICATIONS OF BIDS OR LATE WITHDRAWAL OF BIDS (FAR 14.304).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Jul-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS23B0018

X 9B. DATED (SEE ITEM 11)

16-Jun-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Jul-2023

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS23B0018

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0001

This amendment incorporates the following revision(s) to the solicitation:

- Section 01 57 20.00 10 – Environmental Protection, Paragraph 1.14 – Protection of Environmental Resources, the following is added:

“The contractor must avoid impacts to shellfish beds and Sub Aquatic Vegetation outside of the authorized channel limits. The contractor must notify NJDEP Marine Resources Administration Bureau of Marine Habitat and Shellfisheries of and is fully responsible for any impacts or damage to these resources outside of the channel limits.

The contractor must take all necessary precautions to avoid impacts to shellfish beds and Sub Aquatic Vegetation within the channel limits and outside of dredging footprint.

Work must be sequenced in a manner that ensures that any work in the south branch near SAV habitat must occur outside the SAV growing season of 15 April – 15 October. The NJDEP SAV habitat map can be found attached to this amendment.

BIDDER’S QUESTIONS AND GOVERNMENT REPLY

The following questions and answers are provided for information only. Nothing contained below amends or revises any provision of the solicitation. This is for bidder’s reference only, and is not to be considered as a part of the Contract Documents.

Contract award will be based on what is contained in the printed Plans and Specifications in a hard copy format or Electronic Bid Set if provided and as posted on SAM.Gov.

Q1. Specifications require completion of the project in 41 days from the NTP. If the NTP is granted in mid-August, the 41 days will expire prior to the beginning of the allowable in river work window for environmental constraints (fish window).

Can the required completion date for the project be changed to match the end of the fall/winter work window which closes on 1/15/24? Requiring the project to be completed within 41 days from the NTP also leaves insufficient time for approval of submittals.

W912DS23B0018

A1. NTP will be issued with sufficient time to ensure that all work can be completed outside the environmental no dredging windows. It is anticipated that NTP will be issued in August/September 2023, work can begin in the river as early as 1 July 2023. The environmental window of 15 April- 15 October is only applicable for work near SAV habitat. All submittals shall be submitted after award, prior to NTP and the preconstruction meeting, and therefore should not impact the project completion within the required performance period.

Q2. The 41-day work window to complete all work for the job seems aggressive given the work that needs to be completed. Please consider increasing the days.

A2. The required period of performance is based on a required production rate of 2,000 CY a day. This rate is based on prior projects of similar parameters and size, including the 2009 and 2013 maintenance dredging of Shrewsbury River, NJ. Due to the pumping distance and need for use of the NJDOT pipeline under Route 36, the time for mobilization and demobilization will be increased by 15 calendar days from 20 days to 35 days. This will increase the total period of performance from 41 days to 56 days.

Q3. Are there any culverts that can be used for the pipeline to cross Highway 36 onto the beach? If not, is a ramp as described in the specifications allowable to cross the highway?

A3. A pipeline crossing exists under Route 36 for access to the beach, in the approximate location of Seacrest Road. As stated in specification section 31 24 00.00 18 Beach Fill Placement paragraph 1.7 Quality Control: the contractor must coordinate with New Jersey Department of Transit (NJDOT) and all other applicable agencies to obtain all necessary permits which allow access to the placement site, including use of the pipeline crossing under Route 36.

(End of Summary of Changes)