This document is an amendment to a solicitation for beach erosion control services. The amendment provides revised plans and specifications, adding details for dredging, beachfill placement, and construction of a junction box riser. Bids are due by September 26, 2022 to the Army Corps of Engineers New York District for the Sandy Hook to Barnegat Inlet Beach Erosion Control Project in Monmouth County, New Jersey. The magnitude is between $25 million to $100 million, with unrestricted full and open competition and a HubZone price evaluation preference. The amendment answers seven questions from prospective bidders and provides related surveys.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Add a deadline of 19 September 2022 for submission of RFI.

2. Answ er questions to prospective bidders for informational purposes only.

NOTE: Bidders must acknow ledge receipt of this amendment by the date specif ied in the solicitation (or as amended) by one of the follow ing methods: In the space provided on the SF1442, by separate letter, or by signing the block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE DATE BID, LATE

MODIFICATIONS OF BIDS OR LATE WITHDRAWAL OF BIDS (FAR 14.304).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Sep-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS22B0024

X 9B. DATED (SEE ITEM 11)

26-Aug-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Sep-2022

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS22B0024

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0002

To Bidders The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED and REISSUED:

-G-201, G-102-104, C-101-108, R-501-504

2. The following DRAWINGS have been ADDED:

-None

3. The following DRAWINGS have been REVISED but NOT REISSUED:

-None

SPECIFICATIONS:

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

-None

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

-None

3. The following SPECIFICATION SECTIONS have been REVISED and REISSUED in their entirety:

-None

4. The following SPECIFICATION SECTIONS have been REVISED but NOT REISSUED:

- Section 01 11 00 par 1.1 b

REVISED PLANS & SPECIFICATIONS:

1- Specifications Section 01 11 00 par 1.1 b Revised to ““The Contractor must furnish all labor, materials, equipment, and services for the following work: construction for dredging and beachfill placement, beach tilling and construction for junction box riser as described in the solicitation package.”

2- Sheets G-201, G-102-104, C-101-108, R-501-504

Questions and Answers:

The following questions and answers are provided for information only. Nothing contained below amends or revises any provision of the solicitation. This is for bidder’s reference only, and is not to be considered as a part of the Contract Documents. Contract award will be based on what is contained in the printed Plans and Specifications in a hard copy format or Electronic Bid Set if provided and as posted on SAM.Gov.

Question 1. Section 01 11 00, Summary of Work, 1.1 b. states “The contractor must furnish all labor, materials, equipment and services for the following work: construction for dredging and beach fill placement, installation of marker piles, and construction for scour hole as described in the solicitation package”. Are marker piles and scour hole construction include within this contract?

Response 1. Revised to ““The Contractor must furnish all labor, materials, equipment, and services for the following work: construction for dredging and beachfill placement, beach tilling and construction for junction box riser as described in the solicitation package.”

Question 2. Section 01 11 00, Summary of Work, 1.3 states “This project is estimated between $25,000,000 and $100,000,000” on the SF 1442 it states the magnitude is $25,000,000 to $35,000,000.

Please clarify which is the correct magnitude

Response 2. As per DFARS 236.204, price range is between $25,000,000 and $100,000,000.

Question 4. Please provide the survey of Borrow Area #7 that was performed in 2022.

Response 4. Provided survey of borrow area #7 that was performed in 2022, and also provided survey of placement area.

Question 5. Is the contractor allowed dig in either borrow area of their choosing?

Response 5. Yes.

Question 6. If satisfactory material is available in both borrow areas, will the contractor be allowed to have both borrow areas “open” and go back and forth between both borrow areas?

Response 6. Yes.

Question 7. In the Amendment 1 that was posted, it was stated that there was a change to bid note 9 but the note remained the same as the original note. Please clarify that note 9 is correct on the Amendment.

Response 7. Note 9 is correct.

Question 8. Is there a deadline date for questions for this contract?

Response 8. September 19, 2022.

SECTION 00 10 00 - SOLICITATION

The required performance has changed from Project Title: Sea Bright Section II to Manasquan, NJ (Beach fill) on the Atlantic Coast of New Jersey Monmouth County.1. 100% Unrestricted Full and Open Competition w ith HubZone Price Evaluation preference.2. NAICS Code 237990, Size Standard $32,500,000.00.3. Project Magnitude Range: Between $25,000,000 to $35,000,000.004. Contract Specialist is Nicole Fauntleroy nicole.fauntleroy@usace.army.mil5. Submit Bids no later than 2:00PM EST on 26 Sept 2022 to:U.S. Army Corps of EngineersNew York District, Contracting Division, Room 16-300,26 Federal Plaza, New York, NY 10278- 0090Due to heightened security at U.S. Government installations, all Bidders are instructed to allow ample time to get through the security checkpoint in order to have their bids delivered before 2:00PM EST on the date of the bid opening. to Project Title: Sea Bright Section II to Manasquan, NJ (Beach fill) on the Atlantic Coast of New Jersey Monmouth County.1. 100% Unrestricted Full and Open Competition w ith HubZone Price Evaluation preference.2.

NAICS Code 237990, Size Standard $32,500,000.00.3. Project Magnitude Range: Between $25,000,000 to $100,000,000.004. Contract Specialist is Nicole Fauntleroy nicole.fauntleroy@usace.army.mil5. Submit Bids no later than 2:00PM EST on 26 Sept 2022 to:U.S. Army Corps of EngineersNew York District, Contracting Division, Room 16-300,26 Federal Plaza, New York, NY 10278-0090Due to heightened security at U.S. Government installations, all Bidders are instructed to allow ample time to get through the security checkpoint in order to have their bids delivered before 2:00PM EST on the date of the bid opening..

(End of Summary of Changes)