SHCC14 QC Reports redacted.pdf
PDF 7 MB Posted
- Attached to
- Maintenance Dredging of Shoal Harbor and Compton Creek, New Jersey Federal Navigation Project
- Solicitation number
- W912DS22B0023
About this file
This is a solicitation for maintenance dredging services of Shoal Harbor and Compton Creek in New Jersey. The solicitation is seeking dredging of the federal navigation project areas to required depths and widths. The Army Corps of Engineers District in New York will award a firm fixed-price contract for dredging an estimated 150,000 cubic yards of material. The period of performance is one year from the award date. The solicitation requires the use of a hopper dredge and includes provisions for disposal of dredged materials at the designated confined disposal facility. The response date for proposals is February 28, 2022, with award anticipated by April 2022.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION MANPOWER and EQUIPMENT REPORT
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/20/2015 DAILY REPORT NUMBER: 238
N-POWELL
COMPANY
Classifications
No.
Men
Man
Hrs.
Subcontractors
No.
Men
Equipment
# Pcs. of
Equip.
Quality Control 1 11 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging Foreman Dozers
Shoreman Front End Loaders
Foreman Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-Crane Trenching
Machine
Operator-Dozer 0 0 Articulating off- road Trucks
Operator-Exc. 0 0 Welding Machines
Operator-Roller 0 0 Mini-Exc
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 1
Manhours Today 8
Manhours Previous 9351
Manhours To Date 9359
CONSTRUCTION QUALITY MANAGEMENT REPORT
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/20/2015 Daily Report Number: 238
Weather: Mostly Cloudy Precipitation: .00 in. Temp: Min. 28 Max. 42
Wind Speed: 8-14 MPH from : W Gusts: 18 MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 8 Merit Belford CDF N-61, QC
2 Field
Project Mgr. 0
N. Powell Co. Belford, CDF N-61/ No Site Work k
3 Operators 0 Merit Belford, CDF N-61/ No Site Work
4 Tk Driver 0 Merit Belford, CDF N-61/ No Site Work
5 SSHO 0 Merit Belford CDF N-61, No Site Work
2. Operating Plant or Equipment (Indicate items of construction equipment other than hand tools, at the job and whether or not used.)
PLANT/EQUIPMENT
DATE OF ARRIVAL/
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
REPAIR
No Equipment on site
3. Work Performed Today (Indicate location and description of work performed by prime and/or subcontractors by number in table [1] above.
NO. LOCATION DESCRIPTION OF WORK PERFORMED
1-4 Belford, CDF
N-61
QC, Expecting delivery of dredging materials and equipment this week.
5 Belford, CDF
N-61
No Site Work
4. Results of Control Activities (Indicate P = Preparatory; I = Initial or F – Follow-Up Phase.
When a P or I meeting is conducted, complete attachment I-A or I-B respectively.)
Inspected site to see how things are faring during down time. CDF and spill box are in good condition and the armor stone on the seaward berm appears to have been tested and appears in excellent shape. There is about a foot of water in the bottom of the CDF in the low lying areas. Everything appears to be ready to commence dredging.
5. Tests Performed as Required by Plans and/or Specifications
No tests performed.
6. Materials Received (Indicate Compliance or Non-compliance.)
None
7. Verbal Instructions Received (List instructions given by Government personnel on construction deficiencies, retesting required, etc. Include the name of Government person, time and place instructions given and action taken to comply.)
No Site Work
8. Offsite Surveillance Activities, Including Action Taken
None
9. Job Safety (Report violations; corrective instructions given; corrective actions taken.
No violations observed.
10. Remarks (Conflict[s] in plans and/or specifications or delays).
Expecting delivery of dredging materials and equipment this week.
No deliveries or equipment brought today.
Contractor’s Verification On behalf of the Contractor, I certify this portion of the report is complete and correct, and all materials and equipment used and work performed during this reporting period are in compliance with the plans and specifications, except as noted above.
CONSTRUCTION MANPOWER and EQUIPMENT REPORT
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/21/2015 DAILY REPORT NUMBER: 239
N-POWELL
COMPANY
Classifications
No.
Men
Man
Hrs. Subcontractors
No.
Men
Man
Hrs. Equipment
# Pcs. of
Equip.
Quality Control 1 10 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging Foreman Dozers
Shoreman Front End Loaders
Foreman Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 1
Manhours Today 10
Manhours Previous 9359
Manhours To Date 9369
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/21/2015 Daily Report Number: 239
Weather: Mostly Cloudy Precipitation: .00 in. Temp: Min. 24 Max. 33
Wind Speed: 8-10 MPH from : N Gusts: -- MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 10 Merit Belford CDF N-61, QC
2 Field
Project Mgr.
N. Powell Co. Belford, CDF N-61/ No Site Work k
3 Operators 0 Merit Belford, CDF N-61/ No Site Work
4 Tk Driver 0 Merit Belford, CDF N-61/ No Site Work
5 SSHO 0 Merit Belford CDF N-61, No Site Work
2. Operating Plant or Equipment (Indicate items of construction equipment other than hand tools, at the job and whether or not used.)
PLANT/EQUIPMENT
DATE OF ARRIVAL/
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
REPAIR
No Equipment on site
3. Work Performed Today (Indicate location and description of work performed by prime and/or subcontractors by number in table [1] above.
NO. LOCATION DESCRIPTION OF WORK PERFORMED
1-4 Belford, CDF
N-61
QC, Expecting delivery of dredging materials and equipment this week.
5 Belford, CDF
Inspected site to see how things are faring during down time. CDF and spill box are in good condition and the armor stone on the seaward berm appears to have been tested and appears in excellent shape. There is about a foot of water in the bottom of the CDF in the low lying areas. Everything appears to be ready to commence dredging.
5. Tests Performed as Required by Plans and/or Specifications
No tests performed.
6. Materials Received (Indicate Compliance or Non-compliance.)
7. Verbal Instructions Received (List instructions given by Government personnel on construction deficiencies, retesting required, etc. Include the name of Government person, time and place instructions given and action taken to comply.)
10. Remarks (Conflict[s] in plans and/or specifications or delays).
Expecting delivery of dredging materials and equipment this week, and awaiting approvals from the ACOE in regards to the dredging operations, safety, procedures, and personnel.
No deliveries or equipment brought today.
Contractor’s Verification On behalf of the Contractor, I certify this portion of the report is complete and correct, and all materials and equipment used and work performed during this reporting period are in compliance with the plans and specifications, except as noted above.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/22/2015 DAILY REPORT NUMBER: 240
Classifications
No.
Men
Men
Equip.
Quality Control 1 10 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging Foreman Dozers
Shoreman Front End Loaders
Foreman Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 1
Manhours Today 10
Manhours Previous 9369
Manhours To Date 9379
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/22/2015 Daily Report Number: 240
Weather: Mostly Cloudy Precipitation: .00 in. Temp: Min. 28 Max. 39
Wind Speed: 7-15 MPH from : W NW Gusts: 18 MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 10 Merit Belford CDF N-61, QC
3 Operators 0 Merit Belford, CDF N-61/ No Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
N-61
QC, Expecting delivery of dredging materials and equipment this week.
5 Belford, CDF
Inspected site to see how things are faring during down time. All good.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/23/2015 DAILY REPORT NUMBER: 241
Classifications
No.
Men
Men
Equip.
Quality Control 1 10 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging Foreman Dozers
Shoreman Front End Loaders
Foreman Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 1
Manhours Today 10
Manhours Previous 9379
Manhours To Date 9389
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/23/2015 Daily Report Number: 241
Weather: Mostly Sunny Precipitation: .00 in. Temp: Min. 26 Max. 32
Wind Speed: 11-20 MPH from : WNW Gusts: 25 MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 10 Merit Belford CDF N-61, QC
3 Operators 0 Merit Belford, CDF N-61/ No Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
N-61
QC, Expecting delivery of dredging materials and equipment this week.
5 Belford, CDF
Inspected site to see how things are faring during down time. All good.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/24/2015 to 1/25/2015 No Work Scheduled DAILY REPORT NUMBER: 242-243
Classifications
No.
Men
Men
Equip.
Quality Control 0 0 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging Foreman Dozers
Shoreman Front End Loaders
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 0
Manhours Today 0
Manhours Previous 9389
Manhours To Date 9389
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/24/2015 to 1/25/2015 Daily Report Number: 242-243
Weather: No Work Scheduled Precipitation: .00 in. Temp: Min. -- Max. --
Wind Speed: -- MPH from : -- Gusts: -- MPH
Work Control Feature: No Work Scheduled Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 0 Merit Belford CDF N-61, QC
3 Operators 0 Merit Belford, CDF N-61/ No Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
N-61
No Work Scheduled.
5 Belford, CDF
No Work Scheduled
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 2
Manhours Today 17
Manhours
Previous
Manhours To
Date
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/26/2015 Daily Report Number: 244
Weather: Blizzard Forecasted Precipitation: 6.0 in. Temp: Min. 19 Max. 32
Wind Speed: 14-23 MPH from : NE--NNW Gusts: 31 MPH
Work Control Feature: No Work—Inclement Weather, Portion of Day Suitable for Work: 10%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 9 Merit Belford CDF N-61, QC
Merit Belford, CDF N-61/ PM
3 Operators 0 Merit Belford, CDF N-61/ No Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
N-61
No work due to inclement weather forecasted.
5 Belford, CDF
Inspected site. Blizzard conditions forecasted starting today and ending Tuesday night. Up to 26” of snow anticipated.
Secured Site , Trailer and Generator.
Blizzard conditions forecasted starting Monday and ending Tuesday night. Up to 26” of snow anticipated. Only received approximately 6” to 8” of snow. High winds both Monday night through Tuesday. No Work due to inclement weather.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/27/2015 DAILY REPORT NUMBER: 245
Classifications No.
Men
Names
Men
Equip.
Quality Control 1 5 Air Compressors
Field Project Mgr 1 5 0 0 Cranes
Dredging Foreman Dozers
Shoreman Front End
Loaders
Carpenters Paving
Machines
Mechanics Rollers
Oilers Tractors
Operator-Exc. 0 0 Welding
Machines
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 2
Manhours Today 10
Manhours
Previous
Manhours To 9416
Date
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/27/2015 Daily Report Number: 245
Weather: Blizzard Forecasted Precipitation: 6.0 in. Temp: Min. 19 Max. 32
Wind Speed: 14-23 MPH from : NE--NNW Gusts: 31 MPH
Work Control Feature: No Work—Inclement Weather, Portion of Day Suitable for Work: 10%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 9 Merit Belford CDF N-61, QC
Merit Belford, CDF N-61/ PM
3 Operators 0 Merit Belford, CDF N-61/ No Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
N-61
No work due to inclement weather forecasted.
5 Belford, CDF
Inspected site. Blizzard conditions forecasted ending Tuesday night. Up to 26” of snow anticipated.
Secured Site , Trailer and Generator.
Blizzard conditions forecasted ending Tonight. Up to 26” of snow anticipated. Only received approximately 6” to 8” of snow. High winds through Tuesday. No Work due to inclement weather.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/28/2015 DAILY REPORT NUMBER: 246
Name
Men
Equip.
Quality Control 1 8 Air Compressors
Field Project Mgr 1 4 0 0 Cranes
Dredging Foreman Dozers
Shoreman Front End Loaders
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 2
Manhours Today 12
Manhours Previous 9416
Manhours To Date 9428
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/28/2015 Daily Report Number: 246
Weather: Partly Sunny Precipitation: .00 in. Temp: Min. 15 Max. 32
Wind Speed: 13-21 MPH from : WNW Gusts: 26 MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 8 Merit Belford CDF N-61, QC
Merit Belford, CDF N-61/ P/M
3 Operators 0 Merit Belford, CDF N-61/ No Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
N-61
QC, Expecting delivery of dredging materials and equipment this week.
5 Belford, CDF
Inspected site, everything fared well.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/29/2015 DAILY REPORT NUMBER: 247
Classifications
No.
Men
Name or Sub
Men
Equip.
Quality Control 1 8 Air Compressors
Field Project Mgr 0 0 Cranes
Dredging Foreman Blue Water
Dredging
1 9 Dozers
Shoreman Blue Water
Dreging
5 45 Front End Loaders
Foreman Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E. 0 0 Track Skid-steer
Operator-Skid Steer Excavator
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 7
Manhours Today 65
Manhours Previous 9428
Manhours To Date 9493
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/29/2015 Daily Report Number: 247
Weather: Partly Sunny Precipitation: .00 in. Temp: Min. 10 Max. 33
Wind Speed: 6-8 MPH from : WSW Gusts: -- MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 11 Merit Belford CDF N-61, QC
2 Dredging
Foreman
Blue Water
Dredging
Belford, CDF N-61/ Site Work
3 Shoreman 9 Blue Water
Dredging
Belford, CDF N-61/ Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
Komatsu PC270LC-7L 1/29/2015 1/29/2015 4 0
1-3 Belford, CDF
N-61
QC, Expecting delivery of dredging materials and equipment this week. Blue Water Dredging Co. foreman and a crew of 5 men showed up at 8:00 am. They began cleaning out the conex container left on site by Island Breeze. Excavator arrived at 1:00 pm, and the crew started to assemble the lengths of pipe. Assembled 2-1000 ft.
sections on the beach.
Excavator Komatsu PC270LC
No violations observed. Informed men of the safety requirements for the land work of assembling pipe. Inspected and observed the operation of the excavator.
Mike the foreman for Blue Water Dredging expresses concern that the outlet pipes might not handle the capacity of discharge required to maintain a constant dredging operation.
Informed him that this had been brought up numerous times and in the pre-con meetings, but the
ACOE felt that 2-12” pipes would provide adequate flow and the issue did not need to be addressed at the time.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/30/2015 DAILY REPORT NUMBER: 248
Men
Equip.
Quality Control 1 11 Air Compressors
Field Project Mgr 1 10 0 0 Cranes
Dredging Foreman Blue Water
Dredging
1 9 Dozers
Shoreman Blue Water
Dredging
5 45 Front End Loaders
Foreman Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator 1
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 8
Manhours Today 75
Manhours Previous 9493
Manhours To Date 9568
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/30/2015 Daily Report Number: 248
Weather: Partly Sunny Precipitation: .00 in. Temp: Min. 17 Max. 37
Wind Speed: 11-28 MPH from : WNW Gusts: 39 MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 11 Merit Belford CDF N-61, QC
Dredging
Belford, CDF N-61/ Site Work
3 Shoreman 9 Blue Water
Dredging
Belford, CDF N-61/ Site Work
4 PM 10 Merit Belford CDF N-61, PM
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
Komatsu PC270LC-7L 1/29/2015 1/29/2015 9 0
1 Belford, CDF
N-61
QC
2-3 Belford, CDF Crew assembled 2-1000’ sections of pipe for a total of 4-1000’ sections.
While crew was assembling HDPE pipe two of the flanged ends came off at the fuse. One end was reportedly already off prior to moving the pipe and the other had come off during the moving of the pipe for assembly. of Blue water commented that the cold temperatures could be a factor in the fused joint failure but had no way to determine the integrity of the fused joint prior to the failure.
No violations observed. Informed men of the safety requirements for the land work of assembling pipe. Inspected and observed the operation of the excavator.
for Blue Water Dredging expresses concern that the outlet pipes might not handle the capacity of discharge required to maintain a constant dredging operation.
Informed him that this had been brought up numerous times and in the pre-con meetings, but the
ACOE felt that 2-12” pipes would provide adequate flow and the issue did not need to be addressed at the time.
While crew was assembling HDPE pipe two of the flanged ends came off at the fuse. One end was reportedly already off prior to moving the pipe and the other had come off during the moving of the pipe for assembly. of Blue water commented that the cold temperatures could be a factor in the fused joint failure but had no way to determine the integrity of the fused joint prior to the failure.
Gale force wind warnings New York Harbor beginning at 6:00 pm tonight through tomorrow until 6:00 pm. Wind speeds of 30-40 knots, with gusts up to 50 knots.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 1/31/2015 DAILY REPORT NUMBER: 249
Classifications
No.
Men
Name
Men
Equip.
Quality Control 1 7 Air Compressors
Field Project Mgr 1 4 0 0 Cranes
Dredging Foreman Blue Water
Dredging
1 4 Dozers
Shoreman Blue Water
Dredging
5 20 Front End Loaders
Foreman Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 8
Manhours Today 31
Manhours Previous 9531
Manhours To Date 9562
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 1/31/2015 Daily Report Number: 249
Weather: Mostly Cloudy Precipitation: .00 in. Temp: Min. 12 Max. 24
Wind Speed: 18-28 MPH from : WNW Gusts: 39 MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 0%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 7 Merit Belford CDF N-61, QC
Dredging
Belford, CDF N-61/ Site Work
3 Shoreman 4 Blue Water
Dredging
Belford, CDF N-61/ Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
Komatsu PC270LC-7L 1/29/2015 1/29/2015 4 0
N-61
QC
2-3 Belford, CDF Due to gale force winds and cold temperatures (wind chill),crew was unable to work.
Due to gale force winds and cold temperatures (wind chill),crew was unable to work.
Gale force wind warnings New York Harbor beginning at 6:00 pm 1/30/2015 through
1/31/2015 until 6:00 pm. Wind speeds of 30-40 knots, with gusts up to 50 knots.
Snow with accumulations of 4”- 8” expected Sunday 2/1/2015, through Monday 2/2/2015 expected.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 2/1/2015 DAILY REPORT NUMBER: 250
Classifications
No.
Men
Name/ Sub
Men
Equip.
Quality Control 1 7 Air Compressors
Field Project Mgr 1 7 0 0 Cranes
Dredging Foreman Blue Water
Dredging
1 6 Dozers
Shoreman Blue Water
Dredging
5 30 Front End Loaders
Foreman Mortar Mixers
Carpenters Paving Machines
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator 1
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 7
Manhours Today 43
Manhours Previous 9562
Manhours To Date 9605
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 2/1/2015 Daily Report Number: 250
Weather: Cloudy Precipitation: .00 in. Temp: Min. 17 Max. 37
Wind Speed: 5-12 MPH from : WSW Gusts: -- MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 7 Merit Belford CDF N-61, QC
Dredging
Belford, CDF N-61/ Site Work
3 Shoreman 6 Blue Water
Dredging
Belford, CDF N-61/ Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
Komatsu PC270LC-7L 1/29/2015 1/29/2015 6 0
N-61
QC
2-3 Belford, CDF Prepped pipe for dredging operations. Assembled pipe and removed pipe along the Ferry Terminal berm. Moved a single run of pipe to along the toe of the slope from approximately station 23+00 to
13+00 of the CDF to position it for placement once the dredge gets here.
Blue Water worked six hours at the site then moved to an offsite shop to finish the day out prepping bouys and other miscellaneous materials necessary for the dredging operation.
Winter Weather warning in effect for tonight and Monday with reports of 1” to 8” of snow expected along with freezing rain. We’ll see...
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 2/2/2015 DAILY REPORT NUMBER: 251
Classifications
No.
Men
Men
Equip.
Quality Control 1 4 Air Compressors
Field Project Mgr 1 4 N. Powell Co. 0 0 Cranes
Dredging Foreman Blue Water
Dredging
0 0 Dozers
Shoreman Blue Water
Dredging
0 0 Front End Loaders
Foreman Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator 1
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 1
Manhours Today 4
Manhours Previous 9642
Manhours To Date 9646
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 2/2/2015 Daily Report Number: 251
Weather: Heavy rains, turning to snow Precipitation: 1.06 in. Temp: Min. 15 Max. 44
Wind Speed: 8-16 MPH from : ENE Gusts: 20 MPH
Work Control Feature: No Work--Inclement Weather Portion of Day Suitable for Work: 0%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 4 Merit Belford CDF N-61, QC
2 PM 4 Merit Belford CDF N-61, QC
3 Dredging
Dredging
Belford, CDF N-61/ Site Work—No work onsite due to inclement weather.
4 Shoreman 0 Blue Water
Dredging
Belford, CDF N-61/ Site Work—No work onsite due to inclement weather.
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
Komatsu PC270LC-7L 1/29/2015 1/29/2015 0 0
N-61
QC
2-3 Belford, CDF No work onsite due to inclement weather.
Inspected site, everything faring well.
Blue Water Dredging is going to work off site in there shop with a skeleton crew to get some odds and ends prepared.
Heavy rain turning to snow forecasted today. No work due to inclement weather.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 2/2/2015 DAILY REPORT NUMBER: 251
N-POWELL No. Man No. Man # Pcs. of
Classifications
Men Hrs. Subcontractors Men Hrs. Equipment Equip.
Quality Control 1 4 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging Foreman Blue Water
Dredging
0 0 Dozers
Shoreman Blue Water
Dredging
0 0 Front End Loaders
Foreman Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator 1
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 1
Manhours Today 4
Manhours Previous 9642
Manhours To Date 9646
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 2/2/2015 Daily Report Number: 251
Weather: Heavy rains, turning to snow Precipitation: 1.06 in. Temp: Min. 15 Max. 44
Wind Speed: 8-16 MPH from : ENE Gusts: 20 MPH
Work Control Feature: No Work--Inclement Weather Portion of Day Suitable for Work: 0%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 4 Merit Belford CDF N-61, QC
Dredging
Belford, CDF N-61/ Site Work—No work onsite due to inclement weather.
3 Shoreman 0 Blue Water
Dredging
Belford, CDF N-61/ Site Work—No work onsite due to inclement weather.
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
N-61
2-3 Belford, CDF No work onsite due to inclement weather.
Blue Water Dredging is going to work off site in there shop with a skeleton crew to get some odds and ends prepared.
Heavy rain turning to snow forecasted today. No work due to inclement weather.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 2/3/2015 DAILY REPORT NUMBER: 252
Classifications
No.
Men
Men
Equip.
Quality Control 1 10 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging
Superintendent
Blue Water
Dredging
1 8 Dozers
Shoreman Blue Water
Dredging
6 48 Front End Loaders
Field Supervisor 1 10 Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator 1
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 9
Manhours Today 76
Manhours Previous 9646
Manhours To Date 9722
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 2/3/2015 Daily Report Number: 252
Weather: Cloudy Precipitation: .00 in. Temp: Min. 12 Max.24
Wind Speed: 1-10 MPH from : SW Gusts: 20 MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 10 Merit Belford CDF N-61, QC
Superintendent
Dredging
KT Marine, Perth Amboy, NJ—Received delivery of dredge and began assembly.
3 Shoreman 48 Blue Water
Dredging
KT Marine, Perth Amboy, NJ—Received delivery of dredge and began assembly.
4 Field
Supervision
10 Merit Belford, CDF N-61/Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
N-61
QC
2-3 Belford, CDF KT Marine, Perth Amboy, NJ—Received delivery of dredge and began assembly.
Received Ellicott dredge at KT Marine in Perth Amboy, NJ.
Received Ellicott Dredge at KT Marine and crew began assembly.
Reminded the dredge superintendent that it is required that the men have on hard hats and hi-vis apparel.
Dredging crew received the dredge from Ellicott at KT Marine in Perth Amboy, NJ and began assembly of it. The plan is to spend the next two days assembling it and to fill it with fuel on Thursday. A tug boat will then bring the dredge to Belford for Friday when dredging will commence. The pipe at the site is in 1000’ lengths and still needs completely assembled and placed.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 2/3/2015 DAILY REPORT NUMBER: 252
Classifications
No.
Men
Men
Equip.
Quality Control 1 10 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging
Superintendent
Blue Water
Dredging
1 8 Dozers
Shoreman Blue Water
Dredging
6 48 Front End Loaders
Field Supervisor 1 10 Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 0 0 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator 1
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 9
Manhours Today 76
Manhours Previous 9646
Manhours To Date 9722
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 2/3/2015 Daily Report Number: 252
Weather: Cloudy Precipitation: .00 in. Temp: Min. 12 Max.24
Wind Speed: 1-10 MPH from : SW Gusts: 20 MPH
Work Control Feature: Site Work Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 10 Merit Belford CDF N-61, QC
Dredging
KT Marine, Perth Amboy, NJ—Received delivery of dredge and began assembly.
3 Shoreman 48 Blue Water
Dredging
KT Marine, Perth Amboy, NJ—Received delivery of dredge and began assembly.
4 Field
Supervision
10 Merit Belford, CDF N-61/Site Work
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
2-3 Belford, CDF KT Marine, Perth Amboy, NJ—Received delivery of dredge and began assembly.
Received Ellicott dredge at KT Marine in Perth Amboy, NJ.
Received Ellicott Dredge at KT Marine and crew began assembly.
Reminded the dredge superintendent that it is required that the men have on hard hats and hi-vis apparel.
Dredging crew received the dredge from Ellicott at KT Marine in Perth Amboy, NJ and began assembly of it. The plan is to spend the next two days assembling it and to fill it with fuel on Thursday. A tug boat will then bring the dredge to Belford for Friday when dredging will commence. The pipe at the site is in 1000’ lengths and still needs completely assembled and placed.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 2/4/2015 DAILY REPORT NUMBER: 253
Classifications
No.
Men
Men
Equip.
Quality Control 1 10 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging
Superintendent
Blue Water
Dredging
1 10 Dozers
Shoreman Blue Water
Dredging
6 60 Front End Loaders
Field Supervisor 1 10 Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E.
Loader
0 0 Track Skid-steer
Operator-Skid Steer Excavator 1
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 9
Manhours Today 90
Manhours Previous 9722
Manhours To Date 9812
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 2/4/2015 Daily Report Number: 253
Weather: Partly Cloudy Precipitation: .00 in. Temp: Min. 17 Max. 42
Wind Speed: 5-12 MPH from : SSW Gusts: 16 MPH
Work Control Feature: Site Work/Dredge Assy. Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 10 Merit Belford CDF, QC
Dredging
KT Marine, Perth Amboy, NJ—Worked on dredge assembly.
3 Shoreman 60 Blue Water
Dredging
KT Marine, Perth Amboy, NJ—Worked on
Dredge assembly.
4 Field Superintendent
10 Merit Belford CDF, Assist with spill box preparations.
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
1 Belford, CDF QC
2-3 KT Marine, Perth
Amboy, NJ
KT Marine, Perth Amboy, NJ—Worked on dredge assembly.
4 Belford CDF Gathered and checked stop logs for spill box.
Checked site and spill box structure.
No Materials received.
of Merit is trying to organize a coordination meeting with the ACOE, Monmouth County, and all other entities affected or involved with this phase of the project.
Meeting is set for Friday at 10:00 AM at the Belford Ferry Terminal Building.
Reminded men hi-vis is a requirement.
Still trying to locate a slip at Belford for refueling and docking.
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
DATE: 2/5/2015 DAILY REPORT NUMBER: 254
Classifications
No.
Men
Men
Equip.
Quality Control 1 10 Air Compressors
Field Project Mgr N. Powell Co. 0 0 Cranes
Dredging
Superintendent
Blue Water
Dredging
1 10 Dozers
Shoreman Blue Water
Dredging
6 60 Front End Loaders
Field Supervisor Mortar Mixers
Geo- Tech Pans
Carpenters Paving Machines
SSHO 1 8 Pumps
Mechanics Rollers
Oilers Tractors
Operator-F. E. 0 0 Track Skid-steer
Operator-Skid Steer Excavator 1
Pipe Layers Utility Vehicle
Pump Operators F. E. Loader
Truck Drivers Backhoe
Welders Water Truck
Block Masons
Laborers
Surveyor # of Men Today 9
Manhours Today 88
Manhours Previous 9812
Manhours To Date 9900
M.E.R.I.T., Inc. W912DS-14-B-0001
211 Warren Street Maintenance Dredging
Newark, NJ 07103 Shoal Harbor & Compton Creek, NJ
Date: 2/5/2015 Daily Report Number: 254
Weather: Partly Cloudy Precipitation: .00 in. Temp: Min. 14 Max. 39
Wind Speed: 11-26 MPH from : WNW Gusts: 36 MPH
Work Control Feature: Site Work/Dredge Assy. Portion of Day Suitable for Work: 100%
1. Contractor/Subcontractors and Area of Responsibility
NO. TRADE HOURS EMPLOYER LOCATION/DECRIPTION OF WORK
1 QCM 10 Merit KT Marine, Perth Amboy, NJ, QC
Dredging
KT Marine, Perth Amboy, NJ—Worked on dredge assembly.
3 Shoreman 48 Blue Water
Dredging
KT Marine, Perth Amboy, NJ—Worked on
Dredge assembly.
4 SSHO 6 Merit KT Marine, Perth Amboy, NJ--SSHO
DEPARTURE
DATE OF
SECURITY
CHECK
HOURS
USED
HOURS
IDLE
HOURS
1 KT Marine, Perth
Amboy, NJ
QC, Inspected and observed assembly of dredge. ACOE was supposed to have a safety man show up to inspected and observe the assembly of the dredge also. Did not see anyone from the ACOE onsite.
2-3 KT Marine, Perth
Amboy, NJ
KT Marine, Perth Amboy, NJ—Worked on dredge assembly.
4 KT Marine, Perth
Amboy, NJ
Inspected and observed assembly of dredge. ACOE was supposed to have a safety man show up to inspected and observe the assembly of the dredge also. Did not see anyone from the ACOE onsite.
Inspected and observed the assembly of the dredge.
No Materials received.
of Merit is trying to organize a coordination meeting with the ACOE, Monmouth County, and all other entities affected or involved with this phase of the project.
Meeting is set for Friday at 10:00 AM at the Belford Ferry Terminal Building.
Inspected and observed assembly of dredge. ACOE was supposed to have a safety man show up to inspected and observe the assembly of the dredge also. Did not see anyone from the
ACOE onsite.
Merit provided the men with hi-vis safety vest.
Still trying to locate a slip at Belford for refueling and docking.
M.E.R.I.T., Inc.