This document contains an amendment to the specifications for a federal construction contract opportunity and the related opportunity notice. The amendment extends the contract completion deadline from 400 to 460 calendar days. The construction project is located in Union Beach, New Jersey and includes beach renourishment, construction of pedestrian crossovers, drainage modifications, demolition and restoration of existing structures, installation of dunes and sand fencing. The estimated cost is between $35-45 million. The solicitation will be issued on May 18, 2022 by the U.S. Army Corps of Engineers, New York District for unrestricted competition. The response deadline will be approximately 30 days later.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Union Beach Phase I UNIONBEACHPIH1 Amendment 001

SECTION 01 11 00

SUMMARY OF WORK

08/15, CHG 2: 08/21

PART 1 GENERAL

1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and

(iii) complete the entire work ready for use, not later than 400 460 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises. (FAR 52.212-3)

b. All work shall be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes two terminal groins, hydraulic beachfill placement, crossovers, outfall extension, splash pad, drainage modifications, dune planting, sand fence, demolition, excavation & regrading and incidental related work.

1.2.1.1 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

This project is estimated between $25 million and $100 million.

1.2.2 Location

The work is located at the Union Beach, Monmouth County, New Jersey, on the waterfront Along Front Street/Union Avenue, from Dock Streeet to the Flat Creek bridge.

1.3 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

SECTION 01 11 00 Page 1

Union Beach Phase I UNIONBEACHPIH1 Amendment 001

1.4 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING

Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy shall be provided to the Contracting Officer. The Contractor must hold and save the Government, its officers, and agents free from liability arising from trespassing or damage occasioned by his operations.

1.5 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

1.5.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 2

01 11 00 - SUMMARY OF WORK
PART 1 GENERAL
1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.1.1 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

1.2.2 Location

1.3 EXISTING WORK
1.4 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING
1.5 LOCATION OF UNDERGROUND UTILITIES
1.5.1 Notification Prior to Excavation
PART 2 PRODUCTS
PART 3 EXECUTION