Amendment 000_ Specs 101 11 00.pdf
PDF 12 KB Posted
- Solicitation number
- W912DS22B0011
About this file
This document provides details for an upcoming federal construction contract opportunity with the U.S. Army Corps of Engineers Engineering District New York. The solicitation seeks bids for the construction of Phase 1 of the Union Beach Hurricane and Storm Damage Reduction Project in Monmouth County, New Jersey. Work will include beach fill renourishment of 500,000-1,000,000 cubic yards, construction of pedestrian crossovers, drainage modifications, demolition and restoration, vibration monitoring, and dune planting. The estimated value of the project is between $35-45 million. Bids are due 30 days after issuance of the invitation for bid around May 18, 2022. The contract period of performance is 820 calendar days. Interested parties can access the full solicitation on the Contract Opportunities website. The NAICS code for the work is 237990 and the small business size standard is $39.5 million.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Union Beach Phase I UNIONBEACHPIH1 Amendment 001
SECTION 01 11 00
SUMMARY OF WORK
08/ 15, CHG 2: 08/ 21
PART 1 GENERAL
1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
a. The Contractor shall be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and
(iii) complete the entire work ready for use, not later than 540820 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises. (FAR 52.212-3)
b. All work shall be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes two terminal groins, hydraulic beachfill placement, crossovers, outfall extension, splash pad, drainage modifications, dune planting, sand fence, demolition, excavation & regrading and incidental related work.
1.2.1.1 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS
This project is estimated between $25 million and $100 million.
1.2.2 Location
The work is located at the Union Beach, Monmouth County, New Jersey, on the waterfront Along Front Street/Union Avenue, from Dock Streeet to the Flat Creek bridge.
1.3 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
SECTION 01 11 00 Page 1
Union Beach Phase I UNIONBEACHPIH1 Amendment 001
1.4 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING
Do not inflict damage upon land and properties outside the authorized construction area by unwarranted entry upon, passage through, damage to, or disposal of, material on such land or property. The Contractor may make a separate agreement with any other party, regarding the use of, or right to, land or facilities outside the contract area. If such an agreement is made, it must be in writing and a copy shall be provided to the Contracting Officer. The Contractor must hold and save the Government, its officers, and agents free from liability arising from trespassing or damage occasioned by his operations.
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
| 01 11 00 - SUMMARY OF WORK |
| PART 1 GENERAL |
| 1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK |
| 1.2 WORK COVERED BY CONTRACT DOCUMENTS |
| 1.2.1 Project Description |
| 1.2.1.1 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS |
1.2.2 Location
| 1.3 EXISTING WORK |
| 1.4 AUTHORIZED CONSTRUCTION AREA AND TRESPASSING |
| 1.5 LOCATION OF UNDERGROUND UTILITIES |
| 1.5.1 Notification Prior to Excavation |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |