Section 01 78 02 - Page 1 of 17
SECTION 01 78 02
CLOSEOUT SUBMITTALS
1.0 OVERVIEW
1.1. REFERENCES
1.2. SUBMITTALS
1.3. PROJECT RECORD DOCUMENTS
1.4. EQUIPMENT DATA
1.5. CONSTRUCTION WARRANTY MANAGEMENT
1.6. MECHANICAL TESTING, ADJUSTING, BALANCING AND COMMISSIONING
1.7. OPERATION AND MAINTENANCE MANUALS
1.8. FIELD TRAINING
1.9. PRICING OF CONTRACTOR-FURNISHED AND INSTALLED PROPERTY AND
GOVERNMENT-FURNISHED CONTRACTOR-INSTALLED PROPERTY
1.10. REDZONE MEETING
1.11. FINAL CLEANING
Section 01 78 02 - Page 2 of 17
SECTION 01 78 02
CLOSEOUT SUBMITTALS
1.0 OVERVIEW
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E1971 (2005) Stewardship for the Cleaning of Commercial and Institutional Buildings
GREEN SEAL (GS)
GS-37 (2000; R 2009) Industrial and
Institutional Cleaners
U.S. ARMY CORPS OF ENGINEERS (USACE)
TR-06-X (2006; Supplement 2009) A/E/C (Architectural, Engineering, and Construction) CADD Standard - Release 3.0
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-300-08 (2009, with Change 1) Criteria for Transfer and
Acceptance of DoD Real Property
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Designer of Record or for information only. Submit the following in accordance with Section 01 33 00:
SD-02 Shop Drawings
- As-Built Drawings; G o Drawings showing final as-built conditions of the project. Provide electronic drawing files as specified in section Appendix A-4, 3 sets of blue-line prints and one set of the approved working as-built drawings
SD-03 Product Data
- As-Built Record of Equipment and Materials o Two copies of the record listing the as-built materials and equipment incorporated into the construction of the project
- Construction Warranty Management Plan o Three sets of the construction warranty management plan containing information relevant to the warranty of materials and equipment incorporated into the construction project, including starting date of warranty of construction. Furnish with each warranty the name, address, and telephone number of each guarantor’s representatives nearest the project location.
- Warranty Tags o Two record copies of the warranty tags showing the layout and design
- Final Cleaning o Two copies of the listing of completed final clean-up items
Section 01 78 02 - Page 3 of 17
SD-08 Manufacturer's Instructions
- Preventative Maintenance
- Posted Instructions
SD-10 Operation and Maintenance Data
- Operation and Maintenance Manuals
SD-11 Closeout Submittals
- Record Drawings
1.3 PROJECT RECORD DOCUMENTS
1.3.1 As-Built Drawings - G
An as-built drawing is a construction drawing revised to reflect the final as-built conditions of the project as a result of modifications and corrections to the project design required during construction. The final as-built drawings shall not have the appearance of marked up drawings, but that of professionally prepared drawings as if they were the "as designed" drawings.
1.3.2. Maintenance of As-Built Drawings
1.3.2.1. The Configuration Management Plan shall describe how the Contractor will maintain up-to-date drawings, how it will control and designate revisions to the drawings and specifications (In accordance with Special Contract Requirement: the Designer of Record's approval is necessary for any revisions to the accepted design).
1.3.2.2. Make timely updates, carefully maintaining a record set of working as-built drawings at the job site, marked in red, of all changes and corrections from the construction drawings. Enter changes and corrections on drawings promptly to reflect "Current Construction". Perform this update no less frequently than weekly for the blue line drawings and update no less frequently than quarterly for the CADD/CAD, which were prepared previously in accordance with Appendix A-4. Include a confirmation that the as-builts are up to date with the submission of the monthly project schedule.
1.3.2.3. If the DB Contractor fails to maintain the as-built drawings as required herein, the Government will retain from the monthly progress payment, an amount representing the estimated monthly cost of maintaining the as-built drawings. Final payment with respect to separately priced facilities or the contract as a whole will be withheld until the Contractor submits acceptable as-built drawings and the Government approves them.
1.3.2.4. The marked-up set of drawings shall reflect any changes, alterations, adjustments or modifications. Changes must be reflected on all sheets affected by the change. Changes shall include marking the drawings to reflect structural details, foundation layouts, equipment sizes, and other extensions of design.
1.3.2.5. Typically, room numbers shown on the drawings are selected for design convenience and do not represent the actual numbers intended for use by the end user. Final as-built drawings shall reflect actual room numbers adopted by the end user.
1.3.2.6. If there is no separate contract line item (CLIN) for as-built drawings, the Government will withhold the amount of $35,000, or 1% of the present construction value, whichever is the greater, until the final as-built drawing submittal has been approved by the Government.
1.3.3. Underground Utilities
The drawings shall indicate, in addition to all changes and corrections, the actual location, kinds and sizes of all sub-surface utility lines. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, the as-built drawings shall
Section 01 78 02 - Page 4 of 17 show, by offset dimensions to two permanently fixed surface features, the end of each run including each change in direction. Locate Valves, splice boxes and similar appurtenances by dimensioning along the utility run from a reference point. Record average elevation of the top of each run or underground structure.
1.3.4. Partial Occupancy
For projects where portions of construction are to be occupied or activated before overall project completion, including portions of utility systems, supply as-built drawings for those portions of the facility being occupied or activated at the time the facility is occupied or activated. Show this same as-built information previously furnished on the final set of as-built drawings.
1.3.5. As-Built Conditions That Are Different From the Construction Drawings
Accurately reflect all as-built conditions that are different, such as dimensions, road alignments and grades, and drainage and elevations, from the construction drawings on each drawing. If the as-built condition is accurately reflected on a shop drawing, then furnish that shop drawing in CADD format. Reference the final as-built construction drawing the shop drawing file that includes the as-built information. In turn, the shop drawing shall reference the applicable construction as-built drawing. Delete any options shown on drawings and not selected clearly reflect options selected on final as-built drawings.
1.3.6. Additional As-Built Information That Exceeds the Detail Shown On The Construction
Drawings:
These as-built conditions include those that reflect structural details, foundation layouts, equipment, sizes, mechanical and electrical room layouts and other extensions of design, that were not shown in the project design documents because the exact details were not known until after the time of approved shop drawings.
It is recognized that these shop drawing submittals (revised showing as-built conditions) will serve as the as-built record without actual incorporation into the construction drawings, piping, and equipment drawings.
Include locations of all explorations, logs of all explorations, and results of all laboratory testing, including those provided by the Government. Furnish all such shop drawings in CADD/CAD format. Include fire protection details, such as wiring, performed for the design of the project.
1.3.7. Final As-Built Drawings
Submit final as-built CADD/CAD and Facility Data files at the time of Beneficial Occupancy of the project or at a designated phase of the project. In the event the Contractor accomplishes additional work after this submittal, which changes the as-built conditions, submit a new DVD with all drawing sheets and three blue-line copies of affected sheets which depict additional changes.
1.3.8. Title Blocks
In accordance with the configuration management plan, clearly mark title blocks to indicate final as-built drawings.
1.4. EQUIPMENT DATA
1.4.1. Real Property Equipment
Provide an Equipment-in-Place list of all installed equipment furnished under this contract. Include all information usually listed on manufacturer's name plate. Include the cost of each piece of installed property F.O.B. construction site. For each of the items which is specified herein to be guaranteed for a specified period from the date of acceptance thereof, provide the following information: The name, serial and model number address of equipment supplier, or manufacturer originating the guaranteed item. The Contractor's guarantee to the Government of these items will not be limited by the terms of any manufacturer's guarantee to the Contractor. Furnish the list as one (1) reproducible and three (3) copies thirty (30) calendar days before completion of any segment of the contract work which has an incremental completion date.
1.4.2. Maintenance and Parts Data
Section 01 78 02 - Page 5 of 17
Furnish a brochure, catalog cut, parts list, manufacturer's data sheet or other publication showing detailed parts data on all other equipment subject to repair and maintenance procedures not otherwise required in Operations and Maintenance Manuals specified elsewhere in this contract. Distribution of directives shall follow the same requirements as listed in paragraph above.
1.4.3. Construction Specifications
Furnish permanent electronic files of final as-built construction specifications, including modifications thereto, with the as-built drawings.
1.5. CONSTRUCTION WARRANTY MANAGEMENT
The warranty covers all constructed items in the base contract. If the optional CLIN to transfer ownership is awarded the warranty shall cover the IHUs in their entirety. The warranty period for the IHUs shall be one year and shall begin at the time of the ownership transfer. Cost of the IHUs warranty shall be expressed in the optional CLIN to transfer ownership.
1.5.1. Prior to the end of the one year warranty, the Government may conduct an infrared roof survey on any project involving a membrane roofing system. This survey will be conducted in accordance with ASTM C1153-90, "Standard Practice for Location of Wet Insulation in Roofing Systems Using Infrared Imaging". The Contractor shall replace all damaged materials and locate and repair sources of moisture penetration.
1.5.2. Management
1.5.2.1. Warranty Management Plan
The warranty plan shall be updated to address warranty if IHUs if the optional CLIN to transfer ownership is awarded. The base warranty plan needs only to address warranty of construction items under the base bid.
Develop a warranty management plan containing information relevant to the clause Warranty of Construction in FAR 52.246-21. Submit the warranty management plan for Government approval at least 30 days before the planned pre-warranty conference. In the event of phased turn-over of the contract, update the Warranty Management Plan as necessary to include latest information required. Include all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan shall be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract. The term "status" as indicated below shall include due date and whether item has been submitted or was accomplished. Submit warranty information made available during the construction phase prior to each monthly pay estimate. Assemble information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period shall begin on the date of project acceptance and shall continue for the full product warranty period. The Contractor, Government, including the Customer Representative shall jointly conduct warranty inspections, 4 months and 9 months, after acceptance. The warranty management plan shall include, but shall not be limited to, the following information:
(1) Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the contractors, subcontractors, manufacturers or suppliers involved.
(2) Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers, and for all commissioned systems such as fire protection and alarm systems, sprinkler systems, lightning protection systems, etc.
(3) A list for each warranted equipment, item, feature of construction or system indicating:
(i) Name of item.
Section 01 78 02 - Page 6 of 17
(ii) Model and serial numbers.
(iii) Location where installed.
(iv) Name and phone numbers of manufacturers or suppliers.
(v) Names, addresses and telephone numbers of sources of spare parts.
(vi) Warranties and terms of warranty. Include one-year overall warranty of construction. Indicate those items which have extended warranties with separate with separate warranty expiration dates.
(vii) Cross-reference to warranty certificates as applicable.
(viii) Starting point and duration of warranty period.
(ix) Summary of maintenance procedures required to continue the warranty in force.
(x) Cross-reference to specific pertinent Operation and Maintenance manuals.
(xi) Organization, names and phone numbers of persons to call for warranty service.
(xii) Typical response time and repair time expected for various warranted equipment.
(4) The Contractor’s plans for attendance at the 4 and 9 month post-construction warranty inspections conducted by the Government.
(5) Procedure and status of tagging all equipment covered by extended warranties.
(6) Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
1.5.3. Performance Bond
1.5.3.1. The Contractor's Performance Bond will remain effective throughout the construction warranty period.
1.5.3.2. In the event the Contractor or his designated representative(s) fails to commence and diligently pursue any work required under this clause, and in a manner pursuant to the requirements thereof, the Government shall have a right to demand that said work be performed under the Performance Bond by making written notice on the surety. If the surety fails or refuses to perform the obligation it assumed under the Performance Bond, the Government shall have the work performed by others, and after completion of the work, may make demand for reimbursement of any or all expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
1.5.3.3. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the Contractor's expense, the Government will have the right to recoup expenses from the bonding company.
1.5.3.4. Following oral or written notification of required warranty repair work, the Contractor will respond as dictated by para. 1.5.5. Written verification will follow oral instructions. Failure of the Contractor to respond will be cause for the Government to proceed against the Contractor as outlined in the paragraph
1.5.5.5 and/or above.
1.5.4. Pre-Warranty Conference
Prior to contract completion, or completion of any phase or portion of contract to be turned over, and at a time designated by the Contracting Officer, the Contractor shall meet with the Government to develop a mutual understanding with respect to the requirements of this clause. Communication procedures for Contractor notification of warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Government for the execution of the
Section 01 78 02 - Page 7 of 17 construction warranty shall be established/reviewed at this meeting. In connection with these requirements and at the time of the Contractor's quality control completion inspection, the Contractor will furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue warranty work action on behalf of the Contractor. This point of contact will be located within the local service area of the warrantied construction, will be continuously available, and will be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of his responsibilities in connection with other portions of this provision.
1.5.5. Contractors Response To Warranty Service Requirements.
Following Government oral or written notification, which may include authorized installation maintenance personnel, the Contractor shall respond to warranty service requirements in accordance with the "Warranty Service Priority List" and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. The report shall include the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and backcharge the construction warranty payment item established.
1.5.5.1. First Priority Code 1 Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
1.5.5.2. Second Priority Code 2 Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
1.5.5.3. Third Priority Code 3 All other work to be initiated within 3 work days and work continuously to completion or relief.
1.5.5.4. The "Warranty Service Priority List" is as follows:
Code 1 – Air Conditioning System
(a) Buildings with computer equipment.
(b) Carracks, mess halls (entire building down).
Code 2 – Air Conditioning Systems
(a) Recreational support.
(b) Air conditioning leak in part of building, if causing damage.
(c) Air conditioning system not cooling properly
(d) Admin building with Automated Data Processing (ADR) equipment not on priority list.
Code 1 – Doors
(a) overhead doors not operational
Code 1 – Electrical
(a) Power failure (entire area or any building operational after 1600 hours).
(b) Traffic control devices.
(c) Security lights
(d) Smoke detector and fire alarm systems
(e) Power or lighting failure to an area, facility, portion of a facility, which may adversely impact health, safety, security, or the installation’s mission requirement, or which may result in damage to property.
Code 2 – Electrical
(a) Power failure (no power) for unoccupied buildings or portions thereof or branch circuits within occupied building, not listed as Code 1.
(b) Receptacle and lights, not listed as Code 1.
Code 3 – Electrical
(a) street, parking area lights
Section 01 78 02 - Page 8 of 17
Code 1 – Gas
(a) Leaks and breaks
(b) No gas to cantonment area.
Code 1 – Heat
(a) Area power failure affecting heat.
(b) Heater in unit not working.
Code 2 – Heat
(a) All heating system failures not listed as Code 1
Code 3 – Interior
(a) Floor damage
(b) Paint chipping or peeling
Code 1 – Intrusion Detection System – N/A Code 2 – Intrusion Detection Systems other than those listed under Code 1 Code 1 - Kitchen Equipment
(a) Dishwasher
(b) All other equipment not listed under Code 1.
Code 2 – Plumbing
(a) Flush valves not operating properly
(b) Fixture drain, supply line commode, or water pipe leaking.
(c) Commode leaking at base.
Code 3 – Plumbing
(a) Leaking faucets
Code 1 – Refrigeration
(a) Mess Hall.
(b) Medical Storage.
Code 2- Refrigeration
(a) Mess hall- other than walk-in refrigerators and freezers.
Code 1 – Roof Leaks
(a) Temporary Repairs will be made where major damage to property is occurring.
Code 2 – Roof Leaks
(a) Where major damage to property is not occurring, check for location of leak during rain and complete repairs on a Code 2 basis.
Code 1 – Sprinkler System
(a) All sprinkler systems, valves, manholes, deluge systems, and air systems to sprinklers.
Code 1 – Tank Wash Racks (Bird Baths)
(a) All systems which prevent tank wash.
Code 1 – Water (Exterior)
(a) Normal operation of water pump station.
Section 01 78 02 - Page 9 of 17
Code 2 – Water (Exterior)
(a) No water to facility.
Code 1 – Water, Hot (and Steam)
(a) Barracks (entire building).
Code 2 – Water, Hot
(a) No hot water in portion of building listed under Code 1
1.5.5.5. Should parts be required to complete the work and the parts are not immediately available, the Contractor shall have a maximum of 12 hours after arrival at the job site to provide the Government, with firm written proposals for emergency alternatives and temporary repairs for Government participation with the Contractor to provide emergency relief until the required parts are available on site for the Contractor to perform permanent warranty repair. The Contractors proposals shall include a firm date and time that the required parts shall be available on site to complete the permanent warranty repair. The Government will evaluate the proposed alternatives and negotiate the alternative considered to be in the best interest of the Government to reduce the impact of the emergency condition. Alternatives considered by the Government will include the alternative for the Contractor to "Do Nothing" while waiting until the required parts are available to perform permanent warranty repair. Negotiating a proposal which will require Government participation and the expenditure of Government funds shall constitute a separate procurement action by the using service.
1.5.6. Equipment Warranty Identification Tags
1.5.6.1. Provide warranty identification tags at the time of installation and prior to substantial completion shall provide warranty identification tags on all Contractor and Government furnished equipment which the Contractor has installed.
(a) The tags shall be suitable for interior and exterior locations, resistant to solvents, abrasion, and to fading caused by sunlight, precipitation, etc. These tags shall have a permanent pressure-sensitive adhesive back, and they shall be installed in a position that is easily (or most easily) noticeable. Tag each component of contractor furnished equipment that has differing warranties on its components.
(b) Submit sample tags, representing how the other tags will look, for Government review and approval.
(c) Tags for Warrantied Equipment: The tag for this equipment shall be similar to the following: Exact format and size will be as approved.
EQUIPMENT WARRANTY – CONTRACTOR FURNISHED EQUIPMENT
MFG NAME MODEL NUMBER
SERIAL NUMBER
CONTRACTOR NUMBER
CONTRACTOR NAME
CONTRACTOR WARRANTY EXPIRES
MFG WARRANTY (IES) EXPIRE
EQUIPMENT WARRANTY – GOVERNMENT FURNISHED EQUIPMENT
MFG NAME MODEL NUMBER
SERIAL NUMBER
CONTRACT NUMBER
DATE EQUIPMENT PLACED IN SERVICE
MFG WARRANTY (IES) EXPIRE
Section 01 78 02 - Page 10 of 17
(d) If the manufacturer's name (MFG), model number and serial number are on the manufacturer's equipment data plate and this data plate is easily found and fully legible, this information need not be duplicated on the equipment warranty tag.
1.5.6.2. Execution: Complete the required information on each tag and install these tags on the equipment by the time of and as a condition of final acceptance of the equipment.
1.6 MECHANICAL TESTING, ADJUSTING, BALANCING, AND COMMISSIONING
Submit; all reports, statements, certificates, and completed checklists for testing, adjusting, balancing, and commissioning of mechanical systems prior to final inspection and transfer of the completed facility for approval, as specified in applicable technical specification sections.
1.7 OPERATION AND MAINTENANCE MANUALS
1.7.1. General Requirements
1.7.1.1. In as much as the operations and maintenance manuals are required to operate and maintain the facility, the operations and maintenance (O&M) manuals will be considered a requirement prior to substantial completion of any facility to be turned over to the Government. Beneficial occupancy of all or portions of a facility prior to substantial completion will not relieve the Contractor of liquidated damages, if substantial completion exceeds the required completion date.
1.7.1.2. Provide one permanent electronic copy on CD-ROM and 2 hard copies of the Equipment Operating, Maintenance, and Repair Manuals. Provide separate manuals for each utility system as defined hereinafter. Submit Operations and Maintenance manuals for approval before field training or 90 days before substantial completion (whichever occurs earlier). If there is no separate CLIN for O&M Manuals, the Government will withhold an amount representing $20,000, as non-progressed work, until submittal and approval of all O&M manuals are complete.
1.7.2 Definitions
1.7.2.1. Equipment
A single piece of equipment operating alone or in conjunction with other equipment to accomplish a system function.
1.7.2.2. System
A combination of one or more pieces of equipment which function together to accomplish an intended purpose (i.e. HVAC system is composed of many individual pieces of equipment such as fans, motors, compressors, valves, sensors, relays, etc.)
1.7.3. Hard Cover Binders
The manuals shall be hard cover with posts, or 3-ring binders, so sheets may be easily substituted. Print the following identification on the cover: the words "EQUIPMENT OPERATING, MAINTENANCE, AND REPAIR MANUALS," the project name, building number, and an indication of utility or systems covered, the name of the Contractor, and the Contract number. Manuals shall be approximately 8-1/2 by 11-inches with large sheets folded in and capable of being easily pulled out for reference. All manuals for the project must be similar in appearance, and be of professional quality.
1.7.4 Warning Page
Provide a warning page to warn of potential dangers (if they exist, such as high voltage, toxic chemicals, Section 01 78 02 - Page 11 of 17 flammable liquids, explosive materials, carcinogens, high pressures, etc.). Place the warning page inside the front cover and in front of the title page. Include any necessary Material Safety Data Sheets (MDSD) here.
1.7.5 Title Page
The title page shall include the same information shown on the cover and show the name of the preparing firm and the date of publication.
1.7.6 Table of Contents
Each volume of the set of manuals for this project shall include a table of contents, for the entire set, broken down by volume.
1.7.7 GENERAL
Organize manuals according to the following format, and include information for each item of equipment Submit a draft outline and table of contents for approval at 50% contract completion.
TABLE OF CONTENTS
PART I: Introduction
Equipment Description Functional Description Installation Description
PART II: Operating Principles
PART III: Safety
PART IV: Preventative Maintenance Checklist
Preventative Maintenance Checklist, Lubrication Charts and Diagrams
PART V: Spare Parts Lists
Troubleshooting Guide Adjustments Common Repairs and Parts Replacement
PARTS VI: Illustrations
1.7.7.1. Part I- Introduction
Part I shall provide an introduction, equipment or system description, functional description and theory of operation, and installation instructions for each piece of equipment. Include complete instructions for uncrating, assembly, connection to the power source and pre-operating lubrication in the installation instructions as applicable. Illustrations, including wiring and cabling diagrams, are required as appropriate in this section. Include halftone pictures of the equipment in the introduction and equipment description, as well as system layout drawings with each item of equipment located and marked. Do not use copies of previously submitted shop drawings in these manuals.
1.7.7.2. Part II-Operating Principles
Section 01 78 02 - Page 12 of 17
Part II shall provide complete instructions for operating the system, and each piece of equipment.
Illustrations, halftone pictures, tables, charts, procedures, and diagrams are required when applicable. This will include step-by-step procedures for start-up and shutdown of both the system and each component piece of equipments, as well as adjustments required to obtain optimum equipment performance, and corrective actions for malfunctions. Show performance sheets and graphs showing capacity data, efficiencies, electrical characteristics, pressure drops, and flow rates here, also. Marked-up catalogs or catalog pages do not satisfy this requirement. Present performance information as concisely as possible with only data pertaining to equipment actually installed. Include actual test data collected for Contractor performance here.
1.7.7.3. Part III – Safety
Part III shall contain the general and specific safety requirements peculiar to each item of equipment. Repeat safety information as notes cautions and warnings in other sections where appropriate to operations described.
1.7.7.4. Part IV-Preventive Maintenance
Part IV shall contain a troubleshooting guide, including detailed instructions for all common adjustments and alignment procedures, including a detailed maintenance schedule. Also include a diagnostic chart showing symptoms and solutions to problems. Include test hookups to determine the cause, special tools and test equipment, and methods for returning the equipment to operating conditions. Information may be in chart form or in tabular format with appropriate headings. Include instructions for the removal, disassembly, repair, reassembly, and replacement of parts and assemblies where applicable and the task is not obvious.
1.7.7.5. Part V-Spare Parts List
Part V shall contain a tabulation of description data and parts location illustrations for all mechanical and electrical parts. The heading of the parts list shall clearly identify the supplier, purchase order number, and equipment. Include the unit price for each part. List parts by major assemblies, and arrange the listing in columnar form. Include names and addresses of the nearest manufacturer's representatives, as well as any special warranty information. Provide a list of spare parts that are recommended to be kept in stock by the Government installation.
1.7.7.6. Part VI-Illustrations
Part VI shall contain assembly drawings for the complete equipment or system and for all major components.
Include complete wiring diagrams and schematics. Other illustrations, such as exploded views, block diagrams, and cutaway drawings, are required as appropriate.
1.7.8. Framed Instructions
Post framed instructions are required for substantial completion. Post framed instructions under glass or in laminated plastic, including wiring and control diagrams showing the complete layout of the entire system, including equipment, ductwork, piping valves, dampers, and control sequence at a location near the equipment described. Prepare condensed operating instructions explaining preventive maintenance procedures methods of checking the system for normal safe operation, valve schedule and procedures for safely starting and stopping the system in type form, framed as specified above for the wiring and control diagrams and posted beside the diagrams. Submit proposed diagrams, instructions, and other sheets prior to posting. Post the framed instructions before field training.
1.7.9. (Reserved. See 1.8 for Field Training)
1.7.10. System/Equipment Requirements
1.7.10.1. Facility Heating System
Section 01 78 02 - Page 13 of 17
Provide information on the following equipment: boilers, water treatment, chemical feed pumps and tanks, converters, heat exchangers, pumps, unit heaters, fin-tube radiation, air handling units (both heating only and heating and cooling), and valves (associated with heating systems).
1.7.10.2. Air-Conditioning Systems
Provide information in chillers, packaged air-conditioning equipment, towers, water treatment, chemical feed pumps and tanks, air-cooled condensers, pumps, compressors, air handling units, and valves (associated with air-conditioning systems).
1.7.10.3. Temperature Control and HVAC Distribution Systems
Provide all information described for the following equipment: valves, fans, air handling units, pumps, boilers, converters and heat exchangers, chillers, water cooled condensers, cooling towers, and fin-tube radiation, control air compressors, control components (sensors, controllers, adapters and actuators), and flow measuring equipment.
1.7.10.4. Central Heating Plants
Provide the information described for the following equipment: boilers, converters, heat exchangers, pumps, fans, steam traps, pollution control equipment, chemical feed equipment, control systems, fuel handling equipment, de-aerators, tanks (flash, expansion, return waters, etc.), water softeners, and valves.
1.7.10.5. Heating Distribution Systems
Provide the information described for the following equipment: valves, fans, pumps, converters and heat exchangers, steam traps, tanks (expansion, flash, etc.), and piping systems.
1.7.10.6. Exterior Electrical Systems
Provide information on the following equipment: power transformers, relays, reclosers, breakers, and capacitor bank controls.
1.7.10.7. Interior Electrical Systems
Provide information on the following equipment: relays, motor control centers, switchgear, solid state circuit breakers, motor controller, EPS lighting systems, wiring diagrams and troubleshooting flow chart on control systems, and special grounding systems.
1.7.10.8. Energy Monitoring and Control Systems
The maintenance manual shall include descriptions of maintenance for all equipment, including inspection, periodic preventative maintenance, fault diagnosis, and repair or replacement of defective components.
1.7.10.9. Domestic Water Systems
Provide the identified information on the following equipment: tanks, unit process equipment, pumps, motors, control and monitoring instrumentation, laboratory test equipment, chemical feeders, valves, switching gear, and automatic controls.
1.7.10.10. Wastewater Treatment Systems
Provide the identified information on the following equipment: tanks, unit process equipment, pumps, motors, control and monitoring instrumentations, laboratory test equipment chemical feeders, valves, scrapers, Section 01 78 02 - Page 14 of 17 skimmers, comminutors, blowers, switching gear, and automatic controls.
1.7.10.11. Fire Protection Systems
Provide information on the following equipment: alarm valves, manual valves, regulators, foam and gas storage tanks, piping materials, sprinkler heads, nozzles, pumps, and pump drivers.
1.7.10.12. Fire Alarm and Detection Systems
(1) The maintenance manual shall include description of maintenance for all equipment, including inspection, periodic preventive maintenance, fault diagnosis, and repair or replacement of defective components.
(2) Provide all software; database with complete identification of programmable portions of system equipment and devices, and all other system programming data on all modes of the system; connecting cables; and proprietary equipment necessary for the operation, maintenance, testing, repair and programming, etc. of the system and that may be required for implementation of future changes to the fire system (additional and/or relocated initiating devices, notification devices, etc.
(3) Provide all system and equipment technical data and computer software with the requisite rights to Government use, in accordance with the applicable contract clauses.
(4) Training shall include software and programming required for the effective operation, maintenance, testing, diagnostics and expansion of the system.
1.7.10.13. Plumbing Systems
Provide information on the following equipment: water heaters, valves, pressure regulators backflow preventors, piping materials, and plumbing fixtures.
1.7.10.14. Liquid Fuels Systems
Provide information on the following equipment: tanks, automatic valves manual valves, filter separators, pumps, mechanical loading arms, nozzles, meters, electronic controls, electrical switch gear, and fluidic controls.
1.7.10.15. Cathodic Protection Systems
Provide information on the following material and equipment: rectifiers, meters, anodes, anode backfill, anode lead wire, insulation material and wire size, automatic controls (if any), rheostats, switches, fuses and circuit breakers, type and size of rectifying elements, type of oil in oil-immersed rectifiers, and rating of shunts.
1.7.10.16. Generator Installations
Provide information on the following equipment: generator sets, automatic transfer panels, governors, exciters, regulators starting systems, switchgear, and protective devices.
1.7.10.17. Miscellaneous Systems
Provide information on the following: communication and ADP systems, security and intrusion alarm, elevators, material handling, active solar, photovoltaic, nurse call, paging, intercom, closed circuit TV, irrigation, sound and material delivery systems, kitchen, refrigeration, disposal, ice making equipment, and other similar type special systems not otherwise specified.
1.7.10.18. Laboratory, Environmental and Pollution Control Systems
Section 01 78 02 - Page 15 of 17
Provide information on the following equipment: wet scrubbers, quench chambers, scrub tanks, liquid oil separators, and fume hoods.
1.8. FIELD TRAINING
Field Training is a requirement for substantial completion. Conduct a training course for the operating staff for each particular system. Conduct the training is to be conducted during hours of normal working time after the system is functionally complete. The field instructions shall cover all of the items contained in the Equipment Operating, Maintenance and Repair Manuals. The training will be conducted as a walk-through of the units with the O&M manual in hand. This walk through should occur within 30 days after the units are ready for occupancy.
1.9. PRICING OF CONTRACTOR-FURNISHED AND INSTALLED PROPERTY AND
GOVERNMENT-FURNISHED CONTRACTOR-INSTALLED PROPERTY
Promptly furnish and require any sub-contractor or supplier to furnish, in like manner, unit prices and descriptive data required by the Government for Property Record purposes of fixtures and equipment furnished and/or installed by the Contractor or sub-contractor, except prices do not need to be provided for Government-Furnished Property.
1.10. RED ZONE MEETING
At approximately 80% of contract completion or 60 days before the anticipated Beneficial Occupancy Date (BOD), whichever occurs first, the Contractor and the Government's project delivery team will conduct what is known as the Red Zone Meeting to discuss the close-out process, to schedule the events and review responsibilities for actions necessary to produce a timely physical, as well as fiscal, project close-out. The Red Zone meeting derives its name from the football term used to describe the team effort to move the ball the last 20 yards into the end zone. The close-out of a construction project sometimes can be equally as hard and most definitely requires the whole team’s efforts. The ACO will chair the meeting. If not already provided, shortly before the meeting, the Contractor shall provide an electronic copy or access to the CADD as-built drawings, completed commensurate with the amount of work completed at the time of the Red Zone Meeting, as an indicator of the Contractors’ understanding of and ability to meet the USACE CADD Standards and to ensure that the Contractor is making progress with CADD As-Built requirements. EXHIBIT 1 is a generic meeting checklist.
1.12. FINAL CLEAN
Clean the premises in accordance with FAR clause 52.236-12 and additional requirements stated here.
Remove stains, foreign substances, and temporary labels from surfaces. Vacuum carpet and soft surfaces.
Clean equipment and fixtures to a sanitary condition. Clean or replace filters of operating equipment if cleaning isn’t possible or practicable. Remove debris from roofs, drainage systems, gutters, and downspouts.
Sweep paved areas and rake clean landscaped areas. Remove waste, surplus materials, and rubbish from the site. Remove all temporary structures, barricades, project signs, fences and construction facilities. Submit a list of completed clean-up items on the day of final inspection.
Section 01 78 02 - Page 16 of 17
EXHIBIT 1
SAMPLE
Red Zone Meeting Checklist
Date:
Contract No.
Description / Location
Contractor
Contracting Officer
Action Completion Milestone
Inspections
Fire
Safety
Pre-final
Mechanical Test & Balance
Commissioning
Landscaping Complete
Erosion Control
Beneficial Occupancy Date (BOD)
Furniture Installation
Comm Installation
As-Built Drawings
Provide all O&M manuals, tools, shop drawings, spare parts, etc. to customer
Training of O&M Personnel
Provide Warranty documents to Customer
Contract completion
Final Inspection
User move-in
DD Form 1354, Transfer of Real Property completed & signed
Ribbon cutting
Section 01 78 02 - Page 17 of 17
Payroll Clearances
DD Form 2626 - Construction Contractor Performance Evaluation
DD Form 2631 – A-E Performance Rated after Construction
Status of Pending Mods and REA’s/Claims
Final Payment Completed
Release of Claims
Return of Unobligated Funds
Move Project from CIP to General Ledger
Financial completion
--END OF SECTION 01 78 02.00 10--