Section 01 35 26
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 01 35 26 - Page 1 of 22
SECTION 01 35 26
GOVERNMENT SAFETY REQUIREMENTS
TABLE OF CONTENTS
1.0 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DEFINITIONS
1.4 QUALITY ASSURANCE
2.0 PRODUCTS
2.1 ACCIDENT PREVENTION PLAN
2.2 ACTIVITY HAZARD ANALYSIS
2.3 USACE ENGINEERING MANUAL 385-1-1
2.4 REPORTS
2.5 HOT WORK
2.6 SAFETY INFORMATION
3.0 EXECUTION
3.1 GENERAL
3.2 DAILY TOOLBOX SAFETY MEETING
3.3 CONTROL OF HAZARDOUS ENERGY
3.4 EXCAVATIONS
3.5 UTILITIES WITHIN CONCRETE SLABS
3.6 DEMOLITION
3.7 FALL HAZARD PROTECTION AND PREVENTION PROGRAM
3.8 SCAFFOLDING
3.9 FALLING OBJECT PROTECTION
3.10 EQUIPMENT
3.11 CRYSTALLINE SILICA
3.12 ELECTRICAL
3.13 CLEANING
Section 01 35 26 - Page 2 of 22
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
1.0 GENERAL
For contractor safety on projects associated with this program, compliance with EM 385-1-1 safety requirements will be the long-term goal reached by growing a safety culture.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE / SAFE)
ASSE / SAFE A10.32 Fall Protection (2004)
ASSE / SAFE A10.34 Protection of the Public on or Adjacent to Construction Sites (2001; R 2005)
ASSE / SAFE Z359.1 Safety Requirements for Personal Fall Arrest Systems, Subsystems and Components (2007)
ASME INTERNATIONAL (ASME)
ASME B30.22 Articulating Boom Cranes (2005)
ASME B30.3 Tower Cranes (2009)
ASME B30.5 Mobile and Locomotive Cranes (2007)
ASME B30.8 Floating Cranes and Floating Derricks (2010)
LOCAL LAWS OF THE CITY OF NEW YORK (LLCNY)
Local Law 77 (2003) Rules Concerning the Use of
Ultra-Low Sulfur Fuel and the Best Available Technology by Nonroad Vehicles in City Construction
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 Standard for Portable Fire Extinguishers (2010)
NFPA 241 Standard for Safeguarding Construction, Alteration, and Demolition Operations (2009)
NFPA 51B Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
(2009; TIA 09-1)
Section 01 35 26 - Page 3 of 22
NFPA 70 National Electrical Code (2011)
NFPA 70E Standard for Electrical Safety in the Workplace (2009; Errata 09-1)
NEW YORK CITY ADMINISTRATIVE CODE (NYCAC)
Title 16 Sanitation
Title 24 Environmental Protection and Utilities
Title 27 Construction and Maintenance
Title 28 New York City Construction Codes
Title 29 New York City Fire Code
THE BOARD OF CERTIFIED SAFETY PROFESSIONALS (BCSP)
BCSP Current Board of Certified Safety Professionals Certifications
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual (2008; Change 1-2010; Change 3-2010; Errata 1-2010)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards (OSHA)
29 CFR 1910.146 Permit-required Confined Spaces
29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment
29 CFR 1926 Safety and Health Regulations for Construction
29 CFR 1926.500 Fall-Protection
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G, RO Fall Protection and Prevention Plan; G, RO
Section 01 35 26 - Page 4 of 22
Activity Hazard Analysis (AHA); G, RO Confined Space Entry Plan; G, District Safety Office Crane Critical Lift Plan; G, RO Proof of qualification for Crane Operators; G, RO Demolition Plan; G, RO Excavation Plan; G, RO Severe Storm Plan; G, RO
SD-06 Test Reports Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports" Accident Reports Crane Reports
SD-07 Certificates Confined Space Entry Permit Hot Work Permit Mechanized Equipment Certification
Submit one copy of each permit/certificate attached to each Daily Quality Control Report.
1.3 DEFINITIONS
a. Associate Safety Professional (ASP). An individual currently Certified by BCSP as an ASP.
b. Certified Construction Health and Safety Technician (CHST). An individual currently Certified by BCSP as a CHST.
c. Certified Safety Professional (CSP). An individual currently Certified by BCSP as a CSP.
d. Certified Safety Trained Supervisor (STS). An individual currently Certified by BCSP as an STS.
e. Competent Person. In accordance with EM 385-1-1 and 29 CFR 1926; one who can identify existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, including but not limited to (Confined Spaces), (Excavation/Trenching), (Fall Protection), (Scaffolding) and who has authorization to take prompt corrective measures to eliminate them.
f. High Visibility Accident. Any mishap which may generate publicity and/or high visibility.
g. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
h. Multi-Employer Work Site (MEWS). A multi-employer work site, as defined by OSHA, is one in which many employers occupy the same site. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors.
i. Operating Envelope. This is the area surrounding any crane. Inside this "envelope" is the crane, the operator, riggers and crane walkers, rigging gear between the hook and the load, the load and the crane's supporting structure (ground, rail, etc.).
j. Qualified Person. In accordance with EM 385-1-1 and 29 CFR 1926; one who, by possession of a recognized degree, certificate, or by professional standing, or extensive knowledge, training, and experience, has successfully demonstrated his/her ability to solve or resolve problems related to the
Section 01 35 26 - Page 5 of 22 subject matter, including but not limited to (Electrical), (Fall Protection), (Rigger/Lift Supervisor), the work, or the project.
k. Recordable Injuries or Illnesses. Any work-related injury or illness that results in:
(1) Death, regardless of the time between the injury and death, or the length of the illness;
(2) Days away from work (any time lost after day of injury/illness onset);
(3) Restricted work;
(4) Transfer to another job;
(5) Medical treatment beyond first aid;
(6) Loss of consciousness; or
(7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (6) above.
l. Site Safety and Health Officer (SSHO). Qualified/Competent Persons who are responsible for the on-site safety and health required for the project. The role of SSHO may be performed by the site superintendent or the CQC systems manager as long as the individual meets the qualification requirements for all positions proposed.
m. Site Safety Manager. An individual currently certified by the New York City Department of Buildings as a Site Safety Manager.
n. "USACE" property and equipment specified in USACE EM 385-1-1 should be interpreted as Government property and equipment.
o. Weight Handling Equipment (WHE) Accident. A WHE accident occurs when any one or more of the six elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment; two-blocking; overload; and/or collision, including unplanned contact between the load, crane, and/or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, roll over, etc.) Any mishap meeting the criteria described above shall be documented in both the Contractor Significant Incident Report (CSIR) and using the NAVFAC prescribed Navy Crane Center (NCC) form submitted within five days both as provided by the Contracting Officer.
1.4 QUALITY ASSURANCE
1.4.1 PERSONNEL QUALIFICATIONS
1.4.1.1 SITE SAFETY AND HEALTH OFFICER (SSHO)
a. The Contractor shall provide a Safety oversight team that includes a minimum of one (1) Competent Person at each project site to function as the Safety and Health Officer (SSHO). The SSHO shall be at the work site at all times, to perform safety and occupational health management, surveillance, Section 01 35 26 - Page 6 of 22 inspections, and safety enforcement for the Contractor.
b. The SSHO must have completed the thirty (30) Hour OSHA Construction Safety Course within the last five (5) years and have at the minimum one (1) year full time safety experience working on similar type projects. The submittal of the SSHO’s resume and training certificate(s) shall be accepted by the Contracting Officer in consultation with the Safety Office.
c. A Competent Person shall be provided for all hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. The credentials of the Competent Persons(s) shall be approved by the Contracting Officer in consultation with the Safety Office.
d. The SSHO must demonstrate possession of a current New York City Department of Buildings Site Safety Manager Certification, in accordance with Title 27 and Title 28.
1.4.1.2 COMPETENT PERSON FOR CONFINED SPACE ENTRY
Provide a competent person meeting the requirements of EM 385-1-1 who is assigned in writing by the Government Designated Authority (GDA) to assess confined spaces and who possesses demonstrated knowledge, skill and ability to:
a. Identify the structure, location, and designation of confined and permit-required confined spaces where work is done;
b. Calibrate and use testing equipment including but not limited to, oxygen indicators, combustible gas indicators, carbon monoxide indicators, and carbon dioxide indicators, and to interpret accurately the test results of that equipment;
c. Assess hazardous conditions including atmospheric hazards in confined space and adjacent spaces and specify the necessary protection and precautions to be taken;
d. Determine ventilation requirements for confined space entries and operations;
e. Assess hazards associated with hot work in confined and adjacent space and determine fire watch requirements; and
f. Maintain records required.
1.4.1.3 CRANE OPERATORS
a. The Contractor must submit proof that all crane operators meet the requirements in EM 385-1-1, Section 16 and Appendix I. In addition, for mobile cranes with Original Equipment Manufacturer (OEM) rated capacitates of 50,000 pounds or greater, designate crane operators as qualified by a source that qualifies crane operators (i.e., union, a government agency, or and organization that tests and qualifies crane operators).
b. The Contractor must submit proof that all crane operators also possess the required class of New York City Department of Buildings Hoisting Machine Operator License for the crane they will be operating, in accordance with Title 27 and Title 28.
1.4.2 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, comply with the most recent addition of USACE EM 385-1-1, and the following federal, state, and local, laws, ordinances, criteria, rules and regulations 29 CFR 1910, 29 CFR 1926, 40 CFR, 46 CFR, 49 CFR, Safety Bulletin SB-
Section 01 35 26 - Page 7 of 22
94-4, Section 107-05, Local Law 77, Title 16, Title 24, Title 27, Title 28, and Title 29. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work.
Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.4.3 MEETINGS
1.4.3.1 PRECONSTRUCTION CONFERENCE
The Preconstruction Conference shall occur as described in Section 00 73 00 SPECIAL CONTRACT REQUIREMENTS and encompass the following criteria:
1. Contractor representatives who have a responsibility or significant role in accident prevention on the project shall attend the preconstruction conference. This includes the project superintendent, site safety and health officer, quality control supervisor, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).
2. The Contractor shall discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the Contracting Officer's representative as to which phases will require an analysis. In addition, a schedule for the preparation, submittal, review, and acceptance of AHAs shall be established to preclude project delays.
3. Deficiencies in the submitted APP will be brought to the attention of the Contractor at the preconstruction conference, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance. Work shall not begin until there is an accepted APP.
4. The functions of a Preconstruction conference may take place at the Post-Award Kickoff meeting for Design Build Contracts.
1.4.3.2 SAFETY MEETINGS
Shall be conducted and documented as required by EM 385-1-1. Minutes showing contract title, signatures of attendees and a list of topics discussed shall be attached to the Contractors' daily quality control report.
1.4.3.3 PRE-OUTAGE COORDINATION MEETINGS
Contractors are required to apply for utility outages at least 15 days in advance. As a minimum, the request should include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Special requirements for electrical outage requests are contained elsewhere in this specification section. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.
2.0 PRODUCTS
2.1 ACCIDENT PREVENTION PLAN (APP)
a. The Contractor shall use a qualified person to prepare the written site-specific APP in both English and in the host nation language. Prepare the APP in accordance with the format and requirements of
USACE EM 385-1-1.
Section 01 35 26 - Page 8 of 22
b. Cover all paragraph and subparagraph elements in USACE 385-1-1 which apply. The full reference manual may be obtained from the Contracting Officer.
c. Specific requirements for some of the APP elements are described below. The APP shall be jobspecific and shall address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the Contractor's overall safety and health program. Any portions of the Contractor's overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific.
d. The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP shall be signed by the person and firm (senior person) preparing the APP, the Contractor, the on-site superintendent, the designated site safety and health officer.
e. Submit the APP to the Contracting Officers Representative (COR) or USACE Area/Resident Office Engineer 15 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP.
f. Once accepted by the Contracting Officers Representative or Area/Resident Office Engineer, the APP and attachments will be reviewed for completeness and sent to the USACE Safety Office for technical review and acceptance and enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the COR, until the matter has been rectified.
g. Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the COR, project superintendent, SSHO and quality control manager. Should any hazard become evident, stop work in the area, secure the area, and develop a plan to remove the hazard. Notify the COR within 24 hours of discovery. In the interim, all necessary action shall be taken to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public, and the environment.
h. Copies of the accepted plan will be maintained at the Contracting Officer's office and at the job site.
i. The APP shall be continuously reviewed and amended, as necessary, throughout the life of the contract. Unusual or high-hazard activities not identified in the original APP shall be incorporated in the plan as they are discovered.
j. The APP will be readily available to all workers on the worksite in all native languages of the workers.
2.2 ACTIVITY HAZARD ANALYSIS (AHA)
a. The Activity Hazard Analysis (AHA) format shall be in accordance with USACE EM 385-1-1, and shall be written in both English and the host nation language. Submit the AHA for review at least 15 calendar days prior to the start of each phase and format subsequent AHAs as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.
b. The AHA list will be reviewed periodically (at least monthly) at the Contractor supervisory safety meeting and updated as necessary when procedures, scheduling, or hazards change.
c. The activity hazard analyses shall be developed using the project schedule as the basis for the
Section 01 35 26 - Page 9 of 22 activities performed. Any activities listed on the project schedule will require an AHA. The AHAs will be developed by the contractor, supplier or subcontractor and provided to the prime contractor for submittal to the Contracting Officer.
2.3 USACE ENGINEERING MANUAL 385-1-1
In addition to the requirements outlines in Appendix A of USACE EM 385-1-1, the following is required:
2.3.1 QUALIFICATIONS
a. Names and qualifications (resumes including education, training, experience and certifications) of all site safety and health personnel designated to perform work on this project to include the designated site safety and health officer and other competent and qualified personnel to be used such as CSPs, CIHs, STSs, CHSTs. Specify the duties of each position.
b. As a minimum, designate and submit qualifications of competent persons for each of the following major areas: excavation; scaffolding; fall protection; hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents; personal protective equipment and clothing to include selection, use and maintenance.
2.3.2 CONFINED SPACE ENTRY PLAN
Develop a confined and/or enclosed space entry plan in accordance with USACE EM 385-1-1, applicable OSHA standards 29 CFR 1910, 29 CFR 1915, and 29 CFR 1926, OSHA Directive 2.100, and any other federal, state and local regulatory requirements identified in this contract. Identify the qualified person's name and qualifications, training, and experience. Delineate the qualified person's authority to direct work stoppage in the event of hazardous conditions. Include procedure for rescue by contractor personnel and the coordination with emergency responders. (If there is no confined space work, include a statement that no confined space work exists and none will be created.)
2.3.3 CRANE CRITICAL LIFT PLAN
Prepare and sign weight handling critical lift plans for lifts over 75 percent of the capacity of the crane or hoist (or lifts over 50 percent of the capacity of a barge mounted mobile crane's hoists) at any radius of lift; lifts involving more than one crane or hoist; lifts of personnel; and lifts involving non-routine rigging or operation, sensitive equipment, or unusual safety risks. Submit 15 calendar days prior to on-site work and include the requirements of USACE EM 385-1-1, paragraph 16.H. Table 16.
2.3.4 FALL PROTECTION AND PREVENTION PLAN
The program documentation shall be site specific and address all fall hazards in the work place and during different phases of construction. Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 1.8 m. A qualified person for fall protection shall prepare and sign the program documentation. Include fall protection and prevention systems, equipment and methods employed for every phase of work, responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods. Revise the Fall Protection and Prevention Program documentation every six months for lengthy projects, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and Prevention Program documentation at the job site for the duration of the project. Include the Fall Protection and Prevention Program documentation in the Accident Prevention Plan (APP).
2.3.5 EXCAVATION PLAN
A plan shall be develop taking in consideration the type of soil and the depth, it shall follow the requirements of section 25.A and be site specific.
Section 01 35 26 - Page 10 of 22
2.4 REPORTS
2.4.1 ACCIDENT REPORTS
All accident occurring incidentally to the project shall be investigated, reported, analyzed and documented. For recordable injuries and illnesses, as defined in 1.3.hand property damage accidents resulting in at least $2,000 in damages, to establish the root cause(s) of the accident, complete the USACE Accident Report Form 3394 and provide the report to the Contracting Officer within 5 calendar days of the accident. The Contracting Officer will provide copies of any required or special forms on accident for less than $2,000.00 or not recordable injuries.
2.4.2 ACCIDENT NOTIFICATION
Notify the Contracting Officer as soon as practical, but not later than four (4) hours, after any accident meeting the definition of Recordable Injuries or Illnesses or High Visibility Accidents, property damage equal to or greater than $2,000. Within notification include contractor name; contract title; type of contract;
name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of construction equipment used, PPE used, etc.). Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted.
2.4.3 MONTHLY EXPOSURE REPORTS
Monthly exposure reporting to the Contracting Officer is required to be attached to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both prime and subcontractor. The Contracting Officer will provide copies of any special forms.
2.4.4 CONTRACTOR SAFETY SELF-EVALUATION CHECKLIST
Contractor Safety Self-Evaluation Checklist shall be submitted to Contracting Officer, attached to monthly billing request. This checklist shall be a Quality Control measure established by the Contractor to ensure Safety evaluations are performed daily by site safety and health personnel and evaluated for needed improvements at a minimum rate of once a month.
2.4.5 CRANE REPORTS
a. Submit crane inspection reports required in accordance with USACE EM 385-1-1, Appendix I and as specified herein with Daily Reports of Inspections.
b. Provide a Certificate of Compliance for each crane entering an activity under this contract (see Contracting Officer for a blank certificate). State within the certificate that the crane and rigging gear meet applicable OSHA regulations (with the Contractor citing which OSHA regulations are applicable, e.g., cranes used in construction, demolition, or maintenance comply with 29 CFR 1926 and USACE EM 385-1-1 Section 16 and Appendix I. Certify on the Certificate of Compliance that the crane operator(s) is qualified and trained in the operation of the crane to be used. For cranes at DOD activities in foreign countries, certify that the crane and rigging gear conform to the appropriate host country safety standards. Also certify that all of its crane operators working on the DOD activity have been trained in the proper use of all safety devices (e.g., anti-two block devices). Post certifications on the crane.
2.5 HOT WORK
a. Submit and obtain a written permit prior to performing "Hot Work" (welding, cutting, etc.) or operating other flame-producing/spark producing devices, from the Base Fire Department or as directed by the
Section 01 35 26 - Page 11 of 22
Contracting Officer. A permit is required from the Explosives Safety Office for work in and around where explosives are processed, stored, or handled. CONTRACTORS ARE REQUIRED TO MEET ALL CRITERIA BEFORE A PERMIT IS ISSUED. The Contractor will provide at least two (2) twenty
(20) pound 4A:20 BC rated extinguishers for normal "Hot Work". All extinguishers shall be current inspection tagged, approved safety pin and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any "Hot Work" done at this activity. The Fire Watch shall be trained in accordance with NFPA 51B and remain on-site for a minimum of 30 minutes after completion of the task or as specified on the hot work permit.
b. When starting work in the facility, require personnel to familiarize themselves with the location of the nearest fire alarm boxes and have in their possession the emergency contact phone number. ANY FIRE, NO MATTER HOW SMALL, SHALL BE REPORTED TO THE RESPONSIBLE FIRE DIVISION/
DEPARTMENT IMMEDIATELY.
2.6 SAFETY INFORMATION
2.6.1 DISPLAY
a. Within one (1) calendar day after commencement of work, Contractor shall erect a safety bulletin board at the job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, shall be deemed as meeting the requirement for a bulletin board. All documentation shall be in English and in the native language of all workers on site. Include and maintain information on safety bulletin board as required by EM 385-1-1, section 01.A.06.
b. Additional items required to be posted include:
1. Confined space entry permit;
2. Hot work permit; and
3. Deficiency tracking log.
2.6.2 REFERENCE MATERIAL
Contractor shall maintain safety-related references applicable to the project, including those listed in the article "References,” on site at all times.
2.6.3 EQUIPMENT MANUALS
Contractor shall maintain applicable equipment manufacturer's manuals on site at all times.
3.0 EXECUTION
3.1 GENERAL
3.1.1 FACILITY OCCUPANCY CLOSURE
Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer.
3.1.2 SEVERE STORM PLAN
In the event of a severe storm warning, the Contractor shall:
1. Secure outside equipment and materials and place materials that could be damaged in protected areas.
Section 01 35 26 - Page 12 of 22
2. Check surrounding area, including roof, for loose material, equipment, debris, and other objects that could be blown away or against existing facilities.
3. Ensure that temporary erosion controls are adequate.
3.1.3 EMERGENCY MEDICAL TREATMENT
Contractors will arrange for their own emergency medical treatment. The Government has no responsibility to provide emergency medical treatment. Military medical clinics may provide emergency treatment for serious injuries; the contractor is responsible for coordination with the local military medical clinic prior to mobilization.
3.1.4 DRUG PREVENTION PROGRAM
Conduct a proactive drug and alcohol use prevention program for all workers, prime and subcontractor, on the site. Ensure that no employee uses illegal drugs or consumes alcohol during work hours. Ensure there are no employees under the influence of drugs or alcohol during work hours. After accidents, collect blood, urine, or saliva specimens and test the injured and involved employees for the influence of drugs and alcohol. A copy of the test shall be made available to the Contracting Officer upon request.
3.1.5 PERSONNEL DUTIES
a. The Site Safety and Health Officer (SSHO) shall perform the following duties as described herein:
1. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily quality control report;
2. Conduct mishap investigations and complete required reports. Maintain the OSHA Form 300 and Daily Production reports for prime and sub-contractors;
3. Maintain applicable safety reference material on the job site;
4. Attend the pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings;
5. Implement and enforce accepted APPS and AHAs;
6. Maintain a safety and health deficiency tracking system that monitors outstanding deficiencies until resolution. Post a list of unresolved safety and health deficiencies on the safety bulletin board;
7. Ensure sub-contractor compliance with safety and health requirements. Failure to perform the above duties will result in dismissal of the superintendent, QC Manager, and/or SSHO, and a project work stoppage. The project work stoppage will remain in effect pending approval of a suitable replacement; and
8. Maintain a list of hazardous chemicals on site and their material safety data sheets.
b. Failure to perform the above duties will result in dismissal of the superintendent and/or SSHO, and a project work stoppage. The project work stoppage will remain in effect pending approval of a suitable replacement.
3.1.6 TRAINING
Section 01 35 26 - Page 13 of 22
3.1.6.1 NEW EMPLOYEE INDOCTRINATION
a. New employees (prime and sub-contractor) will be informed of specific site hazards before they begin work. Documentation of this orientation shall be kept on file at the project site.
b. The AHA shall be presented to workers performing the activity in their native language, either in writing or by a qualified interpreter and documentation of the presentation proven via signature of the worker(s).
3.1.6.2 PERIODIC TRAINING
Provide Safety and Health Training in accordance with USACE EM 385-1-1 and the accepted APP.
Ensure all required training has been accomplished for all onsite employees.
3.1.6.3 TRAINING ON ACTIVITY HAZARD ANALYSIS (AHA)
Prior to beginning a new phase, training will be provided to all personnel on the worksite according to the Activity Hazard Analysis (AHA).
3.2 DAILY TOOLBOX SAFETY MEETING
a. Before initiation of work at the job site, an Accident Prevention Plan (APP), written by the Contractor for the specific work and hazards of the contract and implementing in detail the pertinent requirements of EM 385-1-1, will be reviewed and found acceptable by designated Government personnel. Specific requirements for development of the accident prevention plan are found in sections 01.A and Appendix A of EM 385-1-1.
b. Before beginning each activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform the work, activity hazard analysis (AHA) shall be prepared by the Contractor performing the work activity. See paragraph 01.A.13 of EM 385-1-1.
c. The Contractor shall require subcontractors to submit their plan of operations showing methods they propose to use in accomplishing major phases of work.
d. The Contractor shall be prepared to discuss the plans in conferences convened by the Contracting Officer prior to starting work on each major phase of operation. Plans shall include all pertinent information such as layout of haul roads, access roads, storage areas, electrical distribution lines, methods of providing minimum exposure to overhead loads, and methods of access to work areas.
The plan for accomplishing the initial work phase shall be submitted within 15 calendar days after award of the contract. Plans for subsequent major phases of work shall be submitted not later than 15 calendar days prior to initiation of work on each major phase.
e. All areas where construction, demolition, alteration, building, or similarly related activities take place, all workers shall have the following minimum personal protective clothing and equipment:
1. Short sleeve shirt;
2. Long trousers;
3. Steel-toed safety boots; and
4. Hard hat
3.2.1 HAZARDOUS MATERIALS
Section 01 35 26 - Page 14 of 22
Comply with USACE EM 385-1-1, NFPA 241, the APP, the AHA, Federal and/or State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.
3.2.1.1 HAZARDOUS MATERIAL EXCLUSIONS
Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials. The Radiation Safety Officer (RSO) must be notified prior to excepted items of radioactive material and devices being brought on base.
3.2.1.2 UNFORESEEN HAZARDOUS MATERIAL
The design should have identified materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e.29 CFR Part 1910.1000). If additional material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."
3.3 CONTROL OF HAZARDOUS ENERGY
3.3.1 GENERAL
a. Contractor shall ensure that each employee is familiar with and complies with these procedures and USACE EM 385-1-1, Section 12, Control of Hazardous Energy.
b. The Contractor shall, at the Contracting Officer’s request, apply lockout/tag out tags and take other actions that, because of experience and knowledge, are known to be necessary to make the particular equipment safe to work on for government owned and operated systems. No person, regardless of position or authority, shall operate any switch, valve, or equipment that has an official lockout/tag out tag attached to it, nor shall such tag be removed except as allowed by this section.
c. No person shall work on any energized equipment including, but not limited to activities such as erecting, installing, constructing, repairing, adjusting, inspecting, un-jamming, setting up, trouble shooting, testing, cleaning, dismantling, servicing and maintaining machines equipment of processes until an evaluation has been conducted identifying the energy source and the procedures which will be taken to ensure the safety of personnel. Only qualified personnel shall perform work on electrical circuits.
d. A supervisor who is required to enter an area protected by a lockout/tag out tag will be considered a member of the protected group provided he notifies the holder of the tag stub each time he enters and departs from the protected area. Identification markings on building light and power distribution circuits shall not be relied on for established safe work conditions.
e. Before clearance will be given on any equipment other than electrical (generally referred to as mechanical apparatus), the apparatus, valves, or systems shall be secured in a passive condition with the appropriate vents, pins, and locks. Pressurized or vacuum systems shall be vented to relieve differential pressure completely. Vent valves shall be tagged open during the course of the work.
Where dangerous gas or fluid systems are involved, or in areas where the environment may be oxygen deficient, system or areas shall be purged, ventilated, or otherwise made safe prior to entry.
Section 01 35 26 - Page 15 of 22
3.3.2 TAG PLACEMENT
a. Lockout/tag out tags shall be completed in accordance with the regulation printed on the back thereof and attached to any device which, if operated, could cause an unsafe condition to exist. If more than one group is to work on any circuit or equipment, the employee in charge of each group shall have a separate set of lockout/tag out tags completed and properly attached.
b. When it is required that certain equipment be tagged, the Government will review the characteristics of the various systems involved that affect the safety of the operations and the work to be done; take the necessary actions, including voltage and pressure checks, grounding, and venting, to make the system and equipment safe to work on; and apply such lockout/tag out tags to those switches, valves, vents, or other mechanical devices needed to preserve the safety provided. This operation is referred to as "Providing Safety Clearance."
3.3.3 TAG REMOVAL
When any individual or group has completed its part of the work and is clear of the circuits or equipment, the supervisor, project leader, or individual for whom the equipment was tagged shall turn in his signed lockout/tag out tag stub to the Contracting Officer. That group's or individual's lockout/tag out tags on equipment may then be removed on authorization by the Contracting Officer.
3.4 EXCAVATIONS
Perform soil classification by a competent person in accordance with 29 CFR 1926.
The competent person for excavations performed as a result of contract work shall be on-site when excavation work is being performed, and shall inspect, and document the excavations daily prior to entry by workers. The competent person must evaluate all hazards, including atmospheric, that may be associated with the work, and shall have the resources necessary to correct hazards promptly. All excavations shall conform to the requirements of Section 25 of EM 385-1-1.
3.4.1 UTILITY LOCATIONS
a. Prior to any excavation activities, the appropriate digging permit must be obtained.
b. All underground utilities in the work area must be positively identified by a private utility locating service in addition to any station locating service and coordinated with the station utility department.
Any markings made during the utility investigation must be maintained throughout the contract.
c. All underground utilities discovered will be flagged a distance of one-half (1/2) meter on each side of the location, and any markings made during the utility investigation must be maintained throughout the contract.
d. Damage occurring to existing utilities, when the above procedures are not followed, will be repaired at the Contractor’s expense.
3.4.2 UTILITY LOCATION VERIFICATION
The Contractor must physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. Digging within 610 mm of a known utility must not be performed by means of mechanical equipment; hand digging shall be used. If construction is parallel to an existing utility expose the utility by hand digging every 30.5 m if parallel within 1.5 m of the excavation.
3.4.3 SHORING SYSTEMS
Trench and shoring systems must be identified in the accepted safety plan and AHA. Manufacture
Section 01 35 26 - Page 16 of 22 tabulated data and specifications or registered engineer tabulated data for shoring or benching systems shall be readily available on-site for review. Job-made shoring or shielding shall have the registered professional engineer stamp, specifications, and tabulated data. Extreme care must be used when excavating near direct burial electric underground cables.
3.4.4 TRENCHING MACHINERY
Trenching machines with digging chain drives shall be operated only when the spotters/laborers are in plain view of the operator. Operator and spotters/laborers shall be provided training on the hazards of the digging chain drives with emphasis on the distance that needs to be maintained when the digging chain is operating. Documentation of the training shall be kept on file at the project site.
3.5 UTILITIES WITHIN CONCRETE SLABS
Utilities located within concrete slabs or pier structures, bridges, and the like, are extremely difficult to identify due to the reinforcing steel used in the construction of these structures. Whenever contract work involves concrete chipping, saw cutting, or core drilling, the existing utility location must be coordinated with station utility departments in addition to a private locating service. Outages to isolate utility systems shall be used in circumstances where utilities are unable to be positively identified. The use of historical drawings does not alleviate the contractor from meeting this requirement.
3.5.1 WORK IN CONFINED SPACES
a. Contractors entering and working in confined spaces performing general industry work are required to follow the requirements of OSHA 29 CFR Part 1926.
b. USACE personnel entering and working in confined spaces performing non-maritime facility work are required to follow the requirements of OPNAVINST 5100.23G Chapter 27.
c. Comply with the requirements in Section 34 of USACE EM 385-1-1, OSHA 29 CFR 1910.146 and OSHA 29 CFR 1926.21(b)(6). Any potential for a hazard in the confined space requires a permit system to be used.
3.5.2 SIGNAGE
a. Provide permanent signs integral to or securely attached to access covers for new permit-required confined spaces.
b. Signs shall read as follows:
"DANGER -- PERMIT-REQUIRED CONFINED SPACE -- DO NOT ENTER"
c. Provide in bold letters a minimum of 25 mm in height and constructed to be clearly legible with all paint removed.
d. The signal word "DANGER" shall be red and readable from 1520 mm.
3.5.3 PROCEDURES
a. The Contractor shall comply with the requirements in Section 34 of USACE EM 385-1-1. Any potential for a hazard in the confined space requires a permit system to be used.
b. Entry procedures shall prohibit entry into a confined space by personnel for any purpose, including hot work, until the qualified person has conducted appropriate tests to ensure the confined or enclosed space is safe for the work intended and that all potential hazards are controlled or eliminated and documented. (See Section 34 of USACE EM 385-1-1 for entry procedures.)
Section 01 35 26 - Page 17 of 22
c. All hazards pertaining to the space shall be reviewed with each employee during review of the AHA.
d. Forced air ventilation is required for all confined space entry operations and the minimum air exchange requirements must be maintained to ensure exposure to any hazardous atmosphere is kept below its' action level.
e. Ensure the use of rescue and retrieval devices in confined spaces greater than 1.5 m in depth.
Conform to Section 34 of USACE EM 385-1-1.
f. Sewer wet wells require continuous atmosphere monitoring with audible alarm for toxic gas detection.
g. Include training information for employees who will be involved as entrants and attendants for the work. Conform to Section 34 of USACE EM 385-1-1.
h. Daily Entry Permit shall be posted in a conspicuous place, close to the confined space entrance.
3.6 DEMOLITION
3.6.1 DEMOLITION PLAN
The Contractor shall submit a written demolition plan for all demolition work to be carried on the site. In addition, the demolition plan shall be signed by a Professional Registered Engineer and meet the requirements of the Corps of Engineers Safety and Health Manual, EM 385-1-1, section 23. The demolition plan shall be submitted to the COR at least 1 week before the beginning of the work, including structural calculations for the demolition, if necessary. The demolition work shall not begin before the Contractor has received a written approval from the COR.
3.6.2 PROTECTION OF PERSONNEL
During the demolition work the Contractor shall continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the demolition site.
No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workers remove debris or perform other work in the immediate area.
3.6.3 PROTECTION OF STRUCTURES
Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, shall remain standing without additional bracing, shoring, or lateral support until demolished, unless directed otherwise by the COR. The Contractor shall ensure that no elements determined to be unstable are left unsupported and shall be responsible for placing and securing bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, or demolition work performed under this contract.
Interior concrete or masonry walls shall be demolished from the top down unless a Registered Engineer can demonstrate that an alternate method poses no additional safety hazards
3.7 FALL HAZARD PROTECTION AND PREVENTION PROGRAM
3.7.1 GENERAL
The Contractor shall establish a fall protection and prevention program, for the protection of all employees exposed to fall hazards. The program shall include: company policy; identify responsibilities; education and training requirements; fall hazard identification; prevention and control measures; inspection, storage;
care and maintenance of fall protection equipment and rescue and evacuation procedures.
3.7.2 TRAINING
Section 01 35 26 - Page 18 of 22
The Contractor shall institute a fall protection training program. As part of the Fall Hazard Protection and Prevention Program, the Contractor shall provide training for each employee who might be exposed to fall hazards. A competent person for fall protection shall provide the training. Training requirements shall be in accordance with USACE EM 385-1-1, section 21.B.
3.7.3 FALL PROTECTION EQUIPMENT AND SYSTEMS
a. The Contractor shall enforce use of the fall protection equipment and systems designated for each specific work activity in the Fall Protection and Prevention Plan and/or AHA at all times when an employee is exposed to a fall hazard. Protect employees from fall hazards as specified in EM 385-1- 1, Section 21.
b. In addition to the required fall protection systems, safety skiff, personal floatation devices, life rings etc., are required when working above or next to water in accordance with USACE EM 385-1-1, Paragraphs 21.N through 21.N.04. Personal fall arrest systems are required when working from an articulating or extendible boom, swing stages, or suspended platform. In addition, personal fall arrest systems are required when operating other equipment such as scissor lifts if the work platform is capable of being positioned outside the wheelbase.
c. The need for tying-off in such equipment is to prevent ejection of the employee from the equipment during raising, lowering, or travel. Fall protection must comply with 29 CFR 1926.500, Subpart M, USACE EM 385-1-1 and ASSE/SAFE A10.32.
3.7.3.1 PERSONAL FALL ARREST EQUIPMENT
Personal fall arrest equipment, systems, subsystems, and components shall meet ASSE/SAFE Z359.1.
Only a full-body harness with a shock-absorbing lanyard or self-retracting lanyard is an acceptable personal fall arrest body support device. Body belts may only be used as a positioning device system (for uses such as steel reinforcing assembly and in addition to an approved fall arrest system). Harnesses shall have a fall arrest attachment affixed to the body support (usually a Dorsal D-ring) and specifically designated for attachment to the rest of the system.