WA NCW Specifications 20250328 DRAFT.pdf

PDF 8 MB Posted

Attached to
MCMILLAN NORTH CLEARWELL REPLACEMENT
Solicitation number
W912DR25X15AK
Issued by

About this file

This document is a draft specification for the McMillan North Clearwell Replacement project at the Washington Aqueduct in Washington, DC. The project involves completely replacing an existing 14.5 million gallon underground water storage tank within its current footprint, with dimensions of approximately 612 feet long by 162 feet wide. The work includes demolishing two historic brick buildings on the tank's roof, which will be reconstructed to match their original exterior appearance, and installing a new concrete tank with baffles, chambers, slide gates, and a new process chemical and control system.

The project is part of a design-bid-build construction contract with the U.S. Army Corps of Engineers Baltimore District, with an anticipated construction cost between $25-50 million and a 36-month duration starting around November 2025. The contract will use the NAICS code 237110 for Water and Sewer Line and Related Structures Construction, with a small business size standard of $45 million. An industry day presentation is scheduled for March 17, 2025, at 11:30 AM Eastern Time, and the full solicitation is expected to be publicized in May 2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GF-D DESIGN PARTNERS JV

Gannett Fleming+ Dewberry

A Joint Venture

MCMILLAN NORTH CLEARWELL REPLACEMENT

Washington Aqueduct

Washington, DC

USACE - BALTIMORE DISTRICT

SPECIFICATIONS - Original

March 28, 2025

AE Contract Number: W912DR-20-D-0003

3/28/2025

C O

M

MONWEALTH OF VIRG

IN

IA

ARCHITECT

CATHERINE H.

OTIS

Lic. No. 0401018323

3/28/2025

03/28/2025

3/28/2025

Digitally signed by Michael John Morrissey

3/28/2025

DRAFT

NCW Replacement UNCLASSIFED//FOR OFFICIAL USE ONLY 03/28/2025 Washington Aqueduct, DC Original

THIS PAGE INTENTIONALLY LEFT BLANK

UNCLASSIFED//FOR OFFICIAL USE ONLY

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 14 00 11/22, CHG 1: 02/23 WORK RESTRICTIONS

01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES

01 30 00 11/20, CHG 3: 08/23 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 08/23 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 16.00 10 05/16 DESIGN DATA (DESIGN AFTER AWARD)

01 35 26 11/20, CHG 4: 08/23 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 11/16, CHG 2: 11/21 QUALITY CONTROL

01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 35 11/20 SPECIAL INSPECTIONS

01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

01 78 23 05/23 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 05/23 FACILITY DATA REQUIREMENTS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 08/22 DEMOLITION

02 42 91 11/18 REMOVAL AND SALVAGE OF HISTORIC

CONSTRUCTION MATERIALS

DIVISION 03 - CONCRETE

03 01 00 02/18 REHABILITATION OF CONCRETE

03 30 00 02/19, CHG 6: 11/23 CAST-IN-PLACE CONCRETE

03 62 16 02/18 METALLIC NON-SHRINK GROUTING

03 70 00 02/10, CHG 2: 08/20 MASS CONCRETE

DIVISION 04 - MASONRY

04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY

DIVISION 05 - METALS

05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY

ANCHORS

05 05 23.16 08/18 STRUCTURAL WELDING

05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL

05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY

06 71 33 08/23 FIBERGLASS REINFORCED PLASTIC (FRP)

LADDERS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

PROJECT TABLE OF CONTENTS Page 1

07 14 00 02/12, CHG 2: 02/18 FLUID-APPLIED WATERPROOFING

07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION

07 27 26 05/17, CHG 2: 08/20 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 30 24 02/24 WATERTIGHTNESS TESTING FOR HYDRAULIC

STRUCTURES

07 32 13 04/06 ROOF TILES

07 52 00 05/12, CHG 5: 11/19 MODIFIED BITUMINOUS MEMBRANE ROOFING

07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL

07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 14 00 08/16, CHG 1: 08/18 WOOD DOORS

08 52 00 08/20, CHG 1: 02/22 WOOD WINDOWS

08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL LOUVERS

DIVISION 09 - FINISHES

09 90 00 02/21 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE

10 44 16 11/19 FIRE EXTINGUISHERS

DIVISION 22 - PLUMBING

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION

23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.00 28 03/28/2023 CYBERSECURITY FOR CIVIL WORKS

OPERATIONAL TECHNOLOGY

DIVISION 26 - ELECTRICAL

26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM

26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION

26 41 00 11/13 LIGHTNING PROTECTION SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

26 56 00 08/21 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

PROJECT TABLE OF CONTENTS Page 2

DIVISION 31 - EARTHWORK

31 00 00 08/23 EARTHWORK

31 62 16.13 11/20 STEEL MICROPILES

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 16.71 11/22 COLD MILLING ASPHALT PAVING

32 05 33 08/17 LANDSCAPE ESTABLISHMENT

32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE

PAVING

32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 92 19 08/17, CHG 1: 08/21 SEEDING

DIVISION 33 - UTILITIES

33 40 00 11/21 STORMWATER UTILITIES

33 46 16 05/18 SUBDRAINAGE PIPING

33 51 43 05/22 INSTRUMENTATION AND PERFORMANCE

MONITORING OF STRUCTURES

33 61 13.19 02/16 VALVES, PIPING, AND EQUIPMENT IN VALVE

MANHOLES

33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 16.54 05/21 SLIDE GATES AND ACTUATORS

35 45 04.00 10 11/20 SUBMERSIBLE PUMP, CENTRIFUGAL TYPE

DIVISION 40 - PROCESS INTERCONNECTIONS

40 05 13 10/07, CHG 2: 02/20 PIPELINES, LIQUID PROCESS PIPING

40 60 00 05/20 PROCESS CONTROL

DIVISION 46 - WATER AND WASTEWATER EQUIPMENT

46 79 00 10/22 DISINFECTING OF STRUCTURES AND

EQUIPMENT

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 3

THIS PAGE INTENTIONALLY LEFT BLANK

PROJECT TABLE OF CONTENTS Page 4

SECTION 01 11 00

SUMMARY OF WORK

08/15, CHG 2: 08/21

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G

Documentation Of Utilities; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes All labor, materials, and equipment necessary to complete the requirements in the contract drawings and specifications to deliver a complete and useable facility for the replacement of an existing

14.5 MG underground water storage tank within its existing footprint. The tank is approximately 612 ft in length and 162 ft in width.

There are 2 one-story historic brick buildings, M-6 McMillan Control House (North) and M-20 McMillan Flume Building, located on the roof of the existing clearwell that will be demolished. Following replacement of the clearwell, these brick buildings will be rebuilt in their current locations to match their historic exterior appearance. Reconstruction will be carried out in accordance with the Secretary of the Interior's Standards for the Treatment of Historic Properties, (36 CFR, Part 68). The North Clearwell Drain Valve Operator mechanism will be salvaged from building M-6, restored and reinstalled in an alternate location outside the building as indicated, along with an interpretive panel to be provided by others.

The work will include temporary relocation of existing utilities on the roof of the clearwell during construction and reinstallation following the replacement of the clearwell. The existing roof is covered with soil and grass, there is an existing access hatch on the west side of the clearwell to allow construction equipment to gain access into the clearwell.

Lateral bracing of the existing walls will be provided from within the tank to support them during installation of the new tank. This lateral bracing of the existing walls along with SOE micropile, columns, struts and whalers will all be a delegated design by the contractor after award.

After installation of lateral bracing the roof, columns, and floor of the clearwell will be demolished. Lateral bracing will remain installed until the new roof and floor have been installed.

The new tank construction will include a new concrete mat foundation, SECTION 01 11 00 Page 1 columns, walls poured against the existing walls, and roof. New concrete baffles will be installed in select areas to direct water from the tank influent to the tank effluent.

The work will include the installation of new influent and effluent concrete chambers, and a new concrete drain chamber, slide gates, and actuators (gate operators). A new process chemical and control system will be installed, and a new waterproofing membrane and landscaped grass roof will be installed over the new concrete roof and incidental related work.

1.2.2 Location

The work is located at the McMillan Water Treatment Plant on 1st Street, NW DC, approximately as indicated.

1.3 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.4 LOCATION OF UNDERGROUND UTILITIES

Miss utility does not provide utility location services at the site. The locations of utilities on the contract drawings are general and not 100% accurate, and must be verified by the contractor prior to construction.

The location and elevation of utility lines (live and abandoned) within 20ft of proposed construction or utility relocations shall be located by the contractor and shall be positively identified for exact horizontal and vertical locations before construction or utility relocation in these areas. The Documentation of Utilities shall be submitted to the Government in electronic AutoCAD files format for their use, and shall also be incorporated into the as-built drawings for the work.

Coordinate with the Government and provide notification 21 calendar days prior the start of utility location efforts.Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the groundor paved surface where existing underground utilities are discovered. In addition to verifying the elevations of utilities shown on the drawings, v erify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

SECTION 01 11 00 Page 2

1.4.1 Notification Prior to Excavation

Notify the Contracting Officer at least 21 calendar days prior to starting excavation work.

1.5 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location, in accordance with section 02 42 91 REMOVAL AND SALVAGE OF HISTORIC CONSTRUCTION MATERIALS and 01 14 00 WORK RESTRICTIONS.

Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan.

Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 11 00 Page 4

SECTION 01 14 00

WORK RESTRICTIONS

11/22, CHG 1: 02/23

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

Welding Permits; G

Excavation Permits; G

Borrow Permits; G

1.2 SPECIAL SCHEDULING REQUIREMENTS

The list of special scheduling requirements below is to be used in conjunction with all other requirements specified throughout the contract drawings and specifications. The contractor shall review the contract documents as a whole to ensure all special scheduling and construction sequencing requirements are met.

1.2.1 General Requirements

This work is taking place on a water treatment facility that must remain operational at all times. All roads, access routes, buildings and utilities, etc. at the McMillan Water Treatment facility should be considered essential to the water treatment facility operations and care must be taken to avoid damaging any utility lines during construction, or interrupting the plant operations. If the contractor damages any utility, or interrupts plant operations, such outage or interruption is to be treated an emergency and the contractor must correct the outage or interruption immediately and at no additional cost to the government. If the contractor fails to correct such outage or interruption immediately, the government reserves the right to correct the outage or interruption at the contractor's expense.

1.2.2 Utility Location

Miss utility does not provide utility location services at the site. The locations of utilities on the contract drawings are general and not 100% accurate, and must be verified by the contractor prior to construction.

The location and elevation of utility lines (live and abandoned) within 20ft of proposed construction or utility relocations shall be located by the contractor and shall be positively identified for exact horizontal and vertical locations before construction or utility relocation in these areas. Refer to Section 01 11 00 SUMMARY OF WORK, Location Of Underground

SECTION 01 14 00 Page 1

Utilities for additional requirements.

1.2.3 Pre-Demolition

Following the draining of the North Clearwell (NCW) and prior to demolition of the McMillan Flume Building (M-20), the McMillan Control House North (M-6), or the NCW, the contractor must complete Historic American Engineering Record (HAER) Level I photo documentation of the McMillan Flume Building (M-20), the McMillan Control House North (M-6), and the NCW as outlined in specification section 02 41 00 - Demolition.

Prior to demolition of the McMillan flume building (M-20) or the McMillan control house north (M-6) the contractor must schedule an outage to remove all existing equipment to be salvaged and/or relocated within these buildings and turn salvaged material over to the government. In the McMillan control house north (M-6) the contractor will relocate the South Clearwell remote panel to allow continued use during construction. The contractor will also remove the South Clearwell bypass flowmeter transmitter from the building and turn over to the government for contractor reinstallation after construction of the new McMillan Control House North (M-6). Other salvaged equipment within the McMillan Control House North (M-6) includes:

a. To be removed by the contractor and reinstalled by the contractor at a later date:

i. Accusonic control panel

ii. Remote i/o panel

b. To be removed by the contractor and turned over to the government:

i. Turbidimeter/transmitter

ii. Ph meter/transmitter

c. To be removed, restored and reinstalled by the Contractor at a later date:

i. Historic North Clearwell Drain Valve Operator mechanism.

Prior to demolition of the McMillan flume building (M-20) or the McMillan control house north (M-6) the contractor must complete and receive approval of the mockup panels in accordance with Section 04 20 00 Unit Masonry

1.2.4 Other Requirements

The contractor must protect the existing drain chamber sump below the McMillan control house north (M-6) throughout construction. Existing drain chamber walls cannot be demolished until the support of excavation system including the horizontal struts are installed in this area.

The contractor must protect the influent slide gate CV 6-50 to remain in place throughout construction. The influent slide gate CV 6-50 stem and actuator (gate operator) to be removed and stored by the Contractor for reinstallation by the contractor at the end of the project.

There is an upcoming DC Water Project: "Soldiers Home 48 TN REHAB". This project will require site access for construction efforts at the south end and north end of the clearwell. Tentative timeline for this construction effort is late 2024 and early 2025. The contractor shall coordinate with GF-D Design Partners JV and the Washington Aqueduct.

SECTION 01 14 00 Page 2

All new materials in contact with potable water, including but not limited to; expansion joint materials, paint, patching material, and epoxy for adhesive; must comply with ANSI/NSF61.

1.2.5 Permits

ACTIVITY SUBMISSION DATE SUBMISSION FORM

Borrow Permits 14 calendar days prior to work

As Directed by the

COR

Excavation Permits 14 calendar days prior to work

As Directed by the

COR

Welding Permits 14 calendar days prior to work

As Directed by the

COR

Post permits at a conspicuous location in the construction area.

Burning of trash or rubbish is not permitted at on project site.

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 McMillan WTP Regulations

Ensure that Contractor personnel employed on the McMillan WTP become familiar with and obey McMillan WTP regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.3.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.3.1.2 Security Requirements

Two of the contractor's designated employees (typically the foreman and project engineer) will be required to obtain Washington Aqueduct badges.

The badge issuance requires a background and e-verify check. These employees will be responsible for Washington Aqueduct issued keys and maintaining the daily worksite roster, Form 1999. The rosters will need to be submitted to Washington Aqueduct Security Chief weekly.

A badged individual is required on site at all times when work is being performed.

1.3.1.3 No Smoking Policy

Smoking or the use of tobacco products within the clearwell is strictly prohibited.

SECTION 01 14 00 Page 3

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.3.1.4 Food and Drink Policy

Eating and drinking is prohibited within the clearwell except for the consumption of plain water.

1.3.2 Working Hours

Regular working hours will consist of an 8 1/2 hourperiod established by the Contracting Officer, between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays.

1.3.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.3.4 Occupied Buildings

The Contractor shall be working around existing buildings which are occupied and located on McMillan WTP property. Do not enter the buildings without prior approval of the Contracting Officer.

Occupied buildings are not within the contractors SOW. Buildings on The McMillan WTP will remain operational during construction. The contractor shall not interfere with operations on the McMillan WTP.

The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

1.3.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. All outages must be requested no less than 2 weeks in advance.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and water treatment processes are considered utility cutovers.

Such interruptions are further limited to the hours defined for the interruption. This time limit includes time for deactivation and

SECTION 01 14 00 Page 4 reactivation.

d. Operation of Water Treatment Plant Utilities: The Contractor must not operate nor disturb the setting of control devices in the McMillan Water Treatment Plant , including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

1.3.6 Water Treatment Plant Operational Events

There is a distinction between utility cutovers and interruptions discussed above and Water Treatment Plant Operational Events. Water Treatment Plant Operational Events are scheduled events of significant nature affecting the McMillan Plant wide operations. Such scheduled events would include by-passing the North Clearwell, draining the North Clearwell, commissioning and testing of new instrumentation and controls, or similar significant events having an affect on the overall McMillan Water Treatment Plant operations. These events must also be scheduled at least 2 weeks in advance, but must only occur during normal working hours in order that McMillan Water Treatment Plant personnel are on-site and available to monitor such events.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 14 00 Page 5

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 14 00 Page 6

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/20, CHG 3: 02/23

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Contract Cost Breakdown; G

1.2 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in the PRICING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.2.1 Demolition and Selective Salvage of M-6 McMillan Control House (North) and M-20 McMillan Flume Building

Payment: Payment will be made for work associated with the demolition, selective salvage, and HAER level 1 photo documentation of M-20 McMillan Flume Building. Salvage hollow metal doors, frame and transom, window sash and frame units, interior wood window trim, bricks, keystone, cast stone window sills and clay roof tiles in accordance with Section 02 42 91 Removal and Salvage of Historic Construction Materials. Demolish, remove and dispose of remaining building structure in accordance with Section 02 41 00 Demolition. Include palletizing and transport of roof tiles, door and window units for storage.

Payment will be made for work associated with the demolition, selective salvage, and HAER level 1 photo documentation of M-6 McMillan Control House (North). Salvage hollow metal doors and frame, window sash and frame units, interior wood window trim, bricks, brownstone window sills and clay roof tiles in accordance with Section 02 42 91 Removal and Salvage of Historic Construction Materials. Other salvaged equipment within the M-6 McMillan Control House North:

a. To be removed by the contractor and reinstalled by the contractor at a later date:

i. Accusonic control panel

SECTION 01 20 00 Page 1

ii. Remote i/o panel

b. To be removed by the contractor and turned over to the government:

i. Turbidimeter/transmitter

ii. Ph meter/transmitter

c. To be removed, restored and reinstalled by the Contractor at a later date:

i. Historic North Clearwell Drain Valve Operator mechanism.

Demolish, remove and dispose of remaining building structure in accordance with Section 02 41 00 Demolition. Include palletizing and transport of roof tiles, door and window units for storage

Unit of Measure: Job

1.2.2 Demolition and Replacement in Place of WAD-30 McMiIllan North Clearwell

Payment: Payment will be made for the selective demolition and disposal, new construction, and HAER level 1 photo documentation of the new North Clearwell, as shown on the drawing and as specified, including but not limited to new structural systems inclusive of new slab on grade, columns, exterior walls, baffle walls, new chambers, and roof, and all support of excavation and micropiles including delegated design. New roof hatches, ladders, slide gate, valves and actuators, confined space entry costs.

This includes extraordinary cleanup as specified in section 01 78 00 and final testing and commissioning of all systems.

Unit of Measure: Job

1.2.3 Reconstruction of M-6 McMillan Control House (North) and M-20 McMillan Flume Building

Payment: Payment will be made for the reconstruction of M-6 McMillan Control House (North) and M-20 McMillan Flume Building including, but not limited to, concrete foundations, brick masonry walls, wood-framed roof structure, clay tile roofing, wood windows and doors, frames, and trim as shown on the drawings and as specified.

Unit of Measure: Job

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in the PRICING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.3.1 Full Depth Pavement Replacement

Payment: Payment will be made for saw cutting and removal of existing pavement down to subgrade elevation (bituminous surface course, base course and aggregate base course),removal of material from site, preparing in-situ subgrade for application of new pavement

SECTION 01 20 00 Page 2 in accordance with Section 203 of the District of Columbia Standard Specifications (including proof rolling and replacement of un-suitable material as needed such that subgrade meets proper density and compaction requirements), placement of 8" graded aggregate base course, placement of 2.5" HMA Superpave PG 64-22 asphalt binder course, placement of 2" HMA Superpave PG 64-22 asphalt wearing course and placement of asphalt seal along sawcut lines. Limits of full depth pavement restoration are shown on the "Pavement Restoration Plan", Sheet C-128. Total estimated area of full depth pavement replacement: 8,877 SY. Payment will be based on measurement of the actual completed full depth pavement areas.

Unit of Measure: Square Yards

1.3.2 Mill and Overlay Pavement Repairs

Payment: Payment will be made for milling designated areas of the pavement below existing grade to a depth of 2" minimum and inspection of base material to ensure base course repair / replacement is not necessary. Placement of a tack coat and application of placement of 2" HMA Superpave PG 64-22 Asphalt Wearing Course to a depth of 2" minimum and sealing of any joints. Limits of mill and overlay are shown on the "Pavement Restoration Plan", Sheet C-128. Total estimated area of mill and overlay: 9,908 SY. Payment will be based on measurement of the actual completed mill and overlay areas.

Unit of Measure: Square Yards

1.4 CONTRACT COST BREAKDOWN

The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 20 00 Page 3

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 20 00 Page 4

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20, CHG 3: 08/23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Progress and Completion Pictures

Pre-demolition Photographs Building M-6 McMillan Control House (North); G

Pre-demolition Photographs Building M-20 McMillan Flume Building; G

Qualifications For Historic Reconstruction Contractor; G

1.3 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 10 digital photographs each month throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

The Contractor shall photographically document Building M-6 McMillan Control House (North) and Building M-20 McMillan Flume Building prior to start of demolition operations. Photograph all exterior and interior

SECTION 01 30 00 Page 1 elevations, using a wide-angle lens where required to include entire elevation in a single image. Photograph masonry, window, door and roof details. Photograph historic equipment in situ. Provide digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format. Submit two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD). Provide photographs for each building in a separate directory and name each file to indicate its location and orientation on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

1.4 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by District of Columbia law.

1.5 SUPERVISION

1.5.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings.

The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.5.2 Alternate Superintendent Qualifications

Provide an alternate project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The Contracting Officer may request proof of the alternate superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.5.3 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.5.4 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or

SECTION 01 30 00 Page 2 qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.5.5 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.6 RECONSTRUCTION OF M-6 MCMILLAN CONTROL HOUSE (NORTH) AND M-20 MCMILLAN

FLUME BUILDING.

1.6.1 Reconstruction Contractor Qualifications

The Contractor undertaking the reconstruction of buildings M-6 and M-20 shall have specific experience in the reconstruction of historic structures. The reconstruction will be carried out in accordance with the Secretary of the Interior's Standards for Reconstruction and the contractor must demonstrate experience reconstructing other similar historic structures in accordance with these standards. Experience must include new masonry construction, including familiarity with decorative brick bonds, Flemish bond patterns, replicating original mortar joints, installation of new and salvaged terra cotta clay roof tiles, doors and windows. General construction experience in masonry, carpentry, and roofing is insufficient for historic reconstruction, and will not be considered acceptable. The contractor shall demonstrate these qualifications by completing the attached Past Performance Questionnaire for at least three (3) projects within the previous five (5) years, and provide specific details explaining why these projects are similar in scope to the reconstruction of buildings M-6 and M-20. Submit these Qualifications for historic reconstruction contractor with other preconstruction submittals.

1.7 PRECONSTRUCTION CONFERENCE

Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference . The conference must take place within 35 calendar days after award of the contract, but prior to Notice to Proceed.

The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, historic preservation procedures, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.7.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

SECTION 01 30 00 Page 3

1.8 PARTNERING

Contractor shall host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.8.1 Team-Led (Informal) Partnering

a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.

b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.

c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.

d. The Partners will determine the frequency of the follow-on sessions.

e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.

1.9 MOBILIZATION

Contractor shall mobilize to the jobsite within 60 calendar days after Notice to Proceed . Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.

Starting at Notice to Proceed and continuing until final completion the Contractor is responsible for site maintenance to include mowing and trimming. This shall include the LOD, staging and storage areas, and any other area that is in use by or the responsibility of the Contractor during the work.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 30 00 Page 4

SECTION 01 30 00 Page 5

SPECIFICATION SECTION 01 30 00 - QUALIFICATIONS ATTACHMENT

PAST PERFORMANCE QUESTIONNAIRE

USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0) CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: USACE REQUESTS THAT THE CLIENT COMPLETES THIS QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL, AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL

INFORMATION ON THIS FORM.

Source Selection Information - See FAR 2.101 and 3.104

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 30 00 Page 6

SECTION 01 32 01.00 10

PROJECT SCHEDULE

08/23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

AACE 84R-13 (2015) Planning and Accounting for Adverse Weather

AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)

ASCE 67-17 (2017) Schedule Delay Analysis

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (2017) Administration -- Project Schedules

1.2 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Preliminary Project Schedule; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules for projects of similar size and complexity to this contract, using Primavera P6..

Representative must have a comprehensive knowledge of CPM scheduling principles and application.

SECTION 01 32 01.00 10 Page 1

1.4 SEQUENCE OF CONSTRUCTION

The contractor shall adhere to the following sequence of construction below:

1. Relocate power and communication feeders in southwest corner of the North Clearwell (NCW) around the NCW to maintain power and communication to the McMillan Guard House (M-5) and the South Clearwell (SCW). See power phasing notes and communication phasing notes on drawing E-002.

2. Implement NCW by-pass to SCW, drain NCW, and take off line - to be completed by the government after proper notice by the contractor.

Contractor shall close the existing slide gate CV 6-50 and remove the stem and actuator (gate operator) and store for reinstallation by the contractor at the end of the project .

3. Access to the NCW for equipment and Support of Excavation (SOE) is through an existing large hatch along the west side of the NCW that can be removed to allow the installation of strut segments and equipment. Alternately, if the contractor would like to access the NCW by means of cutting any additional openings, these requested access locations shall be included in a comprehensive delegated design package signed and sealed by the contractor's engineer and submitted to the government for review.

4. Prior to demolition of either the NCW, or M-20 the McMillan Flume Building, or M-6 the McMillan Control House (North), the contractor must complete and receive approval of all historic American engineering record (HAER) documentation as discussed in specification sections 01 14 00 - WORK RESTRICTIONS and 02 41 00 - DEMOLITION. This approval must be received prior to any work taking place in the NCW.

Further, prior to any demolition of either m-20 or m-6, the contractor must complete and receive approval of the building mock-ups as discussed in specification section 04 20 00 - UNIT MASONRY. The demolition of m-20 and m-6 include the removal and salvage historic materials, and prior to demolition of these structures the contractor must submit and receive approval of a work plan including detailed descriptions of methods and equipment to be used, and the sequence of operations of demolition, as required by specification section 02 42 91

- removal and salvage of historic construction materials .

5. Assemble the strut segments inside the tank.

6. Install new influent, and effluent chambers.

a. New influent chamber:

i. Existing bypass valve leaks, and allows a flow of water into the NCW during by-pass operations. Contractor will need to install a dewatering sump in the new influent chamber during construction of the new influent chamber.

ii. Install micropile soe around new influent chamber footprint.

iii. Install pile cap beam

iv. Demolish and install new chamber slab

SECTION 01 32 01.00 10 Page 2

V. Install new chamber walls and gates

b. New effluent chamber:

i. Existing effluent gate between the NCW and SCW leaks, and allows a flow of water from the SCW into the NCW even when this gate is in the closed position. Contractor will need to install a dewatering sump in the new effluent chamber during construction of the new effluent chamber.

7. Cut the existing floor and install micropiles underneath the vertical elements supporting the struts. A cap is needed above the micropiles as well but should be beneath the existing floor. The presence of openings at the micropile cap locations undermine the diaphragm action of the existing floor. As such, pour concrete above micropile cap to restore diaphragm action.

8. Install soe columns, upper and lower struts with the necessary walers.

9. Install new drain chamber.

a. The contractor will need to demolish m-6 prior to the construction of the new drain chamber, in order to access the space between the existing drain chamber walls, and the new drain chamber walls

b. Only after all soe has been installed in the NCW, demolish m-6, and cut and remove the NCW roof immediately below m-6 to gain access to the drain chamber

c. Existing effluent pipes from the drain chamber will need to be temporarily securely plugged to prevent water, demolition, or any other debris and material from existing through the drain chamber effluent pipes during construction of the new drain chamber

d. Demolish existing drain chamber walls.

e. Install micropiles for drain chamber foundation.

f. Demolish existing drain chamber slab.

g. Excavate down and install pile cap foundation.

h. Extend new mat slab to face of drain chamber opening, and over pile cap foundation.

i. Install new drain chamber walls.

10. Install dewatering wells around perimeter of NCW to reduce hydrostatic pressure on existing walls and flotation of the NCW. Please see dewatering notes on b-201. These dewatering wells to be installed at any time before demolition of roof and columns.

11. Demolish North Clearwell existing roof and columns.

12. Install dewatering wells within the NCW in select locations, and then remove existing floor as required .

SECTION 01 32 01.00 10 Page 3

13. Construct new tank mat foundation.

14. Remove lower struts only after new mat foundation has been installed.

15. Construct new walls from mat foundation to roof level with minimal openings and joints. Construct new columns and new roof and access hatches.

16. Remove remaining soe upper struts and columns only after new…