This is an amendment to a solicitation for construction services for the SOCOM Training Support Facility at Humphreys Engineer Center in Alexandria, Virginia. The scope of work includes construction of the Training Support Facility building and associated site work, utilities, and optional items such as furniture, audiovisual equipment, IT/communications systems, and electronic surveillance systems. The solicitation is issued by the US Army Corps of Engineers Baltimore District on behalf of the Special Operations Command. The pre-bid site visit will take place on July 16, 2021 at the Humphreys Engineer Center, where valid government ID will be required to enter the facility. Offers are due by August 6, 2021 and will be evaluated by adding the total price for all base and optional items. The selected contractor will be responsible for all work within five feet of the building lines as well as specified additional site and utility connections.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Correct language listed under the site visit information/clause.
2. Remove "Attachment G: Site Visit HECSA Visitor Authorization" from List of Attachments
3. Provide the updated Price Schedule.
1. CONTRACT ID CODE PAGE OF PAGES
1 8
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-Jul-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DR21R0027
X 9B. DATED (SEE ITEM 11)
09-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-Jul-2021
CODE
USACE, BALTIMORE
2 HOPKINS PLAZA
BALTIMORE MD 21201
W912DR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DR21R0027
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The Issued By organization has changed from
USACE, BALTMORE DISTRICT
2 HOPKINS PLAZA
BALTIMORE MD 21201
to
USACE, BALTIMORE
2 HOPKINS PLAZA
BALTIMORE MD 21201
The following have been modified:
PRICE SCHEDULE
Item No.
Description Amount
Base Bid Items 0001 All costs in connection with the construction of the Training Support Facility to points 5 feet outside the building lines, including utilities, complete as shown on drawings and specified, but exclusive of Base Bid Items 0002 – 0004 & Optional Bid Items 0005 – 0013 below. Building Infrastructure for the optional bid items is to be part of the base building package. $_________
0002 All costs in connection with construction of the Storage and
Training Support Building beyond points 5 feet outside the building lines, including site improvements, utilities and applicable related work, complete as shown on the drawings and specified, but exclusive of work covered under Base Bid Items 0001, Base Bid Items 0003 – 0004 & Optional Bid Items 0005 – 0013 below. $_________
0003 All costs in connection with installation of the Gas Utility Connection complete as shown on drawings and specified. $_________
0004 All costs in connection with installation of the Electrical Utility
Connection complete as shown on drawings and specified. $_________
Total Base Bid Amount $__________
Optional Bid Items 0005 All cost associated with the removal of underground communication duct-bank complete as shown on the drawings and specified. $ ________
0006 All costs in connection with the purchase & delivery of
Furniture, Fixtures & Equipment, complete as shown on the drawings and specified. $ ________
0007 All costs in connection with installation of the Furniture, Fixtures & Equipment, complete as shown on drawings and specified. $________
Item No.
Description Amount
0008 All costs in connection with the purchase & delivery of Audio-
Visual Equipment, complete as shown on the drawings and specified. $________
0009 All costs in connection with the installation of the Audio-
Visual Equipment, complete as shown on the drawings and specified. $ _______
0010 All costs in connection with the purchase & delivery of IT/Communication Equipment, complete as shown on the drawings and specified. $________
0011 All costs in connection with the installation of the IT/Communication Equipment, complete as shown on the drawings and specified. $_______
0012 All costs in connection with the purchase & delivery of Electronic Surveillance Systems (ESS), complete as shown on the drawings and specified. $ _______
0013 All costs in connection with installation of the Electronic Surveillance
Systems (ESS), complete as shown on drawings and specified. $ _______
Total Base and Optional Bid Amount $__________
NOTES TO OFFERORS
Offerors must quote on all items including Optional Items. Failure to quote on all items may be cause for rejection of the proposal.
The Contracting Officer may exercise the Optional Items by written notice to the Contractor, postmarked within the period specified below. The Government may exercise any, all or none of the listed Optional Items in any order. Optional items may be exercised as follows:
- Optional Item 0005 may be exercised at any time within 90 calendar days after the Notice to Proceed.
- Optional Items 0006 through 0013 may be exercised at any time within 465 calendar days after the Notice to Proceed.
No additional time for contract completion will be allowed when an Optional Item is exercised.
EVALUATION OF OPTIONS: Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirements. Evaluation of options will not obligate the Government to exercise the option(s). (FAR 52.217-5 JUL 1990)
SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for 9:00 AM on Friday, July 16, 2021.
This will be a dual site visit for the Training Support Facility (TSF) and the Maintenance and Supply Facility
(MSF).
All attendees must process through Tulley Gate to obtain a visitor’s pass. A valid government issued state ID is required for all attendees. Attendees are encouraged to visit the security gate at least 30 minutes prior to the scheduled site visit.
POC: Chimeadu Ewoh Email: Chimeadu.A.Ewoh@usace.army.mil Phone: 443-285-2106
(c) Participants will meet at the overflow parking lot opposite the TSF site as shown on the attached google map.
HECSA ENTRANCE REQUIREMENTS
1. Mask are required at all times while on the installation.
2. A valid government issued state ID is required.
3. All attendees must be U.S. Citizens.
(End of provision)
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
LIST OF ATTACHMENTS
Attachment A: Experience in Relevant Projects Attachment B: Past Performance Questionnaire Attachment C: Small Business Participation Plan Proposal Format Attachment D: Standard Form LLL Attachment E: Certificate of Corporate Authority Attachment F: EFT Form Attachment G: Site Visit HECSA Visitor Authorization
(End of Summary of Changes)
File details come from the government source that posted it. Updated .