B.08.03 Amendment_W912DR21R0018 0002.pdf
PDF 1 MB Posted
- Solicitation number
- W912DR21R0018
About this file
This is a solicitation for design-build construction services for a Vehicle Maintenance Shop project at Fort Belvoir, Virginia. The U.S. Army Corps of Engineers, Engineering District Baltimore is seeking proposals for design and construction of a standard-design medium Vehicle Maintenance Shop, Company Operations Facility, hazardous waste storage, oil storage buildings, vehicle parking, storage facilities, and supporting site work and utilities. The contract will be a firm-fixed-price design-build award made to the offeror representing the best value based on evaluation of past performance, management approach, technical approach, small business participation plan, and price factors. The solicitation is conducted in two phases, with the first phase focused on qualifications and the second on detailed proposals from the up to five most highly qualified offerors selected from phase one. The response deadline for phase one is listed on the SF1442 form.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide a response to an inquiry received during the Request for Information (RFI) period. Additionally, attachment naming has been updated to reflect correct structure. Changes have been highlighted in yellow . All other terms and conditions remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
1 14
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-May-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DR21R0018
X 9B. DATED (SEE ITEM 11)
06-May-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-May-2021
CODE
USACE, BALTIMORE
2 HOPKINS PLAZA
BALTIMORE MD 21201
W912DR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DR21R0018
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS
The following have been modified:
PHASE I PROPOSAL SUBMISSION
SECTION II
PHASE I SOLICITATION PROVISIONS
1. PROPOSAL SUBMISSION INSTRUCTIONS
1.1. General: This request for proposal (“RFP”) seeks proposals from Offerors interested in being selected for design-build construction of the Vehicle Maintenance Shop project at Fort Belvoir, Virginia. This is Phase I of a two-phase RFP issued in accordance with FAR Subpart 36.3. This RFP is requesting submission of proposals under phase one submission criteria ONLY. After evaluating phase one proposals, the contracting officer will select the most highly qualified Offerors and request that only those Offerors submit proposals for Phase II. The maximum number of Offerors that will be selected to submit Phase II proposals is five (5). Offerors shall not submit any proposals under Phase II submission criteria at this time. Phase II of the solicitation will be issued in an amendment directly to those Offerors selected for Phase II. Submitting any information under Phase II criteria may lead to disqualification of your proposal. This is a Full and Open competitive solicitation. Offerors responding to this RFP are required to submit their proposals in accordance with the instructions contained in this Section 00 21 16.
The work is summarized as follows: Construct a standard-design medium Vehicle Maintenance Shop and a Company Operations Facility to include hazardous waste storage and oil storage buildings, organizational vehicle parking, vehicle storage facility, open and organizational equipment storage. Construction will include special foundations and connection to Energy Monitoring Control Systems (EMCS), intrusion detection systems (IDS) installation, fire alarm and suppression and building information system. Supporting Facilities include electric services, water and gas distribution and wastewater collection lines, a water pump for fire suppression system, access road, pavements, curbs and gutters, storm drainage, site preparation, environmental studies and documentation, and information systems. Antiterrorism/force protection measures include laminated glass windows in reinforced frames, reinforced exterior doors, security lighting, fencing, barriers, and visual screening.
Heating and air conditioning will be provided by stand-alone systems. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Code (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance. Sustainability and Energy measures will be provided. Access for individuals with disabilities will be provided. Comprehensive building and furnishings related to interior design services are required. Demolish 1 Building (5,147 Total SF).
Air Conditioning (Estimated 150 Tons) and the other building is modular (4,820 Total SF).
This is a competitive acquisition for the award of a firm-fixed-price design-build contract. A contract will be awarded to the Offeror whose proposal represents the “Best Value” to the Government. The best value determination will be based on a comparative assessment of proposals against all source selection criteria in the solicitation, considering recommendations and minority opinions presented to the Source Selection Authority (SSA). While the SSA may use reports and analyses prepared by others, the source selection decision shall represent the SSA's independent judgment. The evaluation factors applicable to this procurement appear below.
1.2. Basis for Award: A contract will be awarded to the Offeror whose proposal represents the “best value” to the
Government. The best value determination will be based on a comparative assessment of proposals against all source selection criteria in the solicitation, considering recommendations and minority opinions presented to the Source Selection Authority (SSA). While the SSA may use reports and analyses prepared by others, the source selection decision shall represent the SSA's independent judgment.
For the purposes of this solicitation, the Government will utilize the best value Trade-Off Process. The following evaluation factors will be used to evaluate each proposal. Award will be made to the Offeror whose proposal is the most advantageous to the Government based on an integrated assessment of the evaluation factors described below.
PHASE I
Factor 1 - Past Performance and Experience Factor 2 - Management Approach
For Phase I, Past Performance and Experience (Factor 1) and Management Approach (Factor 2) will be adjectivally rated. Past Performance and Experience (Factor 1) is more important than Management Approach (Factor 2). Past Performance & Experience (Factor 1) and Management Approach (Factor 2) will not carry over to Phase II.
PHASE II
Factor 3 - Technical Approach Factor 4 - Small Business Participation Plan (SBPP) Factor 5 - Price
For Phase II, Technical Approach (Factor 3) and SBPP (Factor 4) will be adjectivally rated. Technical Approach (Factor 3) is more important than SBPP (Factor 4). When combined, Technical Approach (Factor 3) and SBPP (Factor 4) are approximately of equal importance to Price (Factor 5).
1.3. Source Selection: It is the intent of the Government to seek proposals from qualified Offerors with experience in the significant features of this RFP and who can demonstrate a successful performance history in completing relevant projects. For the purposes of this solicitation, the Government will utilize the Trade-Off Process. The successful Offeror will be selected based on the “Best Overall Value to the Government”. The Government will not make an award at a significantly higher price to obtain only slightly superior technical advantages; however, the degree of importance of price as a factor could become greater depending upon the equality of the proposals submitted. Where the technical merits of competing proposals are determined to be substantially equal, price could become the controlling factor.
1.4.Each Offeror is required to submit a proposal consisting of the following volumes in separate electronic files
CLEARLY MARKED PHASE I AND IDENTIFIED WITH THE PHASE I SUBMISSION DATE:
a. Phase I: Volume I – Technical Proposal, Part 1 (Factors 1-2), (electronic file)
b. Phase I: Volume II – Administrative Documents (electronic file)
The content of these volumes is discussed in section 1.5, below.
1.5. Specific Requirements: An Offeror’s proposal shall consist of all information and material submitted in writing for evaluation in response to this solicitation. The submission of false or misleading information shall be grounds for disqualification of the proposal. The Offeror’s name, solicitation number and solicitation Closing Time and Date, must be affixed to the outside of each volume. Offerors must organize their proposals as described and outlined below. Each volume must have a table of contents and a Cover Sheet to include the Offeror’s CAGE Code, address, NAICS and business size in accordance with the System for Award Management (SAM) and Point of Contact information, such as email and phone number. Each volume’s contents must be separated by tabs as discussed below. The proposals must be in an 8-1/2” x 11” format. Pages may be single-sided or double-sided (double-sided pages count as two pages) and must be numbered. The minimum acceptable type size is eleven (11) point with a minimum of one-inch margins on all sides. The information in each volume must be organized as follows.
1.5.1. Volume I (Technical Proposal) (Factors 1-2): Offerors must submit the information identified in section 2, below. The information must be divided by tabs and shall be organized as follows:
TAB 1 - Factor 1 Past Performance/Experience TAB 2 - Factor 2 Management Approach
The total number of pages must not exceed 30 pages in the aggregate. The data appearing in Factor 1 behind the tab for 2.2.2 relating to past performance evaluations and awards, are not counted in the overall page limitation. Offerors may distribute the pages among the Factors at their discretion. If the Offeror exceeds the page limitation, then the excess page(s) after page 30 will not be evaluated (cover page/letter, table of contents, actual tabs, and PPQ-0/CPARS are not included in count.).
1.5.2. Volume II (Administrative Documents): The Administrative Documents must be placed in a separate envelope. It must contain the following:
a. SF 1442 (Solicitation, Offer and Award). Note - All amendments must be acknowledged in block 19;
b. Certificate of Corporate Principal/Authority;
c. Section 00 45 00;
d. Proof of Bonding Capability of at least $20,000,000;
Those Offerors selected for Phase II will have to re-sign the SF1442 and acknowledge all amendments.
1.5.3. Proposal shall be marked with the Offeror’s name, Solicitation Number, and the solicitation Closing Time and Date. (See SF1442 Block 1 and Block 13)
1.5.4. Offerors shall submit their proposals using the link, https://safe.apps.mil/, to the Contract Specialist, Michael Getz, Michael.J.Getz@usace.army.mil, and Contracting Officer, Tamara Bonomolo, Tamara.C.Bonomolo@usace.army.mil for both phases of this procurement.
ALL PROPOSALS SHALL BE SUBMITTED ELECTRONICALLY THROUGH THE SAFE SITE.
Submission shall be in searchable Adobe PDF format and legible. You are limited to five (5) maximum files per upload (total size cannot exceed 2 GB). If you have a large number of files, it is recommended that you combine or ZIP your files before uploading to the SAFE site. Offerors may use compression utility software such as WinZip or PKZip to reduce file size and facilitate transmission.
REQUEST FOR UPLOAD CODE: Offerors must email Contract Specialist Michael Getz at Michael.J.Getz@usace.army.mil no later than five (5) working days prior to the proposal due date to receive a request code which will allow for file uploads via the SAFE site. Offerors that fail to email for a request code five (5) working days before proposal submission date may not be able to receive a request code in time to upload their submission.
THIS MUST BE DONE FOR BOTH PHASES OF THE PROCUREMENT.
FILE DESCRIPTION: Include a “File Description” for each file(s) you upload. The “File Description” will be included in the email notice to the recipient you choose to have access your file(s). NOTE: Do NOT enter Privacy Act Data (Personal Identification Information (PII)) in the File Description.)
INSTRUCTIONS TO FOLLOW ON THE SAFE WEBSITE:
1. Once at the SAFE website select the “Drop-off” icon. This allows users without a CAC or users whose computer is not configured to read a CAC, the option to access the SAFE site as a guest.
2. After selecting the “Click Here” link you will be prompted to add your personal information, file information, recipient (Government representative) information and email settings.
3. When completing your file information for transmittal via the SAFE website, you will be required to enter the email address for the recipient. For this solicitation, the recipient is the Contract Specialist and the Contracting Officer. The Contract Specialist for this solicitation is Michael Getz, Michael.J.Getz@usace.army.mil and the Contracting Officer is Tamara Bonomolo, Tamara.C.Bonomolo@usace.army.mil. The E-Mail address of the Government Employee who initiated the request code will be automatically entered. The Proposer must enter the email address for the Contract Specialist and Contracting Officer. After entering the email address, click the ADD button to add the person(s) email to the “Recipients List” of your response. When your proposal is submitted, a notification will be sent to the recipient you added.
NOTE: Do NOT send the SAFE site packages to group email accounts.
Even if you successfully upload your proposal to the SAFE site, notification will not be sent to the government recipient until you verify your email address. Entering an incorrect email may result in the rejection of your submission for lateness. A Proposer can confirm proper submission by the ‘Drop-Off Completed” screen which generates based on proper file submission.
NOTE: It has been reported that documents are more quickly uploaded into the SAFE website when using a Firefox web browser. The Government cannot verify that this is true and offers no guarantee that Offerors will have more success utilizing any particular browser.
RECEIPT OF SUBMISSIONS:
For the purposes of establishing whether a proposal submission is considered timely, the government considers the date and time the submission is completely uploaded into the SAFE website. For proposals larger than the 2GB capacity of the SAFE website and require multiple submissions, the Government will consider the date and time the last submission is completely uploaded into the SAFE website. Do not assume that electronic communication is instantaneous. It can take several minutes or even hours in some cases. The government will not be responsible for submissions delivered to any location or to anyone other than those designated to receive proposals. Offerors are responsible for ensuring that proposals are submitted so as to reach the designated recipient. Offerors are responsible for allowing sufficient time for the proposal to be received in accordance with the instructions provided.
All proposals shall be submitted no later than the time and date specified on the SF 1442, block 13. Offeror’s proposal received after the required time and date deadline will not be evaluated. Offerors should not assume that they will have an opportunity to clarify or correct anything in their proposal after submitting it in response to the original Solicitation, and so any submissions should be submitted on the best terms possible and free of errors.
2. SUBMISSION CRITERIA
2.1. VOLUME I – MINIMUM SUBMISSION CRITERIA (TECHNICAL PROPOSAL, FACTORS 1-2): For purposes of this solicitation, an “Offeror” may include a group of two (2) or more entities that have formed a “contractor team arrangement,” as that term is defined in the Federal Acquisition Regulation, Part 9.6. In the case of entities that have formed a contractor team arrangement, the experience and performance history of any member of the team, whether or not gained while working with the other member(s) of the currently-proposed contractor team arrangement, will be considered as a part of the evaluation of the Offeror’s proposal.
An Offeror that relies upon the experience and performance history of a member, members or affiliates of a proposed contractor team arrangement must provide a teaming agreement or commitment (in the case of any affiliates) signed by all parties. The Teaming agreement/commitment shall:
a. Identify the legal name(s) and cage code(s) of all entities.
b. Describe the nature of each entity’s relationship (partnership, joint venture, prime/sub or mentor/protégé) and their role on this project as a part of their proposal. The Offeror will be expected to maintain that arrangement during performance of any contract awarded to that Offeror under this solicitation.
c. The estimated percentage of work to be completed by each member submitted for the solicitation. This can be a rough order of magnitude for Phase I; however, this agreement/letter must be resubmitted with Phase II to include that actual proposed percentages.
In the case of affiliates, past performance of an Offeror’s “affiliate”, as that term is defined in FAR 2.101, will be evaluated (as described within this section) if the Offeror demonstrates a firm commitment that the affiliate will participate meaningfully (e.g. roles, responsibilities, etc.) in the performance of the contract. This commitment, nature of each entity’s relationship and meaningful participation shall be described in a document signed by authorized representatives of both the Offeror and its affiliate.
The contractor team agreement/commitment shall be provided at the beginning of the Offeror’s technical proposal, prior to Factor 1, and will not be included in the overall page count.
The following are to be used in determining the status of the Offeror’s team for the evaluation of project submissions under Factor 1:
In the case of contractor team arrangements involving a Prime Contractor and Subcontractor(s), where the
Prime Contractor submits the proposal in response to this solicitation, the Prime Contractor is considered the “Prime Offeror”.
In the case of joint ventures, the “Prime Offeror” experience can come from any of the entities involved in the venture.
In the case of mentor/protégé relationships, the relationship must be established by the two Offerors and approved by the chosen Government Agency prior to proposal submission. Once the relationship has been approved, the “Prime Offeror” experience can come from any of the entities involved in the relationship. The approved mentor/protégé document from the Government Agency must be submitted along with the teaming agreement.
In the case of additional projects submitted by subcontractors, the subcontractor must submit the final cost of their portion of the project along with total project cost and all other required information.
In the case of Offerors that are large, multi-function firms (consisting of subsidiaries), experience must only be submitted by the segment of the firm (e.g., division, group, and unit) that is submitting a proposal in response to this solicitation.
In the case of affiliates, Past performance of an Offeror's "affiliate," as that term is defined in FAR 2.101, will be evaluated (as described within this section) if the Offeror demonstrates a firm commitment that the affiliate will participate meaningfully in the performance of the contract. This commitment and meaningful participation shall be described in a document signed by authorized representatives of both the Offeror and its affiliate.
If a teaming agreement or commitment is not provided, the projects of any team members outside of the Prime Offeror will not be considered. If the Joint Venture/Mentor-Protégé is a Small and Large business, the Small Business will be evaluated as the Prime Offeror.
2.2. FACTOR 1 – PAST PERFORMANCE AND EXPERIENCE: The submitted material MUST be organized sequentially under tabs for each numbered section to facilitate evaluation. All narratives must contain sufficient detail to demonstrate technical capability.
An Offeror that relies upon the experience and performance history of a member, members or affiliates of a proposed contractor team arrangement, as indicated above, must provide a teaming agreement or commitment (in the case of any affiliates) signed by all parties.
The Offeror shall provide a teaming agreement with their proposed Designer.
In the case of contractor team arrangements involving a prime contractor and subcontractor(s), where the prime contractor submits the proposal in response to this solicitation, the prime contractor must have completed at least fifty percent (50%) of the total number of projects that meet the requirements for Factor 1 for consideration in response to the experience requirements of this solicitation.
*Note: In reference to Indefinite Delivery/Indefinite Quantity (ID/IQ) contracts: Task orders on ID/IQ contracts can also be submitted under Factor 1; however, each task order submitted must individually meet the requirements of the factor and the teaming agreement requirements in section 2.1 above. Submissions of multiple task orders as a project will not be accepted or evaluated.
2.2.1. EXPERIENCE IN RELEVANT PROJECTS: The Offeror shall submit information on at least three (3) but no more than five (5) design-build (DB) projects. All projects must demonstrate one hundred percent (100%) completion of the design and at least seventy five percent (75%) completion of the construction at the time of proposal submission. These projects must be of relevant scope and complexity and have either a minimum project size of 40,000 Building Gross Square Footage (BGSF) or demonstrate a minimum completion value of $15,000,000.00 considering adjustment for escalation from project completion to 2021, percentage completion no earlier than ten (10) years (preceding the original date of issuance of this RFP) and address the discussions requested on Attachment A while meeting the teaming agreement requirements in section 2 above.
* Note: All escalation values are to be labeled as escalated and the Offeror must explain in detail their escalation rationale, which must include any formulas, calculations, assumptions, etc.
At least one (1) DB project must demonstrate experience from the proposed designer.
If the Offeror’s submission exceeds the maximum project limitation of five completed projects, then the additional project(s) will not be evaluated.
At least one (1) project must demonstrate experience with vehicle maintenance facilities.
Relevant Projects must include at least three (3) or more of the following elements and each element must be demonstrated in at least two (2) projects. Each element must have a description of how the project meets the element to ensure that it meets the project requirements (e.g. concrete paving – For this project, 500 LF of concrete sidewalks were installed, 300 LF of curbs were removed and re-installed, etc.).
*Lists, charts/matrices and bullets will not be accepted when identifying relevant elements.:
Administrative spaces to include interior space construction/finishes HVAC System Installation, TAB and Commissioning Site design of projects containing parking of 10,000 SY or greater and hardstands of 1,500 SF or greater.
Sitework which must include tree removal, utilities, grading, storm drainage, and landscaping at a minimum VADEQ Permits or similar state entities (provide the state, entity, and type of permit) Electrical system installation/renovation Anti-Terrorism/Force Protection (AT/FP) and security measures (i.e. laminated glass windows in reinforced frames, reinforced exteror doors, barriers, fencing, security lighting, etc.)
It is the responsibility of the Offeror to identify, detail and demonstrate the relevancy of the submitted projects to the solicitation criteria elements. The evaluation committee WILL NOT make assumptions.
The information that is required to be supplied is identified on the form provided entitled “EXPERIENCE IN RELEVANT PROJECTS” (Attachment A). Offerors are not required to use the form itself as part of their proposal, but the information requested on the form must be in the Offeror’s proposal and should be in the same format as the form. Offerors may expand the form as necessary to accommodate the required project information.
The only submissions under the tab for this section are to be the completed “Attachment A” forms or similar format as indicated above. Only the information provided in either of these formats will be considered.
Company summaries/introductions, project summary charts/matrices, etc. will not be accepted or evaluated.
2.2.2. PAST PERFORMANCE QUESTIONNAIRES FOR EXPERIENCE IN RELEVANT PROJECTS: Formal performance evaluations shall be provided on the relevant projects submitted in response to Section 1.2.1. above. The Offeror must request that their client complete the USACE Past Performance Questionnaire for Relevant Experience (Form PPQ-0) (Attachment B) and submit the questionnaire as part of the Offeror’s technical proposal. The Offeror may provide an explanation if the performance evaluation rating is less than satisfactory. Where applicable, the Offeror must explain facts related to any partial or completely terminated project and disclose any projects with an assessment of liquidated damages for the failure to meet the contractually required completion date. Offerors are encouraged to follow-up with clients/references to ensure timely submittal of questionnaires.
If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before the proposal closing date, the Offeror must complete and submit with the proposal the first page of the PPQ (Attachment B) for projects submitted under the tab for EXPERIENCE IN RELEVANT PROJECTS, which will provide contract and client information for the respective project(s). Ensure correct phone numbers and email addresses are provided for the owner point of contact.
Previously completed PPQ-0s may be submitted provided that the documents do not reference any other solicitations.
Submitted PPQ-0s must only reference this solicitation. Contractor Performance Assessment Reporting System (CPARS) ratings will be accepted in lieu of PPQ-0s.
Past performance information may be obtained from any other sources available to the Government, to include, but not limited to, the Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS), Contractor Assessment Reporting System (CPARS) or other databases using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal; interviews with Program Managers, Contracting Officers, and Fee Determining Officials; and the Defense Contract Management Agency. The information obtained from these sources will be evaluated supplementary to the past performance questionnaires. In reference to the contracts pulled from these sources, the relevancy of the projects, completion dates, ratings and comments in the individual categories and overall ratings will be considered in making the overall confidence assessment.
The Offeror also may provide information regarding any awards received for work done on any of the projects described by the Offeror (Copies of awards must be included under this factor for validation.). Awards, Past Performance Questionnaires, and other past performance information will not be included in the page count for the proposal submission.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
2.3. FACTOR 2 – MANAGEMENT APPROACH
The submitted material MUST be organized sequentially under tabs for each numbered section to facilitate evaluation.
All narratives must contain sufficient detail to demonstrate management capability.
2.3.1. Describe the proposed management structure for the team to include both the construction and design firms, the resources available to each firm and how those resources will be utilized, their roles and responsibilities, and what subcontracting firms the Offeror is considering utilizing. Offerors are encouraged to describe prior experience working with their proposed designer.
2.3.2. Describe how subcontractors are managed by the contractor to include flow-down of contract requirements, responsibilities and coordination. Discuss how non-performance by subcontractors is handled by the general contractor.
2.3.3.Describe the role and interaction of the design team with the construction team during construction, addressing, at a minimum, design quality control; tracking design evolution and changes during design to meet the schedule;
management of the design during construction, including control and approval of revisions to the accepted design;
requests for information; shop drawing and submittal reviews and approvals; progress meetings; site visits, if any; and as-builts.
The Offerors must also provide a statement that, in accordance with the specifications of the RFP, all individuals, including subcontractors, will be able to gain access to the Fort Belvoir Installation.
3. EVALUATION CRITERIA
3.1. VOLUME I - EVALUATION CRITERIA (TECHNICAL PROPOSAL, PHASE I – FACTORS 1-2)
Offerors are cautioned that “parroting” of the Technical requirements with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal.
3.2. FACTOR 1 - PAST PERFORMANCE: All submissions by Offerors must demonstrate the minimum requirements for experience in relevant projects, as stated in paragraph 2.2. above. Validation of Offeror performance may occur through contacting the client point of contact (POC) provided by the Offeror on the first page of the PPQ and various government and commercial resources.
Past Performance evaluations will be rated in terms of performance confidence for the Government. That is, projects that are considered to be non-relevant in terms of size, scope or complexity, dollar value, percentage completion within eight (8) years, responses to the Attachment A, or not meeting the teaming requirements established in section 2.2.1.
(submitted under Factor 1) and demonstrating low past performance evaluation ratings will be interpreted as indicators of no confidence that the Offeror can successfully perform the work. More relevant projects and high past performance evaluations will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment than past performance of lesser relevance. Higher confidence assessments will be given for higher past performance evaluation ratings.
In the case of Offerors for which there is no information on past contract performance or where past contract performance information is not available, the Offeror may not be evaluated favorably or unfavorably on the factor of past contract performance (see FAR 15.305(a)(2)(iv).) In this case, the Offeror’s past performance is unknown and assigned a performance confidence rating of “neutral.”
3.3. FACTOR 2 - MANAGEMENT APPROACH: The Offeror’s narrative will meet the requirements of this RFP if the narrative is a project specific discussion that addresses the elements identified in paragraph 2.3. in sufficient detail to demonstrate management capability. The narrative must clearly demonstrate a reasonable approach to the management of contract, a general understanding of the requirements of this contract and a plan that has clearly applied the information provided in paragraph 1.1. which will lead to successful completion of all work within the contract duration.
4. EVALUATION PROCESS
4.1. Proposal Compliance Review: A proposal compliance review will be performed to ensure that all required forms and certifications are complete, that the technical proposal has been received and that the Offerors are eligible to propose. Offerors are advised that the evaluation and ratings of all proposals will be conducted in strict confidence. However, an Offeror’s failure to provide all of the requested information may adversely affect the evaluation or result in rejection of the proposal as nonresponsive.
4.2. Volume I (Technical Proposal, Factors 1-2) of the proposals will be evaluated by the Source Selection Evaluation Board (SSEB) as established by the Source Selection Authority (SSA). Offerors submitting proposals for this project should limit submissions to data essential for the evaluation of proposals. Each factor is rated individually based on the information contained in that specific factor; that is, evaluations will not be made across the factors, nor will information found in one factor be used in the evaluation of another factor. Factors 1 through 2 will be adjectivally rated. Factors 1 is more important than Factor 2.
Factor 1 - Past Performance Factor 2 - Management Approach
See section 2 above for a discussion of the evaluation criteria applicable to these factors.
Past Performance Ratings: There are three aspects to the past performance evaluation. The first is to evaluate the recency of the Offeror’s past performance which will be based on percentage completion no earlier than eight (8) years preceding the original date of issuance of this RFP. The second is to determine how relevant a recent effort accomplished by the Offeror is to the effort to be acquired through the source selection. The third aspect of the past performance evaluation is to establish the overall quality of the Offeror’s past performance.
Past Performance for Factor 1 (Past Performance) will be evaluated by examining the projects submitted under the tab for paragraph 2.2.1., Experience in Relevant Projects, to determine the relevancy of a recent effort accomplished by the Offeror and assigning one of the relevancy ratings below. These ratings will then influence the overall Confidence Assessment for Factor 1:
Adjectival Rating Definition
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
The following ratings will be used to identify the Government’s confidence in the Offeror’s Past Performance. These ratings will be influenced by the relevancy ratings, above, the past performance questionnaires (PPQ-0) as well as any Past Performance Information Retrieval System (PPIRS) ratings, Federal Awardee Performance and Integrity Information System (FAPIIS) ratings, Contractor Assessment Reporting System (CPARS) ratings or other databases using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror’s proposal; interviews with Program Managers, Contracting Officers, and Fee Determining Officials; and the Defense Contract Management Agency listed for and associated with the submitted projects; and any awards received for the submitted projects:
Adjectival Rating Description
Substantial Confidence
Based on the offeror's recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror's recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence
No recent/relevant performance record is available or the offeror's performance report is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence
Based on the offeror's recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence
Based on the offeror's recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
The following ratings will be utilized in the evaluation of Factor 2 (Management Approach). :
Adjectival Rating Description
Outstanding
Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Good
Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Acceptable
Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Marginal
Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Unacceptable
Proposal does not meet requirements of the RFP, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.
4.3. Source Selection Evaluation Board: The Source Selection Evaluation Board (SSEB) will conduct a review of the solicitation requirements and the approved evaluation criteria to ensure an equitable, impartial, and comprehensive evaluation against the solicitation requirements. The SSEB does not compare proposals against each other. The fundamental responsibility of the SSEB is to provide the Source Selection Authority (SSA) with information to make an informed and reasoned selection. The SSEB will therefore prepare a summary report containing adjectival assessments for each factor and their supporting rationale; brief the SSA; and prepare any other necessary items.
4.4. Phase I Down Select: After all of the evaluations described above have been completed, the SSA will consider all factors to determine which Offerors submitted the proposal that represents the best value to the Government , taking into consideration the stated evaluation factors and their respective weightings as specified in the RFP. The selection process is complex and depending upon the evaluation factors, the SSA may exercise a significant degree of judgment in selecting the Offerors. The adjectival ratings assigned by the evaluation team are labels and not the sole basis for proposal comparison. The SSA will not base his/her decision merely on the adjectival ratings or the comparative analysis and recommendations, which compares the strengths and weaknesses of the competing proposals but shall exercise independent judgment. It is the Government’s intention to advance up to five (5) of the most highly qualified Offerors from Phase I to Phase II.
4.5. Miscellaneous: The Government reserves the right to reject any or all proposals at any time prior to award, to negotiate with Offerors in a competitive range, if one is established, and to award a contract to the Offeror with the most advantageous proposal to the Government.
5. PHASE II
5.1. Phase II of the solicitation will be issued in an amendment directly to those Offerors selected for Phase II. Offerors are advised that it is the intent of the Government to make a determination for inclusion in Phase II evaluations without communications based on responses to Factors 1 and 2. Therefore, Phase I proposals should be submitted on the most favorable terms that the Offeror can submit to the Government.
PHASE II FACTORS: Phase II proposals will be evaluated based upon the design-build factors identified below.
Technical Approach (Factor 3) and Small Business Participation Plan (SBPP) (Factor 4) will be adjectivally rated and Price (Factor 5) will be evaluated based on the price schedule. Technical Approach (Factor 3) is more important than SBPP (Factor 4) and when combined, are approximately of equal importance to Price (Factor 5). Factors in Phase II will be evaluated in accordance with FAR Part 15.
Factor 3 – Technical Approach Factor 4 - Small Business Participation Plan Factor 5 – Price
If the Offeror cannot provide a Bid Guarantee in accordance with FAR 52.228-1, the Offeror’s proposal will not be considered valid for this solicitation.
6. SUBMISSION DEFINITIONS
Adverse past performance is defined as past performance information that supports a less than satisfactory rating from sources where the information is from other than formal rating systems such as "PPIRS or FAPIIS."
Best Value is the expected outcome of an acquisition that, in the Government’s estimation, provides the greatest overall benefit in response to the requirement.
Beneficial Occupancy Date (BOD) is the point at which the customer determines the facility or area can be occupied from both a regulatory and work function standpoint.
Building Gross Square Foot (BGSF) is the floor area of the entire building or project, which includes floor area occupied by rooms/spaces, walls, corridors, conveyances, mechanical/utility rooms, and shafts.
Contract Completion is determined to be when all the requirements of a contract are complete including Construction, testing, commissioning, documentation and transfer, and completed forms including claims release documentation.
Deficiency is a material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See
FAR 15.001.
Performance Confidence Assessment is an evaluation of the likelihood (or Government’s confidence) that the Offeror will successfully perform the solicitation’s requirements; the evaluation is based upon past performance information.
Rating is the evaluators’ conclusions (supported by narrative write-ups) identifying the strengths, weaknesses, and deficiencies of an evaluation factor. The ratings for the Technical Factors will be expressed as an adjectival or confidence assessment. The “rating” is simply the adjective itself. The strengths, weaknesses, etc., are the findings that support the rating.
Relevancy, as it pertains to past performance information, is a measure of the extent of similarity between the service/support effort, complexity, dollar value, contract type, and subcontract/teaming or other comparable attributes of past performance examples and the source solicitation requirements; and a measure of the likelihood that the past performance is an indicator of future performance.
Risk, as it pertains to source selection, is the potential for unsuccessful contract performance. The consideration of risk assesses the degree to which an Offeror’s proposed approach to achieving the technical factor or subfactor may involve risk of disruption of schedule, degradation of performance, the need for increased Government oversight, and the likelihood of unsuccessful contract performance.
Source Selection is the process used in competitive, negotiated contracting to select the proposal that offers the best value to the Government.
Significant Strength is an aspect of an Offeror’s proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.
Significant Weakness is a flaw that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
Strength is an aspect of an Offeror’s proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
Uncertainty is any aspect of a non-cost/price factor proposal for which the intent of the offer is unclear (e.g. more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission, or mistake).
Weakness means a flaw in the proposal that increases the risk of unsuccessful contract performance. See FAR 15.001.
7. EVALUATION FORMS: Evaluation forms recommended to be used in responding to this RFP are provided on the following pages. They include:
Attachment A - Experience in Relevant Projects Attachment B - Past Performance Questionnaire Attachment C - Certificate of Corporate Authority Form Attachment D - Standard Form LLL
(End of Summary of Changes)
| B.08.03 Amendment W912DR21R0018 0002 |
| RFI Responses for Amendment 0002 |
| B.08.03 Amendment W912DR21R0018 0002 |