Amendment 02

View the file

Other files

File Type Posted
B.01.02_Abstract_of_Bids.pdf PDF
W912DR18B0012-0005.pdf PDF
W912DR18B0012-0004.pdf PDF
W912DR18B0012_AMENDMENT_0003_090518.pdf PDF
I3A_Technical_Criteria_Feb_2010.pdf PDF
Site_Visit_Sign-in_sheet_27_Aug_18.pdf PDF
Site_Visit_Sign_In_8-16-18_.jpg JPG image
W912DR18B0012-01.pdf PDF
W912DR18B0012.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide the follow ing information:

1. An additional site visit w ill be held at 1:00PM EST on 27-August-2018

2. The RFI due date has been extended to 10:00AM EST on 29-August-2018.

3. The Bid Opening date has been extended and w ill be held at 11:00AM EST on 13-September-2018

4. Attached is the Unexploded Ordnance (UXO) Information - (See Continuation Page for information)

5. Attached is the attendee list for the site visit held on 16-August-2018.

1. CONTRACT ID CODE PAGE OF PAGES

1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Aug-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DR18B0012

X 9B. DATED (SEE ITEM 11)

10-Aug-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

21-Aug-2018

CODE

U.S. ARMY CORPS OF ENGINEERS, BALTIMORE

2 HOPKINS PLAZA

ROOM 03-G-01

BALTIMORE MD 21201

W912DR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DR18B0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

UXO INFORMATION

SPECIFICATION FOR GENERAL CONTRACTS

SECTION 02010

PERFORM UNEXPLODED ORDNANCE DETECTION,

PRELIMINARY IDENTIFICATION AND REMOVAL COORDINATION.

(July 1, 2016)

UNEXPLODED ORDNANCE (UXO)

PART I – GENERAL

1. BACKGROUND. This project is sited in the Aberdeen Area (AA) or the Edgewood Area (EA) of Aberdeen Proving Ground (APG). The construction “Statement of Work” lists the location of this project. Exact past usage of the area regarding Unexploded Ordnance (UXO) (impact area, burial site, etc.) is unknown. Since the history of the site is incomplete, it cannot be assumed to be free of subsurface UXO. The surface of the work area will be inspected and investigated for UXO by personnel employed by the Contractor before the Contractor can start any work, including pre-construction site visits. Areas where drilling, excavation, digging, trenching or other earth disturbance are required will be swept with geophysical remote sensing tools/instruments by pre-approved and certified Explosive Ordnance Disposal (EOD) personnel employed by the contractor. The geophysical tools may include seismic methods, metal detection, magnetometry, ground penetrating radar, resistivity and geophysical diffraction tomography. The tools used must be able to clear for both ferrous and nonferrous metals, must be suitable for the field conditions, and capable of locating material as small as 20mm ordnance at a depth of two feet.

During construction the Contractor will take appropriate action regarding the presence of UXO, as listed below.

2. UXO CONSIDERATIONS.

2.1. Removal and disposal of UXO is not a part of this specification. The intent is to assure that all possible efforts to detect and identify the presence of UXO are performed. The potential for UXO on this site is unknown, however due caution must be exercised to ensure that construction and excavation are accomplished with due regard for the potential presence of UXO.

2.2. When UXO is detected and identified as potentially loaded with explosives, chemicals, propellant or pyrotechnics, or when the buried object is exposed and cannot be identified as non-UXO, the contractor will coordinate with the Government Emergency Response Authorities and the Installation Safety Division. The location of the object will be marked with a yellow survey marker flag, all activities on the site will cease, and all personnel will evacuate to a safe observation limit. The EOD contractor will maintain site access control and ensure personnel safety until the Government Emergency Response Authorities arrive and take control of the site. The contractor must supply the Global Positioning System (GPS) coordinates for each item to the Installation Safety Division upon arrival of the Emergency Response Team. The GPS positions must also be noted in the final report. The contractor will allow the Government EOD personnel sufficient time to complete field evaluation, render safe, recover and dispose of UXO, per incident, when UXO is detected and identified.

2.3. UXO reporting procedures: The EOD contractor will notify the government Emergency Response Authority and the Installation Safety Division by dialing:

2.3.1. In the Aberdeen Area (AA):

Emergency Response: Government phone dial 911

Cell or non-government phone 410-278-7220

U.S. Army GarrisonAPG/ Safety: Dial 410-306-1095/1096

2.3.2. In the Edgewood Area (EA):

Emergency Response: Government phone dial 911

Cell/non-government phone 410-676-0960

GAPG/ Safety: Dial 410-306-1095/1096

NOTE: Ensure UXO personnel making the calls inform the Installation Safety Division that the Emergency Response call has been placed.

3. DISCLOSURE. Five days after Notice To Proceed, the name, address and telephone number of the EOD organization to be utilized will be disclosed in writing by the contractor to the Contracting Officer or the Contracting Officer’s Representative (COR). The disclosure of an EOD organization other than those listed in Paragraph 4.1 will be accompanied by information sufficient to enable the Government to determine the organization meets the qualifications listed in Paragraph 4.2. If the Contracting Officer determines that the EOD firm does not meet the qualifications in Paragraph 4.2, the contractor will, upon notification by the Contracting Officer, submit an alternate source. Failure to provide the name of an acceptable EOD firm within 10 days after issuance of Notice to Proceed may be reason for a termination for default action. Upon acceptance by APG of the EOD organization, it may not be changed without written permission from the Contracting Officer. No information regarding the disclosure of the EOD organization will be included in the bid.

4. UTILIZATION.

4.1. The contractor will employ one of the EOD organizations or a Government (APG) approved equal that are listed below. EOD organizations that are readily available in the area are:

U.S. Corps of Engineers Baltimore District 2 Hopkins Plaza Baltimore, MD 21201 Telephone: 410-962-6741

CBRNE Analytical Remediation Activity (CARA) Tech Ops/BE2200

APG, MD 21005-5001

Telephone: 410-436-6351/1924

EA Engineering, Science, and Technology, Inc.

1311 Continental Drive Suite K Abingdon, MD 21009 Telephone: 410-671-6051

Weston Solutions, Inc.

1371 Brass Mill Road, Suite N Belcamp, MD 21017 Telephone: 410-612-5900

Shaw E&I 2113 Emmorton Park Road Edgewood, MD 21040 Telephone: 410-612-6350

Chimera Enterprise International 2893 Yost Ct Edgewood, MD 21040 Telephone: 443-243-7247

Earth Resources Technology, Inc.

6100 Frost Place, Suite A Laurel, Md. 20707 Telephone: 301-361-0620

Other approved EOD organizations that are not readily available, but may be employed are:

CH2M HILL

5700 Cleveland Street, Suite 101 Virginia Beach, VA 23462 Telephone: 757-671-6250

EHS International, Inc.

13228 NE 20th Street, Suite 100 Bellevue, WA 98005 Telephone: 425-455-2959

ECC

Munitions Response Division 1746 Cole Blvd. Suite 350 Lakewood, Co. 80401 Telephone: 804-298-7607

PARSONS

1700 Broadway#900 ATTN: Bill Kelso Denver, CO 80290 Telephone: 303-764-1932

USA Environmental, Inc.

720 Brooker Creek Boulevard, Suite 204 Oldsmar, FL 34677 Telephone: 813-343-6336

Reactives Management Corp.

1025 Executive Blvd., Suite 101 Chesapeake, VA 23320 Telephone: 757-436-1033

UXB International, Inc.

2020 Kraft Drive, Suite 2100 Blacksburg, VA 24060 Telephone: 540-443-3700

IT Corporation 312 Directors Drive Knoxville, TN 37923-4799 Telephone: 423-690-3211

EOD Technology, Inc.

2229 Old Highway 95 Lenoir City, TN 37771 Telephone: 865-988-6063

ISSI Unexploded Ordnance, Inc.

P.O. Box 11 Huntsville, AL 35804 Telephone: 205-247-7050

Tetra Tec FW, Inc 4960 Corporate Drive, Suite 140 Huntsville, AL 35805 Telephone: 256-830-1991

Tetra Tech NUS, Inc (TtNUS) 2046 West Park Place, Suite A Stone Mountain, GA 30087 Telephone: 770-413-0965

Zapata Engineering

6302 Fairview Road Suite 600 Charlotte, NC 28210 Telephone: 704-358-8240

Ordnance & Explosives Remediation, Inc.

135 King Street Cohasset, Ma. 02025-1364 Telephone: 781-838-8339

4.2. The following criteria will apply to all EOD organizations:

4.2.1. The organization will have a minimum of five consecutive years corporate experience in actual UXO fieldwork, including planning, locating, hand excavating and identifying UXO.

4.2.2. The organization will employ at least one technician who holds a Master Badge and/or a Senior UXO

Supervisor, as defined in Attachment to Chapter 20, EP 1110-I-18, Ordnance and Explosive Response. The Corps of Engineers (COE) most current listing of personnel ratings will determine eligibility for Senior UXO Supervisor positions. All UXO field personnel must have a certificate of graduation from the U.S.

Naval School Explosives Ordnance Disposal.

4.2.3. The contractor will employ at least three individuals rated, as a minimum, UXO Technician II, as defined and monitored by the COE, and who hold certificates of graduation from the U.S. Naval School, Explosive Ordnance Disposal. These individuals must have a minimum of five years experience in accepted procedures for detection, identification, and field evaluation of UXO.

4.2.4. The contractor will furnish documentation of their ability to meet the requirements of OSHA Regulation 29 CFR 1910.120, “Hazardous Waste Operations and Emergency Response.”

5. SAFETY. The contractor will follow all safety rules as specified herein and all Occupational Safety and Health Administration (OSHA), Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), and Resource Conservation and Recovery Act (RCRA) requirements that apply to the specific work being performed.

5.1. The approved EOD organization, and any subcontractor employed by the EOD organization, will comply with 29 Code of Federal Regulations (CFR) 1910.120. A Site Specific Health and Safety Plan, prepared in accordance with 29 CFR 1910.120, must be submitted to the Contracting Officer or the COR, for government approval prior to initiation of each project. All work will be conducted according to the approved plan.

5.1.1. At a minimum, each two-person field team must be comprised of no less than one Master Rated UXO Technician and/or U.S. Army Corps of Engineers (COE) qualified UXO Safety Officer, and one UXO Technician II. Any variation must be addressed in the Site Specific Health and Safety Plan. The organization will use only technicians holding a certificate of graduation from the U.S. Naval School, Explosive Ordnance Disposal, for potential UXO location, excavation, and identification. When two or more field teams are deployed, an additional Safety Officer must be on-site to supervise and perform Quality Assurance/ Quality Control (QA/QC) functions.

5.2. APG Edgewood Area health and safety: In addition to the preceding health and safety requirements, the following will apply to work in the Edgewood Area of APG:

5.2.1 EOD contractor employees will be considered Red Blood Cell Cholinesterase (RBC-ChE) Category II and III as classified by ISO site categories. Each employee performing field work in the Edgewood Area will have an annual physical as required by Technical Bulletin (TB) Med 40-8 and 29 CFR 1910.120. Contractors must have a current RBC-ChE as part of their HAZWOPER physical, and must include documentation with their Site Specific Safety & Health Plan. To establish uniform specimen processing, shipping, and receiving procedures for the Department of Defense (DOD) Cholinesterase Monitoring Program and to establish a common reference point for these procedures, contractors are required to have their RBC-ChE specimens drawn by their own medical laboratory/physician and sent to:

Commander Public Health Command ATTN: MCHB-TS-LRD (Cholinesterase Laboratory) Bldg. E-2100 Aberdeen Proving Ground, MD 21010-5403

NOTE: Provisions to coordinate accounts with PHC are the contractor’s responsibility.

5.2.2 Specimens for cholinesterase analysis are to be collected in lavender-top Ethylenediaminetetraacetic acid (EDTA) vacutainers using standard venipuncture techniques. Phlebotomist will ensure that at least 2 mLs of blood are collected to allow sufficient red blood cells for analysis. All specimens will be identified with the patient’s full name, age, social security number, date and time the specimen was drawn, and phlebotomist initials.

All specimens shall be centrifuged to ensure that the red blood cells (RBCs) have been separated from the plasma in accordance with local standard operating procedures. Separation must occur within four hours of specimen acquisition. Any hemolyzed specimens must be discarded and redrawn. The plasma and the buffy coat are removed from the packed RBCs and discarded immediately after centrifugation. If the specimens cannot be analyzed and/or shipped immediately, they must be refrigerated at 2-8°C, and not frozen.

Facilities requesting primary RBC-ChE analysis by the CRL must ensure that specimens are received at the CRL within five days of date drawn.

5.2.3 Specimens shall be packed in an appropriately sized, insulated container with a sufficient number of ice packs to ensure the internal temperature of the shipping container is maintained at 2-8°C for a 24-hour shipping period.

Use the following guidelines for shipping RBC-ChE specimens:

(a) Layer bottom with appropriate number of ice packs, i.e. Polar Pack or Super Ice Re-usable freezer packs. DO

NOT USE DRY ICE OR WET ICE TO SHIP SPECIMENS.

(b) Layer of packing material, i.e. absorbent pads or bubble plastic.

(c) Specimens

(d) Layer of packing material.

(e) Layer of appropriate number of ice packs.

(f) Repeat steps (b)-(e) until all specimens are packed.

(g) Fill in all dead space with appropriate amount of packing material.

Shipments of specimens to CRL, PHC shall be scheduled to ensure that the specimens will arrive between 0830 hrs Monday and 1500 hrs Thursday. This scheduling is necessary to ensure that laboratory personnel will be present to accept the shipment and that the specimens will be properly stored. Questions concerning specimen shipping procedures should be directed to CRL, PHC, at commercial (410) 436-3983/2550 or DSN 584-3983/2550.

5.2.4. The UXO personnel working on-site will be trained and qualified to wear National Institute for Occupational Safety and Health (NIOSH) approved Chemical, Biological, Radiological, Nuclear and high-yield Explosives (CBRNE) or military masks. CBRNE masks can be provided by the contractor, military masks must be issued by the government. Each UXO contractor will carry their mask at all times while working on-site, as required. The masks are to enhance safety, and are intended for escape purposes only. The UXO personnel must be trained and certified to use MARK I antidote kits.

5.2.5. The field team will wear contractor provided chemical resistant gloves when performing intrusive work.

5.2.6. Each two-person field team will have one Gross Level Chemical Agent Detector unless otherwise specified.

The detector will be contractor provided, in sufficient quantity to prevent delay of the UXO search or construction.

The detectors may require maintenance and calibration downtime. Spare units for each team are recommended

5.2.7. The Government will provide a written or computerized toxic aide briefing to the contractor. The contractor will brief his/her employees prior to performing any intrusive investigation, excavation, or surface sweep on any site in the Edgewood Area.

6. EOD CONTRACTOR OPERATIONS.

6.1. Notification requirements:

6.1.1 All UXO contractors shall provide a written schedule of their planned activities to the Aberdeen Test Center (ATC) Range Control office at least one week prior to commencing work.

6.1.2. All UXO contractors shall contact ATC Range Control prior to any intrusive work. For work in the Aberdeen Area contact ATC, B Tower, at 410-278-2250. For work in the Edgewood Area contact ATC Range Central at 410-436-4471. No intrusive work is allowed until coordinated with ATC Range Control.

6.1.3. All UXO contractor’s Safety and Health Plans shall include a statement to the effect that no intrusive work will be conducted without the assurance of ATC Range Control support and availability.

6.2. The UXO search will consist of a visual surface inspection, and surface and subsurface sweeps with geophysical tools/instruments capable of detecting both ferrous and non-ferrous metals. Suspected UXO items will be investigated further to determine if they are UXO. If UXO avoidance is required due to the nature of the project, the zero anomaly area will be clearly demarked with adequate signage.

6.3. The EOD organization will comply with the Site Safety And Health Plan, in accordance with 29 CFR 1910.120, once the U.S. Army Garrison, Aberdeen Proving Ground, Installation Safety Office (ISO) has approved

it. The ISO must also approve any changes to the Plan prior to its implementation.

6.4. The EOD organization will provide UXO recognition training to all site workers.

6.5. Disposal of debris generated by UXO search: All ordnance related materials and debris (such as empty casings, parts, fragments, etc.) that are determined to be non-UXO will be segregated from all other waste accumulated as part of the UXO search and identification project.

6.5.1. Both ordnance related and non-ordnance related waste will be disposed of through the APG Directorate of Public Works. Arrangements for disposal must be made through the COR prior to the initiation of fieldwork.

7. EOD RESPONSIBILITY OF THE GOVERNMENT. Government EOD personnel (i.e. military EOD Personnel) will accomplish field evaluation, render safe, recovery and final disposition of all UXO.

8. SCHEDULE REQUIREMENTS FOR UXO. Submit site-specific safety plan within 7 days after receipt of Notice to Proceed. Work will not commence on clearing, grubbing, and excavation operations until the initial UXO search has determined the area to be free of UXO to a safe depth as required for the phase of work to begin.

9. FINAL REPORTS. The Contractor will submit six copies of a final UXO findings report for each site completed. The report will detail the number, type, location as determined by GPS, and depth of UXO and non- UXO contacts identified and removed from the site. One copy of the report must be provided directly to the Installation Safety Division.

PART 2 – Not used.

PART 3 – Not used.

---End of Section 02010---

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 10-Sep-2018 11:00 AM to 13-Sep-2018 11:00 AM.

SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

The following have been modified:

INSTRUCTIONS TO BIDDERS

IMPORTANT NOTES REGARDING THIS ACQUISITION:

A. BIDDING MATERIAL

Copies of the Solicitation, Specifications, and Drawings forms are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the Federal Business Opportunity (FedBizOpps) website at: https://www.fbo.gov.

BID DOCUMENTS: The following documents must be submitted with your bid package:

1. SF 1442, Solicitation, Offer and Award

2. Schedule of bids/prices

3. Representations and Certifications (Section 004500)

5. Standard Form LLL (Section 007300)

6. Certificate of Corporate Authority (Section 007300)

7. All amendments (if any) must be acknowledged

8. Bid Bond (Standard Form 24)

9. One (1) compact disk (CD) with the above documents in individual PDF files.

B. PROPOSAL CONDITIONS

1. Contractors must bid all items in the above price schedule, with no exceptions. Should a contractor fail to fully complete the price schedule, its BID will not be considered responsive to the solicitation and will be ineligible for the resultant contract award.

2. Split awards or multiple award contracts will not result from this Solicitation.

3. Arithmetic Discrepancies:

a) For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of the bidding schedule as submitted by bidder:

(1) Obviously misplaced decimal points will be corrected;

(2) Discrepancy between unit price and extended price, the unit price will govern;

(3) Apparent errors in extension of unit prices will be corrected;

(4) Apparent errors in addition of lump-sum and extended prices will be corrected.

b) For the purpose of bid evaluation, the Government will proceed on the assumption that the bidder intends his bid to be evaluated on the basis of the unit prices and the total bid amount, subject to any arithmetic discrepancies as provided above. The resultant unit prices and total amounts will then be so reflected on the abstract of bids.

c) These correction procedures shall not be used to resolve any ambiguity concerning which bid is low.

4. Caution to Bidders – Bid Errors: You are cautioned to exercise extreme care in preparation of your bid.

Errors in bids are costly and could result in substantial loss to you as well as delayed award of contracts.

C. COMPETITION: Competition for this acquisition is UNRESTRICTED.

D. SUBMISSION OF BIDS

1. All bids shall be submitted in accordance with the procedures set forth in Block 13 of Page 1 of this Solicitation document. BIDS OR MODIFICATIONS TO BIDS THAT ARE RECEIVED BY FACSIMILE WILL NOT BE

CONSIDERED.

2. SF 1442 BACK (Page 2 of the Solicitation): Bidders are required to acknowledge the receipt of all amendments to the Solicitation on the Standard Form 1442 in Block 19. Bidders shall fully complete all the required areas located under the section designated as “OFFER” (refer to Items 14 through 20C).

3. Section 004500 (Representation and Certifications): The bidders must fully complete Section 004500 of this Solicitation and submit it along with all other documents required by this Solicitation. Bidders received without this Section fully completed may be rejected, considered non-responsive and ineligible for award.

4. BID GUARANTEE: The bidders are required to submit a Bid Guarantee for this procurement. Any bidders failing to submit an authentic Bid Guarantee will be considered non-responsive to the Solicitation and ineligible for award. The Bid Guarantee shall be in the amount of 20% of the bidder’s price or $3,000,000.00, whichever is less.

5. BONDS AND INSURANCE: The Contractor will be required to furnish proof of insurance, including copies of the required endorsements, and performance and payment bonds within 10 calendar days following the Contractor’s receipt of the contract award.

E. REQUESTS FOR INFORMATION

Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) 10:00 A.M. (EST), 29 August 2018. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective vendor once the reply is available for viewing.

The Bidder Inquiry Key is: 98R24V-HADXFN

Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

PLEASE NOTE: THE LAST DAY FOR INTERESTED BIDDERS TO SUBMIT THEIR CONTRACTING

AND TECHNICAL REQUESTS FOR INFORMATION IN PROJNET IS 29 AUGUST 2018 AT 10:00AM

EST. NO OTHER REQUESTS FOR INFORMATION WILL BE ACCEPTED AFTER 29 AUGUST 2018

AT 10:00AM EST.

****** NOTE: QUESTIONS ANSWERED IN PROJNET ARE NOT OFFICIAL UNTIL AN

AMENDMENT IS ISSUED. ***

F. DELIVERY OF BIDS

1. Sealed Bids: Regardless of the method of delivery (mailed or hand-carried), bids and all other documents called out in the Solicitation shall be enclosed and sealed in an envelope that is clearly marked “Bid” and shall include the assigned Solicitation Number, and the Bid Opening Date and Time.

2. Hand Carried Bids: It is the responsibility of each bidder to ensure that its Sealed Bid is received by the Baltimore District’s – Contracting Branch at the following location:

Contracting Division, Baltimore District, Corps of Engineers ATTN: Robert Jackson

W912DR18B0012

2 Hopkins Plaza, Room 00-A-26 Baltimore, Maryland 21201

Sealed bids must be received prior to the date and time set for the opening of the bids – See Block 13A of Page 1 of the Solicitation.

G. EVIDENCE OF AUTHORITY TO SIGN BIDS/PROPOSALS

Evidence of the authority of individuals signing bids/proposals to submit firm bids/proposals on behalf of the bidder/offeror is required except where the bid/offer is signed, and shows that it is so signed, by: The President, Vice-President, or Secretary of Incorporated bidders; a partner in case of partnership; the owner in the case of sole proprietorships. Failure to submit with the bid satisfactory evidence of authority of all other persons may be cause for rejection of bid as an invalid or non-responsive bid.

H. BID OPENING ROOM:

1. In order to gain access, all interested participants must check in at the Security Desk in the lobby with a valid photo ID, and will then be directed to the Bid Opening Room 00-A-26. All individuals attending the Bid Opening must allow enough time to go through security and arrive at the Bid Opening room no later than than the time prescribed in (Block 13 of the SF1442).

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) The site visit will be held 1:00 PM EST on 27 August 2018. Attendees will meet in Building 330 (BRL conference hall). All attendees must have valid identification to gain entrance on post.

(End of provision)

(End of Summary of Changes)