W912DQ24R4000 Amendment-0004 CDC.pdf

PDF 9 MB Posted

Attached to
Child Development Center Construction
Solicitation number
W912DQ24R4000
Issued by

About this file

This solicitation requires construction services for a Child Development Center at Fort Leavenworth, Kansas. The scope of work includes building a playground with age-appropriate equipment, safety surfacing and fencing. Additional requirements are for cybersecurity, sustainability, and energy measures along with building information, energy monitoring control, intrusion detection, CCTV, access control, public address, fire protection and alarm systems. Supporting facilities such as site development, utilities, lighting, paving, parking, walks, storm drainage and landscaping are also included. The building will have self-contained HVAC and meet DoD antiterrorism standards. Comprehensive interior design services for building furnishings are required. The facility must accommodate individuals with disabilities and be designed for a 40-year lifespan per DoD criteria including energy efficiency and building systems performance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Child Development Center (CDC) Construction at Ft. Leavenw orth, KS.

The purpose of this Amnendment is to update the Solicitation Plans, Specif ication and Requirements. See SF30 Block 14 Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Feb-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DQ24R4000

X 9B. DATED (SEE ITEM 11)

19-Jan-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Feb-2024

CODE

USACE, KANSAS CITY CT

FEDERAL BLDG CT-M 601 E 12TH STREET

KANSAS CITY MO 64106-2896

W912DQ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DQ24R4000

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT-0004

THE SOLICITATION IS AMENDED AS FOLLOWS:

Deleted text is shown with a strikethrough. Added text is shown with underline.

1. Specifications.

a. Section 01 30 00, Administrative Requirements. The following paragraphs are revised.

i. Add paragraph 1.6.4 shown below.

1.6.4 Stream Credits

This project occurs within the Kansas River and Missouri River Ecological Drainage Unit. The contractor shall purchase 1,463 stream credits from an approved mitigation provider within this service area and include the cost in their price proposal. At this time, credits may be obtained only from the Swallow Tail, LLC, Kansas River and Missouri River Umbrella Bank Sites. Credit availability is subject to market change; therefore, the contractor must contact this office to verify credit availability prior to completing the transaction. The purchase of the compensatory mitigation must be completed prior to the commencement of work within this regulatory jurisdiction. The contractor must submit a receipt of payment from the mitigation sponsor that includes the amount of credits purchased and the date of credit purchase. Point of contact: Mr. Shane Staten with Swallow Tail LLC at 314-984-0050 or by email at sstaten@swallowtailenvironmental.com

ii. Paragraph 1.29 is revised as shown below.

1.29 SURVEY INFORMATION NOT USED

iii. Paragraph 1.31 is revised as shown below.

1.31 SITE INFORMATION NOT USED

iv. Paragraph 1.32 is revised as shown below.

1.32 ROADS

1.32.1 Existing Roads

Where roads under construction follow or tie into existing roads open to traffic, the roads constructed under such conditions shall be open and passable to traffic at all times during construction. Roadbeds shall be maintained to eliminate hazards to traffic, insure a reasonably smooth riding surface, and to provide positive drainage by constant maintenance of sufficient crowns and ditches as construction progresses. During rainy or inclement periods, the roads shall be kept passable by applying adequate surfacing material to the roadbed or by providing a full time attendant to offer assistance to motorists. Upon failure to comply with foregoing requirements, the Contracting Officer reserves the right to direct non-Government sources to correct deficiencies with costs deducted from payment due to the Contractor. This does not apply to the Hancock Road realignment construction.

b. Section 01 45 00, Quality Control. Paragraph 6.6 narrative is revised as shown below.

1.6.6 Quality Control (QC) Specialists

Provide a separate QC Specialist at the work site for each of the areas as listed in the Matrix listed below, who must assist and report to the QC Manager and who must have no duties other than their assigned quality control duties.

These individuals or specialized technical companies are employees of the Prime or subcontractor. QC Specialists must be physically present at the work site with frequency as indicated in the Experience Matrix below, to participate in the QC Meetings, perform the three phases of control, including participation in Preparatory and Initial Phase meetings, and to perform and document Follow-up inspections as an extension of the QC Manager for each definable feature of work in their area of responsibility. QC Specialist must assist and be present for training events, and Critical System Acceptance inspections by the Government. Qualification, experience, Area of Responsibility, and frequency of QC surveillance are provided in Matrix listed herein.

c. Specification 01 45 35, SPECIAL INSPECTIONS. This section has been revised. A copy of the revised section is attached. Attachments 1 and 2 are replaced in their entirety as well as an additional paragraph was added to the body of the specification.

d. Section 01 50 00, Temporary Construction Facilities and Controls. Paragraph 2.2 is revised as shown below.

2.2 TEMPORARY TRAFFIC CONTROL

The Contractor must prepare and submit a traffic control plan. During construction the Contractor shall provide access and temporary relocated roads as necessary to maintain traffic. The Contractor shall maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment and the work, and the erection and maintenance of adequate warning, danger, and direction signs, shall be as required by the State and local authorities having jurisdiction. The plan must follow the requirements of the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD). The traveling public shall be protected from damage to person and property. The Contractor's traffic on roads selected for hauling material to and from the site shall interfere as little as possible with public traffic. The Contractor shall investigate the adequacy of existing roads and the allowable load limit on these roads. The Contractor shall be responsible for the repair of any damage to roads caused by construction operations.

See also section 01 30 00, paragraph 1.32.

e. Section 01 78 00, Closeout Submittals. Attachment 2, Fort Leavenworth BUILDER Contract Requirements, is added. A copy of the attachment is provided.

f. Section 09 65 66 RESILIENT FLOORING. Removed paragraph 3.3.4 Line Marking and Finishing

3.3.4 Line Marking and Finishing

After installation is complete, clean the floor surface in accordance with installation instructions. Lay out, mask, and paint line marking according to approved detail drawings and approved installation instructions. Finish in accordance with the manufacturer's recommendations.

g. Specification 23 08 00 COMMISSIONING OF MECHANICAL AND PLUMBING SYSTEMS. Add submittal requirement language and section reference.

i. Section 1.1 SEQUENCING AND SCHEDULING

b. Air Leakage Test Reports and Diagnostic test reports submitted and approved in accordance with Section 01 91 19 BUILDING ENCLOSURE COMMISSIONING.

ii. Section 1.2 SUBMITTALS is revised as shown below.

SD-03 Product Data

Test Equipment; G, DO RO

SD-06 Test Reports

Pipe Flushing, Testing, And Water Treatment Reports; G, DO RO

Completed Pre-Functional Checklists; G, , DO RO

Seasonal Test Report; G, DO RO

Full-Load Test Report; G, DO RO

iii. Section 3.12 SEASONAL TESTS is revised as shown below.

Execute seasonal functional performance testing, witnessed by the Contracting Officer. Correct deficiencies and make adjustments to O&M manuals and as-built drawings for applicable issues identified in any seasonal testing. Season of maximum heating load: The time of year when the outdoor temperature at the project site remains within plus or minus 30 20 degrees Fahrenheit of the project site's winter outdoor design temperature, throughout the period of TAB Commissioning Data recording. Season of maximum cooling load:

The time of year when the outdoor temperature at the project site remains within plus or minus 5 degrees Fahrenheit of the project site's summer outdoor design temperature, throughout the period of TAB Commissioning data recording

iv. Section 3.14 TRAINING is added.

3.14 TRAINING

The Mechanical Systems Technical Commissioning Specialist must review the training plan required by Section 01 78 00 OPERATION AND MAINTENANCE DATA and identify any deficiencies to the Contracting Officer's Representative and the Contractor's Quality Control Personnel. The Commissioning Provider is responsible for overseeing and approving the training plan required by Section 01 78 00 OPERATION AND MAINTENANCE DATA and identifying any deficiencies to the Contracting Officer's Representative and the Contractor's Quality Control Personnel. Coordinate, schedule, and document all required training. At a minimum, include the following items in the training report for commissioned systems:

a. Complete commissioning documentation

b. Complete O&M data

c. Complete Training

d. Purpose of equipment.

e. Principle of how the equipment works.

f. Important parts and assemblies.

g. How the equipment achieves its purpose and necessary operating conditions.

h. Most likely failure modes, causes and corrections.

i. On site demonstration.

j. Provide updates to O&M manuals based on field modifications.

k. Provide training of the post-occupancy operations and maintenance staff.

v. Section 3.16 POST-CONSTRUCTION ENDURANCE TEST is revised shown below.

Perform an Endurance Test in accordance with the paragraph ENDURANCE TEST in Section 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC once during the peak heating season and once during the peak cooling season during outdoor air condition extremes with the exception that network bandwidth usage measurement and recording is not required.

The Mechanical System Commissioning Specialists must review the trend logs from the Endurance Tests to ensure that the systems have stable operation and operate as required by the construction contract and the accepted design. The Commissioning Specialists must provide a Post-Construction Trend Log Report that identifies any deficiencies noted in operation, recommendations for correction, and includes a graphical representation of the trends. Provide one Trend Log Report for the peak cooling season and one Trend Log Report for the peak heating season. Submit the Post-Construction Trend Log Reports no later than 14 calendar days following receipt of the trend log data by the Commissioning Specialist. Provide a Post-Construction Trend Log Report meeting the same requirements as the Endurance Testing Results Format in Section 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC. Provide one Trend Log Report for the peak cooling season and one Trend Log Report for the peak heating season. Submit the Post- Construction Trend Log Reports no later than 14 calendar days following download of the trended data.

Include the post-construction trend log report Post-Construction Trend Log Reports in the Updated Final Commissioning Report as specified in Section 01 91 00.15 BUILDING

COMMISSIONING

g. Specification 26 20 00 INTERIOR DISTRIBUTION SYSTEM.

Delete para 3.1.6 – Camera Cable Support Installation

Install open top and closed ring cable supports on 4 ft to 5 ft centers to adequately support and distribute the cable’s weight. Use these types of supports to support a maximum of 50 0.25 in diameter cables. Install suspended cables with at least 3 in of clear vertical space above the ceiling tiles and support channels (T-bars). Open top and closed ring cable supports: suspended from or attached to the structural ceiling or walls with hardware or other installation aids specifically designed to support their weight.

2. Drawings.

a. B-102 – Added sheet note.

b. B-103 – Added sheet note and blow counts to boring logs.

c. B-105 – Changed the surcharge requirements.

d. B-301 – Removed hatched box that represented the building and added the surcharge to the section view.

e. C-501 – Updated note on details A7 and D7

f. C-502 – Updated note on detail A8

g. S-001 Clarification of truss design requirements

h. S-310 revised footing graphics

i. S-311 revised foundation section

j. S-510 clarification of subgrade requirements

k. S-601 revised footing schedule and reinforced concrete column detail

l. S-412A revised foundation

m. S-413A revised foundation, added general notes

n. A-600, Provide HM frame for HM steel door 120A, 120B, and 120C.

o. A-412A revised screen wall, below grade detailing

p. A-413A revised screen wall. Updated exterior door to mechanical yard to match A-413

q. IN204 - Removed reference to specification from detail C7

r. IN602 – Added note # indicating full height impact resistant drywall where indicated on schedule.

Updated Ceiling Finishes to match RCP.

s. MH113 – Added Airflow Monitoring station location keynotes and updated keynote legends.

t. MH410 - Added Airflow Monitoring station location keynotes and updated keynote legends.

u. MI601 – Updated Fort Leavenworth UMCS systems language.

v. MI620 – Updated Airflow Monitoring Station location keynotes and updated keynote legend. Updated

Return Fan Sequence Language. Added VFD to return and Supply Fan Schematic.

w. M-601 – Updated Boilers Schedule to Show min. Pressure Relief valve settings.

x. M-603 – Updated Expansion Tank schedules

3. The time and date for submission of proposals is not changed and remains February 28, 2024, at 11:00 AM local Time.

4. Offerors are required to acknowledge receipt of this amendment. Failure to acknowledge receipt of all amendments may cause rejection of offeror’s proposal.

5. All other terms and conditions remain unchanged and in full force.

(End of Amendment)

(End of Summary of Changes)

504741LVNCDC W912DQ24R4000

Ft. Leavenworth, KS

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 45 35

SPECIAL INSPECTIONS

PART 1 GENERAL

1.1 REFERENCES

1.2 GENERAL REQUIREMENTS

1.3 DEFINITIONS

1.3.1 Continuous Special Inspections

1.3.2 Perform

1.3.3 Observe

1.3.4 Special Inspector (SI)

1.3.5 Associate Special Inspector (ASI)

1.3.6 Third Party

1.3.7 Special Inspector of Record (SIOR)

1.3.8 Contracting Officer

1.3.9 Contractor's Quality Control (QC) Manager

1.3.10 Structural Engineer of Record (SER)

1.3.11 Statement of Special Inspections (SSI)

1.3.12 Schedule of Special Inspections (SSI)

1.3.13 Definable Feature of Work (DFOW)

1.4 SUBMITTALS

1.5 SPECIAL INSPECTOR QUALIFICATIONS

1.5.1 Steel Construction and High Strength Bolting

1.5.1.1 Special Inspector

1.5.1.2 Associate Special Inspector

1.5.2 Welding Structural Steel

1.5.2.1 Special Inspector

1.5.2.2 Associate Special Inspector

1.5.3 Nondestructive Testing of Welds

1.5.3.1 Special Inspector

1.5.3.2 Associate Special Inspector

1.5.4 Cold Formed Steel Framing

1.5.4.1 Special Inspector

1.5.4.2 Associate Special Inspector

1.5.5 Concrete Construction

1.5.5.1 Special Inspector

1.5.5.2 Associate Special Inspector

1.5.6 Verification of Site Soil Condition, Fill Placement and

Load-Bearing Requirements

1.5.6.1 Special Inspector

1.5.6.2 Associate Special Inspector

1.5.7 Sprayed Fire Resistant Material

1.5.7.1 Special Inspector

1.5.7.2 Associate Special Inspector

1.5.8 Fire-Resistant Penetrations and Joints

1.5.8.1 Special Inspector

1.5.8.2 Associate Special Inspector

1.5.9 Special Inspector of Record (SIOR)

01 45 35 - 1

1.5.10 Adhesive Anchors

1.5.10.1 Special Inspector Qualifications for Anchors Installed in the Horizontal or Upwardly Inclined Position

PART 2 PRODUCTS

2.1 FABRICATOR SPECIAL INSPECTIONS

PART 3 EXECUTION

3.1 RESPONSIBILITIES

3.1.1 Special Inspector of Record

3.1.2 Quality Control Manager

3.1.3 Special Inspectors

3.2 DEFECTIVE WORK

-- End of Section Table of Contents --

01 45 35 - 2

SECTION 01 45 35

SPECIAL INSPECTIONS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

INTERNATIONAL CODE COUNCIL (ICC)

ICC IBC (2021) International Building Code

1.2 GENERAL REQUIREMENTS

Perform Special Inspections in accordance with the Statement of Special Inspections, Schedule of Special Inspections and Chapter 17 of ICC IBC .

The Statement of Special Inspections and Schedule of Special Inspections are included as an attachment to this specification. Special Inspections are to be performed by an independent third party and are intended to ensure that the work of the Prime Contractor is in accordance with the Contract Documents and applicable building codes. Special inspections do not take the place of the three phases of control inspections performed by the Contractor's QC Manager or any testing and inspections required by other sections of the specifications.

Structural observations will be performed separately by the Government .

The Contractor must provide notification to the Contracting Officer 14 days prior to the following points of construction to allow for structural observation:

a. Completion of installation of all OSB shear walls (and prior to covering with dry wall).

b. Completion of installation of all collector trusses.

c. Completion of installation of metal roof deck and related fastening system.

d. Completion of installation of front entrance canopy structural steel framing.

1.3 DEFINITIONS

1.3.1 Continuous Special Inspections

Continuous Special Inspections is the constant monitoring of specific tasks by a special inspector. These inspections must be carried out continuously over the duration of the particular tasks.

1.3.2 Perform

Perform these Special Inspections tasks for each welded joint or member.

01 45 35 - 3

1.3.3 Observe

Observe these Special Inspections items on a periodic daily basis.

Operations need not be delayed pending these inspections.

1.3.4 Special Inspector (SI)

A qualified person retained by the Contractor and approved by the Contracting Officer as having the competence necessary to inspect a particular type of construction requiring Special Inspections. The SI must be an independent third party hired directly by the Prime Contractor.

1.3.5 Associate Special Inspector (ASI)

A qualified person who assists the SI in performing Special Inspections but must perform inspection under the direct supervision of the SI and cannot perform inspections without the SI on site.

1.3.6 Third Party

A Special inspector must not be an employee of the Contractor or of any Sub-Contractor performing the work to be inspected.

1.3.7 Special Inspector of Record (SIOR)

A licensed engineer in responsible charge of supervision of all special inspectors for the project and approved by the Contracting Officer. The SIOR must be an independent third party entity hired directly by the Prime Contractor.

1.3.8 Contracting Officer

The Government official having overall authority for administrative contracting actions. Certain contracting actions may be delegated to the Contracting Officer's Representative (COR).

1.3.9 Contractor's Quality Control (QC) Manager

An individual retained by the Prime Contractor and qualified in accordance with the Section 01 45 00 QUALITY CONTROL having the overall responsibility for the Contractor's QC organization.

1.3.10 Structural Engineer of Record (SER)

A registered design professional employed by the Government responsible for the overall design and review of submittal documents prepared by others. The SER is registered or licensed to practice their respective design profession as defined by the statutory requirements of the professional registration laws in the state in which the design professional works. The SER is also referred to as the Engineer of Record (EOR) in design code documents.

1.3.11 Statement of Special Inspections (SSI)

A document developed by the SER identifying the material, systems, components and work required to have Special Inspections. This statement is included at the end of this specification.

01 45 35 - 4

1.3.12 Schedule of Special Inspections (SSI)

A schedule which lists each of the required Special Inspections, the extent to which each Special Inspection is to be performed, and the required frequency for each in accordance with ICC IBC Chapter 17. This schedule is included at the end of this specification.

1.3.13 Definable Feature of Work (DFOW)

An inspection group that is separate and distinct from other inspection groups, having inspection requirements or inspectors that are unique.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals SIOR Letter of Acceptance; G , RO Special Inspections Project Manual; G , RO

SD-06 Test Reports

Special Inspections Daily Reports

Special Inspections Biweekly Reports

SD-07 Certificates

AISC Certified Steel Fabricator

AC472 Accreditation

Certificate of Compliance

Special Inspector of Record Qualifications; G , RO Special Inspector Qualifications; G , RO

SD-11 Closeout Submittals

Comprehensive Final Report of Special Inspections; G , RO

1.5 SPECIAL INSPECTOR QUALIFICATIONS

Submit qualifications for each special inspector.

1.5.1 Steel Construction and High Strength Bolting

1.5.1.1 Special Inspector

a. ICC Structural Steel and Bolting Special Inspector certificate with one year of related experience, or

b. Registered Professional Engineer with three years of related experience

01 45 35 - 5

1.5.1.2 Associate Special Inspector

Engineer-In-Training with one year of related experience.

1.5.2 Welding Structural Steel

1.5.2.1 Special Inspector

a. ICC Structural Welding Special Inspector certificate with one year of related experience, or

b. AWS Certified Welding Inspector

1.5.2.2 Associate Special Inspector

AWS Certified Associate Welding Inspector

1.5.3 Nondestructive Testing of Welds

1.5.3.1 Special Inspector

NDT Level III Certificate

1.5.3.2 Associate Special Inspector

NDT Level II Certificate plus one year of related experience

1.5.4 Cold Formed Steel Framing

1.5.4.1 Special Inspector

a. ICC Structural Steel and Bolting Special Inspector certificate with one year of related experience, or

b. ICC Commercial Building Inspector with one year of experience, or

c. ICC Residential Building Inspector with one year of experience, or

d. Registered Professional Engineer with three years related experience

1.5.4.2 Associate Special Inspector

Engineer-In-Training with one year of related experience.

1.5.5 Concrete Construction

1.5.5.1 Special Inspector

a. ICC Reinforced Concrete Special Inspector Certificate with one year of related experience, or

b. ACI Concrete Construction Special Inspector, or

c. Registered Professional Engineer with three years of related experience

1.5.5.2 Associate Special Inspector

a. ACI Concrete Construction Special Inspector in Training, or

01 45 35 - 6

b. Engineer-In-Training with one year of related experience

1.5.6 Verification of Site Soil Condition, Fill Placement and Load-Bearing Requirements

1.5.6.1 Special Inspector

a. ICC Soils Special Inspector Certificate with one year of related experience, or

b. NICET Soils Technician Level II Certificate in Construction Material Testing, or

c. Geologist-In-Training with three years of related experience, or

d. Registered Professional Engineer with three years of related experience

1.5.6.2 Associate Special Inspector

a. NICET Soils Technician Level I Certificate in Construction Material Testing with one year of related experience, or

b. Engineer-In-Training with one year of related experience

1.5.7 Sprayed Fire Resistant Material

1.5.7.1 Special Inspector

a. ICC Spray-applied Fireproofing Special Inspector Certificate, or

b. ICC Fire Inspector I Certificate with one year of related experience, or

c. Registered Professional Engineer or Architect with related experience

1.5.7.2 Associate Special Inspector

Engineer-In-Training with one year of related experience

1.5.8 Fire-Resistant Penetrations and Joints

1.5.8.1 Special Inspector

a. Passed the UL Firestop Exam with one year of related experience, or

b. Passed the FM Firestop Exam with one year of related experience, or

c. Registered Professional Engineer with related experience

1.5.8.2 Associate Special Inspector

Engineer-In-Training with one year of related experience.

1.5.9 Special Inspector of Record (SIOR)

Registered Professional Engineer with five years of related experience.

01 45 35 - 7

1.5.10 Adhesive Anchors

1.5.10.1 Special Inspector Qualifications for Anchors Installed in the Horizontal or Upwardly Inclined Position

a. Certification as an ACI/CRSI Adhesive Anchor Installation Inspector, or equivalent.

PART 2 PRODUCTS

2.1 FABRICATOR SPECIAL INSPECTIONS

Special Inspections of fabricator's work performed in the fabricator's shop is required to be inspected in accordance with the Statement of Special Inspections and the Schedule of Special Inspections unless the fabricator is certified by the approved agency to perform such work without Special Inspections. Submit the following certifications to the Contracting Officer for information to allow work performed in the fabricator's shop to not be subjected to Special Inspections.

AISC Certified Steel Fabricator.

International Accreditation Service, AC472 Accreditation

At the completion of fabrication, submit a certificate of compliance, to be included with the comprehensive final report of Special Inspections, stating that the materials supplied and work performed by the fabricator are in accordance with the construction documents.

PART 3 EXECUTION

3.1 RESPONSIBILITIES

3.1.1 Special Inspector of Record

a. Supervise all Special Inspectors required by the Contract Documents and the IBC.

b. Submit a SIOR Letter of Acceptance to the Contracting Officer attesting to acceptance of the duties of SIOR, signed and sealed by the SIOR.

c. Verify the qualifications of all of the Special Inspectors.

d. Verify the qualifications of fabricators.

h. Prepare a Special Inspections Project Manual, which must cover the following:

(1) Roles and responsibilities of the following individuals during Special Inspections: SIOR, SI, ASI, General Contractor's QC Manager and SER.

(2) Organizational chart or communication plan, indicating lines of communication.

(3) Contractor's internal plan for scheduling inspections. Address items such as timeliness of inspection requests, who to contact for inspection requests, and availability of alternate inspectors.

01 45 35 - 8

(4) Indicate the Government reporting requirements.

(5) Propose forms or templates to be used by SI and SIOR to document inspections.

(6) Indicate procedures for tracking nonconforming work and verification that corrective work is complete.

(7) Indicate how the SIOR and SI will participate in weekly QC meetings.

(8) Indicate how Special Inspections of shop fabricated items will be handled when the fabricator's shop is not certified in accordance with paragraph FABRICATOR SPECIAL INSPECTIONS.

(9) Include a section in the manual that covers each specific item requiring Special Inspections that is indicated on the Schedule of Special Inspections. Provide names and qualifications of each special inspector who will be performing the Special Inspections for each specific item. Provide detail on how the Special Inspections are to be carried out for each item so that the expectations are clear for the General Contractor and the Subcontractor performing the work.

Make a copy of the Special Inspections Project Manual available on the job site during construction. Submit a copy of the Special Inspections Project Manual for approval.

i. Attend coordination and mutual understanding meeting where the information in the Special Inspections Project Manual will be reviewed to verify that all parties have a clear understanding of the Special Inspections provisions and the individual duties and responsibilities of each party.

j. Maintain a 3-ring binder for the Special Inspector's daily and biweekly reports and the Special Inspections Project Manual. This file must be located in a conspicuous place in the project trailer/office to allow review by the Contracting Officer and the SER.

k. Submit a copy of the Special Inspector's daily reports to the QC Manager.

l. Discrepancies that are observed during Special Inspections must be reported to the QC Manager for correction. If discrepancies are not corrected before the special inspector leaves the site the observed discrepancies must be documented in the daily report.

m. Submit a biweekly Special Inspections report until all work requiring Special Inspections is complete. A report is required for each biweekly period in which Special Inspections activity occurs, and must include the following:

(1) A brief summary of the work performed during the reporting time frame.

(2) Changes and discrepancies with the drawings, specifications that were observed during the reporting period.

01 45 35 - 9

(3) Discrepancies which were resolved or corrected.

(4) A list of nonconforming items requiring resolution.

(5) All applicable test results including nondestructive testing reports.

o. At the completion of the project submit a comprehensive final report of Special Inspections that documents the Special Inspections completed for the project including corrections of all discrepancies noted in the daily reports. The comprehensive final report of Special Inspections must be signed, dated and bear the seal of the SIOR.

3.1.2 Quality Control Manager

a. Maintain a rework items list that includes discrepancies noted on the Special Inspectors daily report.

3.1.3 Special Inspectors

a. Inspect all elements of the project for which the special inspector is qualified to inspect and are identified in the Schedule of Special Inspections.

b. Attend preparatory phase meetings related to the Definable Feature of Work (DFOW) for which the special inspector is qualified to inspect.

c. Submit a copy of the daily reports to the QC Manager.

d. Report discrepancies that are observed during Special Inspections to the QC Manager for correction. If discrepancies are not corrected before the special inspector leaves the site the observed discrepancies must be documented in the daily report.

e. Submit a biweekly Special Inspection Report until all inspections are complete. A report is required for each biweekly period in which Special Inspections activity occurs, and must include the following:

(1) A brief summary of the work performed during the reporting time frame.

(2) Changes and discrepancies with the drawings, specifications that were observed during the reporting period.

(3) Discrepancies which were resolved or corrected.

(4) A list of nonconforming items requiring resolution.

(5) All applicable test result including nondestructive testing reports.

f. At the completion of the project submit a comprehensive final report of Special Inspections that documents the Special Inspections completed for the project and corrections of all discrepancies noted in the daily reports. The comprehensive final report of Special Inspections must be signed, dated and indicate the certification of the special inspector qualifying them to conduct the inspection.

01 45 35 - 10

k. Submit daily reports to the SIOR. 3.2 DEFECTIVE WORK

Check work as it progresses, but failure to detect any defective work or materials must in no way prevent later rejection if defective work or materials are discovered, nor obligate the Contracting Officer to accept such work.

-- End of Section --

01 45 35 - 11

Project:

Location:

Project #:

Date:

B

III

No

CFMF Sheathed Shear Walls

Statement of Special Inspections Page 1 of 2

Identified on plan with key notes

See roof plans

Horizontal LFRS Elements Notes

Metal roof deck and related fastening system

Collector Elements

Following is a listing of critical main wind/seismic force resisting systems for this structure. Carefully inspect these elements as part of the roles and responsiblities of the Special Inspector (reference the Schedule of Special Inspections for inspection checklists).

Lateral Force Resisting System (LFRS)

2021 IBC 1704.3.2 and 1704.3.3

Vertical LFRS Elements Notes

Hazardous Occupancy or attached to such?

STATEMENT OF SPECIAL INSPECTIONS

Special Inspector of Record (SIOR)

A Special Inspector of Record (SIOR)

SIOR Name (Registered Professional):

Professional Registration Number:

Consulting Firm Name (if any):

SIOR Office AND Mobile Phone Number:

IS

Group H Occupancies required (per UFGS 01 45 35, Section 1.3.7)

Child Development Center

Fort Leavenworth, KS

504741 PN 97509

2/6/2024

Project Seismic Design Category:

Project Risk Category:

Project Design Wind Speed (mph):

Number of Stories:

Structure Height Above Grade (ft):

Project:

Location:

Project #:

Date:

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

2/6/2024

504741 PN 97509

Fort Leavenworth, KS

Child Development Center

Designated Seismic Systems (DSS)

DSS Component XX

Final Walk Down Inspection and Report

(UFC 3 301 01 SECTION 2-5.4)

Final Walk Down Inspection of non-structural Designated Seismic Systems does not apply to this project (no

Designated Seismic Systems)

Final Walk Down Report, Prepared by the Registered Design Professional in Responsible Charge, Must Include:

1. Record observations of Final Walk Down Inspection

2. Document that Inspections were performed in accordance with the Schedule of Special Inspections

3. Document that all Designated Seismic Systems are installed according to construction/manufacturer document requirements, and that Compliance Certificates have been collected (UFC 03 301 01, 3-6.2, 13.2.2.2).

Statement of Special Inspections Page 2 of 2

DSS Gas lines and associated fittings, anchorage, & flexible Connections

DSS Component XX

DSS Component XX

DSS Component XX

DSS Component XX

DSS Component XX

(2021 IBC 1705.14.3) (ASCE 7-16, 13.2.2, C13.2.2) (UFC 3-301-1, 2-5.4)

DESIGNATED SEISMIC SYSTEMS DO NOT APPLY TO THIS PROJECT, due to the Seismic Design Category being less than C.

ELECTRICAL Designated Seismic Systems (DSS) Requiring a Certificate of Compliance

If additional space is required, append an additional sheet listing the remaining DSS

If additional space is required, append an additional sheet listing the remaining DSS

DSS Emergency or Standby Power System

DSS Component XX

DSS Component XX

DSS Component XX

DSS Component XX

MECHANICAL/PLUMBING Designated Seismic Systems (DSS) Requiring a Certificate of Compliance

OTHER Designated Seismic Systems (DSS) Requiring a Certificate of Compliance

DSS Building egress stair systems

DSS Building fire sprinkler systems

DSS Component XX

DSS Component XX

DSS Component XX

SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024

SCHEDULE OF SPECIAL INSPECTIONS

Reference UFGS 01 45 35 for all requirements not noted as part of this schedule.

INSPECTION DEFINITIONS:

PERFORM: Perform these tasks for each weld, fastener or bolted connection, and noted verification.

OBSERVE: Observe these items randomly during the course of each work day to insure that applicable requirements are being met. Operations need not be delayed pending these inspections at contractor’s risk.

DOCUMENT: Document, with a report, that the work has been performed in accordance with the contract documents. This is in addition to any other reports required in the Special Inspections guide specification.

CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.

The Seismic Design Category for this project is: ☐ A, ☒ B, ☐ C, ☐ D, ☐ E, ☐ F (check appropriate box)

SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024

STRUCTURAL - STEEL – WELDING SECTION

ALL OR PORTIONS OF THIS SECTION ARE APPLICABLE IF BOX IS CHECKED: ☒

STEEL INSPECTION PRIOR TO WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

2021 IBC 1705.2.1, AISC 360-16: Table C-N5.4-1

TASK INSPECTION TYPE1 DESCRIPTION

1. Verify that the welding procedures specification

(WPS) is available

PERFORM

2. Verify manufacturer certifications for welding consumables are available

PERFORM

3. Verify material identification PERFORM Type and grade.

4. Welder Identification

System

PERFORM The fabricator or erector, as applicable, shall maintain a system by which a welder who has welded a joint or member can be identified. Stamps, if used, shall be the low-stress type.

5. Fit-up of groove welds

(including joint geometry)

OBSERVE Joint preparation

Dimensions (alignment, root opening, root face, bevel)

Cleanliness (condition of steel surfaces)

Tacking (tack weld quality and location)

Backing type and fit (if applicable)

6. Configuration and finish of access holes

OBSERVE

7. Fit-up of fillet welds OBSERVE Dimensions (alignment, gaps at root)

Cleanliness (condition of steel surfaces)

Tacking (tack weld quality and location)

STEEL INSPECTION DURING WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

2021 IBC 1705.2.1, AISC 360-16: Table C-N5.4-2

TASK INSPECTION TYPE DESCRIPTION

8. Use of qualified welders PERFORM Welding by welders, welding operators, and tack welders who are qualified in conformance with requirements.

9. Control and handling of welding consumables

OBSERVE Packaging

Electrode atmospheric exposure control

10. No welding over cracked tack welds

OBSERVE

11. Environmental conditions OBSERVE Wind speed within limits

Precipitation and temperature

12. Welding Procedures

Specification followed

OBSERVE Settings on welding equipment

Travel speed

Selected welding materials

Shielding gas type/flow rate

Preheat applied

Interpass temperature maintained (min./max.)

Proper position (F, V, H, OH)

Intermix of filler metals avoided

13. Welding techniques OBSERVE Interpass and final cleaning

Each pass within profile limitations

Each pass meets quality requirements

1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.

OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.

SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024

STRUCTURAL - STEEL – WELDING SECTION (CONTINUED)

STEEL INSPECTION AFTER WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

2021 IBC 1705.2.1, AISC 360-16: Table C-N5.4-3

TASK INSPECTION TYPE 1 DESCRIPTION

14. Welds cleaned OBSERVE

15. Size, length, and location of all welds

PERFORM Size, length, and location of all welds conform to the requirements of the detail drawings.

16. Welds meet visual acceptance criteria

PERFORM AND

DOCUMENT

Crack prohibition

Weld/base-metal fusion

Crater cross section

Weld profiles

Weld size

Undercut

Porosity

17. Arc strikes PERFORM

18. k-area PERFORM When welding of doubler plates, continuity plates or stiffeners has been performed in the k-area, visually inspect the web k-area for cracks.

19. Backing removed, weld tabs removed and finished, and fillet welds added where required

PERFORM

20. Repair activities PERFORM AND

DOCUMENT

21. Document acceptance or rejection of welded joint or member

PERFORM

END SECTION

1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.

DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.

SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024

STRUCTURAL - STEEL – BOLTING SECTION

STEEL INSPECTION TASKS PRIOR TO BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

2021 IBC 1705.2.1, AISC 360-16: Table C-N5.6-1

TASK INSPECTION TYPE 1 DESCRIPTION

1. Manufacture’s certifications available for fastener materials

PERFORM

2. Fasteners marked in accordance with

ASTM requirements

OBSERVE

3. Proper fasteners selected for joint detail

(grade, type, bolt length if threads are to be excluded from shear plane)

OBSERVE

4. Proper bolting procedure selected for joint detail

OBSERVE

5. Connecting elements, including appropriate faying surface condition and hole preparation, if specified, meet applicable requirements

OBSERVE

6. Proper storage provided for bolts, nuts, washers, and other fastener components

OBSERVE

STEEL INSPECTION TASKS DURING BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

2021 IBC 1705.2.1, AISC 360-16: Table C-N5.6-2

TASK INSPECTION TYPE 1 DESCRIPTION

7. Fastener assemblies of suitable condition, placed in all holes and washers (if required) are positioned as required

OBSERVE

8. Joint brought to the snug-tight condition prior to pretensioning operation

OBSERVE

9. Fastener component not turned by the wrench prevented from rotating

OBSERVE

10. Bolts are pretensioned in accordance with

RCSC Specification, progressing systematically from the most rigid point toward the free edges

OBSERVE

STEEL INSPECTION TASKS AFTER BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

2021 IBC 1705.2.1, AISC 360-10: Table C-N5.6-3

TASK INSPECTION TYPE 1 DESCRIPTION

11. Document acceptance or rejection of all bolted connections

1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.

OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need

DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.

SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024

STRUCTURAL - STEEL - NON DESTRUCTIVE TESTING SECTION

NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

2021 IBC 1705.2.1, AISC 360-16: Section N5.5

TASK INSPECTION TYPE 1 DESCRIPTION

1. Use of qualified nondestructive testing personnel

PERFORM Visual weld inspection and nondestructive testing (NDT) shall be conducted by personnel qualified in accordance with AWS

D1.8 clause 7.2

2. CJP groove welds OBSERVE [NOTE: DOR must delete this row if section D (SEISMIC

PROVISIONS SECTION) is checked]

Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 20% of CJP groove welds for materials greater than 5/16” (8mm) thick. Testing rate must be increased to 100% if greater than 5% of welds tested have unacceptable defects.

3. Welded joints subject to fatigue

OBSERVE Dye penetrant testing (DT) and Ultrasonic testing (UT) shall be performed on 100% of welded joints identified on contract drawings as being subject to fatigue.

4. Weld tab removal sites OBSERVE At the end of welds where weld tabs have been removed, magnetic particle testing shall be performed on the same beam-to-column joints receiving UT

1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.

OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need

SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024

STRUCTURAL - STEEL – AISC 341 REQUIREMENTS (SEISMIC PROVISIONS) SECTION

ALL OR PORTIONS OF THIS SECTION ARE APPLICABLE IF BOX IS CHECKED: ☐

NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

2021 IBC 1705.2.1, AISC 341-16: Section J6.2

TASK INSPECTION TYPE 1 DESCRIPTION

[NOTE: DOR may uncheck this section for projects NOT designed in accordance with AISC 341 (Seismic

Provisions) or for projects designed according to AISC 341, but using an R value equal to 3]

5. CJP groove welds OBSERVE Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 100% of CJP groove welds for materials greater than

5/16” thick (8mm).

6. Beam cope and access hole.

OBSERVE At welded splices and connections, thermally cut surfaces of beam copes and access holes shall be tested using magnetic particle testing

(MT) or dye penetrant testing (DT), when the flange thickness exceeds 1 1/2 in. for rolled shapes, or when the web thickness exceeds 1 1/2 in. for built-up shapes.

7. K-area NDT (AISC

341)

PERFORM Where welding of doubler plates, continuity plates or stiffeners has been performed in the k-area, the web shall be tested for cracks using magnetic particle testing (MT). The MT inspection area shall include the k-area base metal within 3-inches of the weld. The MT shall be performed no sooner than 48 hours following completion of the welding.

8. Placement of reinforcing or contouring fillet welds

1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.

OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need

DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.

SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024

STRUCTURAL - STEEL - COMPOSITE CONSTRUCTION 1

COMPOSITE CONSTRUCTION PRIOR TO PLACING CONCRETE – VERIFY THE FOLLOWING ARE IN COMPLIANCE 2021 IBC 1705.2.1, AISC 360-16: Table N6.1, AISC 341-16: Table J9.1

TASK INSPECTION TYPE 2 DESCRIPTION

1. Placement and installation of steel headed stud anchors

PERFORM

2. Material identification of reinforcing steel (Type/Grade)

OBSERVE

3. Determination of carbon equivalent for reinforcing steel other than ASTM A706

OBSERVE

4. Proper reinforcing steel size, spacing, clearances, support, and orientation

OBSERVE

5. Reinforcing steel has not been re-bent in the field

OBSERVE

6. Reinforcing clearances have been provided

OBSERVE

7. Reinforcing steel has been tied and supported as required

OBSERVE

8. Composite member has required size

OBSERVE

STRUCTURAL - STEEL - OTHER INSPECTIONS

OTHER STEEL INSPECTIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

2021 IBC 1705.2.1, AISC 341-16: Tables J8.1 & J10.1

TASK INSPECTION TYPE 2 DESCRIPTION

1. Anchor rods and other embedments supporting structural steel

PERFORM Verify the diameter, grade, type, and length of the anchor rod or embedded item, and the extent or depth of embedment prior to placement of concrete.

2. Fabricated steel or erected steel frame

OBSERVE Verify compliance with the details shown on the construction documents, such as braces, stiffeners, member locations and proper application of joint details at each connection.

3. Reduced beam sections (RBS) where/if occurs

DOCUMENT Contour and finish

Dimensional tolerances

4. Protected zones DOCUMENT No holes or unapproved attachments made by fabricator or erector

5. H-piles where/if occurs DOCUMENT No holes or unapproved attachments made by the responsible contractor

1 See Concrete Construction Section for all concrete related inspection of composite steel construction.

2 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.

OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need

DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.

SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024

STRUCTURAL - COLD-FORMED METAL DECK - PLACEMENT SECTION

METAL DECK INSPECTION PRIOR TO DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE

SDI QA/QC-2017, Appendix 1, Table 1.1

TASK INSPECTION TYPE 1 DESCRIPTION

1. Verify compliance of materials

(deck and all deck accessories) with construction documents, including profiles, material properties, and base metal thickness

PERFORM

2. Document acceptance or rejection of deck and deck accessories

DOCUMENT

METAL DECK INSPECTION AFTER DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE

SDI QA/QC-2017, Appendix 1, Table 1.2

TASK INSPECTION TYPE 1 DESCRIPTION

3. Verify compliance of deck and all deck accessories installation with construction documents

PERFORM

4. Verify deck materials are represented by the mill certifications that comply with the construction documents

PERFORM

5. Document acceptance or…