This solicitation requires construction services for a Child Development Center at Fort Leavenworth, Kansas. The scope of work includes building a playground with age-appropriate equipment, safety surfacing and fencing. Additional requirements are for cybersecurity, sustainability, and energy measures along with building information, energy monitoring control, intrusion detection, CCTV, access control, public address, fire protection and alarm systems. Supporting facilities such as site development, utilities, lighting, paving, parking, walks, storm drainage and landscaping are also included. The building will have self-contained HVAC and meet DoD antiterrorism standards. Comprehensive interior design services for building furnishings are required. The facility must accommodate individuals with disabilities and be designed for a 40-year lifespan per DoD criteria including energy efficiency and building systems performance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Child Development Center (CDC) Construction at Ft. Leavenw orth, KS.
The purpose of this Amnendment is to update the Solicitation Plans, Specif ication and Requirements. See SF30 Block 14 Continuation Page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Feb-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DQ24R4000
X 9B. DATED (SEE ITEM 11)
19-Jan-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Feb-2024
CODE
USACE, KANSAS CITY CT
FEDERAL BLDG CT-M 601 E 12TH STREET
KANSAS CITY MO 64106-2896
W912DQ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DQ24R4000
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT-0004
THE SOLICITATION IS AMENDED AS FOLLOWS:
Deleted text is shown with a strikethrough. Added text is shown with underline.
1. Specifications.
a. Section 01 30 00, Administrative Requirements. The following paragraphs are revised.
i. Add paragraph 1.6.4 shown below.
1.6.4 Stream Credits
This project occurs within the Kansas River and Missouri River Ecological Drainage Unit. The contractor shall purchase 1,463 stream credits from an approved mitigation provider within this service area and include the cost in their price proposal. At this time, credits may be obtained only from the Swallow Tail, LLC, Kansas River and Missouri River Umbrella Bank Sites. Credit availability is subject to market change; therefore, the contractor must contact this office to verify credit availability prior to completing the transaction. The purchase of the compensatory mitigation must be completed prior to the commencement of work within this regulatory jurisdiction. The contractor must submit a receipt of payment from the mitigation sponsor that includes the amount of credits purchased and the date of credit purchase. Point of contact: Mr. Shane Staten with Swallow Tail LLC at 314-984-0050 or by email at sstaten@swallowtailenvironmental.com
ii. Paragraph 1.29 is revised as shown below.
1.29 SURVEY INFORMATION NOT USED
iii. Paragraph 1.31 is revised as shown below.
1.31 SITE INFORMATION NOT USED
iv. Paragraph 1.32 is revised as shown below.
1.32 ROADS
1.32.1 Existing Roads
Where roads under construction follow or tie into existing roads open to traffic, the roads constructed under such conditions shall be open and passable to traffic at all times during construction. Roadbeds shall be maintained to eliminate hazards to traffic, insure a reasonably smooth riding surface, and to provide positive drainage by constant maintenance of sufficient crowns and ditches as construction progresses. During rainy or inclement periods, the roads shall be kept passable by applying adequate surfacing material to the roadbed or by providing a full time attendant to offer assistance to motorists. Upon failure to comply with foregoing requirements, the Contracting Officer reserves the right to direct non-Government sources to correct deficiencies with costs deducted from payment due to the Contractor. This does not apply to the Hancock Road realignment construction.
b. Section 01 45 00, Quality Control. Paragraph 6.6 narrative is revised as shown below.
1.6.6 Quality Control (QC) Specialists
Provide a separate QC Specialist at the work site for each of the areas as listed in the Matrix listed below, who must assist and report to the QC Manager and who must have no duties other than their assigned quality control duties.
These individuals or specialized technical companies are employees of the Prime or subcontractor. QC Specialists must be physically present at the work site with frequency as indicated in the Experience Matrix below, to participate in the QC Meetings, perform the three phases of control, including participation in Preparatory and Initial Phase meetings, and to perform and document Follow-up inspections as an extension of the QC Manager for each definable feature of work in their area of responsibility. QC Specialist must assist and be present for training events, and Critical System Acceptance inspections by the Government. Qualification, experience, Area of Responsibility, and frequency of QC surveillance are provided in Matrix listed herein.
c. Specification 01 45 35, SPECIAL INSPECTIONS. This section has been revised. A copy of the revised section is attached. Attachments 1 and 2 are replaced in their entirety as well as an additional paragraph was added to the body of the specification.
d. Section 01 50 00, Temporary Construction Facilities and Controls. Paragraph 2.2 is revised as shown below.
2.2 TEMPORARY TRAFFIC CONTROL
The Contractor must prepare and submit a traffic control plan. During construction the Contractor shall provide access and temporary relocated roads as necessary to maintain traffic. The Contractor shall maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment and the work, and the erection and maintenance of adequate warning, danger, and direction signs, shall be as required by the State and local authorities having jurisdiction. The plan must follow the requirements of the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD). The traveling public shall be protected from damage to person and property. The Contractor's traffic on roads selected for hauling material to and from the site shall interfere as little as possible with public traffic. The Contractor shall investigate the adequacy of existing roads and the allowable load limit on these roads. The Contractor shall be responsible for the repair of any damage to roads caused by construction operations.
See also section 01 30 00, paragraph 1.32.
e. Section 01 78 00, Closeout Submittals. Attachment 2, Fort Leavenworth BUILDER Contract Requirements, is added. A copy of the attachment is provided.
f. Section 09 65 66 RESILIENT FLOORING. Removed paragraph 3.3.4 Line Marking and Finishing
3.3.4 Line Marking and Finishing
After installation is complete, clean the floor surface in accordance with installation instructions. Lay out, mask, and paint line marking according to approved detail drawings and approved installation instructions. Finish in accordance with the manufacturer's recommendations.
g. Specification 23 08 00 COMMISSIONING OF MECHANICAL AND PLUMBING SYSTEMS. Add submittal requirement language and section reference.
i. Section 1.1 SEQUENCING AND SCHEDULING
b. Air Leakage Test Reports and Diagnostic test reports submitted and approved in accordance with Section 01 91 19 BUILDING ENCLOSURE COMMISSIONING.
ii. Section 1.2 SUBMITTALS is revised as shown below.
SD-03 Product Data
Test Equipment; G, DO RO
SD-06 Test Reports
Pipe Flushing, Testing, And Water Treatment Reports; G, DO RO
Completed Pre-Functional Checklists; G, , DO RO
Seasonal Test Report; G, DO RO
Full-Load Test Report; G, DO RO
iii. Section 3.12 SEASONAL TESTS is revised as shown below.
Execute seasonal functional performance testing, witnessed by the Contracting Officer. Correct deficiencies and make adjustments to O&M manuals and as-built drawings for applicable issues identified in any seasonal testing. Season of maximum heating load: The time of year when the outdoor temperature at the project site remains within plus or minus 30 20 degrees Fahrenheit of the project site's winter outdoor design temperature, throughout the period of TAB Commissioning Data recording. Season of maximum cooling load:
The time of year when the outdoor temperature at the project site remains within plus or minus 5 degrees Fahrenheit of the project site's summer outdoor design temperature, throughout the period of TAB Commissioning data recording
iv. Section 3.14 TRAINING is added.
3.14 TRAINING
The Mechanical Systems Technical Commissioning Specialist must review the training plan required by Section 01 78 00 OPERATION AND MAINTENANCE DATA and identify any deficiencies to the Contracting Officer's Representative and the Contractor's Quality Control Personnel. The Commissioning Provider is responsible for overseeing and approving the training plan required by Section 01 78 00 OPERATION AND MAINTENANCE DATA and identifying any deficiencies to the Contracting Officer's Representative and the Contractor's Quality Control Personnel. Coordinate, schedule, and document all required training. At a minimum, include the following items in the training report for commissioned systems:
a. Complete commissioning documentation
b. Complete O&M data
c. Complete Training
d. Purpose of equipment.
e. Principle of how the equipment works.
f. Important parts and assemblies.
g. How the equipment achieves its purpose and necessary operating conditions.
h. Most likely failure modes, causes and corrections.
i. On site demonstration.
j. Provide updates to O&M manuals based on field modifications.
k. Provide training of the post-occupancy operations and maintenance staff.
v. Section 3.16 POST-CONSTRUCTION ENDURANCE TEST is revised shown below.
Perform an Endurance Test in accordance with the paragraph ENDURANCE TEST in Section 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC once during the peak heating season and once during the peak cooling season during outdoor air condition extremes with the exception that network bandwidth usage measurement and recording is not required.
The Mechanical System Commissioning Specialists must review the trend logs from the Endurance Tests to ensure that the systems have stable operation and operate as required by the construction contract and the accepted design. The Commissioning Specialists must provide a Post-Construction Trend Log Report that identifies any deficiencies noted in operation, recommendations for correction, and includes a graphical representation of the trends. Provide one Trend Log Report for the peak cooling season and one Trend Log Report for the peak heating season. Submit the Post-Construction Trend Log Reports no later than 14 calendar days following receipt of the trend log data by the Commissioning Specialist. Provide a Post-Construction Trend Log Report meeting the same requirements as the Endurance Testing Results Format in Section 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC. Provide one Trend Log Report for the peak cooling season and one Trend Log Report for the peak heating season. Submit the Post- Construction Trend Log Reports no later than 14 calendar days following download of the trended data.
Include the post-construction trend log report Post-Construction Trend Log Reports in the Updated Final Commissioning Report as specified in Section 01 91 00.15 BUILDING
COMMISSIONING
g. Specification 26 20 00 INTERIOR DISTRIBUTION SYSTEM.
Delete para 3.1.6 – Camera Cable Support Installation
Install open top and closed ring cable supports on 4 ft to 5 ft centers to adequately support and distribute the cable’s weight. Use these types of supports to support a maximum of 50 0.25 in diameter cables. Install suspended cables with at least 3 in of clear vertical space above the ceiling tiles and support channels (T-bars). Open top and closed ring cable supports: suspended from or attached to the structural ceiling or walls with hardware or other installation aids specifically designed to support their weight.
2. Drawings.
a. B-102 – Added sheet note.
b. B-103 – Added sheet note and blow counts to boring logs.
c. B-105 – Changed the surcharge requirements.
d. B-301 – Removed hatched box that represented the building and added the surcharge to the section view.
e. C-501 – Updated note on details A7 and D7
f. C-502 – Updated note on detail A8
g. S-001 Clarification of truss design requirements
h. S-310 revised footing graphics
i. S-311 revised foundation section
j. S-510 clarification of subgrade requirements
k. S-601 revised footing schedule and reinforced concrete column detail
l. S-412A revised foundation
m. S-413A revised foundation, added general notes
n. A-600, Provide HM frame for HM steel door 120A, 120B, and 120C.
o. A-412A revised screen wall, below grade detailing
p. A-413A revised screen wall. Updated exterior door to mechanical yard to match A-413
q. IN204 - Removed reference to specification from detail C7
r. IN602 – Added note # indicating full height impact resistant drywall where indicated on schedule.
Updated Ceiling Finishes to match RCP.
s. MH113 – Added Airflow Monitoring station location keynotes and updated keynote legends.
t. MH410 - Added Airflow Monitoring station location keynotes and updated keynote legends.
u. MI601 – Updated Fort Leavenworth UMCS systems language.
v. MI620 – Updated Airflow Monitoring Station location keynotes and updated keynote legend. Updated
Return Fan Sequence Language. Added VFD to return and Supply Fan Schematic.
w. M-601 – Updated Boilers Schedule to Show min. Pressure Relief valve settings.
x. M-603 – Updated Expansion Tank schedules
3. The time and date for submission of proposals is not changed and remains February 28, 2024, at 11:00 AM local Time.
4. Offerors are required to acknowledge receipt of this amendment. Failure to acknowledge receipt of all amendments may cause rejection of offeror’s proposal.
5. All other terms and conditions remain unchanged and in full force.
(End of Amendment)
(End of Summary of Changes)
504741LVNCDC W912DQ24R4000
Ft. Leavenworth, KS
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 35
SPECIAL INSPECTIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 GENERAL REQUIREMENTS
1.3 DEFINITIONS
1.3.1 Continuous Special Inspections
1.3.2 Perform
1.3.3 Observe
1.3.4 Special Inspector (SI)
1.3.5 Associate Special Inspector (ASI)
1.3.6 Third Party
1.3.7 Special Inspector of Record (SIOR)
1.3.8 Contracting Officer
1.3.9 Contractor's Quality Control (QC) Manager
1.3.10 Structural Engineer of Record (SER)
1.3.11 Statement of Special Inspections (SSI)
1.3.12 Schedule of Special Inspections (SSI)
1.3.13 Definable Feature of Work (DFOW)
1.4 SUBMITTALS
1.5 SPECIAL INSPECTOR QUALIFICATIONS
1.5.1 Steel Construction and High Strength Bolting
1.5.1.1 Special Inspector
1.5.1.2 Associate Special Inspector
1.5.2 Welding Structural Steel
1.5.2.1 Special Inspector
1.5.2.2 Associate Special Inspector
1.5.3 Nondestructive Testing of Welds
1.5.3.1 Special Inspector
1.5.3.2 Associate Special Inspector
1.5.4 Cold Formed Steel Framing
1.5.4.1 Special Inspector
1.5.4.2 Associate Special Inspector
1.5.5 Concrete Construction
1.5.5.1 Special Inspector
1.5.5.2 Associate Special Inspector
1.5.6 Verification of Site Soil Condition, Fill Placement and
Load-Bearing Requirements
1.5.6.1 Special Inspector
1.5.6.2 Associate Special Inspector
1.5.7 Sprayed Fire Resistant Material
1.5.7.1 Special Inspector
1.5.7.2 Associate Special Inspector
1.5.8 Fire-Resistant Penetrations and Joints
1.5.8.1 Special Inspector
1.5.8.2 Associate Special Inspector
1.5.9 Special Inspector of Record (SIOR)
01 45 35 - 1
1.5.10 Adhesive Anchors
1.5.10.1 Special Inspector Qualifications for Anchors Installed in the Horizontal or Upwardly Inclined Position
PART 2 PRODUCTS
2.1 FABRICATOR SPECIAL INSPECTIONS
PART 3 EXECUTION
3.1 RESPONSIBILITIES
3.1.1 Special Inspector of Record
3.1.2 Quality Control Manager
3.1.3 Special Inspectors
3.2 DEFECTIVE WORK
-- End of Section Table of Contents --
01 45 35 - 2
SECTION 01 45 35
SPECIAL INSPECTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
INTERNATIONAL CODE COUNCIL (ICC)
ICC IBC (2021) International Building Code
1.2 GENERAL REQUIREMENTS
Perform Special Inspections in accordance with the Statement of Special Inspections, Schedule of Special Inspections and Chapter 17 of ICC IBC .
The Statement of Special Inspections and Schedule of Special Inspections are included as an attachment to this specification. Special Inspections are to be performed by an independent third party and are intended to ensure that the work of the Prime Contractor is in accordance with the Contract Documents and applicable building codes. Special inspections do not take the place of the three phases of control inspections performed by the Contractor's QC Manager or any testing and inspections required by other sections of the specifications.
Structural observations will be performed separately by the Government .
The Contractor must provide notification to the Contracting Officer 14 days prior to the following points of construction to allow for structural observation:
a. Completion of installation of all OSB shear walls (and prior to covering with dry wall).
b. Completion of installation of all collector trusses.
c. Completion of installation of metal roof deck and related fastening system.
d. Completion of installation of front entrance canopy structural steel framing.
1.3 DEFINITIONS
1.3.1 Continuous Special Inspections
Continuous Special Inspections is the constant monitoring of specific tasks by a special inspector. These inspections must be carried out continuously over the duration of the particular tasks.
1.3.2 Perform
Perform these Special Inspections tasks for each welded joint or member.
01 45 35 - 3
1.3.3 Observe
Observe these Special Inspections items on a periodic daily basis.
Operations need not be delayed pending these inspections.
1.3.4 Special Inspector (SI)
A qualified person retained by the Contractor and approved by the Contracting Officer as having the competence necessary to inspect a particular type of construction requiring Special Inspections. The SI must be an independent third party hired directly by the Prime Contractor.
1.3.5 Associate Special Inspector (ASI)
A qualified person who assists the SI in performing Special Inspections but must perform inspection under the direct supervision of the SI and cannot perform inspections without the SI on site.
1.3.6 Third Party
A Special inspector must not be an employee of the Contractor or of any Sub-Contractor performing the work to be inspected.
1.3.7 Special Inspector of Record (SIOR)
A licensed engineer in responsible charge of supervision of all special inspectors for the project and approved by the Contracting Officer. The SIOR must be an independent third party entity hired directly by the Prime Contractor.
1.3.8 Contracting Officer
The Government official having overall authority for administrative contracting actions. Certain contracting actions may be delegated to the Contracting Officer's Representative (COR).
1.3.9 Contractor's Quality Control (QC) Manager
An individual retained by the Prime Contractor and qualified in accordance with the Section 01 45 00 QUALITY CONTROL having the overall responsibility for the Contractor's QC organization.
1.3.10 Structural Engineer of Record (SER)
A registered design professional employed by the Government responsible for the overall design and review of submittal documents prepared by others. The SER is registered or licensed to practice their respective design profession as defined by the statutory requirements of the professional registration laws in the state in which the design professional works. The SER is also referred to as the Engineer of Record (EOR) in design code documents.
1.3.11 Statement of Special Inspections (SSI)
A document developed by the SER identifying the material, systems, components and work required to have Special Inspections. This statement is included at the end of this specification.
01 45 35 - 4
1.3.12 Schedule of Special Inspections (SSI)
A schedule which lists each of the required Special Inspections, the extent to which each Special Inspection is to be performed, and the required frequency for each in accordance with ICC IBC Chapter 17. This schedule is included at the end of this specification.
1.3.13 Definable Feature of Work (DFOW)
An inspection group that is separate and distinct from other inspection groups, having inspection requirements or inspectors that are unique.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals SIOR Letter of Acceptance; G , RO Special Inspections Project Manual; G , RO
SD-06 Test Reports
Special Inspections Daily Reports
Special Inspections Biweekly Reports
SD-07 Certificates
AISC Certified Steel Fabricator
AC472 Accreditation
Certificate of Compliance
Special Inspector of Record Qualifications; G , RO Special Inspector Qualifications; G , RO
SD-11 Closeout Submittals
Comprehensive Final Report of Special Inspections; G , RO
1.5 SPECIAL INSPECTOR QUALIFICATIONS
Submit qualifications for each special inspector.
1.5.1 Steel Construction and High Strength Bolting
1.5.1.1 Special Inspector
a. ICC Structural Steel and Bolting Special Inspector certificate with one year of related experience, or
b. Registered Professional Engineer with three years of related experience
01 45 35 - 5
1.5.1.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.2 Welding Structural Steel
1.5.2.1 Special Inspector
a. ICC Structural Welding Special Inspector certificate with one year of related experience, or
b. AWS Certified Welding Inspector
1.5.2.2 Associate Special Inspector
AWS Certified Associate Welding Inspector
1.5.3 Nondestructive Testing of Welds
1.5.3.1 Special Inspector
NDT Level III Certificate
1.5.3.2 Associate Special Inspector
NDT Level II Certificate plus one year of related experience
1.5.4 Cold Formed Steel Framing
1.5.4.1 Special Inspector
a. ICC Structural Steel and Bolting Special Inspector certificate with one year of related experience, or
b. ICC Commercial Building Inspector with one year of experience, or
c. ICC Residential Building Inspector with one year of experience, or
d. Registered Professional Engineer with three years related experience
1.5.4.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.5 Concrete Construction
1.5.5.1 Special Inspector
a. ICC Reinforced Concrete Special Inspector Certificate with one year of related experience, or
b. ACI Concrete Construction Special Inspector, or
c. Registered Professional Engineer with three years of related experience
1.5.5.2 Associate Special Inspector
a. ACI Concrete Construction Special Inspector in Training, or
01 45 35 - 6
b. Engineer-In-Training with one year of related experience
1.5.6 Verification of Site Soil Condition, Fill Placement and Load-Bearing Requirements
1.5.6.1 Special Inspector
a. ICC Soils Special Inspector Certificate with one year of related experience, or
b. NICET Soils Technician Level II Certificate in Construction Material Testing, or
c. Geologist-In-Training with three years of related experience, or
d. Registered Professional Engineer with three years of related experience
1.5.6.2 Associate Special Inspector
a. NICET Soils Technician Level I Certificate in Construction Material Testing with one year of related experience, or
b. Engineer-In-Training with one year of related experience
1.5.7 Sprayed Fire Resistant Material
1.5.7.1 Special Inspector
a. ICC Spray-applied Fireproofing Special Inspector Certificate, or
b. ICC Fire Inspector I Certificate with one year of related experience, or
c. Registered Professional Engineer or Architect with related experience
1.5.7.2 Associate Special Inspector
Engineer-In-Training with one year of related experience
1.5.8 Fire-Resistant Penetrations and Joints
1.5.8.1 Special Inspector
a. Passed the UL Firestop Exam with one year of related experience, or
b. Passed the FM Firestop Exam with one year of related experience, or
c. Registered Professional Engineer with related experience
1.5.8.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.9 Special Inspector of Record (SIOR)
Registered Professional Engineer with five years of related experience.
01 45 35 - 7
1.5.10 Adhesive Anchors
1.5.10.1 Special Inspector Qualifications for Anchors Installed in the Horizontal or Upwardly Inclined Position
a. Certification as an ACI/CRSI Adhesive Anchor Installation Inspector, or equivalent.
PART 2 PRODUCTS
2.1 FABRICATOR SPECIAL INSPECTIONS
Special Inspections of fabricator's work performed in the fabricator's shop is required to be inspected in accordance with the Statement of Special Inspections and the Schedule of Special Inspections unless the fabricator is certified by the approved agency to perform such work without Special Inspections. Submit the following certifications to the Contracting Officer for information to allow work performed in the fabricator's shop to not be subjected to Special Inspections.
AISC Certified Steel Fabricator.
International Accreditation Service, AC472 Accreditation
At the completion of fabrication, submit a certificate of compliance, to be included with the comprehensive final report of Special Inspections, stating that the materials supplied and work performed by the fabricator are in accordance with the construction documents.
PART 3 EXECUTION
3.1 RESPONSIBILITIES
3.1.1 Special Inspector of Record
a. Supervise all Special Inspectors required by the Contract Documents and the IBC.
b. Submit a SIOR Letter of Acceptance to the Contracting Officer attesting to acceptance of the duties of SIOR, signed and sealed by the SIOR.
c. Verify the qualifications of all of the Special Inspectors.
d. Verify the qualifications of fabricators.
h. Prepare a Special Inspections Project Manual, which must cover the following:
(1) Roles and responsibilities of the following individuals during Special Inspections: SIOR, SI, ASI, General Contractor's QC Manager and SER.
(2) Organizational chart or communication plan, indicating lines of communication.
(3) Contractor's internal plan for scheduling inspections. Address items such as timeliness of inspection requests, who to contact for inspection requests, and availability of alternate inspectors.
01 45 35 - 8
(4) Indicate the Government reporting requirements.
(5) Propose forms or templates to be used by SI and SIOR to document inspections.
(6) Indicate procedures for tracking nonconforming work and verification that corrective work is complete.
(7) Indicate how the SIOR and SI will participate in weekly QC meetings.
(8) Indicate how Special Inspections of shop fabricated items will be handled when the fabricator's shop is not certified in accordance with paragraph FABRICATOR SPECIAL INSPECTIONS.
(9) Include a section in the manual that covers each specific item requiring Special Inspections that is indicated on the Schedule of Special Inspections. Provide names and qualifications of each special inspector who will be performing the Special Inspections for each specific item. Provide detail on how the Special Inspections are to be carried out for each item so that the expectations are clear for the General Contractor and the Subcontractor performing the work.
Make a copy of the Special Inspections Project Manual available on the job site during construction. Submit a copy of the Special Inspections Project Manual for approval.
i. Attend coordination and mutual understanding meeting where the information in the Special Inspections Project Manual will be reviewed to verify that all parties have a clear understanding of the Special Inspections provisions and the individual duties and responsibilities of each party.
j. Maintain a 3-ring binder for the Special Inspector's daily and biweekly reports and the Special Inspections Project Manual. This file must be located in a conspicuous place in the project trailer/office to allow review by the Contracting Officer and the SER.
k. Submit a copy of the Special Inspector's daily reports to the QC Manager.
l. Discrepancies that are observed during Special Inspections must be reported to the QC Manager for correction. If discrepancies are not corrected before the special inspector leaves the site the observed discrepancies must be documented in the daily report.
m. Submit a biweekly Special Inspections report until all work requiring Special Inspections is complete. A report is required for each biweekly period in which Special Inspections activity occurs, and must include the following:
(1) A brief summary of the work performed during the reporting time frame.
(2) Changes and discrepancies with the drawings, specifications that were observed during the reporting period.
01 45 35 - 9
(3) Discrepancies which were resolved or corrected.
(4) A list of nonconforming items requiring resolution.
(5) All applicable test results including nondestructive testing reports.
o. At the completion of the project submit a comprehensive final report of Special Inspections that documents the Special Inspections completed for the project including corrections of all discrepancies noted in the daily reports. The comprehensive final report of Special Inspections must be signed, dated and bear the seal of the SIOR.
3.1.2 Quality Control Manager
a. Maintain a rework items list that includes discrepancies noted on the Special Inspectors daily report.
3.1.3 Special Inspectors
a. Inspect all elements of the project for which the special inspector is qualified to inspect and are identified in the Schedule of Special Inspections.
b. Attend preparatory phase meetings related to the Definable Feature of Work (DFOW) for which the special inspector is qualified to inspect.
c. Submit a copy of the daily reports to the QC Manager.
d. Report discrepancies that are observed during Special Inspections to the QC Manager for correction. If discrepancies are not corrected before the special inspector leaves the site the observed discrepancies must be documented in the daily report.
e. Submit a biweekly Special Inspection Report until all inspections are complete. A report is required for each biweekly period in which Special Inspections activity occurs, and must include the following:
(1) A brief summary of the work performed during the reporting time frame.
(2) Changes and discrepancies with the drawings, specifications that were observed during the reporting period.
(3) Discrepancies which were resolved or corrected.
(4) A list of nonconforming items requiring resolution.
(5) All applicable test result including nondestructive testing reports.
f. At the completion of the project submit a comprehensive final report of Special Inspections that documents the Special Inspections completed for the project and corrections of all discrepancies noted in the daily reports. The comprehensive final report of Special Inspections must be signed, dated and indicate the certification of the special inspector qualifying them to conduct the inspection.
01 45 35 - 10
k. Submit daily reports to the SIOR. 3.2 DEFECTIVE WORK
Check work as it progresses, but failure to detect any defective work or materials must in no way prevent later rejection if defective work or materials are discovered, nor obligate the Contracting Officer to accept such work.
-- End of Section --
01 45 35 - 11
Project:
Location:
Project #:
Date:
B
III
No
CFMF Sheathed Shear Walls
Statement of Special Inspections Page 1 of 2
Identified on plan with key notes
See roof plans
Horizontal LFRS Elements Notes
Metal roof deck and related fastening system
Collector Elements
Following is a listing of critical main wind/seismic force resisting systems for this structure. Carefully inspect these elements as part of the roles and responsiblities of the Special Inspector (reference the Schedule of Special Inspections for inspection checklists).
Lateral Force Resisting System (LFRS)
2021 IBC 1704.3.2 and 1704.3.3
Vertical LFRS Elements Notes
Hazardous Occupancy or attached to such?
STATEMENT OF SPECIAL INSPECTIONS
Special Inspector of Record (SIOR)
A Special Inspector of Record (SIOR)
SIOR Name (Registered Professional):
Professional Registration Number:
Consulting Firm Name (if any):
SIOR Office AND Mobile Phone Number:
IS
Group H Occupancies required (per UFGS 01 45 35, Section 1.3.7)
Child Development Center
Fort Leavenworth, KS
504741 PN 97509
2/6/2024
Project Seismic Design Category:
Project Risk Category:
Project Design Wind Speed (mph):
Number of Stories:
Structure Height Above Grade (ft):
Project:
Location:
Project #:
Date:
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
2/6/2024
504741 PN 97509
Fort Leavenworth, KS
Child Development Center
Designated Seismic Systems (DSS)
DSS Component XX
Final Walk Down Inspection and Report
(UFC 3 301 01 SECTION 2-5.4)
Final Walk Down Inspection of non-structural Designated Seismic Systems does not apply to this project (no
Designated Seismic Systems)
Final Walk Down Report, Prepared by the Registered Design Professional in Responsible Charge, Must Include:
1. Record observations of Final Walk Down Inspection
2. Document that Inspections were performed in accordance with the Schedule of Special Inspections
3. Document that all Designated Seismic Systems are installed according to construction/manufacturer document requirements, and that Compliance Certificates have been collected (UFC 03 301 01, 3-6.2, 13.2.2.2).
Statement of Special Inspections Page 2 of 2
DSS Gas lines and associated fittings, anchorage, & flexible Connections
DSS Component XX
DSS Component XX
DSS Component XX
DSS Component XX
DSS Component XX
(2021 IBC 1705.14.3) (ASCE 7-16, 13.2.2, C13.2.2) (UFC 3-301-1, 2-5.4)
DESIGNATED SEISMIC SYSTEMS DO NOT APPLY TO THIS PROJECT, due to the Seismic Design Category being less than C.
ELECTRICAL Designated Seismic Systems (DSS) Requiring a Certificate of Compliance
If additional space is required, append an additional sheet listing the remaining DSS
If additional space is required, append an additional sheet listing the remaining DSS
DSS Emergency or Standby Power System
DSS Component XX
DSS Component XX
DSS Component XX
DSS Component XX
MECHANICAL/PLUMBING Designated Seismic Systems (DSS) Requiring a Certificate of Compliance
OTHER Designated Seismic Systems (DSS) Requiring a Certificate of Compliance
DSS Building egress stair systems
DSS Building fire sprinkler systems
DSS Component XX
DSS Component XX
DSS Component XX
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024
SCHEDULE OF SPECIAL INSPECTIONS
Reference UFGS 01 45 35 for all requirements not noted as part of this schedule.
INSPECTION DEFINITIONS:
PERFORM: Perform these tasks for each weld, fastener or bolted connection, and noted verification.
OBSERVE: Observe these items randomly during the course of each work day to insure that applicable requirements are being met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT: Document, with a report, that the work has been performed in accordance with the contract documents. This is in addition to any other reports required in the Special Inspections guide specification.
CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.
The Seismic Design Category for this project is: ☐ A, ☒ B, ☐ C, ☐ D, ☐ E, ☐ F (check appropriate box)
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024
STRUCTURAL - STEEL – WELDING SECTION
ALL OR PORTIONS OF THIS SECTION ARE APPLICABLE IF BOX IS CHECKED: ☒
STEEL INSPECTION PRIOR TO WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2021 IBC 1705.2.1, AISC 360-16: Table C-N5.4-1
TASK INSPECTION TYPE1 DESCRIPTION
1. Verify that the welding procedures specification
(WPS) is available
PERFORM
2. Verify manufacturer certifications for welding consumables are available
PERFORM
3. Verify material identification PERFORM Type and grade.
4. Welder Identification
System
PERFORM The fabricator or erector, as applicable, shall maintain a system by which a welder who has welded a joint or member can be identified. Stamps, if used, shall be the low-stress type.
5. Fit-up of groove welds
(including joint geometry)
OBSERVE Joint preparation
Dimensions (alignment, root opening, root face, bevel)
Cleanliness (condition of steel surfaces)
Tacking (tack weld quality and location)
Backing type and fit (if applicable)
6. Configuration and finish of access holes
OBSERVE
7. Fit-up of fillet welds OBSERVE Dimensions (alignment, gaps at root)
Cleanliness (condition of steel surfaces)
Tacking (tack weld quality and location)
STEEL INSPECTION DURING WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2021 IBC 1705.2.1, AISC 360-16: Table C-N5.4-2
TASK INSPECTION TYPE DESCRIPTION
8. Use of qualified welders PERFORM Welding by welders, welding operators, and tack welders who are qualified in conformance with requirements.
9. Control and handling of welding consumables
OBSERVE Packaging
Electrode atmospheric exposure control
10. No welding over cracked tack welds
OBSERVE
11. Environmental conditions OBSERVE Wind speed within limits
Precipitation and temperature
12. Welding Procedures
Specification followed
OBSERVE Settings on welding equipment
Travel speed
Selected welding materials
Shielding gas type/flow rate
Preheat applied
Interpass temperature maintained (min./max.)
Proper position (F, V, H, OH)
Intermix of filler metals avoided
13. Welding techniques OBSERVE Interpass and final cleaning
Each pass within profile limitations
Each pass meets quality requirements
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024
STRUCTURAL - STEEL – WELDING SECTION (CONTINUED)
STEEL INSPECTION AFTER WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2021 IBC 1705.2.1, AISC 360-16: Table C-N5.4-3
TASK INSPECTION TYPE 1 DESCRIPTION
14. Welds cleaned OBSERVE
15. Size, length, and location of all welds
PERFORM Size, length, and location of all welds conform to the requirements of the detail drawings.
16. Welds meet visual acceptance criteria
PERFORM AND
DOCUMENT
Crack prohibition
Weld/base-metal fusion
Crater cross section
Weld profiles
Weld size
Undercut
Porosity
17. Arc strikes PERFORM
18. k-area PERFORM When welding of doubler plates, continuity plates or stiffeners has been performed in the k-area, visually inspect the web k-area for cracks.
19. Backing removed, weld tabs removed and finished, and fillet welds added where required
PERFORM
20. Repair activities PERFORM AND
DOCUMENT
21. Document acceptance or rejection of welded joint or member
PERFORM
END SECTION
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024
STRUCTURAL - STEEL – BOLTING SECTION
STEEL INSPECTION TASKS PRIOR TO BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2021 IBC 1705.2.1, AISC 360-16: Table C-N5.6-1
TASK INSPECTION TYPE 1 DESCRIPTION
1. Manufacture’s certifications available for fastener materials
PERFORM
2. Fasteners marked in accordance with
ASTM requirements
OBSERVE
3. Proper fasteners selected for joint detail
(grade, type, bolt length if threads are to be excluded from shear plane)
OBSERVE
4. Proper bolting procedure selected for joint detail
OBSERVE
5. Connecting elements, including appropriate faying surface condition and hole preparation, if specified, meet applicable requirements
OBSERVE
6. Proper storage provided for bolts, nuts, washers, and other fastener components
OBSERVE
STEEL INSPECTION TASKS DURING BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2021 IBC 1705.2.1, AISC 360-16: Table C-N5.6-2
TASK INSPECTION TYPE 1 DESCRIPTION
7. Fastener assemblies of suitable condition, placed in all holes and washers (if required) are positioned as required
OBSERVE
8. Joint brought to the snug-tight condition prior to pretensioning operation
OBSERVE
9. Fastener component not turned by the wrench prevented from rotating
OBSERVE
10. Bolts are pretensioned in accordance with
RCSC Specification, progressing systematically from the most rigid point toward the free edges
OBSERVE
STEEL INSPECTION TASKS AFTER BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2021 IBC 1705.2.1, AISC 360-10: Table C-N5.6-3
TASK INSPECTION TYPE 1 DESCRIPTION
11. Document acceptance or rejection of all bolted connections
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024
STRUCTURAL - STEEL - NON DESTRUCTIVE TESTING SECTION
NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2021 IBC 1705.2.1, AISC 360-16: Section N5.5
TASK INSPECTION TYPE 1 DESCRIPTION
1. Use of qualified nondestructive testing personnel
PERFORM Visual weld inspection and nondestructive testing (NDT) shall be conducted by personnel qualified in accordance with AWS
D1.8 clause 7.2
2. CJP groove welds OBSERVE [NOTE: DOR must delete this row if section D (SEISMIC
PROVISIONS SECTION) is checked]
Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 20% of CJP groove welds for materials greater than 5/16” (8mm) thick. Testing rate must be increased to 100% if greater than 5% of welds tested have unacceptable defects.
3. Welded joints subject to fatigue
OBSERVE Dye penetrant testing (DT) and Ultrasonic testing (UT) shall be performed on 100% of welded joints identified on contract drawings as being subject to fatigue.
4. Weld tab removal sites OBSERVE At the end of welds where weld tabs have been removed, magnetic particle testing shall be performed on the same beam-to-column joints receiving UT
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024
STRUCTURAL - STEEL – AISC 341 REQUIREMENTS (SEISMIC PROVISIONS) SECTION
ALL OR PORTIONS OF THIS SECTION ARE APPLICABLE IF BOX IS CHECKED: ☐
NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2021 IBC 1705.2.1, AISC 341-16: Section J6.2
TASK INSPECTION TYPE 1 DESCRIPTION
[NOTE: DOR may uncheck this section for projects NOT designed in accordance with AISC 341 (Seismic
Provisions) or for projects designed according to AISC 341, but using an R value equal to 3]
5. CJP groove welds OBSERVE Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 100% of CJP groove welds for materials greater than
5/16” thick (8mm).
6. Beam cope and access hole.
OBSERVE At welded splices and connections, thermally cut surfaces of beam copes and access holes shall be tested using magnetic particle testing
(MT) or dye penetrant testing (DT), when the flange thickness exceeds 1 1/2 in. for rolled shapes, or when the web thickness exceeds 1 1/2 in. for built-up shapes.
7. K-area NDT (AISC
341)
PERFORM Where welding of doubler plates, continuity plates or stiffeners has been performed in the k-area, the web shall be tested for cracks using magnetic particle testing (MT). The MT inspection area shall include the k-area base metal within 3-inches of the weld. The MT shall be performed no sooner than 48 hours following completion of the welding.
8. Placement of reinforcing or contouring fillet welds
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024
STRUCTURAL - STEEL - COMPOSITE CONSTRUCTION 1
COMPOSITE CONSTRUCTION PRIOR TO PLACING CONCRETE – VERIFY THE FOLLOWING ARE IN COMPLIANCE 2021 IBC 1705.2.1, AISC 360-16: Table N6.1, AISC 341-16: Table J9.1
TASK INSPECTION TYPE 2 DESCRIPTION
1. Placement and installation of steel headed stud anchors
PERFORM
2. Material identification of reinforcing steel (Type/Grade)
OBSERVE
3. Determination of carbon equivalent for reinforcing steel other than ASTM A706
OBSERVE
4. Proper reinforcing steel size, spacing, clearances, support, and orientation
OBSERVE
5. Reinforcing steel has not been re-bent in the field
OBSERVE
6. Reinforcing clearances have been provided
OBSERVE
7. Reinforcing steel has been tied and supported as required
OBSERVE
8. Composite member has required size
OBSERVE
STRUCTURAL - STEEL - OTHER INSPECTIONS
OTHER STEEL INSPECTIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2021 IBC 1705.2.1, AISC 341-16: Tables J8.1 & J10.1
TASK INSPECTION TYPE 2 DESCRIPTION
1. Anchor rods and other embedments supporting structural steel
PERFORM Verify the diameter, grade, type, and length of the anchor rod or embedded item, and the extent or depth of embedment prior to placement of concrete.
2. Fabricated steel or erected steel frame
OBSERVE Verify compliance with the details shown on the construction documents, such as braces, stiffeners, member locations and proper application of joint details at each connection.
3. Reduced beam sections (RBS) where/if occurs
DOCUMENT Contour and finish
Dimensional tolerances
4. Protected zones DOCUMENT No holes or unapproved attachments made by fabricator or erector
5. H-piles where/if occurs DOCUMENT No holes or unapproved attachments made by the responsible contractor
1 See Concrete Construction Section for all concrete related inspection of composite steel construction.
2 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2021 ON 02/07/2024
STRUCTURAL - COLD-FORMED METAL DECK - PLACEMENT SECTION
METAL DECK INSPECTION PRIOR TO DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE
SDI QA/QC-2017, Appendix 1, Table 1.1
TASK INSPECTION TYPE 1 DESCRIPTION
1. Verify compliance of materials
(deck and all deck accessories) with construction documents, including profiles, material properties, and base metal thickness
PERFORM
2. Document acceptance or rejection of deck and deck accessories
DOCUMENT
METAL DECK INSPECTION AFTER DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE
SDI QA/QC-2017, Appendix 1, Table 1.2
TASK INSPECTION TYPE 1 DESCRIPTION
3. Verify compliance of deck and all deck accessories installation with construction documents
PERFORM
4. Verify deck materials are represented by the mill certifications that comply with the construction documents
PERFORM
5. Document acceptance or…