About this file
This solicitation seeks custodial services at five locations within the Harry S. Truman Lake Project for the U.S. Army Corps of Engineers Kansas City District. The contractor will perform all custodial services in accordance with the Performance Work Statement for Bledsoe Ferry, Shawnee Bend, Dam Road, East Access Road, and West Access Road, complying with all applicable laws and regulations. The solicitation includes fixed price line items for an initial one-year base period of performance at each location, with four optional one-year periods that can be exercised at the government's discretion. Pricing will constitute full compensation for all required labor, equipment, materials and work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912DQ24Q1017
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES
QUANTITY
Bledsoe Ferry Custodial Services - Base
FFP
UNIT
Days
UNIT PRICE
The Government's payment for Custodian Services shall constitute full compensation to the Contractor for furnishing all labor, equipment, and materials;
and performing all operations required to complete the work in conformity with Performance Work Statement (PWS) located in section C.
FOB: Destination
PSC CD: S201
ITEM NO SUPPLIES/SERVICES
QUANTITY
Shawnee Bend Custodial Services - Base
FFP
UNIT
Days
NET AMT
UNIT PRICE
The Government's payment for Custodian Services shall constitute full compensation to the Contractor for furnishing all labor, equipment, and materials;
and performing all operations required to complete the work in conformity with Performance Work Statement (PWS) located in section C.
FOB: Destination
PSC CD: S201
NET AMT
AMOUNT
ITEM NO SUPPLIES/SERVICES
QUANTITY
UNIT
Days
UNIT PRICE
Dam and Access Roadways, Outlet Channel
FFP
The Government's payment for Custodian Services shall constitute full compensation to the Contractor for furnishing all labor, equipment, and materials;
and performing all operations required to complete the work in conformity with Performance Work Statement (PWS) located in section C.
FOB: Destination
PSC CD: S201
NET AMT
ITEM NO SUPPLIES/SERVICES
QUANTITY
UNIT
Days
UNIT PRICE
OPTION Bledsoe Ferry Custodial Services
FFP
The Government's payment for Custodian Services shall constitute full compensation to the Contractor for furnishing all labor, equipment, and materials;
and performing all operations required to complete the work in conformity with Performance Work Statement (PWS) located in section C.
FOB: Destination
PSC CD: S201
NET AMT
QUANTITY
UNIT
Days
UNIT PRICE
OPTION Shawnee Bend Custodial Services
FFP
The Government's payment for Custodian Services shall constitute full compensation to the Contractor for furnishing all labor, equipment, and materials;
and performing all operations required to complete the work in conformity with Performance Work Statement (PWS) located in section C.
FOB: Destination
PSC CD: S201
NET AMT
ITEM NO SUPPLIES/SERVICES
QUANTITY
UNIT
Days
UNIT PRICE
OPTION Dam and Access Roadways, Outlet Channel
FFP
The Government's payment for Custodian Services shall constitute full compensation to the Contractor for furnishing all labor, equipment, and materials;
and performing all operations required to complete the work in conformity with Performance Work Statement (PWS) located in section C.
FOB: Destination
PSC CD: S201
NET AMT
QUANTITY
UNIT
Days
UNIT PRICE
OPTION Bledsoe Ferry Custodial Services
FFP
The Government's payment for Custodian Services shall constitute full compensation to the Contractor for furnishing all labor, equipment, and materials;
and performing all operations required to complete the work in conformity with Performance Work Statement (PWS) located in section C.
FOB: Destination
PSC CD: S201
NET AMT
ITEM NO SUPPLIES/SERVICES
QUANTITY
UNIT
Days
UNIT PRICE
OPTION Shawnee Bend Custodial Services
FFP
The Government's payment for Custodian Services shall constitute full compensation to the Contractor for furnishing all labor, equipment, and materials;
and performing all operations required to complete the work in conformity with Performance Work Statement (PWS) located in section C.
FOB: Destination
PSC CD: S201
NET AMT
QUANTITY
UNIT
Days
UNIT PRICE
OPTION Dam and Access Roadways, Outlet Channel
FFP
The Government's payment for Custodian Services shall constitute full compensation to the Contractor for furnishing all labor, equipment, and materials;
and performing all operations required to complete the work in conformity with Performance Work Statement (PWS) located in section C.
FOB: Destination
PSC CD: S201
NET AMT
File details come from the government source that posted it. Updated .