Salient Characteristics.docx

DOCX document 35 KB Posted

Attached to
Replace Exterior Cipher Locks and Exit Hardware Retrofit, Hawaii
Solicitation number
W912CN27QA010
Issued by

About this file

This is a Salient Characteristics document supporting a U.S. Army solicitation for the replacement of exterior cipher locks and exit hardware retrofit at a facility in Hawaii. The document outlines the critical specifications and requirements that vendors must meet to submit a competitive quote under solicitation number W912CN27QA010, issued by the Department of the Army Materiel Command Army Contracting Command.

The salient characteristics typically establish the minimum technical and performance standards for the cipher locks and exit hardware systems, including specifications for security ratings, durability, compatibility with existing infrastructure, installation requirements, and compliance with applicable federal and military standards. These characteristics serve as the baseline requirements that differentiate acceptable proposals from non-responsive submissions. Vendors responding to this solicitation must ensure their proposed products and installation methodologies align with the specified characteristics to be considered for award. Additional details regarding pricing terms, delivery schedules, response deadlines, and award timelines would be found in the associated solicitation document.

View the file

Other files

File Type Posted
Solicitation - W912CN27QA010.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SALIENT CHARACTERISTICS & INSTALLATION INSTRUCTIONS

Project: Exterior Cipher Locks & Exit Hardware Retrofit Location: Schofield Barracks, Building 768, Hawaii User Agency: 125th Intelligence & Electronic Warfare Battalion (125th IEW BN) Coordination Authority: Schofield Barracks Directorate of Public Works (DPW) / Facility Management

1. Project Background & Objective The 125th Intelligence & Electronic Warfare Battalion (125th IEW BN) requires an upgrade of exterior and egress locking hardware at Building 768, Schofield Barracks, Hawaii.

The primary objective of this contract is the removal of obsolete hardware and the installation of Department of Defense (DoD) approved, standalone electronic pushbutton cipher locks, heavy-duty vertical rod panic exit hardware, high-security Small Format Interchangeable Cores (SFIC), and specialized conversion trim for standard and bullet-resistant door assemblies.

All installations must be performed by GSA-certified lock technicians to satisfy DoD physical security requirements and fire/life-safety egress regulations.

2. Door Hardware Matrix

Door Identifier(s)
Door Category
Hardware Specified
Trim & Conversion Plates

131, 130A, 129A, 149, 129B, 129C, 130B, 131B, 131C, 117, S1 Stairs, S2 Stairs (12 Openings)

Perimeter / Egress (Exit Device)
10-PIN Cipher Lock, DoD Approved;

Panic Bar Exit Devices with Vertical Locking Bars Custom Bullet-Resistant Dress Plates & Extended Tailpieces where applicable

132, 138, 101 Entry, F Latrine, M Latrine (5 Openings)

Interior / Controlled Entry (Mortise)
10-PIN Cipher Lock, Mortise Trim, DoD Approved
Standard Conversion Dress Plates (5 total); Door 101 receives Custom BR Plate

131, 129A, 149, 129B, 129C, 131B, 131C, 117, 101 Entry (9 Openings Sub-group)

Bullet-Resistant (BR) Assemblies
Integrated with above locksets
• (18) Custom Conversion Dress Plates for BR Doors

• (9) Custom Fabricated Extended Key Override Tailpieces

3. Salient Characteristics All equipment provided must meet or exceed federal and military physical security criteria:

Item
Description & Technical Details
Qty
1
GSA-Certified Lock Installation: Labor by GSA-certified locksmiths for 10-PIN cipher locks and associated devices
17
2
DoD-approved 10-PIN cipher lock shall be a standalone electronic pushbutton lock that does not require external wiring, connection to an access-control panel, or replaceable batteries for normal lock operation
12
3
Surface vertical locking bars, heavy-duty commercial/government grade
20
4
DoD-approved 10-PIN mechanical/electronic mortise lockset
5
5
Keys: Stamped "1", "2", "3" and marked "US Property, Do Not Duplicate"
3
6
Keys: Control keys stamped "US Property, Do Not Duplicate" for core extraction/insertion
2
7
Standard Conversion Dress Plates: Heavy-duty aesthetic and mounting retrofitting plates
5
8
Custom Bullet-Resistant Door Dress Plates: Heavy-gauge custom plates engineered for high-security bullet-resistant assemblies
18
9
Custom Tailpiece Fabrication: Machined extended override tailpieces designed for deep cylinder throw on bullet-resistant doors
9

4. Quality Assurance & Key Custody

4.1 Certified Labor & Quality Assurance

GSA Certification: All lock installations, core pinning, and exit device alignments must be executed by certified technicians qualified to handle GSA-approved and DoD-compliant locking systems.

Surface Preparation & Dressing: Standard and bullet-resistant doors must be retrofitted using the custom conversion dress plates to conceal prior preparations, ensure structural integrity, and maintain ballistic resistance.

Vertical Rod Adjustment: The Contractor shall install, adjust, and test all required heavy-duty exit-device and vertical latching components to ensure smooth operation, positive latching, and free egress without binding or drag.

4.2 Key Control & DPW Custodial Turnover

SFIC Master Override Keys: Exactly three (3) master override keys stamped sequentially "1", "2", and "3" and inscribed with "US Property, Do Not Duplicate" shall be generated.

SFIC Control Keys: Exactly two (2) core removal/control keys inscribed with "US Property, Do Not Duplicate" shall be generated.

Direct Handover Protocol: In compliance with military installation regulations, the Contractor shall turn over all master override keys and control keys directly to the Schofield Barracks Directorate of Public Works (DPW). The 125th IEW BN designated key control officer will sign out keys through DPW channels.

5. Technical Installation Instructions Phase 1: Site Preparation & Demolition Conduct an opening-by-opening audit against the Door Hardware Matrix to confirm door hand, stile width, and ballistic rating.

Remove all existing, obsolete locks, mortise cartridges, panic hardware, and vertical locking bars without damaging underlying structural frames.

Clean, deburr, and prepare all door preps. Apply rust-inhibiting primer to any bare cutouts to guard against tropical marine corrosion.

Phase 2: Plate Retrofit & Lockset Installation Standard Hollow Metal Doors: Fit standard conversion dress plates over existing cutout footprints on both interior and exterior faces. Secure through-bolts to manufacturer specifications to ensure rigid seating without deforming the door skins.

Bullet-Resistant Doors (9 Openings):

Align custom heavy-gauge bullet-resistant conversion plates over door preps, ensuring a minimum 1.25-inch perimeter overlap of existing penetrations.

Secure plates using high-strength tamper-resistant fasteners to maintain ballistic integrity.

Install custom-machined extended key override tailpieces into the cylinder assembly to guarantee full cylinder throw depth across the reinforced door core.

Mount the DoD-approved 10-PIN cipher locksets. (The cipher lock shall be a standalone electronic pushbutton lock that does not require external wiring, connection to an access-control panel, or replaceable batteries for normal lock operation).

Phase 3: Vertical Rod Panic Device Installation & Synchronization Mount the heavy-duty vertical rod panic bar chassis at standard finish height (40-5/16" centerline AFF).

Install top Pullman latch and bottom vertical locking rod bolt.

Adjust top and bottom rod linkages simultaneously to ensure synchronized release upon push-bar depression.

Verify bottom rod bolt maintains at least 3/16" floor/threshold clearance during opening motion to eliminate floor strike dragging.

Phase 4: SFIC Core Pinning & DPW Turnover Pin 7-pin SFIC cores to master specifications.

Verify mechanical stamping: Master keys sequentially stamped "1", "2", "3" with "US Property, Do Not Duplicate"; Control keys stamped "US Property, Do Not Duplicate".

Insert pinned cores into locksets using the designated Control Key and verify positive locking cam engagement.

Deliver master override keys and control keys directly to the Schofield Barracks DPW Key Control Facility under DA Form 5513 custody receipt.

6. Testing, Inspection, and Acceptance Prior to final acceptance, the Contractor and the Government-designated facility representative shall conduct a joint functional inspection of all 17 cipher-lock assemblies and associated exit hardware. The Contractor shall correct all deficiencies identified during Government inspection at no additional cost to the Government before final acceptance. Final payment is processed upon Government final acceptance of the completed installation and all deliverables identified in DEL-01 through DEL-05.

Operational opening and locking functions on all 17 standalone pushbutton cipher-lock assemblies.

Single-motion free egress via all vertical rod exit devices (NFPA 101 / Life Safety compliance).

Smooth operation of the extended tailpiece override on all bullet-resistant doors using the authorized override keys.

Clean handover of site debris, removed hardware, and manufacturer manuals.

Item
Test Parameter
Required Standard
Acceptance Criteria
1
Cipher Access Code Operation
17 Units
Code entry immediately retracts latch
2
Self-Powered Kinetic Charging
12 Units
Full operational power without batteries or wires
3
Single-Motion Egress
12 Exit Doors
Push-bar releases vertical rods in one smooth motion
4
Vertical Rod Clearance
20 Rod Sets
Zero drag on floor threshold; positive deadlocking
5
Mechanical Key Override
9 BR / 8 Standard Doors
Override key turns smoothly without binding
6
Ballistic Plate Rigidity
9 BR Openings
Custom plates rigidly seated with zero deflection
7
Site Cleanup & Hardware Disposition
Complete Facility
100% legacy hardware and scrap turned over/cleared

7. Deliverables

Deliverable Ref
Description
Recipient
DEL-01
17 Fully Installed and Operational Cipher Locks & Exit Devices
125th IEW BN
DEL-02
(3) Master Override Keys & (2) Control Keys (Stamped & Marked)
Schofield Barracks DPW
DEL-03
DPW Key Custody & Transfer Receipt Documentation
125th IEW BN S4 / DPW
DEL-04
Master PIN Programming Guides & Operator Reference Sheets
125th IEW BN Security / S2
DEL-05
Final Workmanship & Hardware Warranty Certification
125th IEW BN

8. Warranty

(a) General Warranty Obligation The Contractor warrants that all physical security hardware, locking mechanisms, exit devices, cipher electronic cores, and peripheral interfaces furnished and installed under this Contract shall conform to contract specifications and be free of any defects in equipment, materials, design, integration, or workmanship for a minimum period of two (2) years [source: 1, 2] commencing on the date of Government Final Acceptance [source: 1].

(b) Corrective Action The Contractor shall, at its own expense, remedy any failure to conform, or any defect in material or workmanship, including all parts, shipping, travel, and on-site labor required to return the lock to fully functional operations [source: 1, 2].

(c) Classification of Service Calls and Response Times The Contractor shall provide emergency and non-emergency warranty support during the warranty period in accordance with the following Service Level Agreements (SLAs):

(d) Extension of Warranty Any hardware component repaired or replaced under this warranty shall be warranted for an additional period of one (1) year from the date of the repair/replacement, or until the expiration of the original two (2) year warranty period, whichever is longer.