0011221174

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The solicitation cited in Block 9a is amended to respond to additional questions received. As a result, Section 01026 is revised.

Solictation deadline is not extended. All other Terms and Conditions remain unchanged.

See Summary of Changes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 27

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Nov-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912CN19B0001

X 9B. DATED (SEE ITEM 11)

26-Oct-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Nov-2018

CODE

EXPEDITIONARY CONTRACTING COMMAND

413TH CSB, RCO-HAWAII,

742 SANTOS DUMONT AVENUE

BLDG 108, 3RD FLOOR (WAAF)

SCHOFIELD BARRACKS HI 96857-5026

W912CN 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912CN19B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

QUESTIONS AND RESPONSES #2

QUESTION GOVERNMENT RESPONSE

Line item 0028 - What size chem curbs are required? Can go from 4” to unlimited size with straight and corner accessories.

Up to 7.5" round curb.

Line item 0041, 0043 – EPS & Polyiso is difficult to price out per square foot. Would be easier to price out using cubic feet.

Different heights for different lengths, pitch requirements and starting heights.

Unit is board feet which is also a unit of volume.

Line item 0032 – Building code looks to require installation of solid sheathing when replacing a tile roof. Should we include cost to resheath?

Do not resheath the entire roof. CLIN 25 can be used if needed for damaged portions.

Line item 0033 – Depending on condition of the existing tiles, installation of clear coat would cause broken tiles. Depending on profile of the tile, method of securing, and age it adds to factoring in how much will require replacement. This one could turn into a disaster. No way we can guess if existing tiles are already brittle, Already leaking? We can go in and clean tiles and get nailed for leaks and breakage due to our men accessing the roof. How do you suggest we approach this

CLIN?

This CLIN will only be applied to newly installed tiles. Each task order should have the same quantities of CLIN 32 and 33.

Line item 0037 (/0038) – Gravel roofs – Often times there are multiple layers on these

CLIN includes 3-6 layers. Removal of a typical roofing system.

types of roofs. Are we pricing out a single layer?

Line item 0044 – What is the required DFT?

Or gallons per square? We found the gallons per square and mils for the Silicone coating but not the Acrylic coating

The DFT varies for different substrates.

Complete manufacturer’s instructions are available online. Foundation Coat Application Rate: 1.00-1.50 gal per 100 ft2 (4.08 - 6.11 L/10 m2) per coat. Finish Coat Application Rate: 0.75-1.50 gal per 100 ft2 (3.05 - 6.11 L/10 m2) per coat.

We are wondering how to determine the building location of each CLIN.

In regards to the basic contract, the CLINs do not have specific building location. The location will be identified with the individual task orders. The Government has provided estimated quantities, which are based on anticipated need for various Army installations.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

SECTION 01026

SECTION 01026

STATEMENT OF WORK

PART 1 GENERAL

1.1 GENERAL

Contractor shall furnish all labor, equipment, materials, and other services required to perform Reroofing, Roof Repairs, guarantee workmanship for all work described below and provide a warranty in strict accordance with these technical provisions. Equipment including telescoping boom lifts, articulating boom lifts, stairway scaffolding etc., shall be considered incidental to roofing. Costs for these items shall be included in bid items for shingles, roofing panels, BUR, flashing, gutters, lumber, etc. Tie-downs shall be installed in accordance with EM 385-1-1 and remain in place after roofing is complete. The scope of work covered by this Contract does not cover Reroofing and Roof Repair work which might arise as part of a

Contract to repair or renovate a Building or group of Buildings. The work covered by this Contract does not include projects awarded by The U.S. Army Engineering District, Honolulu, excluding the Medical Facilities under Tripler (TAMC), to be designated by the Government during the contract period.

1.2 LOCATION OF WORK

The sites of work will be at Miscellaneous Buildings at Various Army Installations, on the Island of Oahu, excluding the Medical Facilities under Tripler (TAMC), to be designated by the Government during the contract period.

1.3 DESCRIPTION OF WORK:

Description of work are as follows: Repair Roofs of Miscellaneous Buildings which includes removal of existing and installation of new Fiberglass composition Shingles, Preformed Sheet-metal Roofing, Sheet-metal Gutters, Downspouts, Flashing, and replacement of deteriorated and Termite damaged Roof Lumber & Sheathing as required. Including incidental Painting of all bare exposed repaired wood surfaces, and all incidental items necessary to complete the work as required.

1.4 ITEMS OF WORK

Reroofing and Roof Repairs of Miscellaneous Buildings at Fort Shafter, Aliamanu Military Reservation, Fort DeRussy, Schofield Barracks, East Range, Leilehua Golf Course, Wheeler Army Airfield, Helemano Military Reservation and Tripler, (excluding the Medical Facilities, (TAMC).

1.5 BID ITEM NO. 001

REPLACE CERAMIC COATED MINERAL SURFACED SELF-SEALING FIBERGLASS COMPOSITION

STRIP SHINGLES, composed of a fiberglass mat base with ceramic-coated mineral granules tightly embedded in carefully refined, water-resistant asphalt. Two pieces of the shingle are firmly laminated together in a special tough asphaltic cement. Includes Removal & Disposal of existing Strip Shingles, Roofing Felt Underlayment, Metal Drip Edge and Installation of new, Felt Underlayment & Metal Drip Edge.

Estimated At: 100,000 S.F.

BID ITEM NO. 002

ROOFING PANELS Removal and Disposal, Includes Preformed & Corrugated Aluminum Roofing Panels, Preformed, Corrugated, Ribbed & Standing Seam Galvanized, Zinc & Colored Sheet Metal; and Preformed, Corrugated & Ribbed Fiberglass Panels. Estimated At: 100,000 S.F.

BID ITEM NO. 003

TRANSITE ROOFING PANELS, Removal and Disposal.

Includes Asbestos Abatement Air Monitoring, Temporary Fence Barricades, Personnel, Waste and Decontamination Unit. Estimated At: 8,000 S.F.

BID ITEM NO. 004

ALUMINUM ROOFING PANELS, Installation of Preformed or Corrugated Panels.

Estimated At: 8,000 S.F.

BID ITEM NO. 005

STEEL SHEET METAL ROOFING PANELS, Installation of Preformed, Standing Seam, Zinc Coated & Factory Painted. Estimated At: 100,000 S.F.

BID ITEM NO. 006

SHEET METAL FLASHING, Removal and Disposal. Includes Aluminum, Galvanized Steel, Copper, and Aluminum Fascia. Estimated At: 30,000 S.F.

BID ITEM NO. 007

SHEET METAL FLASHING, Installation of Aluminum Flashing.

Estimated At: 5,000 S.F.

BID ITEM NO. 008

SHEET METAL FLASHING, Installation of Aluminum Fascia.

Estimated At: 1,000 S.F.

BID ITEM NO. 009

SHEET METAL FLASHING, Installation of Galvanized Steel Flashing.

Estimated At: 25,000 S.F.

BID ITEM NO. 010

SHEET METAL FLASHING, Installation of Copper Flashing.

Estimated At: 10,000 S.F.

BID ITEM NO. 011

VENT THRU ROOF FLASHING, Installation, Includes Removal and Disposal.

Aluminum Vent Flashing. Estimated at 20 each.

BID ITEM NO. 012

VENT THRU ROOF FLASHING, INSTALLATION, INCLUDES REMOVAL AND DISPOSAL.

Galvanized Vent Flashing. Estimated at 20 each.

BID ITEM NO. 013

VENT THRU ROOF FLASHING, INSTALLATION, INCLUDES REMOVAL AND DISPOSAL. Lead Vent Flashing. Estimated at 300 each.

BID ITEM NO. 014

SHEET METAL GUTTERS & DOWNSPOUTS, Removal and Disposal of existing Gutter and Downspouts. Estimated At: 15,000 FT.

BID ITEM NO. 015

SHEET METAL GUTTERS & DOWNSPOUTS, Installation of Aluminum Gutters and Downspouts, 5". Estimated At: 7,000 FT.

BID ITEM NO. 016

Aluminum Gutters and Downspouts, 7". Estimated At: 3,000 FT.

BID ITEM NO. 017

SHEET METAL GUTTERS & DOWNSPOUTS, Installation of Galvanized Steel Gutters and Downspouts. Estimated At: 2,000 FT.

BID ITEM NO. 018

SHEET METAL GUTTERS & DOWNSPOUTS, Installation of Copper Gutters and Downspouts, K-Style. Estimated At: 4,000 FT.

BID ITEM NO. 019

Downspouts, Half-round style. Estimated At: 2,000 FT.

BID ITEM NO. 020

SPLASH BLOCKS, Installation of Concrete Splash Blocks.

Estimated At: 250 EA.

BID ITEM NO. 021

ROOF VENT PIPE EXTENSION, Installation of Roof Vent Pipe Extension.

Estimated At: 10 EA.

BID ITEM NO. 022

SCUPPER DRAINS, Re-install existing Scupper drains. Estimated at 10 EA.

BID ITEM NO. 023

SCUPPER DRAINS, Install new Scupper drains. Estimated at 10 EA.

BID ITEM NO. 024

STRUCTRUAL LUMBER, Replacement of existing Deteriorated or Termite Damaged Lumber. Includes Removal & Disposal of existing Deteriorated or Termite damaged Structural Lumber, and Incidental Painting of new Exposed Woodwork at Eaves, or as required. (1-Primer and 2- finish coats to match adjacent existing surfaces). Estimated At: 50,000 B.F.

BID ITEM NO. 025

ROOF SHEATHING, Replacement of existing Deteriorated Termite Damaged Sheathing Includes Removal & Disposal of existing Deteriorated or Termite damaged Sheathing and Incidental Painting of new Exposed Woodwork at Eaves, or as required. (1-Primer and 2- finish coats to match adjacent existing surfaces). Estimated At: 10,000 B.F.

BID ITEM NO. 026

METAL ROOF PURLINS, Replacement of existing Rusted or Damaged Purlins.

Includes Removal & Disposal of existing Rusted or Damaged Metal Purlins, and Incidental Painting of new Purlins as required. (1-Primer and 2- finish coats to match adjacent existing surfaces). Estimated At: 5,000 FT.

BID ITEM NO. 027

PITCH PANS, Replacement of existing Pitch Pans, Includes Removal and disposal. Estimated At: 10 EA.

BID ITEM NO. 028

CHEMCURB PITCH POCKET, Installation of CHEMCURB Pitch Pocket or approved equal. To include Removal, installation disposal and all required materials and equipment to complete work. Up to 7.5” round curb. Estimated At: 100

EA.

BID ITEM NO. 029

ROOF DRAINS, Removal and Re-installation of existing Roof Drains, Includes cleaning, testing, and installing Modified Bitumen Sheet Flashing.

Estimated At: 25 EA.

BID ITEM NO. 030

ROOF VENTILATORS, Removal and Re-installation of existing Electrical Power Aluminum Roof Ventilators. Estimated At: 25 EA.

BID ITEM NO. 031

Galvanized Roof Ventilators. Estimated At: 100 EA.

BID ITEM NO. 032

REPLACE CLAY TILE ROOFING, Includes Removal & Disposal of existing Clay Tile Roofing, Roofing Felt Underlayment, and Installation of new Clay Tile Roofing, Felt Underlayment, and Flashing as required.

Estimated At: 15,000 S.F.

BID ITEM NO. 033

CLAY TILE ROOF SEALER Installation of Low moisture absorption Clear drying penetrating water repellent barrier, Clay Tile Roof Sealer. To include Surface preparation and Installation of Roof Coating, clean-up and all required materials and equipment to complete work.

BID ITEM NO. 034

ASBESTOS ABATEMENT, Bulk Sampling, Field. Estimated At: 300 EA.

BID ITEM NO. 035

ASBESTOS ABATEMENT, Remove Asbestos Contaminated Metal Flashing, Base Flashing, Mastic, and Built-Up Roofing as required.

BID ITEM NO. 036

ASBESTOS ABATEMENT, Total Demolition and Disposal of existing Built-Up Roofing System clear down to existing Roof Deck as required.

ITEM NO. 037

90 LB. MINERAL SURFACE on Built-up Roofing, Removal and disposal. Remove Existing roofing down to existing substrate. Remove typical roof system of 3-6 layers.

Estimated At: 80,000 S.F.

ITEM NO. 038

Gravel on Built-up Roofing, Removal and disposal. Remove existing gravel roofing down to existing substrate. Remove typical roof system of 3-6 layers.

BID ITEM NO. 039

Built-up Roofing Installation of 2-Ply, Includes 90LB. SBS Mineral Surfaced Roll-Roofing Cap Sheet on SBS fiberglass Base Sheet.

ITEM NO: 040

Walkway Surface, Installation, Mineral Asphalt Plank.

BID ITEM NO. 041

ROOFING INSULATION (without Fire Proofing Insulation), Removal & Disposal.

Includes Tapered or Flat Insulation Boards. Estimated At: 300,000 B.F.

BID ITEM NO. 042

ROOFING INSULATION, Installation. Complete Installation to include 1/2” thick. Fiberglass Reinforced Gypsum Roof Boards and adhesive.

Estimated At: 300,000 B.F.

BID ITEM NO. 043

ROOFING INSULATION, Installation. Tapered. Complete Installation to Include1/2” thick. Fiberglass Reinforced Gypsum Roof Boards and adhesive.

Estimated At: 50,000 B.F.

BID ITEM NO. 044

ROOF COATING, Installation of Hydro-Stop Elastomeric Roofing with 1/16” reinforcing or approved equal.

BID ITEM NO. 045

ROOF COATING - Silicone, Installation of silicone roof coating per manufacturer’s instruction. Clean, prime coat, two top coats, clean-up, and all incidental items included.

Estimated At: 200,000 S.F.

BID ITEM NO. 046

Equipment Rental of 25 ton Crane with Operator. Unit of measure is a 7 day week.

Estimated at 40 Weeks

BID ITEM NO. 047

Equipment Hauling, round trip to include delivery to jobsite location and return to Rental Company.

Estimated at 5 Ea

BID ITEM NO. 048

REMOVE AND REINSTALL SOLAR PANELS, Remove and Reinstall Solar Panels Estimated at 30 Ea

BID ITEM NO. 049

Install RIDGE VENTS, Installation of Ridge Vents, for Composition Shingle Roofing. Includes creating new opening & installing preformed material, cap sheet and all incidental items required. Estimated at 25 FT

BID ITEM NO. 050

SAMPLE ANALYSIS, Collection and Laboratory analysis to determine if paint contains lead. To include all incidental items required. Estimated at 30

EA

BID ITEM NO. 051

SAMPLE ANALYSIS, Collection and Laboratory analysis (TCLP) to determine if paint/demolition debris contains Lead Based Paint and resulting debris can be classified as hazardous waste. To include all incidental items required.

Estimated at 15 EA

BID ITEM NO. 052

LEAD BASED PAINT ABATEMENT, Removal/Disposal of lead containing (hazardous) materials to include all incidental items required. Estimated at 20,000 SF

BID ITEM NO. 053

Install RIDGE VENTS, Installation of Ridge Vents for metal roofing (10” to 36”W X10’-0”L), Includes creating new opening & installing preformed material, flashing, and all incidental items required to provide a complete useable product. Estimated at 50 EA

BID ITEM NO. 054

Install Cant Strips, Installation of Cant Strips. To include all incidental items required. To include Removal, installation, disposal and all required materials and equipment to complete work. Estimated at 5,000 FT

BID ITEM NO. 055

ROOFING PANELS (With Fire Proofing Insulation), Removal and Disposal, Includes Preformed & Corrugated Aluminum Roofing Panels, Preformed, Corrugated, Ribbed & Standing Seam Galvanized, Zinc & Colored Sheet Metal;

and Preformed, Corrugated & Ribbed Fiberglass Panels. To include Removal, disposal, clean-up and all required materials and equipment to complete work. Estimated At: 10,000 S.F.

BID ITEM NO. 056

Fire Proofing Insulation, Installation of Spray-on Fire Proofing Insulation, To include clean-up and all required materials and equipment to complete work. Estimated At: 10,000 S.F.

BID ITEM NO. 057

Plastic Sheeting, Install plastic sheeting over flooring, furniture, equipment, supplies, etc. to protect from dust and debris. Includes clean-up and removal and all required materials and equipment to complete work.

Estimated At: 30,000 S.F.

BID ITEM NO. 058

Contractor Manpower Reporting (CMR), in accordance with paragraph 1.11 of Section 01026. Estimated At: 1 EA.

BID ITEM NO. 1001

STRIP SHINGLES, composed of a fiberglass mat base with ceramic-coated mineral granules tightly embedded in carefully refined, water-resistant asphalt. Two pieces of the shingle are firmly laminated together in a special tough asphaltic cement. Includes Removal & Disposal of existing

Strip Shingles, Roofing Felt Underlayment, Metal Drip Edge and Installation

BID ITEM NO. 1002

Aluminum Roofing Panels, Preformed, Corrugated, Ribbed & Standing Seam

BID ITEM NO. 1003

BID ITEM NO. 1004

BID ITEM NO. 1005

BID ITEM NO. 1006

BID ITEM NO. 1007

Estimated At: 5,000 S.F.

BID ITEM NO. 1008

BID ITEM NO. 1009

BID ITEM NO. 1010

BID ITEM NO. 1011

BID ITEM NO. 1012

BID ITEM NO. 1013

BID ITEM NO. 1014

BID ITEM NO. 1015

BID ITEM NO. 1016

BID ITEM NO. 1017

BID ITEM NO. 1018

BID ITEM NO. 1019

BID ITEM NO. 1020

Estimated At: 250 EA.

BID ITEM NO. 1021

BID ITEM NO. 1022

BID ITEM NO. 1023

BID ITEM NO. 1024

damaged Structural Lumber, and Incidental Painting of new Exposed Woodwork

BID ITEM NO. 1025

Sheathing Includes Removal & Disposal of existing Deteriorated or Termite damaged Sheathing and Incidental Painting of new Exposed Woodwork at Eaves, BID ITEM NO. 1026

BID ITEM NO. 1027

BID ITEM NO. 1028

equal. To include Removal, installation disposal and all required materials

BID ITEM NO. 1029

BID ITEM NO. 1030

BID ITEM NO. 1031

BID ITEM NO. 1032

Roofing, Roofing Felt Underlayment, and Installation of new Clay Tile

BID ITEM NO. 1033

penetrating water repellent barrier, Clay Tile Roof Sealer. To include Surface preparation and Installation of Roof Coating, clean-up and all

BID ITEM NO. 1034

BID ITEM NO. 1035

BID ITEM NO. 1036

ITEM NO. 1037

Existing roofing down to existing substrate. Remove typical roof system of

ITEM NO. 1038

roofing down to existing substrate. Remove typical roof system of 3-6

BID ITEM NO. 1039

ITEM NO: 1040

BID ITEM NO. 1041

BID ITEM NO. 1042

thick. Fiberglass Reinforced Gypsum Roof Boards and adhesive.

Estimated At: 300,000 B.F.

BID ITEM NO. 1043

ROOFING INSULATION, Installation. Tapered. Complete Installation to

BID ITEM NO. 1044

BID ITEM NO. 1045

manufacturer’s instruction. Clean, prime coat, two top coats, clean-up, BID ITEM NO. 1046

BID ITEM NO. 1047

BID ITEM NO. 1048

BID ITEM NO. 1049

BID ITEM NO. 1050

BID ITEM NO. 1051

paint/demolition debris contains Lead Based Paint and resulting debris can

BID ITEM NO. 1052

BID ITEM NO. 1053

36”W X10’-0”L), Includes creating new opening & installing preformed

BID ITEM NO. 1054

BID ITEM NO. 1055

Includes Preformed & Corrugated Aluminum Roofing Panels, Preformed, Corrugated, Ribbed & Standing Seam Galvanized, Zinc & Colored Sheet Metal;

and Preformed, Corrugated & Ribbed Fiberglass Panels. To include Removal, BID ITEM NO. 1056

BID ITEM NO. 1057

equipment, supplies, etc. to protect from dust and debris. Includes clean-

BID ITEM NO. 1058

BID ITEM NO. 2001

STRIP SHINGLES, composed of a fiberglass mat base with ceramic-coated mineral granules tightly embedded in carefully refined, water-resistant asphalt. Two pieces of the shingle are firmly laminated together in a special tough asphaltic cement. Includes Removal & Disposal of existing Strip Shingles, Roofing Felt Underlayment, Metal Drip Edge and Installation

BID ITEM NO. 2002

Aluminum Roofing Panels, Preformed, Corrugated, Ribbed & Standing Seam

BID ITEM NO. 2003

BID ITEM NO. 2004

BID ITEM NO. 2005

BID ITEM NO. 2006

BID ITEM NO. 2007

BID ITEM NO. 2008

BID ITEM NO. 2009

BID ITEM NO. 2010

BID ITEM NO. 2011

BID ITEM NO. 2012

BID ITEM NO. 2013

BID ITEM NO. 2014

BID ITEM NO. 2015

BID ITEM NO. 2016

BID ITEM NO. 2017

BID ITEM NO. 2018

BID ITEM NO. 2019

BID ITEM NO. 2020

Estimated At: 250 EA.

BID ITEM NO. 2021

BID ITEM NO. 2022

BID ITEM NO. 2023

BID ITEM NO. 2024

damaged Structural Lumber, and Incidental Painting of new Exposed Woodwork

BID ITEM NO. 2025

Sheathing Includes Removal & Disposal of existing Deteriorated or Termite damaged Sheathing and Incidental Painting of new Exposed Woodwork at Eaves, BID ITEM NO. 2026

BID ITEM NO. 2027

BID ITEM NO. 2028

equal. To include Removal, installation disposal and all required materials

BID ITEM NO. 2029

BID ITEM NO. 2030

BID ITEM NO. 2031

BID ITEM NO. 2032

Roofing, Roofing Felt Underlayment, and Installation of new Clay Tile

BID ITEM NO. 2033

penetrating water repellent barrier, Clay Tile Roof Sealer. To include Surface preparation and Installation of Roof Coating, clean-up and all

BID ITEM NO. 2034

BID ITEM NO. 2035

BID ITEM NO. 2036

ITEM NO. 2037

Existing roofing down to existing substrate. Remove typical roof system of

ITEM NO. 2038

roofing down to existing substrate. Remove typical roof system of 3-6

BID ITEM NO. 2039

ITEM NO: 2040

BID ITEM NO. 2041

BID ITEM NO. 2042

thick. Fiberglass Reinforced Gypsum Roof Boards and adhesive.

Estimated At: 300,000 B.F.

BID ITEM NO. 2043

ROOFING INSULATION, Installation. Tapered. Complete Installation to

BID ITEM NO. 2044

BID ITEM NO. 2045

manufacturer’s instruction. Clean, prime coat, two top coats, clean-up, BID ITEM NO. 2046

BID ITEM NO. 2047

BID ITEM NO. 2048

BID ITEM NO. 2049

BID ITEM NO. 2050

BID ITEM NO. 2051

paint/demolition debris contains Lead Based Paint and resulting debris can

BID ITEM NO. 2052

BID ITEM NO. 2053

36”W X10’-0”L), Includes creating new opening & installing preformed

BID ITEM NO. 2054

BID ITEM NO. 2055

Includes Preformed & Corrugated Aluminum Roofing Panels, Preformed, Corrugated, Ribbed & Standing Seam Galvanized, Zinc & Colored Sheet Metal;

and Preformed, Corrugated & Ribbed Fiberglass Panels. To include Removal, BID ITEM NO. 2056

BID ITEM NO. 2057

equipment, supplies, etc. to protect from dust and debris. Includes clean-

BID ITEM NO. 2058

1.6 ESTIMATED QUANTITIES OF WORK:

The quantities for the items of work are estimated only, and shall be performed in strict accordance with Special Contract Requirements Clause

"COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK ORDERED".

1.7 METHOD OF MEASUREMENT FOR LUMBER AND STEEL REPLACEMENT:

Lumber and Plywood replaced shall be tabulated in the actual quantity of board feet of lumber and square feet of plywood replaced. Wastage due to sawing, other field operations, and correction of deficiencies as a result of the Contractor's negligence or fault shall not be included in the allowances. The Contractor shall maintain a record of quantities of lumber and plywood replaced and shall submit it to the Contracting Officer for verification. The contract shall be modified for variances of 10% or greater.

Purlins and steel members replaced shall be tabulated in the actual quantity replaced. Wastage, other field operations, and correction of deficiencies as a result of the Contractor's negligence or fault shall not be included in the allowances. The Contractor shall maintain a record of quantities of steel replaced and shall submit it to the Contracting Officer for verification. The contract shall be modified for variances of 10% or greater.

1.8 METHOD OF MEASUREMENT FOR SHINGLE, METAL, TILE AND BUILT UP ROOFING:

Roofing shall be tabulated in the actual area of roofing replaced (plan view). Factor for roof pitch will be allowed. Excess waste and overlap shall not be included in the allowances.

1.9 OBSTRUCTION AND INTERFERENCES:

In the prosecution of this work, the Contractor shall move, return, or relocate all obstructions or interferences such as signs, furniture, rugs, appliances, office furnishings, draperies, desks, cabinets, office equipment, and (1/2" diameter, bright yellow "Ethernet", 1 EEE 82.3 which is not to be painted wherever encountered), with the exception of valuables and personal effects. Prior to the commencement, the Contractor should report to the occupants and the Technical Representative of the Contracting Officer any noticeable damage to all items.

1.10 DAILY CLEAN-UP:

During the course of the work, the Contractor shall keep the entire premises free from any accumulation of empty cans, rags, or rubbish that constitutes a fire hazard. At the end of each days work, the Contractor shall remove all paint smears and stains. The entire area shall be cleaned and left in a condition acceptable to the Technical Representative of the Contracting Officer.

1.11 CONTRACT MANPOWER REPORTING (CMR)

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the fencing via a secure data collection site. The contractor is required to fill in all required data fields completely using the following web address: http://www.ecmra.mil/, and then click on "Department of the Army CMRA" or the icon of the DoD organization that is receiving or benefitting from the contracted services.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), this runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk by clicking on "Send an email" which is located under the Help Resources ribbon on the right side of the login page of the applicable Service/Component's CMR website. Reporting is required for each task order issued, and shall be entered via the CMR website.

-- End of Section --