Amendment_0001,_Attachment_2_-_CLIN_Structure_(Revised_as_of_7Sep18).docx

DOCX document 15 KB Posted

Attached to
CCTV Upgrade/Preventive Maintenance and Repair Services
Solicitation number
W912CL-18-Q-0328
Issued by

About this file

CLIN structure (Revised as of 7 SEP 18)

View the file

Other files

File Type Posted
Questions_and_Answers.docx DOCX document
PWS_Attachment_3_-_Orion_Building_Rules_for_Contractors.pdf PDF
Amendment_0001,_W912CL18Q0328.docx DOCX document
PWS_Attachment_2_-_CCTV_Layout_for_Bldg_1000.pptx PPTX presentation
Amendment_0001,_Attachment_1_-_PWS_(Revised_as_of_7Sep18).docx DOCX document
W912CL18Q0328_QA.docx DOCX document
CCTV_layout_B-1000.pptx PPTX presentation
W912CL18Q0328.pdf PDF
Performance_Work_Statement.pdf PDF
CLIN_Structure.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 2 – CLIN Structure. All changes are noted in red. Revised as of 7 September 2018.

CLIN
ITEM DESCRIPTION
QTY
UNIT
UNIT PRICE
0001
Remove and Dispose of Surveillance System

In accordance with Performance Work Statement paragraphs 5.1 through 5.1.2.8, contractor shall remove and dispose of the existing surveillance system and components in US Army South HQs, building 1000.

1
Job
$
0002
Install Digital IP Network Surveillance System

In accordance with Performance Work Statement paragraphs 5.1 through 5.1.2.8, contractor shall install a digital IP network surveillance system in US Army South HQs, building 1000.

1
Job
$
0003
Training

In accordance with Performance Work Statement paragraph 5.1.5, contractor shall provide operators training for up to 4 personnel.

1
Job
$
0004
Preventive Maintenance and Repair Services Base Year

In accordance with Performance Work Statement paragraphs 5.1.6 through 5.1.7, contractor shall provide preventive maintenance services semi-annually on the surveillance system.

1
Job
$
0005
Contractor Manpower Reporting

Base Year

In accordance with Performance Work Statement paragraph 5.3, The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for US Army South via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2018. If contract period of performance ends prior to September 30, the contractor has 30 days from end date of the contract to complete the CMR requirement. Contractors may direct questions to the help desk at help desk at: http://www.ecmra.mil/

1
Each
$
1001
Preventive Maintenance and Repair Services Option Year One

In accordance with Performance Work Statement paragraphs 5.1.6 through 5.1.7, contractor shall provide preventive maintenance services semi-annually on the surveillance system.

1
Job
$
1002
CMR

Option Year One

In accordance with Performance Work Statement paragraph 5.3, The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for US Army South via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/.

1
Each
$
2001
Preventive Maintenance and Repair Services Option Year Two

In accordance with Performance Work Statement paragraphs 5.1.6 through 5.1.7, contractor shall provide preventive maintenance services semi-annually on the surveillance system.

1
Job
$
2002
CMR

Option Year Two

In accordance with Performance Work Statement paragraph 5.3, The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for US Army South via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/.

1
Each
$
3001
Preventive Maintenance and Repair Services Option Year Three

In accordance with Performance Work Statement paragraphs 5.1.6 through 5.1.7, contractor shall provide preventive maintenance services semi-annually on the surveillance system.

1
Job
$
3002
CMR

Option Year Three

In accordance with Performance Work Statement paragraph 5.3, The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for US Army South via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/.

1
Each
$
4001
Preventive Maintenance and Repair Services Option Year Four

In accordance with Performance Work Statement paragraphs 5.1.6 through 5.1.7, contractor shall provide preventive maintenance services semi-annually on the surveillance system.

1
Job
$
4002
CMR

Option Year Four

In accordance with Performance Work Statement paragraph 5.3, The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for US Army South via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/.

1
Each
$