SECTION 02722
AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE
1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)
AASHTO T 180
Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and an 457 mm (18-in) Drop
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
ASTM C 29/C 29M
Bulk Density ("Unit Weight") and Voids in Aggregate
ASTM C 88
Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate
ASTM C 117
Materials Finer Than 75 micrometer (No. 200) Sieve in Mineral Aggregates by Washing
ASTM C 127
Specific Gravity and Absorption of Course Aggregate
ASTM C 128
Specific Gravity and Absorption of Fine Aggregate
ASTM C 131
Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine
ASTM C 136
Sieve Analysis of Fine and Coarse Aggregates
ASTM D 75
Sampling Aggregates
ASTM D 422
Particle-Size Analysis of Soils
ASTM D 1556
Density and Unit Weight of Soil in Place by the Sand-Cone Method
ASTM D 1557
Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/cu. ft. (2,700 kN-m/cu. m.))
ASTM D 2167
Density and Unit Weight of Soil in Place by the Rubber Balloon Method
ASTM D 2487
Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D 2922
Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth)
ASTM D 3017
Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth)
ASTM D 4318
Liquid Limit, Plastic Limit, and Plasticity Index of Soils
ASTM E 11
Wire Cloth Sieves for Testing Purposes
NEW JERSEY STATE HIGHWAY DEPARTMENT (NJSHD)
Standard Specifications for
Road and Bridge Construction
1.2 DEFINITIONS
For the purposes of this specification, the following definitions apply.
1.2.1 Aggregate Base Course
Aggregate base course (ABC) is well graded, durable aggregate uniformly moistened and mechanically stabilized by compaction.
1.2.2 Graded-crushed Aggregate Base Course
Graded-crushed aggregate (GCA) base course is well graded, crushed, durable aggregate uniformly moistened and mechanically stabilized by compaction. GCA is similar to ABC, but it has more stringent requirements and it produces a base course with higher strength and stability.
1.2.3 Degree of Compaction
Degree of compaction shall be expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D 1557 or AASHTO T 180, Method D.
1.3 UNIT PRICES
1.3.1 Measurement
1.3.1.1 Area
The quantity of ABC and GCA completed and accepted, as determined by the Contracting Officer, will be measured in square yards.
1.3.1.2 Volume
The quantity of ABC and GCA completed and accepted, as determined by the Contracting Officer, will be measured in cubic yards. The volume of material in-place and accepted will be determined by the average job thickness obtained in accordance with paragraph THICKNESS CONTROL and the dimensions shown.
1.3.1.3 Weight
The tonnage of ABC and GCA material will be the number of tons of aggregate, placed and accepted in the completed course plus the amount placed in authorized stockpiles, as determined by the Contracting Officer. Deductions will be made for any material wasted, unused, rejected, or used for convenience of the Contractor, and for water exceeding specified amount at time of weighing.
1.3.2 Payment for Quantities
Quantities of ABC and GCA, determined as specified above, will be paid for at the respective contract unit prices, which shall constitute full compensation for the construction and completion of the ABC and GCA.
1.3.3 Payment for Stabilization of Underlying Course
Stabilization of cohesion-less sub-grade or sub-base courses, as specified in paragraph PREPARATION OF UNDERLYING COURSE, will be paid for as a special item on a tonnage basis. This tonnage price shall include the price of extra manipulation as required.
1.4 SUBMITTALS
Government approval is required for submittals with a "GA" designation; submittals having an "FIO" designation are for information only. The following shall be submitted in accordance with Section 01330 SUBMITTAL PROCEDURES:
SD-01 Data Plant, Equipment, and Tools; GA.
List of proposed equipment to be used in performance of construction work, including descriptive data.
SD-09 Reports Sampling and testing; GA. Field Density Tests; GA.
Calibration curves and related test results prior to using the device or equipment being calibrated. Copies of field test results within 24 hours after the tests are performed. Certified copies of test results for approval not less than 30 days before material is required for the work.
SD-18 Records Waybills and Delivery Tickets; GA.
Copies of waybills and delivery tickets during the progress of the work. Before the final statement is allowed, the Contractor shall file certified waybills and certified delivery tickets for all aggregates actually used.
1.5 SAMPLING AND TESTING
Sampling and testing shall be the responsibility of the Contractor. Sampling and testing shall be performed by a testing laboratory approved in accordance with Section 01451 CONTRACTOR QUALITY CONTROL. Work requiring testing will not be permitted until the testing laboratory has been inspected and approved. The materials shall be tested to establish compliance with the specified requirements; testing shall be performed at the specified frequency. The Contracting Officer may specify the time and location of the tests. Copies of test results shall be furnished to the Contracting Officer within 24 hours of completion of the tests.
1.5.1 Sampling
Samples for laboratory testing shall be taken in conformance with ASTM D 75. When deemed necessary, the sampling will be observed by the Contracting Officer.
1.5.2 Tests
The following tests shall be performed in conformance with the applicable standards listed.
1.5.2.1 Sieve Analysis
Sieve analysis shall be made in conformance with ASTM C 117 and ASTM C 136 or ASTM D 422. Sieves shall conform to ASTM E 11.
1.5.2.2 Liquid Limit and Plasticity Index
Liquid limit and plasticity index shall be determined in accordance with ASTM D 4318.
1.5.2.3 Moisture-Density Determinations
The maximum density and optimum moisture content shall be determined in accordance with ASTM D 1557 or AASHTO T 180, Method D.
1.5.2.4 Field Density Tests
Density shall be field measured in accordance with ASTM D 1556, ASTM D 2167 or ASTM D 2922. For the method presented in ASTM D 1556 the base plate as shown in the drawing shall be used. For the method presented in ASTM D 2922 the calibration curves shall be checked and adjusted if necessary using only the sand cone method as described in paragraph Calibration, of the ASTM publication. Tests performed in accordance with ASTM D 2922 result in a wet unit weight of soil and when using this method, ASTM D 3017 shall be used to determine the moisture content of the soil. The calibration curves furnished with the moisture gauges shall also be checked along with density calibration checks as described in ASTM D 3017. The calibration checks of both the density and moisture gauges shall be made by the prepared containers of material method, as described in paragraph Calibration of ASTM D 2922, on each different type of material being tested at the beginning of a job and at intervals as directed.
1.5.2.5 Wear Test
Wear tests shall be made on ABC and GCA course material in conformance with ASTM C 131.
1.5.2.6 Soundness
Soundness tests shall be made on GCA in accordance with ASTM C 88.
1.5.2.7 Weight of Slag
Weight per cubic foot of slag shall be determined in accordance with ASTM C 29/C 29M on the ABC and GCA course material.
1.5.3 Testing Frequency
1.5.3.1 Initial Tests
One of each of the following tests shall be performed on the proposed material prior to commencing construction to demonstrate that the proposed material meets all specified requirements when furnished. If materials from more than one source are going to be utilized, this testing shall be completed for each source.
a. Sieve Analysis including No. 635 size material.
b. Liquid limit and plasticity index moisture-density relationship.
c. Moisture-density relationship.
d. Wear.
e. Soundness.
f. Weight per cubic foot of Slag.
1.5.3.2 In Place Tests
One of each of the following tests shall be performed on samples taken from the placed and compacted ABC and GCA. Samples shall be taken and tested at the rates indicated.
a. Density tests shall be performed on every lift of material placed and at a frequency of one set of tests for every 250 square yards, or portion thereof, of completed area.
b. Sieve Analysis [including No. 635 size material] shall be performed for every 500 tons, or portion thereof, of material placed.
c. Liquid limit and plasticity index tests shall be performed at the same frequency as the sieve analysis.
1.5.4 Approval of Material
The source of the material shall be selected 30 days prior to the time the material will be required in the work. Tentative approval of material will be based on initial test results. Final approval of the materials will be based on sieve analysis, liquid limit, and plasticity index tests performed on samples taken from the completed and fully compacted ABC and GCA.
1.6 WEATHER LIMITATIONS
Construction shall be done when the atmospheric temperature is above 35 degrees F. When the temperature falls below 35 degrees F, the Contractor shall protect all completed areas by approved methods against detrimental effects of freezing. Completed areas damaged by freezing, rainfall, or other weather conditions shall be corrected to meet specified requirements.
1.7 PLANT, EQUIPMENT, AND TOOLS
All plant, equipment, and tools used in the performance of the work will be subject to approval before the work is started and shall be maintained in satisfactory working condition at all times. The equipment shall be adequate and shall have the capability of producing the required compaction, meeting grade controls, thickness control, and smoothness requirements as set forth herein.
2 PRODUCTS
2.1 AGGREGATES
The ABC and GCA shall consist of clean, sound, durable particles of crushed stone, crushed slag, crushed gravel, crushed recycled concrete, angular sand, or other approved material. ABC shall be free of lumps of clay, organic matter, and other objectionable materials or coatings. GCA shall be free of silt and clay as defined by ASTM D 2487, organic matter, and other objectionable materials or coatings. The portion retained on the No. 4 sieve shall be known as coarse aggregate; that portion passing the No. 4 sieve shall be known as fine aggregate.
2.1.1 Coarse Aggregate
Coarse aggregates shall be angular particles of uniform density. When the coarse aggregate is supplied from more than one source, aggregate from each source shall meet the specified requirements and shall be stockpiled separately.
a. Crushed Gravel: Crushed gravel shall be manufactured by crushing gravels, and shall meet all the requirements specified below.
b. Crushed Stone: Crushed stone shall consist of freshly mined quarry rock, and shall meet all the requirements specified below.
c. Crushed Recycled Concrete: Crushed recycled concrete shall consist of previously hardened portland cement concrete or other concrete containing pozzolanic binder material. The recycled material shall be free of all reinforcing steel, bituminous concrete surfacing, and any other foreign material and shall be crushed and processed to meet the required gradations for coarse aggregate. Crushed recycled concrete shall meet all other applicable requirements specified below.
d. Crushed Slag: Crushed slag shall be an air-cooled blast-furnace product having an air dry unit weight of not less than 65 pcf as determined by ASTM C 29/C 29M, and shall meet all the requirements specified below.
2.1.1.1 Aggregate Base Course
ABC coarse aggregate shall not show more than 50 percent loss when subjected to the Los Angeles abrasion test in accordance with ASTM C 131. The amount of flat and elongated particles shall not exceed 30 percent. A flat particle is one having a ratio of width to thickness greater than 3; an elongated particle is one having a ratio of length to width greater than 3. In the portion retained on each sieve specified, the crushed aggregates shall contain at least 50 percent by weight of crushed pieces having two or more freshly fractured faces with the area of each face being at least equal to 75 percent of the smallest mid-sectional area of the piece. When two fractures are contiguous, the angle between planes of the fractures must be at least 30 degrees in order to count as two fractured faces. Crushed gravel shall be manufactured from gravel particles 50 percent of which, by weight, are retained on the maximum size sieve listed in TABLE 1.
2.1.1.2 Graded-Crushed Aggregate Base Course
GCA coarse aggregate shall not show more than 40 percent loss when subjected to the Los Angeles abrasion test in accordance with ASTM C 131. GCA coarse aggregate shall not exhibit a loss greater than 40 percent weighted average, at five cycles, when tested for soundness in magnesium sulfate in accordance with ASTM C 88. The amount of flat and elongated particles shall not exceed 20 percent for the fraction retained on the 1/2 inch sieve nor 20 percent for the fraction passing the 1/2 inch sieve. A flat particle is one having a ratio of width to thickness greater than 3; an elongated particle is one having a ratio of length to width greater than 3. In the portion retained on each sieve specified, the crushed aggregate shall contain at least 90 percent by weight of crushed pieces having two or more freshly fractured faces with the area of each face being at least equal to 75 percent of the smallest mid-sectional area of the piece. When two fractures are contiguous, the angle between planes of the fractures must be at least 30 degrees in order to count as two fractured faces. Crushed gravel shall be manufactured from gravel particles 90 percent of which by weight are retained on the maximum size sieve listed in TABLE 1.
2.1.2 Fine Aggregate
Fine aggregates shall be angular particles of uniform density. When the fine aggregate is supplied from more than one source, aggregate from each source shall meet the specified requirements.
2.1.2.1 Aggregate Base Course
ABC fine aggregate shall consist of screenings, angular sand, crushed recycled concrete fines, or other finely divided mineral matter processed or naturally combined with the coarse aggregate.
2.1.2.2 Graded-Crushed Aggregate Base Course
GCA fine aggregate shall consist of angular particles produced by crushing stone, slag, recycled concrete, or gravel that meets the requirements for wear and soundness specified for GCA coarse aggregate. Fine aggregate shall be produced by crushing only particles larger than No. 4 sieve in size. The fine aggregate shall contain at least 90 percent by weight of particles having two or more freshly fractured faces in the portion passing the No. 4 sieve and retained on the No. 10 sieve, and in the portion passing the No. 10 sieve and retained on the No. 40 sieve.
2.1.3 Gradation Requirements
The specified gradation requirements shall apply to the completed base course. The aggregates shall have a maximum size of 1=1/2 inches and shall be continuously well graded within the limits specified in TABLE 1. Sieves shall conform to ASTM E 11.
TABLE I. GRADATION OF AGGREGATES
Percentage by Weight Passing Square-Mesh Sieve
Sieve
Designation No. 1 No. 2 No. 3
2 inch 100 ---- ----
1-1/2 inch 70-100 100 ----
1 inch 45-80 60-100 100
1/2 inch 30-60 30-65 40-70
No. 4 20-50 20-50 20-50
No. 10 15-40 15-40 15-40
No. 40 5-25 5-25 5-25
No. 200 0-10 0-10 0-10
NOTE 1: Particles having diameters less than 0.0008 inch shall not be in excess of 3 percent by weight of the total sample tested.
NOTE 2: The values are based on aggregates of uniform specific gravity. If materials from different sources are used for the coarse and fine aggregates, they shall be tested in accordance with ASTM C 127 and ASTM C 128 to determine their specific gravity. If the specific gravity varies by more than 10 percent, the percentages passing the various sieves shall be corrected as directed by the Contracting Officer.
NOTE 3: The contractor may submit, as an option, in lieu of the above gradation and here-in-before specified aggregates, the aggregate base course Type 2, Class A of Class B, as specified in Article 3.1.2 of the
NJSHD Standard Specifications for Road and Bridge Construction.
2.1.4 Liquid Limit and Plasticity Index
Liquid limit and plasticity index requirements shall apply to the completed course and shall also apply to any component that is blended to meet the required gradation. The portion of any component or of the completed course passing the No. 40 sieve shall be either nonplastic or have a liquid limit not greater than 25 and a plasticity index not greater than 5.
3 EXECUTION
3.1 GENERAL REQUIREMENTS
When the ABC or GCA is constructed in more than one layer, the previously constructed layer shall be cleaned of loose and foreign matter by sweeping with power sweepers or power brooms, except that hand brooms may be used in areas where power cleaning is not practicable. Adequate drainage shall be provided during the entire period of construction to prevent water from collecting or standing on the working area. Line and grade stakes shall be provided as necessary for control. Grade stakes shall be in lines parallel to the centerline of the area under construction and suitably spaced for string lining.
3.2 OPERATION OF AGGREGATE SOURCES
Aggregate sources shall be cleared, stripped and excavated to working depths producing excavation faces that are as nearly vertical as practicable for the materials being excavated. Strata of unsuitable materials overlying or occurring in the deposit shall be wasted. Methods of operating aggregate sources, and the processing and blending of the materials, shall be changed or modified if necessary to obtain material conforming to the specified requirements. Upon completion of the work, aggregate sources shall be conditioned to drain readily and be left in a satisfactory condition. Aggregates shall be obtained from offsite sources.
3.3 STOCKPILING MATERIAL
Prior to stockpiling of material, storage sites shall be cleared and leveled by the Contractor. All materials, including approved material available from excavation and grading, shall be stockpiled in the manner and at the locations designated. Aggregates shall be stockpiled on the cleared and leveled areas designated by the Contracting Officer to prevent segregation. Materials obtained from different sources shall be stockpiled separately.
3.4 PREPARATION OF UNDERLYING COURSE
Prior to constructing the ABC and GCA, the underlying course or sub-grade shall be cleaned of all foreign substances. At the time of construction of the ABC and GCA, the underlying course shall contain no frozen material. The surface of the underlying course or sub-grade shall meet specified compaction and surface tolerances. The underlying course shall conform to Section 02721 SUBBASE COURSES. Ruts or soft yielding spots in the underlying courses, areas having inadequate compaction, and deviations of the surface from the requirements set forth herein shall be corrected by loosening and removing soft or unsatisfactory material and by adding approved material, reshaping to line and grade, and re-compacting to specified density requirements. For cohesion-less underlying courses containing sands or gravel, as defined in ASTM D 2487, the surface shall be stabilized prior to placement of the [ABC] [and] [GCA]. Stabilization shall be accomplished by mixing ABC or GCA into the underlying course and compacting by approved methods. The stabilized material shall be considered as part of the underlying course and shall meet all requirements of the underlying course. The finished underlying course shall not be disturbed by traffic or other operations and shall be maintained by the Contractor in a satisfactory condition until the ABC and GCA is placed.
3.5 INSTALLATION
3.5.1 Mixing the Materials
The coarse and fine aggregates shall be mixed in a stationary plant, or in a traveling plant or bucket loader on an approved paved working area. The Contractor shall make adjustments in mixing procedures or in equipment as directed to obtain true grades, to minimize segregation or degradation, to obtain the required water content, and to insure a satisfactory ABC and GCA meeting all requirements of this specification.
3.5.2 Placing
The mixed material shall be placed on the prepared sub-grade or sub-base in layers of uniform thickness with an approved spreader. When a compacted layer 6 inches or less in thickness is required, the material shall be placed in a single layer. When a compacted layer in excess of 6 inches is required, the material shall be placed in layers of equal thickness. No layer shall exceed 6 inches or less than 3 inches when compacted. The layers shall be so placed that when compacted they will be true to the grades or levels required with the least possible surface disturbance. Where the ABC and GCA is placed in more than one layer, the previously constructed layers shall be cleaned of loose and foreign matter by sweeping with power sweepers, power brooms, or hand brooms, as directed. Such adjustments in placing procedures or equipment shall be made as may be directed to obtain true grades, to minimize segregation and degradation, to adjust the water content, and to insure an acceptable ABC and GCA.
3.5.3 Grade Control
The finished and completed ABC and GCA shall conform to the lines, grades, and cross sections shown. Underlying material(s) shall be excavated and prepared at sufficient depth for the required ABC and GCA thickness so that the finished ABC and GCA with the subsequent surface course will meet the designated grades.
3.5.4 Edges of Base Course
The ABC and GCA shall be placed so that the completed section will be a minimum of 5 feet wider, on all sides, than the next layer that will be placed above it. Additionally, approved fill material shall be placed along the outer edges of ABC and GCA in sufficient quantities to compact to the thickness of the course being constructed, or to the thickness of each layer in a multiple layer course, allowing in each operation at least a 2 foot width of this material to be rolled and compacted simultaneously with rolling and compacting of each layer of ABC and GCA. If this base course material is to be placed adjacent to another pavement section, then the layers for both of these sections shall be placed and compacted along this edge at the same time.
3.5.5 Compaction
Each layer of the [ABC] [and] [GCA] shall be compacted as specified with approved compaction equipment. Water content shall be maintained during the compaction procedure to within plus or minus one (1) percent of the optimum water content determined from laboratory tests as specified in paragraph SAMPLING AND TESTING. Rolling shall begin at the outside edge of the surface and proceed to the center, overlapping on successive trips at least one-half the width of the roller. Alternate trips of the roller shall be slightly different lengths. Speed of the roller shall be such that displacement of the aggregate does not occur. In all places not accessible to the rollers, the mixture shall be compacted with hand-operated power tampers. Compaction shall continue until each layer has a degree of compaction that is at least 98 percent of laboratory maximum density through the full depth of the layer. The Contractor shall make such adjustments in compacting or finishing procedures as may be directed to obtain true grades, to minimize segregation and degradation, to reduce or increase water content, and to ensure a satisfactory [ABC] [and] [GCA]. Any materials that are found to be unsatisfactory shall be removed and replaced with satisfactory material or reworked, as directed, to meet the requirements of this specification.
3.5.6 Thickness
Compacted thickness of the aggregate course shall be as indicated. No individual layer shall exceed 8 inches nor be less than 3 inches in compacted thickness. The total compacted thickness of the ABC and GCA course shall be within 1/2 inch of the thickness indicated. Where the measured thickness is more than 1/2 inch deficient, such areas shall be corrected by scarifying, adding new material of proper gradation, Re-blading, and re-compacting as directed. Where the measured thickness is more than 1/2 inch thicker than indicated, the course shall be considered as conforming to the specified thickness requirements. Average job thickness shall be the average of all thickness measurements taken for the job, but shall be within 1/4 inch of the thickness indicated. The total thickness of the ABC and GCA course shall be measured at intervals in such a manner as to ensure one measurement for each 500 square yards of base course. Measurements shall be made in 3 inch diameter test holes penetrating the base course.
3.5.7 Proof Rolling
Proof rolling of the areas indicated shall be in addition to the compaction specified and shall consist of the application of 30 coverages with a heavy pneumatic-tired roller having four or more tires, each loaded to a minimum of 30,000 pounds and inflated to a minimum of 150 psi. In areas designated, proof rolling shall be applied to the top of the underlying material on which ABC and GCA is laid and to each layer of ABC and GCA. Water content of the underlying material shall be maintained at optimum or at the percentage directed from start of compaction to completion of proof rolling of that layer. Water content of each layer of the ABC and GCA shall be maintained at the optimum percentage directed from start of compaction to completion of proof rolling. Any ABC and GCA materials or any underlying materials that produce unsatisfactory results by proof rolling shall be removed and replaced with satisfactory materials, re-compacted and proof rolled to meet these specifications.
3.5.8 Finishing
The surface of the top layer of ABC and GCA shall be finished after final compaction and proof rolling by cutting any overbuild to grade and rolling with a steel-wheeled roller. Thin layers of material shall not be added to the top layer of base course to meet grade. If the elevation of the top layer of ABC and GCA is 1/2 inch or more below grade, then the top layer should be scarified to a depth of at least 3 inches and new material shall be blended in, compacted and proof rolled to bring to grade. Adjustments to rolling and finishing procedures shall be made as directed to minimize segregation and degradation, obtain grades, maintain moisture content, and insure an acceptable base course. Should the surface become rough, corrugated, uneven in texture, or traffic marked prior to completion, the unsatisfactory portion shall be scarified, reworked and re-compacted or it shall be replaced as directed.
3.5.9 Smoothness
The surface of the top layer shall show no deviations in excess of 3/8 inch when tested with a 12 foot straightedge. Measurements shall be taken in successive positions parallel to the centerline of the area to be paved. Measurements shall also be taken perpendicular to the centerline at 50 foot intervals. Deviations exceeding this amount shall be corrected by removing material and replacing with new material, or by reworking existing material and compacting it to meet these specifications.
3.6 TRAFFIC
Completed portions of the ABC and GCA course may be opened to limited traffic, provided there is no marring or distorting of the surface by the traffic. Heavy equipment shall not be permitted except when necessary to construction, and then the area shall be protected against marring or damage to the completed work.
3.7 MAINTENANCE
The ABC and GCA shall be maintained in a satisfactory condition until the full pavement section is completed and accepted. Maintenance shall include immediate repairs to any defects and shall be repeated as often as necessary to keep the area intact. Any ABC and GCA that is not paved over prior to the onset of winter, shall be re-tested to verify that it still complies with the requirements of this specification. Any area of ABC and GCA that is damaged shall be reworked or replaced as necessary to comply with this specification.
3.8 DISPOSAL OF UNSATISFACTORY MATERIALS
Any unsuitable materials that must be removed shall be disposed of as directed in waste disposal areas indicated. No additional payments will be made for materials that must be replaced.
3.9 METHOD OF MEASUREMENT AND PAYMENT: All measurements shall be units as identified in the appropriate SLINS in the Unit Price Schedule. Measurements for preparing payments shall be taken jointly with the Government Representative.
Payment for these items shall constitute full compensation for completed work including all labor and incidentals necessary to accomplish the work required by this section of the specifications.
END OF SECTION