SECTION 01330 PAV 2008.doc

DOC document 38 KB Posted

Attached to
Post Wide Paving And Repair Effort
Solicitation number
W912CF-09-B-0001
Issued by

About this file

SECTION 01330 PAV 2008.doc

View the file

Other files

File Type Posted
BidAbstract-W912CF09B0001Paving.pdf PDF
W912CF09B0001-0005 Paving FtMonmouth.doc DOC document
W912CF09B0001-0004 Paving FtMonmouth.doc DOC document
W912CF09B0001-0003 Paving FtMonmouth.doc DOC document
BondBid-sf24_f.pdf PDF
Map-Bid Opening-Eatontown Library.doc DOC document
C_PAV_2008_CONTRACT_WITH_TWO_OPTION_YEAR.xls XLS spreadsheet
W912CF09B0001-0002_Paving_FtMonmouth.doc DOC document
W912CF09B0001-0001 Paving FtMonmouth.doc DOC document
Visitor Center-Ft Monmouth-Oceanport Ave.doc DOC document
SECTION 02975 PAV 2008.doc DOC document
SECTION 02232 PAV 2008.doc DOC document
SECTION 02225 PAV 2008.doc DOC document
SEC-02511 PAV 2008.doc DOC document
SECTION 01100 PAV 2008.doc DOC document
DPW Paving Spec. local section.doc DOC document
SECTION 02721 PAV 2008.doc DOC document
SECTION 02745 PAV 2008.doc DOC document
C PAV 2008 CONTRACT WITH THREE OPTION YEAR.xls XLS spreadsheet
SECTION 02713 PAV 2008.doc DOC document
SECTION 02581 PAV 2008.doc DOC document
SECTION 02763 PAV 2008.doc DOC document
SECTION 02722 PAV 2008.doc DOC document
TABLE OF CONTENTS PAV2008.doc DOC document
SECTION 02935 PAV 2008.doc DOC document
SECTION 02210 PAV 2008.doc DOC document
SPECIAL STANDARDS AND REQUIREMENTS.doc DOC document
SECTION 01560 PAV 2008.doc DOC document
SECTION 02720 PAV 2008.doc DOC document
SOW PAV 2008.rtf RTF text file
SECTION 02964 PAV 2008.doc DOC document
SECTION 02050 PAV 2008.doc DOC document
SECTION 02730 PAV 2008.doc DOC document
SECTION 02786 PAV 2008.doc DOC document
SECTION 02770 PAV 2008.doc DOC document
SECTION 02748 PAV 2008.doc DOC document
W912CF09B0001Paving FtMonmouth.doc DOC document
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01330

SUBMITTAL PROCEDURES

1. GENERAL

1.1 SUBMITTAL IDENTIFICATION

Submittals required are identified by SD numbers as follows:

SD-01 Data SD-04 Drawings SD-06 Instructions SD-07 Schedules SD-08 Statements SD-09 Reports SD-13 Certificates SD-14 Samples SD-18 Records SD-19 Operation and Maintenance Manuals

1.2 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.2.1 Government Approved

Governmental approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."

1.2.2 Information Only

All submittals not requiring Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.3 APPROVED SUBMITTALS

The Contracting Officer's approval of submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error, which may exist, as the Contractor under the CQC requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work. After the Contracting Officer has approved submittals, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.4 DISAPPROVED SUBMITTALS

The Contractor shall make all corrections required by the Contracting Officer and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause "Changes" shall be given promptly to the Contracting Officer.

1.5 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

2 PRODUCTS (Not Applicable)

3 EXECUTION

3.1 GENERAL

The Contractor shall make submittals as required by the specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the Contractor's Quality Control (CQC) representative and each item shall be stamped, signed, and dated by the CQC representative indicating action taken. Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as: Contractor’s, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals. Submittals requiring Government approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

3.2 SUBMITTAL REGISTER (ENG FORM 4288)

At the end of this section is one set of ENG Form 4288 listing items of equipment and materials for which submittals are required by the specifications; this list may not be all inclusive and additional submittals may be required. The Contractor will also be given the submittal register as a diskette containing the computerized ENG Form 4288 and instructions on the use of the diskette. Columns "d" through "r" have been completed by the Government; the Contractor shall complete columns "a" and "s" through "u" and submit the forms (hard copy plus associated electronic file) to the Contracting Officer for approval within 15 calendar days after Notice to Proceed. The Contractor shall keep this diskette up-to-date and shall submit it to the Government together with the monthly payment request. The approved submittal register will become the scheduling document and will be used to control submittals throughout the life of the contract. The submittal register and the progress schedules shall be coordinated.

3.3 SCHEDULING

Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 30 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals. Additional 15 calendar days shall be allowed and shown on the register for review and approval of submittals for [food service equipment] [and] [refrigeration and HVAC control systems].

3.4 TRANSMITTAL FORM (ENG FORM 4025)

The sample transmittal form (ENG Form 4025) attached to this section shall be used for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. This form shall be properly completed by filling out all the heading blank spaces and identifying each item submitted. Special care shall be exercised to ensure proper listing of the specification paragraph and/or sheet number of the contract drawings pertinent to the data submitted for each item.

3.5 SUBMITTAL PROCEDURE

Submittals shall be made as follows:

3.5.1 Procedures

3.5.1.1 All submissions shall be delivered to the Contracting Officer or his authorized representative.

3.5.2 Deviations

For submittals which include proposed deviations requested by the Contractor, the column "variation" of ENG Form 4025 shall be checked. The Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

3.6 CONTROL OF SUBMITTALS

The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

3.7 GOVERNMENT APPROVED SUBMITTALS

Upon completion of review of submittals requiring Government approval, the submittals will be identified as having received approval by being so stamped and dated. The Contracting Officer will retain three copies of the submittal and one copies of the submittal will be returned to the Contractor.

3.8 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

3.9 STAMPS

Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements shall be similar to the following:

| CONTRACTOR |

| (Firm Name) |

| _____ Approved |

| _____ Approved with corrections as noted on submittal data and/or |

| attached sheets(s). |

| SIGNATURE: __________________________________________________________ |

| TITLE: ______________________________________________________________ |

| DATE: _______________________________________________________________ |

END OF SECTION

01330-2

File details come from the government source that posted it. Updated .