W912BV21R0003-0002.pdf

PDF 9 MB Posted

Attached to
Advanced Individual Training Barracks, Fort Sill Oklahoma Amendment 0004 Federal contract opportunity
Solicitation number
W912BV21R0003
Issued by
Department of the Army Corps of Engineers Engineering District Tulsa

About this file

This is a solicitation amendment for the construction of advanced individual training barracks at Fort Sill, Oklahoma. The U.S. Army Corps of Engineers Tulsa District seeks to award a firm-fixed price design-bid-build contract to construct 180,000 square feet of barracks housing 600 soldiers. The project includes building information systems, fire protection and alarm systems, an ARMS vault, a FEMA storm shelter, extensive fire separation, video surveillance and intrusion detection system installation, and connection to an energy monitoring and control system. Special foundations are required. Supporting facilities incorporate a canopy, utilities, lighting, paving, parking, walks, drainage, landscaping and signage. Heating and air conditioning will use self-contained systems and a geothermal hybrid system. Access for individuals with disabilities will be provided. The solicitation incorporates cyber security and sustainability measures.

View the file

Other files for this federal contract opportunity

Other files attached to Advanced Individual Training Barracks, Fort Sill Oklahoma Amendment 0004, newest first.
File Type Posted
W912BV21R0003-00004.pdf PDF
W912BV21R0003-0003.pdf PDF
Site Visit Sign-In Sheet 29 JUL 2021.pdf PDF
AIT Barracks Pre-Bid Site Visit.pdf PDF
W912BV21R0003-0001.pdf PDF
AIT BARRACKS BRAND NAME OR EQUAL NOI.xlsx XLSX spreadsheet
JA Brand Name or Equal AIT Barracks.pdf PDF
FtSill_AIT_RTA - COMPILED_VOLUME 2 OF 4.pdf PDF
FtSill_AIT_RTA - COMPILED_VOLUME 4 OF 4.pdf PDF
FtSill_AIT_RTA - COMPILED_VOLUME 1 OF 4.pdf PDF
AIT_Barracks Solicitation RFP_20210719.pdf PDF
FtSill_AIT_RTA - COMPILED_VOLUME 3 OF 4.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

AIT BARRACKS COMPLEX, FORT SILL, OKLAHOMA

(1) Amendment 0002 updates/replaces sections as listed below .

(2) All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 66

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Aug-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BV21R0003

X 9B. DATED (SEE ITEM 11)

19-Jul-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Aug-2021

CODE

CONTRACTING DIV

US ARMY CORPS OF ENGINEERS, TULSA DISTRICT

2488 E. 81ST STREET

TULSA OK 74137-4290

W912BV 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912BV21R0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

AMENDMENT 0002

W912BV-21-R-0003

Advanced Individual Training Barracks (AIT) Complex, Phase 2 Fort Sill, Oklahoma

1. The revised/new sections/appendices/pages listed below are hereby added to or revised and made a part of the solicitation. Revised or added/deleted information can be located in the specifications by searching for an asterisk and amendment number (i.e., *AM and *). The beginning of the amendment will begin with *AM and end with an * for each amended section.

The following have been revisedmodified:

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 240 days after notice to proceed. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of clause) i

REVISED SECTIONS

Remove previously issued specifications sections 00 11 00, 01 04 00, and 31 00 00 in their entirety and replace with new specification sections 00 11 00, 01 04 00, and 31 00 00 hereto.

ADDED NEW SPECIFICATION SECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS (FORT SILL)

09 66 16 TERAZZO FLOOR TILE

REVISED DRAWINGS

Remove previously issued drawing A-201, A-202, IN114, IN712, IN713, IN721, IN722, IN723, IN731, IN732, IN733, IN600, IN616, IN711, S-302, S-304, S-510, S517, S-551, S-600, M-104, M-114, M-403, M-603, M- 605, M-904 in their entirety and replace with A-201, A-202, IN114, IN712, IN713, IN721, IN722, IN723, IN731, IN732, IN733, IN600, IN616, IN711, S-302, S-304, S-510, S517, S-551, S-600, M-104, M-114, M-403, M-603, M-605, M-904 hereto.

A summary of the changes made to these drawings includes, but is not limited to:

• A-201: ELEVATION C1 – Added mechanical louvers to elevation.

• A-202: ELEVATION A1 – Added mechanical louvers and annotation to elevation.

• IN114: Revise general notes to include solid surface wall cap in scrub room.

• IN600: Revise Terrazzo tile and Terrazzo Base to reference correct specification section

• IN616: Ceiling type for multipurpose area D changed from GYP to ACT.

• IN711: Revise Terrazzo Tile item code to “TZ-1”. Revise room numbers to represent true second and third floor

• IN712: Revise Terrazzo Tile item code to “TZ-1”. Revise room numbers to represent true second and third floor

• IN713: Revise Terrazzo Tile item code to “TZ-1”. Revise room numbers to represent true second and third floor

• IN721: Revise Terrazzo Tile item code to “TZ-1”. Revise room numbers to represent true second and third floor

• IN722: Revise Terrazzo Tile item code to “TZ-1”. Revise room numbers to represent true second and third floor

• IN723: Revise Terrazzo Tile item code to “TZ-1”. Revise room numbers to represent true second and third floor

• IN731: Revise Terrazzo Tile item code to “TZ-1”. Revise room numbers to represent true second and third floor ii

• IN732: Revise Terrazzo Tile item code to “TZ-1”. Revise room numbers to represent true second and third floor

• IN733: Revise Terrazzo Tile item code to “TZ-1”. Revise room numbers to represent true second and third floor

• S-302: Detail 4, Revised detail of stirrup in grade beam.

• S-304: Detail 9, Corrected dimension for rebar embedment.

• S-510: Detail 3, Roof ridge bent plate and note added

• S-517: Corrected grout pocket hatching on detail 2. Reduced joint filler thickness and revised deformed bar anchor on details 4, 5, and 6.

• S-551: Weld length shown as continuous, edited to match other roof plate details of weld length.

• S-600: Baseplate 3 field weld revised to shop weld on detail 1.

• M-104: Plan B3 revised to add annotation for hurricane louvers and intake louvers as well as outside air ductwork.

• M-114: Plan B3 revised to add annotation for hurricane louvers.

• M-403: Plan A4 revised to add intake louvers, outside air duct work, rescale and renumbering of plan view and title, added annotation for hurricane louvers, extended blower coil ducting to electrical room, and added diffusers and callouts.

• M-603: Blower Coil Schedule revised to include Mechanical Room Units.

• M-605: Revised Shelter Hurricane Louver Schedule and Wall OA Intake Louver Schedule

• M-904: Isometric A1 revised to add intake louvers and outside air duct work.

End of Continuation Sheet

AIT Barracks Construction

Fort Sill, OK

00 11 00 - Page 1

SECTION 00 11 00

PRICING (CLIN) SCHEDULE

CLIN Description of Item Quantity Unit Unit

Price

Amount

BASE BID ITEMS

0001 General Conditions 1 JOB - $

0002 Demolition 1 JOB - $

0003 AIT B/COF Building C 1 JOB - $ 0004 AIT B/COF Building D 1 JOB - $

0005 Supporting Facilities 1 JOB - $

0006 Building Commissioning - Building C 1 JOB - $

0008 As-Built Drawings 1 JOB - $ 300,000 0009 O&M Manuals 1 JOB - $ 200,000 0010 Mechanical Integrator 1 JOB - $

TOTAL AMOUNT BASE BID (CLINS 0001 – 0010, inclusive) $

OPTION BID ITEMS

0011 OPTION 1 - Geothermal System 1 JOB - $

0012 OPTION 2 - Troop Canopies and Training 1 JOB - $

0013 OPTION 3 - Landscaping 1 JOB - $

TOTAL AMOUNT OPTION BID (CLINS 0011 – 0013, inclusive) $

TOTAL BID (BASE + OPTIONS) (CLINS 0001 – 0013, inclusive) $

Contract Duration (See Note 6):

Notes:

1. The offeror agrees to perform the work required at the prices specified above in strict accordance with the terms of this scope of work, if this offer is accepted by the Government in writing within 60 calendar days after the date offers are due.

2. The Offeror shall submit pricing data on the latest Pricing Schedule as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.

3. Offerors must insert a price on all numbered items of the Pricing Schedule. Failure to do so will disqualify the Offer.

0007 Building Commissioning - Building D 1 JOB - $

M5ECFADB

Typewritten Text *AM: Replace Specification Section 00 11 00 in its entirety.

00 11 00 - Page 2

4. All quantities are estimated except where the unit is given as JOB. If a modification to a proposal is submitted and provides for a lump-sum adjustment to the total estimated cost, the application of the lump-sum adjustment to each unit price and/or lump-sum price, in the Pricing Schedule must be stated or, if it is not stated, the Offeror agrees that the lump-sum adjustment shall be applied on the prorated basis to every litem in the Bidding Schedule.

5. All the extensions of the unit prices shown (if applicable) will be subject to verification by the Government.

In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

6. The Offeror shall propose total contract duration in number of calendar days after the notice to Proceed (NTP) is issued by the Government, whether via electronic means or hard copy, whichever is the earliest method of delivery. The total number of proposed calendar days for construction through completion, ready for turnover shall not exceed the days shown at, SCR: 5.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK. The proposed duration shall become the required contract duration. The Government may issue the NTP via e-mail or by other means. Day number 1 is the day after the date of issuance of the NTP.

7. CLIN DESCRIPTION AND INCLUSIONS

CLIN 0001 – General Conditions: includes, Prime contractor’s field management labor (project manager, superintendent, QC and safety personnel), materials testing, field office, telephone services, copying services, photograph development and binding, vehicles and travel, per diem and allowable expenses for field personnel.

CLIN 0002 – Demolition: including all excavation, earthwork and manhole demolition.

CLIN 0003 – AIT Building C: includes all construction for architecture, structural, fire protection, roofing, communication, electrical, mechanical and plumbing, cooling tower *AM , cooling tower foundation and screen walls *.

CLIN 0004 – AIT Building D: includes all construction for architecture, structural, fire protection, roofing, communication, electrical, mechanical and plumbing, cooling tower *AM , and cooling tower foundation and screens *.

CLIN 0005 – Supporting Facilities: includes cooling tower foundation and screen walls, walkways, ramps, curbs, stripping, bollards and gutters. All site improvements, storm drainage, electrical site work, communications site work, water, sewer, gas and sodding will be priced under this CLIN.

CLIN 0006 & CLIN 0007– Building Commissioning: price building C and D separately.

CLIN 0008 – As-built Drawings: includes maintaining redlines for each building and preparing a separate set of as-builts for each building. The Government will provide Microstation files to contractor for as-built preparation.

CLIN 0009 – O&M Manuals: includes data and instructions for major systems installed. A separate manual is required for each building.

CLIN 0010 – Mechanical Integrator: includes performing building systems integration for each building.

http://www.sam.gov/SAM/

M5ECFADB

Cross-Out

M5ECFADB

Cross-Out

00 11 00 - Page 3

OPTION CLINS:

CLIN 0011 - OPTION 1 Geothermal System: Provide new ground-loop heat pump systems complete and ready for operation. Systems include heat pumps, system equipment, piping, pumps, electrical equipment, controls, wells, and condenser. Includes demolition, removal, and proper capping of existing electrical utilities found to be in conflict with the geothermal system construction, to the minimal extent possible.

CLIN 0012 - OPTION 2, Troop Canopies and Training: Provide canopies for troop assembly as shown on drawings and specifications.

CLIN 0013 - OPTION 3, Landscaping: Planting and establishment of plantings as presented in drawings and specifications.

8. OPTIONS: The Government reserves the right to exercise any or all options at any time from contract award and up to 240 days after Notice to Proceed.

9. AWARD

Only one contract will be awarded under this solicitation.

--END SECTION 00 11 00--

M5ECFADB

Typewritten Text End of Amendment

AIT Barracks Complex

SECTION 01 04 00

COORDINATION, FIELD ENGINEERING, AND MEETINGS (FSAO)

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00.15 DIGITAL SUBMITTAL

PROCEDURES AND CORRESPONDENCE:

SD-09 Manufacturer's Field Reports

Survey Field Notes ; G, .

1.2 WORK SCHEDULE

Contractor shall work between 7 a.m. and 5 p.m. Monday through Friday unless otherwise directed by the Contracting Officer. Deviation from these hours or work on weekends and holidays will require written authorization from the Contractig Officer.

1.3 FEDERAL HOLIDAYS

The following Federal holidays are excluded from standard work days:

HOLIDAY DATE OBSERVED

New Year's Day 1 January

Martin Luther King's Birthday 3rd Monday in January

President's Day 3rd Monday in February

Memorial Day Last Monday in May

Juneteenth Day 19 June

Independence Day 4 July

Labor Day 1st Monday in September

Columbus Day 2nd Monday in October

Veteran's Day 11 November

Thanksgiving 4th Thursday in November

SECTION 01 04 00 Page 1

*AM *

HOLIDAY DATE OBSERVED

Christmas Day 25 December

1.4 UTILITY OUTAGE COORDINATION

1.4.1 Approval

The Contractor shall obtain written permission/approval from the Contracting Officer 60 days prior to:

(1) Performing any work which will close any runway or street or interrupt any utility service.

(2) Making any excavation: Any damage to underground utilities, communication lines, etc., will be the responsibility of the Contractor if the approval is not obtained.

(3) Contractors shall use extreme care in all excavations on Fort Sill. Subsurface utilities are congested in nature. Damaging these systems in some areas could result in thousands of man-hours of lost production time, which could result in claims against the Contractor to the extent of the actual supportable damage.

1.4.2 Government Right to Delay

The Government reserves the right to postpone for 7 days, any scheduled outages. There shall be no outages when the outside temperature is expected to be below 35 degrees F .

1.4.3 Government Performance

Government personnel shall perform all shutting off and turning on of valves and switches necessary to accomplish scheduled outage.

1.5 QUANTITY SURVEYS (APR 1984) (FAR 52.236-16)

1.5.1 General

Quantity surveys shall be conducted, and the data derived from these surveys shall be used in computing the quantities of work performed and the actual construction completed and in place.

1.5.2 Conducting Surveys and Computations

The Contractor shall conduct the original and final surveys and surveys for any periods for which progress payments are requested. All these surveys shall be conducted under the direction of a representative of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance. The Contractor shall make the computations based on the surveys for any periods for which progress payments are requested. The Government shall make such computations as are necessary to confirm the quantities of work performed or finally in place.

1.5.3 Survey Procedure

Appropriate instrumentation and procedures shall be selected to obtain the

SECTION 01 04 00 Page 2 precision requirements necessary to meet or exceed Third Order Accuracy standards. Total Station or GPS shall be considered appropriate for performing the survey. The Contractor shall use a field crew experienced in performing the surveys as outlined in the scope of work and capable of responding to and completing work assignments within the critical time schedules allotted for this project. The standard 4 3/4-inch by 7 1/2-inch hardback field book shall be used. The party setup, weather conditions, and date shall be entered at the top of the page for each workday. The original notebook shall be turned in at the completion of the work and shall become the property of the Government. If electronic distance measuring devices and data collectors are used, the hard copy notes shall be provided with X, Y, Z coordinates of the survey data recorded at right angles to established base lines. It is also required that in addition to cross section lines that all breaklines are located and provided as X, Y, Z values and appropriately identified. A digital files in X, Y, Z format shall be provided for all data collected. All natural ground elevations shall be located to the nearest 0.1 foot and hard surfaces to the nearest 0.01 foot.

1.6 LAYOUT OF WORK (APR 1984) (FAR 52.236-17)

The Contractor shall lay out his work from Government-established base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at his own expense, all stakes, templates, platforms, equipment, tools, and materials and labor required to lay out any part of the work.

The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through his negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

1.7 MONUMENT REPLACEMENT

1.7.1 General

Government-established horizontal and vertical control monuments that are shown on the drawings, if destroyed shall be reestablished by the Contractor in locations as directed by the Contracting Officer. Control points set by the Contractor for the purpose of reestablishing the monuments and to properly control the work, if destroyed and not reset by the Contractor, shall be reestablished by the Government at the Contractor's expense. Survey shall be performed by a Registered Land Surveyor.

1.7.2 Horizontal Control

Horizontal control shall be based on the State Plane Coordinate System as developed by the National Geodetic Survey. Horizontal control shall originate and close on control points established by the Government.

1.7.3 Vertical Control

Elevations shall originate and close on vertical controls established by the Government. Third Order Accuracy or better shall be maintained for

SECTION 01 04 00 Page 3 all vertical survey control. Vertical error shall be adjusted for all control markers established throughout each level loop. A transcript of all adjusted vertical marks set and adjusted horizontal marks set, shall be furnished on forms furnished by the Government. (SWD Form 598)

1.7.4 Monuments

Concrete monuments shall be set as control monuments, where required.

Horizontal data for monuments is based on NAD 27, and vertical data is based on NGVD 29 in US feet. The monuments shall consist of 6-inch -diameter concrete posts of standard mix and a Government-furnished bronze disk flush with top, set at least 2.6 feet into solid ground and 0.4 foot above the ground surface. A No. 4 18-inch reinforcing bar shall be cast in the top portion of the monument. Each monument shall be identified by stamping the bronze disk with steel dies, indicating thereon the name of the site and number of the monument. A Government-furnished galvanized U-channel rail steel delineator post, 6.5 feet in length with a USCE sign attached shall be set in concrete within 1 foot of each control monument.

Markers which fall in roads or improved areas shall be either buried or a disk set flush in pavement, whichever may be appropriate to the situation. Control monuments shall be referenced by chain distance and angle to at least three objects, such as blazed trees, crosses in solid rock, or other physical features in the immediate vicinity.

1.8 OTHER CONTRACTORS

(Reference CONTRACT CLAUSE entitled "Other Contracts.") Other Contractors may be working in the project area during construction under this contract. The Contractor shall arrange and perform his work and store his materials in cooperation with other Contractors and as directed by the Contracting Officer.

1.9 ELECTRONIC PAYROLL REQUIREMENT

Refer to Section 01 30 01 ADDITIONAL ADMINISTRATIVE REQUIREMENTS SCR entitled "(S-102) Contractor Supply and Use of Electronic software for Processing David-Bacon Act Certified Labor Payrolls (April 2011)".

a. Replace the first sentence with the following: "The Contractor shall use a commercially-available electronic system to process and submit certified payrolls electronically to the Government."

b. Replace the 2nd paragraph with the following: "The Contractor shall be responsible for obtaining and providing all access, license, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the Contractor to comply with David-Bacon and related Act regulations. The electronic payroll service shall be used by the Contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract, and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. The Contractor shall obtain and provide electronic system access to the Government as required to comply with the Davis-Bacon and related Act regulations over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used

SECTION 01 04 00 Page 4

*AM

by the Contractor.

The remainder of the SCR is unchanged.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 04 00 Page 5

SECTION 01 50 00

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS (FORT SILL)

08/21

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Energy Conservation Plan ; G

Memorandum of Understanding For Sale of Utility Services (Da2100-R) ;

G

1.2 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1994 (FAR 52.236-14)

1.2.1 Availability

The Government will make available to the Contractor, from existing outlets and supplies, all reasonably required amounts of utilities as specified in the Contract. The Contractor shall carefully conserve any utilities furnished without charge.

1.2.2 Use

The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.

1.3 TEMPORARY UTILITY CONNECTION PROCEDURES FOR FORT SILL

Efficient use of resources is a Command priority at Fort Sill. Contractors shall be responsible for the following to help maintain energy and water consumption and intensity goals and aid in tracking energy consumption.

Any request for an exemption from this policy shall be submitted through the Contracting Officer to Fort Sill's DPW for review and approval.

a. The Contractor shall submit and Energy Conservation Plan through the Contractign Officer to DPW showing compliance with this policy prior to construction activities.

(1) Plan shall outline all expected activities that will consume water, electricity, and natural gas along with estimates of consumption.

SECTION 01 50 00 Page 1

*AM2 - Added this section in it's entirety*

(2) Plan shall outline an action to install any and all meters necessary pursuant to this policy (i.e. job trailers, and/or buildings unoccupied with the exception of the Contractor), including a detailed map with the location of the meters.

(3) Plan shall describe efforts to comply with reporting standards as described below and the DPW energy website located at http://sill-www.army.mil/USAG/dpw/bmb.html#tab-3.

(4) Plan shall demonstrate efforts to conserve electricity, natural gas, and water and compliance with any installation policies and best management proctices on conservation of electricity, natural gas and water.

(5) The Contractor shall be responsible for installing their own meters for temporary utility hookups in accordance with pragraph entititled AVAILABILITY AND USE OF UTILITY SERVICES. All meters shall comply with all local codes and regulations and shall include any additional equipment necessary (e.g. backflow preventers).

(6) The Contractor shall submit through the Contracting Officer to DPW a signed Memorandum of Understanding for Sale of Utility Services (DA2100-R) to utilities being turned on.

(7) If there is a change during design or construction that will or may change utility connections requirements, a revised compliance plan must be submitted through the Contracting Officer to DPW for review and approval.

b. The Contractor shall report meter readings to DPW on the 15th of each month and immediately upon disconnection of utilities.

Provide a copy of the report to the Contracting Officer. Meter readings shall be reported from the beginning of construction to the completion of construction. If, during that time, there is a period of inactivity, readings shall still be reported. Reporting procedures shall be included in the Contractor's Energy Consumption Plan.

c. Abuse of this policy may result in disconnection from utilities.

1.4 UTILITY SERVICES

To obtain current information, contact the following:

a. Water and Sanitary Sewer: American Water Services, Ronnie Graves, 580-248-3046.

b. Gas: Oklahoma Natural Gas, 580-353-1985.

c. Electricity and Landfill: Fort Sill DPW, Andrew Bennett, 580-581-5230.

d. Covernment Communication Lines: Kathy Banks, NEC, Fort Sill, 580-442-3617.

e. Telephone: Southwestern Bell, 58/0-581-5230.

SECTION 01 50 00 Page 2

1.5 SECURITY REQUIREMENTS FOR CORPS OF ENGINEERS' UNCLASSIFIED CONTRACTS

The Contractor shall be required to comply with requirements of Clause

52.0000-4515, SECURITY CONTRACT LANGUAGE FOR ALL CORPS' OF ENGINEERS'

UNCLASSIFIED CONTRACTS (APR 2004), paragraphs A. AUTOMATED INFORMATION SYSTEM (AIS) EFFORT and C. FOREIGN NATIONALS. rEFER TO sECTION 00 21 00 for clause. Refer to the basic contract documents for additional information regarding foreign nationals.

1.6 IDENTIFICATION OF EMPLOYEES (APR 1985)

The Contractor shall furnish identification to each employee as directed by the Contracting Officer. Upon the release of any employee, the identification shall be delivered to the Contracting Officer for cancellation.

1.7 HAUL ROADS (CESWT-CT)

1.7.1 Maintenance

It shall be the Contractor's responsibility to ensure proper loading of all vehicles used for transport of materials and construction debris. Any spillage en route on the Base shall be promptly removed and disposed of off-Base in accordance with applicable local, State, and Federal laws and regulations.

1.8 MOWING

Grass and weedy vegetation within the areas utilized by the Contractor, including work areas, administrative areas, and storage areas, shall be kept mowed to control vegetative growth. Vegetation shall be mowed to a height of 3 inches when it reaches a height of 6 inches. Mowing shall be done with a rotary mower. Mowing shall be done during periods and in such a manner that the soil and grass will not be damaged. Areas adjacent to trees, shrubs, fences, buildings, etc. shall be hand trimmed. The Government may, after notice to the Contractor and at the discretion of the Contracting Officer, mow the Contractor's areas at any time the vegetation height exceeds 6 inches and all costs incurred by the Government for performing such work will be deducted from the contract.

1.9 STAGING AREA PREPARATION (REQUEST BY DE, JUL 91)

The Contractor's staging area or areas shall be located within the boundaries of the project parking lots or other areas as directed by the Contracting Officer. The Contractor shall be responsible for the maintenance of the staging area(s) and shall repair any damage prior to acceptance of the project.

1.10 CONSTRUCTION MATERIAL STORAGE

Contractors shall store construction materials only in designated staging areas or areas designated by the Contracting Officer. Grass and weedy vegetation shall be mowed during the duration of the contract in accordance with paragraph entitled MOWING. Storage areas located along the Distinguished Visitor Route shall be screened to a height of 6 feet above grade and supported by a chainlink fence system. Fence posts shall be set in concrete bases. The storage area gates shall also be screened.

Screening material shall provide 80 percent concealment, minimum, and shall be installed in a permanent manner. No roofing or other material shall be

SECTION 01 50 00 Page 3 stored on roofs on inhabited buildings unless prior written authority has been obtained from the Contracting Officer.

1.11 WARNING SIGNS

The Contractor shall place warning signs at the construction area perimeter designating the presence of construction hazards and requiring unauthorized persons to keep out. For exterior construction, signs must be placed on all sides of the project with at least one sign every 300 feet. All points of entry shall have signs designating the construction site as a hardhat area. For interior construction projects, signs shall be placed only at points of entry. Warning signs shall be removed by the Contractor at the end of construction.

1.12 TEMPORARY CONSTRUCTION FENCING AND WINDSCREENING

The contractor shall provide temporary construction fencing and windscreening on all projects unless directed otherwise by the Contracting Officer. Temporary fencing shall consist of 6-foot high chain link fencing and windscreening. Chain-link fencing shall have a top rail and schedule 40 (minimum) posts at 10 foot maximum spacing. Contractor shall install temporary fencing with set-back at 45 degree angles at fence corners that terminate at road intersections and entrances to site to provide adequate site distance for vehicle safety. Contractor shall submit a site plan with proposed fencing layout for the Contracting Officer's approval. Temporary fencing and windscreening shall be removed at the end of the construction, and the areas affected by the fencing shall be returned to the original state prior to construction.

1.12.1 Windscreening

Windscreening shall consist of polyethylene closed or knit mesh fabric that provides between 94 to 100 percent visual privacy. Windscreen fabric shall be finished on all sides by hemming or binding and shall have built-in grommets. Windscreening shall cover the full-height and length of the temporary fencing including gates and shall be attached to the fencing as recommended by the manufacturer. Color shall be dark brown. Windscreening fabric that becomes torn or worn during the construction period shall be replaced by the Contractor at no additional cost to the Government.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used -- End of Section --

SECTION 01 50 00 Page 4

SECTION 09 66 16

TERRAZZO FLOOR TILE

08/16, CHG 1: 08/18

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C97/C97M (2015) Absorption and Bulk Specific Gravity of Dimension Stone

ASTM C109/C109M (2020b) Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2-in. or (50-mm) Cube Specimens)

ASTM C501 (1984; R 2015) Relative Resistance to Wear of Unglazed Ceramic Tile by the Taber Abraser

ASTM D2047 (2017) Standard Test Method for Static Coefficient of Friction of Polish-Coated Floor Surfaces as Measured by the James Machine

ASTM E84 (2020) Standard Test Method for Surface Burning Characteristics of Building Materials

ASTM E648 (2019a) Standard Test Method for Critical Radiant Flux of Floor-Covering Systems Using a Radiant Heat Energy Source

CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)

CDPH SECTION 01350 (2010; Version 1.1) Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources using Environmental Chambers

SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)

SCAQMD Rule 1168 (2017) Adhesive and Sealant Applications

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

SECTION 09 66 16 Page 1

*AM2 - Added this section in it's entirety*

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-02 Shop Drawings

Terrazzo Tile ; G, DO

SD-03 Product Data ; G, DO

Terrazzo Tile ; G, DO

Recycled Content for Terrazzo Tile ; S; G,DO

Adhesive ; G, DO

Indoor Air Quality for Adhesive ; S; G, DO

Installation ; G, DO

SD-04 Samples

Terrazzo Tile ; G, DO

Terrazzo Base ; G, DO

Metal Edge Strips ; G, DO

SD-10 Operation and Maintenance Data

Manufacturer's Maintenance Instructions ; G, RO

SD-11 Closeout Submittals

Warranty ; G, RO

1.3 QUALITY ASSURANCE

Installer must possess, to the satisfaction of the Contracting Officer, the technical qualifications, experience, trained personnel, and facilities to properly install the specified items.

1.4 DELIVERY, STORAGE, AND HANDLING

Deliver materials to the jobsite in the manufacturer's original unopened containers marked with the manufacturer's brand name, color, and pattern.

Store materials delivered and placed in storage protected from damage, weather, humidity and temperature variation, dirt and dust, or other contaminants. Temperature of storage area must not be lower than 50 degrees F or higher than 90 degrees F .

1.5 SITE CONDITIONS

Do not install tiles until other work that could cause damage to the finished flooring has been completed. Maintain a temperature of not less than 70 degrees F in all areas where tile is to be installed for a period of not less than 48 hours before, during and after laying of tiles. Bring tiles into installation areas and allow to condition at not less than 70 degrees F for a period of 72 hours prior to installation. After installation of tiles, maintain a minimum temperature of 55 degrees F .

SECTION 09 66 16 Page 2

1.6 WARRANTY

Provide manufacturer's standard performance guarantees or warranties that extend beyond a one year period.

PART 2 PRODUCTS

2.1 STANDARD PRODUCTS

Provide materials which are the standard products of a manufacturer regularly engaged in the manufacture of the material and that essentially duplicate products that have been in satisfactory use at least 2 years prior to bid opening.

2.2 TERRAZZO TILE

Provide terrazzo tile of the indicated colors and consisting of marble or glass chips embedded in a epoxy resin matrix. Submit drawings indicating pattern, size, style, and color of tiles and two 6 by 6 inch minimum samples of each color and pattern of terrazzo tile to be used. Tiles must be 1/4" inch thick and nominal 12 by 12 inches . Provide tiles with a polished finish with uniform color distribution of chips. Granite chips must be manufacturer's standard gradation. Provide tile with the following properties:

TERRAZZO TILE PROPERTIES

PROPERTY TEST METHOD VALUE

Compressive Strength ASTM C109/C109M 3000 psi minimum

Water Absorption ASTM C97/C97M 0.7 percent maximum

Abrasive Wear ASTM C501 Index 28

Coefficient of Friction ASTM D2047 0.5 wet

Flame Spread ASTM E84 Class A

Critical Radiant Flux ASTM E648 Class I

2.3 ADHESIVE

Adhesive must be flooring manufacturer's standard product or a product recommended by the manufacturer. Submit documentation from manufacturer indicating that the materials conform to the specified requirements and flooring manufacturer's approval of underlayment, adhesive, and cleaners.

Adhesive products used on the interior of the building (defined as inside of the weatherproofing system) must meet either emissions requirements of CDPH SECTION 01350 (limit requirements for either office or classroom spaces regardless of space type) or VOC content requirements of SCAQMD Rule 1168 . Provide validation of indoor air quality for adhesive .

SECTION 09 66 16 Page 3

2.4 TERRAZZO BASE

Provide terrazzo base of colors as indicated, meeting the requirements of paragraph TERRAZZO TILE and being a manufacturer's standard product.

Base/strips shall be 3/8 inch thick . Base/strips shall have polished finish. Submit two 4 inch long samples of each type and color of trim pieces.

2.5 METAL EDGE STRIPS

Metal edge strips must be extruded aluminum, butt type, approximately 1-1/2 inches wide with thickness to set top surface flush with top of tile and with bevel at exposed edge. Edge strips must have countersunk holes near each end and spaced not more than 8 inches on center for securement.

Submit one 6 inch long sample of metal edge strip

2.6 COLOR

Color must be as indicated.

PART 3 EXECUTION

3.1 GENERAL

Install flooring and base on floor surfaces and walls where indicated.

Except as required for installation of new tile, keep traffic new tile for at least 48 hours after installation.

3.2 EXAMINATION

After becoming familiar with details of the work, verify dimensions in the field, and advise the Contracting Officer of any discrepancy before performing the work.

3.3 SUBSTRATE PREPARATION

Fill holes and cracks with mortar. Floors must be free of curing compounds, grease, dirt, loose particles and other foreign matter that would prevent adhesion. Chip and grind smooth projecting irregularities.

Fill depressions and level uneven surfaces. Rinse subfloors and allow to dry prior to applying adhesive.

3.4 MOISTURE TEST

After concrete floor surfaces have been cleaned, spread small patches of adhesive in several locations in each room or area to receive tile and allowed to dry overnight. If the adhesive can be peeled easily from the floor surfaces, the surface is not sufficiently dry. Repeat the steps until the adhesive adheres properly. Do not apply tiles until adhesive adheres tightly to the floor.

3.5 INSTALLATION

Submit the manufacturer's printed installation instructions for the conditions indicated.

3.5.1 Tile

Install tile in accordance with the manufacturer's approved installation

SECTION 09 66 16 Page 4 instructions, except as specified herein. Lay tile symmetrical about center lines of rooms or areas. Joints must be tight, inconspicuous as possible, and in alignment. Cut tile to fit snugly at pipes and other vertical surfaces. Seal joints at pipes with adhesive. Remove spots or smears of adhesive immediately. Entire surface of finished tile floor must be smooth, straight, and free from bleeding adhesive, buckles, waves, or projecting tile edges upon completion. Bleeding of adhesive on finished floors is cause for rejection by the Contracting Officer. Remove and replace damaged or rejected tiles.

3.5.2 Metal Edge Strips

Secure edge strips with No. 10 aluminum alloy, counter-sunk, flathead machine screws with expansion sleeves. Provide exposed edges of tile with one-piece metal edge strips.

3.5.3 Terrazzo Base/Strips

Terrazzo base/strips must be continuous and adhesively applied. Joints must be tight and inconspicuous in same manner as floor tile.

3.6 CLEANING

Upon completion of the installation and after adhesive has cured, flooring shall be thoroughly cleaned in accordance with the manufacturer's recommendations.

3.7 PROTECTION

Cover and protect the terrazzo tile work from damage until completion of the work of all other trades. Remove and replace defects which develop, such as loose, broken, or curled tiles. Submit six copies of the Manufacturer's Maintenance Instructions .

-- End of Section --

SECTION 09 66 16 Page 5

SECTION 31 00 00

EARTHWORK

08/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO T 180 (2017) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop

AASHTO T 224 (2010) Standard Method of Test for Correction for Coarse Particles in the Soil Compaction Test

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA C600 (2017) Installation of Ductile-Iron Mains and Their Appurtenances

AMERICAN WELDING SOCIETY (AWS)

AWS D1.1/D1.1M (2015; Errata 1 2015; Errata 2 2016) Structural Welding Code - Steel

AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)

AWPA P5 (2015) Standard for Waterborne Preservatives

ASTM INTERNATIONAL (ASTM)

ASTM A139/A139M (2016) Standard Specification for Electric-Fusion (ARC)-Welded Steel Pipe (NPS 4 and over)

ASTM A252 (2010) Standard Specification for Welded and Seamless Steel Pipe Piles

ASTM C33/C33M (2018) Standard Specification for Concrete Aggregates

ASTM C136/C136M (2014) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates

ASTM D698 (2012; E 2014; E 2015) Laboratory Compaction Characteristics of Soil Using

SECTION 31 00 00 Page 1

Standard Effort (12,400 ft-lbf/cu. ft.

(600 kN-m/cu. m.))

ASTM D1140 (2017) Standard Test Methods for Determining the Amount of Material Finer than 75-µm (No. 200) Sieve in Soils by Washing

ASTM D1556/D1556M (2015; E 2016) Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method

ASTM D1557 (2012; E 2015) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)

ASTM D2487 (2017) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)

ASTM D2937 (2017; E 2017; E 2018) Standard Test Method for Density of Soil in Place by the Drive-Cylinder Method

ASTM D4318 (2017; E 2018) Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils

ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA 600/4-79/020 (1983) Methods for Chemical Analysis of Water and Wastes

EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test Methods for Evaluating Solid Waste:

Physical/Chemical Methods

1.2 DEFINITIONS

1.2.1 Satisfactory Materials

Satisfactory materials comprise any materials classified by ASTM D2487 as

GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, SW, SP, SM, SW-SM, SC, SW-SC, SP-SM,

SP-SC, CL. Satisfactory materials for grading comprise stones less than 8 inches , except for fill material for pavements which comprise stones less than 3 inches in any dimension.

1.2.2 Unsatisfactory Materials

Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction; and

SECTION 31 00 00 Page 2 material classified as satisfactory which contains root and other organic matter or frozen material. Notify the Contracting Officer when encountering any contaminated materials.

1.2.3 Cohesionless and Cohesive Materials

Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesionless only when the fines are nonplastic. Perform testing, required for classifying materials, in accordance with ASTM D4318, ASTM C136/C136M and ASTM D1140.

1.2.4 Degree of Compaction

Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum density. Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, express the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve as a percentage of the maximum density in accordance with AASHTO T 180 and corrected with AASHTO T 224 . To maintain the same percentage of coarse material, use the "remove and replace" procedure as described in NOTE 8 of Paragraph 7.2 in AASHTO T 180 .

1.2.5 Topsoil

Material suitable for topsoils obtained from offsite areas and/or excavations is defined as: Natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth. Amend topsoil pH range to obtain a pH of 5.5 to 7.

1.2.6 Hard/Unyielding Materials

Hard/Unyielding materials comprise weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" with stones greater than 3 inch in any dimension or as defined by the pipe manufacturer, whichever is smaller. These materials usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.

1.2.7 Rock

Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1/2 cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production.

SECTION 31 00 00 Page 3

1.2.8 Unstable Material

Unstable materials are too wet to properly support the utility pipe, conduit, or appurtenant structure.

1.2.9 Select Granular Material

1.2.9.1 General Requirements

Select granular material consist of materials classified as GW, GP, SW,or SP by ASTM D2487 where indicated. Additionally, non-expansive backfill shall be in accordance with the geotechnical report prepared for this project by Reits & Jens, inc.; dated April 5, 2019.

1.2.10 Initial Backfill Material

Initial backfill consists of select granular material or satisfactory materials free from rocks 3 inches or larger in any dimension or free from rocks of such size as recommended by the pipe manufacturer, whichever is smaller. When the pipe is coated or wrapped for corrosion protection, free the initial backfill material of stones larger than 3 inches in any dimension or as recommended by the pipe manufacturer, whichever is smaller.

1.2.11 Expansive Soils

Expansive soils are defined as soils that have a plasticity index equal to or greater than 15 when tested in accordance with ASTM D4318.

1.2.12 Nonfrost Susceptible (NFS) Material

Nonfrost susceptible material are a uniformly graded washed sand with a maximum particle size of 2 inch and less than 5 percent passing the No. 200 size sieve, and with not more than 3 percent by weight finer than 0.02 mm grain size.

1.2.13 Pile Supported Structure

As used herein, a structure where both the foundation and floor slab are pile supported.

1.3 SYSTEM DESCRIPTION

Subsurface soil boring logs are shown on the drawings. These data represent the best subsurface information available; however, variations may exist in the subsurface between boring locations.

1.3.1 Classification of Excavation

No consideration will be given to the nature of the materials, and all excavation will be designated as unclassified excavation.

1.3.2 Blasting

Blasting will not be permitted.

1.3.3 Dewatering Work Plan

Submit procedures for accomplishing dewatering work.

SECTION 31 00 00 Page 4

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .