RFP NO. : W912BV-12-R-0027
US Army Corps of Engineers
Tulsa District
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS
(SDVOSB) SET ASIDE INDEFINITE DELIVERY INDEFINITE
QUANTITY (IDIQ) SINGLE AWARD TASK ORDER CONTRACT
(SATOC) FOR GENERAL CONSTRUCTION SERVICES IN
SUPPORT OF VARIOUS MILITARY AND CIVIL WORKS
CONSTRUCTION PROJECTS WITHIN BOUNDARIES OF THE
USACE TULSA DISTRICT BOUNDARIES. (“USACE Tulsa District SDVOSB IDIQ SATOC for General Construction Services”)
Specifications (SATOC only)
14 MARCH 2012________________________________________________
TABLE OF CONTENTS
- - End Table of Contents - -
SECTION TITLE
DIVISION 01 – GENERAL REQUIREMENTS
01 01 00.00 44 Work Plan Requirements 01 32 01.00 10 Project Schedule (Full Schedule) 01 32 01.00 03 Project Schedule for Small Projects 01 32 01.00 12 Project Schedule – Barchart Format 01 33 00 Submittal Procedures 01 35 26 Governmental Safety Requirements 01 42 00 Sources for Reference Publications 01 45 00.00 10 Quality Control 01 45 01.10.10 Quality Control System (QCS) 01 45 00.10 20 Quality Control for Minor Construction 01 50 00 Temporary Construction Facilities and Controls 01 57 20.00 10 Environmental Protection 01 57 73 Temporary Storm Water Pollution Control 01 62 35 Recycled/Recovered Materials 01 74 19 Construction and Demolition Waste Management 01 75 00 Starting and Adjusting 01 78 00 Project Closeout and Submittals
Tulsa District SDVOSB SATOC IDIQ for Construction Services
01 01 00.00 44 Page 1
WORK PLAN REQUIREMENTS
SECTION 01 01 00.00 44
FSAO 7 Nov 2011
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
INTERNATIONAL CODE COUNCIL (ICC)
ICC Bldg Code ICC International Building Code
INTERNATIONAL CONFERENCE OF BUILDING OFFICIALS (ICBO)
ICBO Bldg Code Uniform Building Code (3 Vol.)
UNIFIED FACILITIES CRITERIA (UFC)
UFC 3-600-01 Design: Fire Protection Engineering For Facilities
U.S. ARMY CORPS OF ENGINEERS, SOUTHWESTERN DIVISION PUBLICATIONS
(CESWD)
CESWD-01 (Current Version) Corps of
Engineers Southwestern Division Architectural and Engineering Instruction Manual (CESWD-AEIM)
1.3 SUBMISSION OF TASK ORDER DRAWINGS, SPECIFICATIONS, AND OTHER DATA
1.3.1 Number of Copies
The Contractor shall submit, in accordance with Section 00 90 00 DESCRIPTION/SPECS/WORK STATEMENT and Section 01 33 16 DESIGN AFTER AWARD (if applicable), the required number of copies of the construction drawings, specifications, calculations, equipment schedules, and all other submittal data for each review submittal. These submittals shall be in accordance with the requirements of this SATOC Contract, all current revisions, the task order, and all other terms and conditions of the Contract.
1.3.2 Task Order Drawings
See Section 01 33 16 DESIGN AFTER AWARD, if applicable, and Section 01 78 00 CONTRACT CLOSEOUT for CADD drawing requirements and standards. Provide CAD files in the format required by the installation.
1.3.2.4 Drawings Sequence
Arrange drawings by design discipline in accordance with the CESWD-01, SWD Architectural and Engineering Instruction Manual, Chapter VIII, Appendix A, Plate D1, Standard Arrangement Of Drawings.
1.3.2.5 Drawings Required
As a minimum, the construction drawings shall consist of the following as required by the task order:
01 01 00.00 44 Page 2
a. Title Sheet, Index of Drawings (each technical discipline shall have a separate drawing legend sheet located in front of each respective section), Legend, and Abbreviations and Soil Borings
b. Civil Drawings
c. Utility Drawings (Water Supply, Wastewater, Gas, Electrical, Fiber and Communication)
d. Architectural Drawings
e. Interior Design Drawings
f. Structural Drawings
g. Mechanical Drawings
h. Electrical Drawings (including security and fire alarm)
i. Lightning Protection
j. Fire Protection Drawings
k. Environmental Drawings (including identification and removal of hazardous materials from the buildings, storm water control details, etc.)
l. Kitchen Equipment Drawings
m. Landscape Architectural Drawings
n. Irrigation Layout Drawings
1.3.3 Task Order Specifications
Construction specifications shall be in sufficient detail to fully describe and demonstrate the quality of materials, the installation and performance of equipment, and the quality of workmanship. Use any commercially available guide specifications such as "SpecText" published by The Construction Specifications Institute, manufacturers' product specifications utilizing CSI's Manu-Spec format, or the Corps of Engineers Unified Facilities Guide Specifications (UFGS), the Tulsa District's local guide specifications. The specifications shall clearly identify, where appropriate, the specific products chosen to meet the requirements of the Contract (manufacturers' brand names and model numbers or similar product information). The Contractor shall be responsible for coordinating references, along with the Contract performance requirements, to specific specification sections (number and title) within the construction specifications.
1.3.3.1 Commercially Available Guide Specifications
When commercially available construction guide specifications are used, change references to the "Architect", "Engineer", and "Owner" to refer to the "Government" or "Contracting Officer".
1.3.3.2 Guide Specification Editing
01 01 00.00 44 Page 3
When the UFGS are used, specification paragraphs and subparagraphs shall not be rewritten to lessen the quality of materials as specified in the original guide specifications. Edit to tailor the specifications to fit the project.
1.3.3.3 Format
Submit construction specifications, including cover page and Project Table of Contents, using software applicable to the guide specification version; the current version of Specsintact for UFGS guides and Microsoft Word 2003 or later version for other commercially available guide specifications. Print hard copies using laser or inkjet printer and good quality white bond paper (75 g/m 2 (20 pound Copier/Laser/Fax/Inkjet/Offset type), 215 mm by 279 mm (8 1/2 by 11 inch) in size. Review copies shall be the marked-up version with the editing shown by using redlining for text insertions and strikeouts for text deletions. The corrected 100 percent specifications with review comments incorporated shall be cleaned up (markings for insertion and deletion removed) and submitted in both hard copy and on magnetic media (CD-ROM disk).
Carbon copies are not acceptable. Electronic version: Print the specifications to Adobe Acrobat .pdf format and include on the CD-ROM disc with the drawings. The specifications shall be a single file with bookmarks utilized for each section. File shall open with bookmarks showing. Include the native word files of the specifications on the CD for the final submitted specifications. Include Adobe Acrobat Reader and the Contract Viewer software on the CD Disc. Contract Viewer software, along with instructions, can be copied from the Solicitation files.
1.3.3.4 Submittal Register
Submit a submittal register with each task order. See Sections 01 45 01.10 10 QUALITY CONTROL SYSTEM (QCS) and 01 33 00 SUBMITTAL PROCEDURES. Use the Corps QCS software described in Section 01 45 01.10 10 QUALITY CONTROL SYSTEM (QCS) When UFGS guide specifications are used, the Specsintact software can be used to generate the submittal register. Submit with the review and final submittals.
1.3.3.5 Cover Page
Include the following information:
a. Project title, location, and task order title
b. Construction contract number
c. Task Order number
d. Construction Contractor's name and address
1.3.4 Task Order Documents
In general, task order documents shall include construction drawings, specifications, Storm Water Pollution Prevention Plan if applicable, construction schedule, and calculations for categories such as, but not limited to, architectural, structural, mechanical, electrical, grading, drainage, paving, and outside utility services. Detailing and installation of all equipment and materials shall comply with the manufacturers' recommendations. See also Sections 00 90 00 DESCRIPTION/SPECS/WORK STATEMENT and 01 33 16 DESIGN AFTER AWARD.
1.3.5 Task Order Reviews
01 01 00.00 44 Page 4
See Sections 01 33 16 DESIGN AFTER AWARD and Sections 00 90 00 DESCRIPTION/SPECS/WORK STATEMENT for review requirements.
1.3.5.1 Material normally required for preliminary submittal
a. Drawings; All drawings required for completion of the task order, developed to approximately 35 percent completion.
b. Specifications; Draft of specifications for task work, including index and manufacturers' catalog and engineering data.
c. SID Interior and Exterior Finish Samples; See Section 01 33 16 DESIGN
AFTER AWARD.
d. Calculations; Calculations developed to the extent required to support the task order development of that portion of utility distribution, structural, electrical, and mechanical systems included in this submittal.
e. Storm Water Pollution Prevention Plan (SWPPP)
f. Construction Schedule; Construction schedule shall conform to the requirements Section.
1.3.5.2 Material normally required for final (100 percent) submittal Includes all documents submitted for the preliminary review, upgraded to 100 percent completion.
a. Drawings
1) Site Drawings; Site drawings shall include plans and details required by the task order.
2) Architectural Drawings; Architectural drawings shall include plans, elevations, building sections; fire exits; wall, ceiling, and floor fire ratings; and details required by the task order.
3) Structural Drawings; Structural drawings shall include plans, details, and connections applicable to the task order.
4) Mechanical and Electrical Drawings; Mechanical/electrical drawings, with complete schematics, shall show all heating, air conditioning, plumbing and electrical work.
5) Fire Protection Drawings; Fire Protection drawings, with complete schematics, shall show all fire sprinkler system layout, pipe sizes, locations of heads, details, etc. as required for construction and to meet the codes.
6) Equipment Schedules; Based on the results of calculations, provide a complete list(s) of the materials and equipment proposed for heating, air conditioning and plumbing, with the manufacturer's published cataloged product installation specifications and roughing-in data. The heating and air conditioning equipment data shall include the manufacturer's wiring diagrams, installation specifications, ARI certification, 01 01 00.00 44 Page 5 and the standard warranty for the equipment. When new diffusers are required in a task order, provide the manufacturer's published cataloged capacities for supply diffusers as evidence that the arrangement of supply air outlets in each room will provide the throw and spread characteristics required to cover completely all exterior wall surfaces with the blanket of warm air at the proper design velocities.
b. Specifications; Specifications for all task order work upgraded to 100 percent completion. Contractor shall make final proposal of all materials and finishes at this submittal.
c. Calculations; Complete calculations for utility distribution systems, structural elements, and electrical and mechanical systems. Include computations for sizing equipment, air duct arrangement, and R-values for ceilings, roofs and exterior walls and floors. Calculations shall conform to the military installation’s yearly energy budget requirements (i.e. BTU's and KW's). Include codes, manuals, and criteria used for calculations. Include, as applicable:
1) loads, load factors, and allowances for future loads,
2) energy performance calculations,
3) working stresses and factors of safety,
4) deflection calculations,
5) Expansion-, contraction-, and crack-control measures,
6) Foundation characteristics,
7) Construction or erection limitations, and
8) Fire Protection: Comprehensive analysis of all fire-safety factors with indication of treatment provided for each potential hazard.
d. Construction Schedule
e. Submittal Register; Printed copy shall be provided. Upon approval of the government, the register shall be loaded into QCS by the contactor.
1.3.7 Common Design Deficiencies
The work involved in making corrections due to common deficiencies becomes lost effort and time for both the designer and the reviewer. Contractor and Designer shall carefully compare the design and contract documents with all requirements at several points in the design process to avoid unnecessary changes at a later date. Some of the requirements which are most often overlooked include:
a. Requirements of required design publications, such as the Border Patrol design guides or the CESWD-01, Southwestern Division's ARCHITECTURAL AND ENGINEERING INSTRUCTIONS MANUAL (SWD-AEIM), have been repeatedly overlooked in the past.
b. Not using correct abbreviations or terminology on the drawings.
Abbreviations must match what is used on the standard abbreviation sheet and terminology must match what is used in the standard technical guide specifications.
c. Not using the correct scales, north arrow designation, section cut system, or incomplete dimensioning on the drawings. Failure to orient
01 01 00.00 44 Page 6 the North arrow in the same direction on all sheets (civil, site, arch).
d. Failure to use the latest edition (at time of task order start) of applicable criteria unless a specific edition is specified.
e. Not providing sufficient space for door operation hardware at doors which swing into a wall running perpendicular to the opening. 4 inches (100 mm) minimum is required between edge of door frame and perpendicular walls. Proper mechanical and electrical clearances to meet building codes.
f. Not providing correct and complete Design Analysis information written in the present tense. The Design Analysis will be written following the format indicated herein. A separate Fire Protection section in the Design Analysis with input from all disciplines is one area which is often overlooked and shall be included.
g. Not correctly presenting or coordinating (to avoid interference) features of Fire Protection, Noise Control, Mechanical Systems, and Physical Security.
h. Not correctly referencing and cross referencing building sections, wall sections, details, etc.
i. Not sufficiently providing enough architectural details to show how building envelope requirements will meet the testing criteria to include provision of supporting calculations.
j. Failure to read and use technical notes in editing technical guide specifications.
k. Failure to coordinate all disciplines prior to review submittals.
l. Improper use of fire-retardant wood. Fire-retardant wood is combustible; its use in buildings that are of noncombustible construction is extremely limited (see ICBO Bldg Code,or ICC Bldg Code for the minor allowable uses). Because of the potential for severe degradation, fire retardant plywood shall not be used in a roof or roofing system or in structural applications.
m. Not listing the ANSI/BHMA numbers in addition to trade names in door hardware specifications and failure to correctly specify hardware finishes.
n. Not showing control joints in CMU walls or brick expansion joints in face brick on both architectural plans, elevations and structural plans, or the joints are inconsistent. Also, locate and coordinate control joints for floor tile in accordance with the Tile Council of America recommendations.
o. For LEED projects, not properly defining in the specifications the design and construction deliverables required to meet USGBC requirements or to allow the Quality Control Manager in the field to understand what LEED requirements must be met and how.
01 01 00.00 44 Page 7
p. Failure to delete all publications which do not apply to the particular project.
1.4 COE GUIDE SPECIFICATIONS AND SOFTWARE
The Corps of Engineers Unified Facilities Guide Specifications (UFGS) can be downloaded from the Corps of Engineers web site. These guide specifications (UFGS) are in the Specsintact SGML format. The UFGS guide specifications are in the current CSI MasterFormat 2004 division and section numbering series.
a. The Corps of Engineers Specsintact software can be downloaded free of charge from the Internet at the following address:
http://specsintact.ksc.nasa.gov/software/software.htm
b. The Corps of Engineers UFGS Guide Specifications, Lighting Fixture Standard Drawing 40-06-04 Details, and Design Criteria (e.g. Unified Facilities Criteria, Army Technical Manuals (TM's), Engineering Manuals, Engineering Technical Letters, Engineer Circulars, Engineer Pamphlets, Design Guides, and Military Handbooks) can be downloaded from the Huntsville Division's Techinfo web site at the following address: http://www.hnd.usace.army.mil/techinfo/
c. UFGS guide specifications and other design guides can also be obtained from the National Institute of Building Sciences (NIBS)'s Construction Criteria Base (CCB) Whole Building Design Guide web site at:
http://www.ccb.org/.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --http://specsintact.ksc.nasa.gov/software/software.htm� http://www.hnd.usace.army.mil/techinfo/� http://www.ccb.org/�
01 32 01.00 12 Page 1
PROJECT SCHEDULE FOR SMALL PROJECTS
SECTION 01 32 01.00 03
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ECB 2005-10 (2005) Scheduling Requirements for Testing of Mechanical Systems in Construction
ER 1-1-11 (1995) Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule - G
SD-02 Designated Authorized Representative Qualifications
Documentation listing, not limited to:
a: Years of experience in scheduling b: Minimum of 3 previously developed, created, and maintained project similar in nature and complexity to the project c: Qualifications to meet or exceed requirements under Section 01320-1.3 Quality Assurance.
Designated Authorized Representative - G
1.3 QUALITY CONTROL
Contractor to have a Designated Authorized Representative for Schedule.
Designated Authorized Representative shall be same person or employee of a company approved under Section 01320-1.2 Submittals. An Authorized Representative change shall be submitted and approved, per Section 01320-1.2 Submittals, before new authorized representative takes over responsibilities from previous authorized representative. Authorized representative to be responsible for the preparation of the schedule, all required updating, and preparing of reports. Authorized representative shall have experience in the
01 32 01.00 12 Page 2 use of the scheduling software that meets the requirements of this specification.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Bar Chart Schedule, or Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of construction, design and construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.
Subcontractors and suppliers, Designers, Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project-monitoring tool. Dates based on calendar days, not working days.
3.2 Approved Project Schedule (Bar Chart)
Use the approved Project Bar Chart Schedule to measure the progress of the work and to aid in evaluating time extensions. The Bar Chart will provide the basis for all progress payments. If the Contractor fails to submit any Bar Chart Schedules within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required Bar Chart Schedule.
3.3 Schedule Status Reports
Provide a Bar Chart Schedule Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained. Once the schedule (either Design/Preliminary, Initial or Updated) is approved, changing original durations of activities shall not be done.
3.4 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any
01 32 01.00 12 Page 3 separable part of it, in accordance with the default terms of the contract.
3.5 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment.
Lack of an approved monthly update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the Initial and subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Bar Chart Schedule have been made.
3.6 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) shall be corrected before Pay Application is sent to Government. Out-of-Sequence Progress will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate all out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule.
3.7 Narrative Report for Progress Payments
Provide a Narrative Report as the basis of the progress payment request.
The Narrative Report shall include: Statement declaring who is the Designated Authorized Representative for Schedule, a description of activities along the 2 most critical paths where the total float is less than or equal to 20 work days, a description of current and anticipated problem areas or delaying factors and their impact, and an explanation of corrective actions taken or required to be taken. The narrative report is expected to communicate to the Government, the Contractor's thorough analysis of the schedule output and its plans to compensate for any problems, either current or potential, which are revealed through that analysis. Identify and explain why any activities that, based their calculated late dates, should have either started or finished during the update period but did not.
3.8 REQUESTS FOR TIME EXTENSIONS
In the event the Contractor believes it is entitled to an extension of the contract performance period, completion date, or any interim milestone date, furnish the following for a determination by the Contracting Officer: justification, project schedule data, and supporting evidence as the Contracting Officer may deem necessary. Submission of proof of excusable delay, based on revised activity logic, duration, and costs (updated to the specific date that the delay occurred) is a condition precedent to any approvals by the Government. In response to each Request For Proposal issued by the Government, the Contractor shall submit a schedule impact analysis demonstrating whether or not the change contemplated by the Government impacts the critical path.
01 32 01.00 12 Page 4
3.9 Justification of Delay
The project schedule shall clearly display that the Contractor has used, in full, all the float time available for the work involved with this request. The Contracting Officer's determination as to the number of allowable days of contract extension shall be based upon the project schedule updates in effect for the time period in question, and other factual information. Actual delays that are found to be caused by the Contractor's own actions, which result in a calculated schedule delay, will not be a cause for an extension to the performance period, completion date, or any interim milestone date.
3.10 Bar Chart Schedule Method
Provide submittal for a cost-loaded network diagram (GNATT/bar chart) for approval. Bar Chart shall be in sequential order from NTP to Close Out Documents Complete. Contractor shall provide a second Bar Chart or Report showing breakdown of each activity assigned to a CLIN (BIDI) code with grand totals for each CLIN (BIDI), along with assigned cost for each activity, even if amount is zero ($.00). Contractor shall provide a disk with the submittal that has the backup file used to create the Bar Chart schedules/reports. The Bar Chart schedule shall have the following columns:
3.10.1 Activity ID
3.10.2 Activity Description
3.10.3 Original Duration
3.10.4 Remaining Duration
3.10.5 Total Float
3.10.6 Percent Complete
3.10.7 Early Start
3.10.8 Late Start
3.10.9 Actual Start
3.10.10 Early Finish
3.10.11 Late Finish
3.10.12 Actual Finish
3.10.13 CLIN (BIDI) Assigned
3.10.14 Total Budgeted Cost
3.10.15 Actual Cost
3.10.16 As part of Narrative Report, statement designating who is authorized representative responsible for updating and experience of representative.
3.10.17 Linkage between remaining duration and percent complete in software shall be disabled.
3.10.18 If mobilization activity is used, a demobilization activity shall be in the schedule and both activities will have same total budgeted cost.
3.10.19 Once Original Durations are approved, they cannot be
changed.
01 32 01.00 12 Page 5
3.10.20 Original and/or Remaining durations shall not be over 20 calendar days. Only exceptions are Hammock and Level of Effort activities.
3.10.21 Dates based on calendar days, not working days.
3.10.22 NTP shall be the only activity without a predecessor and constraint.
3.10.23 “Construction Complete/ End of Project” shall be the only activity without a successor. Activity shall be constrained only by a “Project must finish by” in software. Mandatory or any other type of constraint shall not be used.
3.10.24 Create a “Construction Complete/ End of Project” activity based on contract completion date. Use “project must end by” in software. Do not use any other constraint.
3.10.25 Create a “Close Out Documents Complete” activity based on 30 days after “Construction Complete”. Do not use any other constraint. This activity does not increase the contract duration.
3.10.26 The schedule shall start no earlier than the date the NTP was issued, not acknowledged. The first activity of the schedule shall be called “NTP”.
3.10.27 Provide a milestone for “RED ZONE MEETING” and any other milestones per directive of COE and as applicable.
3.10.28 Show Government and other agency activities that could impact progress. These activities include, but are not limited to: approvals, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.10.29 With each month’s Pay Estimate/Invoice, Contractor shall provide hard copy of Bar Chart schedule, hard copy of each of the two (2) critical paths and disk containing backup (zip file) of the project file created from the software utilized to create updated schedule, critical paths, and Narrative report.
3.10.30 In response to each Contractual Change (Modification)
Proposal issued by the Government, the Contractor shall submit a
3.10.31 Submission of proof of excusable delay, based on revised activity logic, duration, and costs (updated to the specific date that the delay occurred) is a condition precedent to any approvals by the Government. The Contractor shall submit a
3.10.32 Schedule to be submitted 15 calendar days after Contractor
NTP acknowledgement.
01 32 01.00 12 Page 6
3.10.33 Calendars shall be “Project” specific. Global or “software templates” shall not be used.
3.10.34 Submittal shall be have description on 4025 as “Initial
Schedule”.
3.11.34 Commissioning Coding (MCOM)
A Commissioning Code shall be assign to every activity that part of the Commissioning Scope of Work whether it is a submittal, report, or construction. Each activity shall have only one Commissioning Code. The Contractor shall provide (as required or as a minimum) in the schedule the following activities:
ACTIVITY DESCRIPTIONS
Submit Commissioning Firm Gov’t Review Commissioning Firm Approval Commissioning Firm Submit Commissioning Agent Gov’t Review Commissioning Agent Approval Commissioning Agent Submit Commissioning Plan Gov’t Review Commissioning Plan Approval Commissioning Plan Submit TAB Firm Gov’t Review TAB Firm Approval TAB Firm Submit TAB Specialist Gov’t Review TAB Specialist Approval TAB Specialist Submit TAB Procedures Gov’t Review TAB Procedures Approval TAB Procedures Submit TAB Schematic Drawings-Forms Gov’t Review TAB Schematic Drawings-Forms Approval TAB Schematic Drawings-Forms Submit Design Review Report Gov’t Review Design Review Report Approval Design Review Report Pre FPT Checks Equipment Start-Up
TAB
Submit TAB Report Gov’t Review TAB Report Approval TAB Report TAB Verification Submit TAB Verification Report Gov’t Review TAB Verification Report Approval TAB Verification Report Control Start-Up Test Submit Control Start-Up Test Report Gov’t Review Control Start-Up Test Report Approval Control Start-Up Test Report
PVT (CONTROLS)
Submit PVT Report Gov’t Review PVT Report
01 32 01.00 12 Page 7
Approval PVT Report LNS Development UMCS Integration Contractor Front End Test Submit UMCS Start-Up Report Gov’t Review UMCS Start-Up Report Approval UMCS Start-Up Report
PVT (FRONT END)
FPT
Submit FPT Report Gov’t Review FPT Report Approval FPT Report Submit Commissioning Report Gov’t Review Commissioning Report Approval Commissioning Report
Contractor shall include the activities and logic to show a complete trail from start to final completion of commissioning, including LEED requirements. Schedule shall incorporate the above list, along with other activities required to provide a complete logic trail. Activities related to building construction that effect Commissioning (example: Building dry-in) shall have a Commission code assign. Commissioning activities shall be part of Construction logic and be completed on or before Contract Required Completion date.
3.12 TIME EXTENSIONS FOR WEATHER
3.12.1 Reference: FAR 52.249-10
3.12.2 Definitions:
3.12.2.1 “Adverse weather” – atmospheric conditions at a definite time and place that are unfavorable to construction activities.
3.12.2.2 “Unusually severe weather” – weather that is more severe than the adverse weather anticipated for the season or location involved.
3.12.3 Provision:
This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled “Default: (Fixed Price Construction)”. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault of negligence of the contractor.
01 32 01.00 12 Page 8
c. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor’s scheduled work day.
d. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated as defined in the contract, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather days, and issue a modification in accordance with the contract clause entitled “Default (Fixed Price Construction)”.
3.8.4 Analysis of Actual Adverse Weather During Construction
a. The contractor shall document the occurrence and effect of adverse weather on the work.
b. The schedule of anticipated adverse weather delays included in the contract is established in work days. Similarly, actual weather data should be collected and recorded on a work day basis. Monthly summaries shall be maintained by the contractor indicating actual adverse weather conditions and the impact on work activities. These impacts shall be discussed with the government at the monthly meeting after the adverse weather condition took place.
c. To determine if any particular month experience unusually severe weather, the number of actual adverse delay days is compared to that given in the contract table in the special clause. If the number of actual delay days is greater than that in the contract the contractor has experienced unusually severe weather.
d. THE DETERMINATION THAT UNUSUALLY SEVERE WEATHER OCCURRED DOES NOT
AUTOMATICALLY MEAN THAT THE CONTRACTOR RECEIVES A TIME EXTENSION FOR
THE DIFFERENCE OF DAYS BETWEEN THE ANTICIPATED AND ACTUAL ADVERSE
WEATHER DELAY DAYS. Further analysis is necessary to determine if the unusually severe weather delayed work activities critical to contract completion. The contractor’s progress schedule must be evaluated to make this determination. If it is found that unusually severe weather delayed the contact, a contract modification shall be issued pursuant to FAR 52.249-10.
e. Any necessary modifications will be issued not less than quarterly.
However, the contactor will be notified on a monthly basis of the government’s determination and be instructed to incorporate the expected time extension, if any, in their monthly progress schedule update. It is equally important for the government to notify the contractor of negative determinations on a monthly basis so that the government’s intentions are clearly understood.
-- End of Section --
SECTION 01 32 01.00 10 Page 1
PROJECT SCHEDULE (FULL)
SECTION 01 32 01.00
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
ECB 2005-10 (2005) Scheduling Requirements for Testing of
Mechanical Systems in Construction
ER 1-1-11 (1995) Progress, Schedules, and Network Analysis Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit number of hard copies and disks as required by Contracting Officer. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule - G
SD-02 Designated Authorized Representative Qualifications
Documentation listing, not limited to:
a: Detailed documentation of experience in scheduling (school, training, software, years scheduling, etc.).
b: Minimum of 3 previously developed, created, and maintained projects similar in nature and complexity to the project, detailing name and location of projects.
c: Qualifications to meet or exceed requirements under Section 01320-1.3 Quality Assurance.
Designated Authorized Representative – G
Submittals SD-01 and SD-02 shall be submitted as separate 4025’s for approval.
SECTION 01 32 01.00 10 Page 2
1.3 QUALITY ASSURANCE
Contractor shall have a Designated Authorized Representative for Schedule.
Designated Authorized Representative shall be same person or employee of a company approved under Section 01320-1.2 Submittals. An Authorized Representative change shall be submitted and approved, per Section 01320-1.2 Submittals, before new authorized representative takes over responsibilities from previous authorized representative. Authorized representative to be responsible for the preparation of the schedule, all required updating, preparing of reports, and all requirements of these specifications.
Authorized representative shall have experience in the use of the scheduling software that meets the requirements of this specification.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in the development.
Subcontractors and suppliers, Designers, Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project-monitoring tool.
3.1.1 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
SECTION 01 32 01.00 10 Page 3
3.1.3 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT AND COST LOADING
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the Design/Preliminary, Initial, Periodic, or Recovery schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer. Contractor shall meet with COE prior to submission of Design/Preliminary and Initial schedules to evaluate the cost loading and resolve any differences before the schedule is submitted (via 4025).
Construction related submittals shall be treated as being subsidiary to the corresponding physical work items. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification.
The Contractor shall utilize the most current version and/or update for the schedule software at no additional cost to the Government. If Contractor refuses to update software to most current version and/or update, then Contractor shall provide to Government a sealed, dedicated licensed version of the software they are using, at no additional cost to Government.
Software shall meet requirements of Section 1.1 of these specifications.
Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.
3.3.1 Critical Path Method
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule. Prepare the Project Schedule using the Precedence Diagram Method (PDM) or GANTT as directed by ACO/COR.
SECTION 01 32 01.00 10 Page 4
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2.1 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities shall have Original Durations (OD) greater than 10 work days or 14 calendar days. Procurement activities are defined herein. Once the schedule (Design/Preliminary, Initial, or Recovery) is approved, no changes to original activity durations shall be made without prior approval of the Government.
3.3.2.2 Design and Permit Activities
Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period.
This shall be at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. The schedule shall include review and correction periods associated with each item.
3.3.2.3 Procurement Activities
The schedule must include activities associated with the submittal, Gov’t review, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, Gov’t review, approve, procure, fabricate, and deliver.
3.3.2.4 Mandatory Tasks
The following tasks must be included and properly scheduled:
a. Submission, review and acceptance of design packages.
b. Submission of mechanical/electrical/information systems layout drawings.
c. Submission and approval of O & M manuals.
d. Submission and approval of as-built drawings.
e. Submission and approval of 1354 data and installed equipment lists.
SECTION 01 32 01.00 10 Page 5
f. Submission and approval of testing and air balance (TAB).
g. Submission of TAB specialist design review report.
h. Submission and approval of fire protection specialist.
i. Submission and approval of testing and balancing of HVAC plus commissioning plans and data. Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with ECB 2005-10.
j. Air and water balancing.
k. HVAC commissioning.
l. Controls testing plan submission.
m. Controls testing.
n. Performance Verification testing.
o. Other systems testing, if required.
p. Contractor's pre-final inspection.
q. Correction of punchlist from Contractor's pre-final inspection.
r. Government's pre-final inspection.
s. Correction of punch list from Government's pre-final inspection.
t. Final inspection.
3.3.2.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.2.6 Activity Responsibility Coding (RESP)
Assign responsibility Code for all activities to the Prime Contractor or, Subcontractor. Government shall not be used for any activity that has costs associated with it. Activities shall not have more than one Responsibility Code. Examples of acceptable activity code values for (RESP) are: DOR (for the designer of record); ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); GOVT (for Government). Unacceptable code values are abbreviations of the names of prime contractors or subcontractors. RESP codes shall be alpha; numeric is not allowed for RESP codes. Activity Responsibility Codes shall be imported through the SDEF conversion of the schedule into QCS/RMS. Manual inputting of Activity Responsibility Codes into QCS/RMS is prohibited.
SECTION 01 32 01.00 10 Page 6
3.3.2.7 Activity Work Area Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew, from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings. Each activity shall be identified within a single project area and have only one Work Area code. AREA codes shall be alpha; numeric is not allowed for AREA codes. Activity Work Area Codes shall be imported through the SDEF conversion of the schedule into QCS/RMS. Manual inputting of Activity Work Area Codes into QCS/RMS is prohibited.
3.3.2.8 Contract Changes/Requests for Equitable Adjustment (REA) Coding
(MODF)
Assign Activity code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by the Contracting Officer, with a Contract Changes/REA Code. Key all Code values to the Government's modification numbering system. Any activity or sequence of activities added to the schedule as a result of alleged constructive changes made by the Government may be added to a copy of the current schedule, subject to the approval of the Contracting Officer. Assign Activity codes for these activities with a Contract Changes/REA Code. Key the code values to the Contractor's numbering system. Approval to add these activities does not necessarily mean the Government accepts responsibility and, therefore, liability for such activities and any associated impacts to the schedule, but rather the Government recognizes such activities are appropriately added to the schedule for the purposes of maintaining a realistic and meaningful schedule. Such activities shall not be Responsibility Coded to the Government unless approved. An activity shall not have more than one Contract Changes/REA Code. Contract Changes/Requests for Equitable Adjustment Codes shall be imported through the SDEF conversion of the schedule into QCS/RMS. Manual inputting of. Contract Changes/Requests for Equitable Adjustment Codes into QCS/RMS is prohibited.
3.3.2.9 Contract Line Item (CLIN) Coding (BIDI)
Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN Item Code. CLIN Item code all activities, even when an activity is not cost loaded.