IRI Industry Day_2025_Presentation Slides_5Mar25 Final.pptx
PPTX presentation 36 MB Posted
- Solicitation number
- W912BU25T14ND
About this file
This is a PowerPoint presentation for an Industry Day event on March 5, 2025, regarding repairs to the North Jetty at Indian River Inlet, Delaware, managed by the U.S. Army Corps of Engineers Philadelphia District. The project is a firm-fixed-price construction contract valued between $10-25M with an 18-month period of performance, anticipated solicitation issuance on August 4, 2025, and award by December 4, 2025, using Best Value Trade-Off procedures.
The scope includes selective removal of existing sand and stone (5,100 CY), installation of stone stabilization within inlet channel (27,500 tons), marine mattresses (33,000 SF), bedding stone (710 tons), core stone (1,500 tons), new capstone (31,000 tons), rehandling existing capstone (4,100 tons), and installing new steel railing (50 LF). The work involves complex coastal engineering in a dynamic environment with steep slopes. The presentation includes detailed technical specifications, geotechnical analysis, and construction requirements. Contractors must submit questions by March 14, 2025, to Connor.A.Struckmeyer@usace.army.mil. The Industry Day event will be held at Delaware Seashore State Park, with registration required by March 3, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sign-In Sheet_IRI Industry Day_5Mar2025.pdf | ||
| Questionnaire - Industry Day_Indian River Inlet.docx | DOCX document | |
| Industry Day Announcement Indian River Inlet_2025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Indian River Inlet, DE North Jetty Repairs Industry Day March 5, 2025
Monica Chasten Project Manager Operations Division
Connor Struckmeyer Contract Specialist Contracting Division
Eric Huefner Design Manager Engineering and Construction Division
Jeff McAleer Chief, O&M Contracts Section Operations Division
Introductions Indian River Inlet, DE Overview Scope Review for North Jetty Repairs Industry Day Questions Contractor Questions Meeting Agenda
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
CONTRACTING’S BRIEFING
The Government assumes no responsibility for any conclusions or interpretations made by the prospective Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of any contract, unless that understanding or representation is expressly stated in a contract.
The information in these slides are subject to change prior to Solicitation.
Firm Fixed-Price Construction Contract
Disclosure of Magnitude of the Proposed Construction Project: Between $10-25M
Total Period of Performance: 18-Months
Anticipated Solicitation issuance 4 August 2025
Anticipated Award by 4 December 2025
Best Value Trade-Off (BVTO); FAR Part 15 procedures
Slides and Attendance listed to be published on SAM.gov
Comments are ENCOURAGED.
If providing responses to the Industry Day questions electronically, please send them to Connor.A.Struckmeyer@usace.army.mil no later than 2:00 PM EDT on 14 March 2025.
There will be a question and answer session after the Solicitation is issued.
Project authorization Navigation project authorized in 1937 and modified in 1945
Authorization includes stabilizing the inlet by construction of parallel jetties 500 ft apart; the dredging of a channel generally 200 ft wide and 15 ft deep from the inner ends of the jetties to a point in the Bay substantially 7000 ft from the ocean shoreline……then about 8200 ft to highway bridge at Millsboro, 60 ft wide, 4 ft deep.
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
Indian River Inlet OVERVIEW
North Jetty
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
Indian river inlet OVERVIEW
North Jetty
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
Fiscal Year 2023 contract solicitation proceeded with North Bulkhead and South Jetty repairs since north jetty required further evaluation; Bulkhead/South Jetty Contract to be complete in Spring 2025
Conducted hydrodynamic modeling focused on north jetty using the Coastal Modeling System (USACE’s Engineering Research and Development Center)
Data Collection Efforts Hydrodynamic data (Summer 2023) Inlet bathymetry & topo surveys (periodic) Geotechnical data & modeling (2024)
Indian River Inlet North Jetty Repair
GEOTECHNICAL ANALYSIS
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
GEOTECHNICAL ANALYSIS
Initial Phase of Subsurface Exploration Land-Based Six CPT Soundings with Vane Shear Testing in Clay Stratum Four SPT Borings
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
Soil Stratigraphy from Land Borings Upper Sand Extends to 35 to 46 feet below grade Loose to Medium Dense in Upper 15 to 20 feet Medium Dense to Very Dense Beneath
Clay Extends to 60 to 92 feet below grade 25 to 47 feet Thick Very Soft to Stiff Consistency Lower Sand Extends to Investigated Depth Medium Dense in Upper Zone Dense to Very Dense in Lower Zone
Eastern-Most Boring (KFB-35) Used For 60% Design Soil Profile
Slope Stability Analysis Sections
STA 08+00 – Jetty Trunk & Deep Scour STA 11+00 – Approx. Midway Between Scour & Ridge STA 13+00 – Shoaled Ridge STA 17+00 – Original Jetty Tip
Slope Stability Analysis
Design Approach Capstone Modeled as Surcharge Load Live Load Surcharge Applied to All Cases 500 psf During Construction 300 psf Post Construction Crest Elevation Varies Along Length of Jetty EL +7.0 at Trunk EL +4.0 at Tip
Design Challenges Proximity to Deep Scour Thick Stratum of Soft Clay Alignment Offset Limitations
Existing Conditions – STA 08+00 Existing Conditions – STA 17+00
Key Elements of Selected Design Offset Jetty Alignment 15 Feet North Reinforce Submerged Scour Slope with Stone Buttress
PROJECT OVERVIEW / STAGING & ACCESS
North Jetty Repair Components Selective removal of existing sand and stone Installation of “stone stabilization” within inlet channel Rehandling of existing capstone to allow for better interlocking of new stone Installation of corestone up to capstone bottom elevation Installation of bedding stone in select locations to provide an even subgrade for marine mattress installation Installation of marine mattresses where capstone will not bear on existing stone Installation of two-layer capstone crest Installation of new steel railing
PROJECT OVERVIEW
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
EXISTING CONDITIONS AND DEMOLITION
PLAN – STA 6+50 TO STA 12+50
PLAN – STA 12+50 TO STA 15+00
PROFILE VIEW
N jetty repair (DEMOLITION section)
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
N jetty repair (typical section)
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
CROSS-SECTION WITH STONE STABILIZATION
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
NORTH jetty repair
| Scope of Work (PRELIMINARY) | Estimated Quantity |
| Removal and disposal of sand and stone | 5,100± CY |
| Demolish and dispose of watch tower foundation | 1 LS |
| Install stone-filled marine mattresses (9” thick) | 33,000± SF |
| Install bedding stone (W50 = ) | 710± tons |
| Install core stone (W50 = 1.2 tons) | 1,500± tons |
| Install new capstone (W50 = 12 tons) | 31,000± tons |
| Rehandle existing capstone | 4,100± tons |
| Install stone stabilization within inlet channel (W50 = 0.5 tons) | 27,500± tons |
| Install new steel railing | 50 LF |
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
Industry day questions
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
DISCLAIMER: Information discussed today is subject to change prior to Solicitation.
1. To what extent is waterborne work likely to be required for the North Jetty repair?
2. If waterborne work is necessary, what are the best locations to load barges at the inlet?
3. How will rock be transported to the site from the quarry (trucking, barge, etc.)? What size vehicles will be used to transport materials to the site?
4. Please provide feedback regarding the staging and access shown, particularly regarding access under the SR 1 bridge over Indian River Inlet. Does the bridge pose any problems with mobilization and use of a large crane?
5. Does available construction equipment permit excavation and relocation of material from the north side of the jetty at the reach and depth depicted?
6. Is it feasible to excavate and construct the rubble mound structure toe as shown, where a significant amount of sand will need to be removed adjacent to the north side of the existing structure?
7. Describe contractor means and methods for jetty construction in general (i.e. rock handling, land-based or barge-based operations.
8. Describe methodology for placement of submerged stone stabilization feature. From a long-term maintenance standpoint, how would you maintain and replenish the “stone stabilization” within the inlet channel over time?
9. Do you have concerns about the feasibility of filling and installing marine mattresses in this application (including required excavation prior to mattress placement)?
10. Discuss feasibility/experience with construction of temporary works (e.g. trestle structures) to facilitate jetty construction.
11. Describe contractor means and methods to deal with construction surcharge load restrictions if deemed necessary by USACE.
12. Can you estimate an average productivity rate (# of 12-ton capstone placed per day)?
13. Do you have a rough estimate of construction duration, assuming a spring start?
14. Do you have any other constructability feedback on the repair project as designed?
CONTACT INFORMATION
Please contact Connor Struckmeyer with any questions: connor.a.struckmeyer@usace.army.mil
This is a Special Notice and is for planning purposes only as defined by FAR 15.201. This is not a solicitation announcement, nor is it an Invitation for Bid (IFB), Request for Proposal (RFP), or Request for Quote (RFQ). No solicitation is currently published. Participation in this conference by any party does not obligate the Government in any contract award. The Government will not pay for the provision of any information, nor will it compensate any respondents for the development of such information. The Government is not responsible for any costs associated with reviewing the Draft Documents, preparing and submitting comments, or any other efforts towards participation in this conference. Furthermore, the Government is not obligated to compensate respondents for any information received, even if the Draft Documents are revised as a result of a respondent’s comment or question. Respondents should refrain from providing proprietary information in the course of the conference, since any information acquired by the Government in this forum will not be treated as proprietary. The information gathered will be used by the Government to make appropriate acquisition decisions. Replies to responses, comments, or suggestions will not be provided or published.
Closing image4.png image8.png image9.png image10.png image11.emf image12.jpeg image13.jpeg image14.jpg image15.jpg image16.emf image17.png image18.png image19.jpeg image20.png image21.png image22.png image23.png image24.png image25.png image26.png image27.png image28.jpg image29.png image30.png image31.png image32.png image1.png image2.png image3.png image7.png