This document is a Statement of Work (SOW) for the modification of the U.S. Army Corps of Engineers (USACE) Dredge HURLEY, a diesel electric dustpan dredge. The SOW describes the work required to replace the three main diesel generator sets and make modifications to the associated auxiliary equipment. Key details include:
The contract consists of two phases - Phase I for shipyard preparation and Phase II for repower execution, installation, and testing. The contractor is responsible for developing a detailed design based on the provided contract design drawings and specifications, and must obtain ABS approvals for any deviations. Major work includes removing and replacing the generator sets, exhaust system, cooling water system, fuel oil system, and compressed air system. The contractor will also modify the walkways, railings, gratings, insulation, and electrical systems. Government-furnished equipment includes the new generator sets. The contractor must follow all applicable USACE, ABS, USCG, and other regulatory requirements. The work is for the Philadelphia District of the USACE.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART I - THE SCHEDULE - SECTION C
DESCRIPTION/SPECIFICATION/WORK STATEMENT
C000 CONTRACT MANAGEMENT 3
C001 GENERAL DESCRIPTION OF WORK 3
C003 DESIGN & INSTALLATION STANDARDS 4
C004 CLASSING & CERTIFICATION 4
C005 VESSEL IDENTIFICATION 5
C010 DEFINITIONS 6
C025 CONTRACTOR QUALITY STANDARDS 7
C040 SCOPE OF WORK 10
C041 CARE OF VESSEL 14
C043 VESSEL SHIP CHECK AND INSPECTION 16
C045 ACCESS TO EQUIPMENT & MACHINERY 16
C100 SCIENTIFIC 17
C115 WEIGHT ESTIMATE & INCLINING EXPERIMENT 17
C170 BERTHING, DRYDOCKING, AND SERVICES 17
C180 NOISE AND VIBRATION 18
C200 ARRANGEMENTS 18
C201 GENERAL 19
C245 MACHINERY ARRANGEMENT 19
C300 STRUCTURE 19
C301 GENERAL 20
C305 STRUCTURAL MODIFICATIONS 20
C320 CONDENSATE COLLECTION TANK 21
C330 FOUNDATIONS 22
C400 OUTFIT 23
C406 COATING SYSTEM 23
C425 WALWAYS, RAILINGS, & GRATING 24
C436 INSULATION & SHEATHING 25
C460 NAMEPLATES, NOTICES, & MARKINGS 25
C500 SPECIAL FEATURES 25
C501 REMOVAL OF EXISTING EQUIPMENT 25
C517 MONORAILS MODIFICAITONS 32
C600 MACHINERY 34
C601 GENERAL REQUIREMENTS FOR PIPING SYSTEMS & MACHINERY 34
C630 FUEL OIL SYSTEM 38
C637 LUBE & WASTE OIL SYSTEM 39
C640 COOLING WATER SYSTEM 39
C650 EXHAUST SYSTEM 41
C665 POTABLE WATER SYSTEM 43
C669 CONDENSATE DRAINAGE SYSTEM 43
C685 GENERATOR ROOM VENTILATION SYSTEM 45
C690 COMPRESSED AIR SYSTEM 46
C700 ELECTRICAL 48
C701 GENERAL 48
C705 AC ELECTRICAL SYSTEM 49
C710 ELECTRICAL LOAD ANALYSIS 50
C715 FAULT CURRENT ANALYSIS & CIRCUIT BREAKER COORDINATION STUDY 50
C720 ONE-LINE DIAGRAM 51
C725 CABLE SCHEDULE & VOLTAGE DROP 52
C730 LIGHTING & RECEPTACLES 53
C733 ELECTRICAL POWER PLANT 54
C740 SWITCHBOARD & POWER CONTROL 54
C750 MOTORS AND PUMPS ELECTRICAL MODIFICATIONS 65
C780 MONITORING, ALARM & CONTROL SYSTEM 67
C800 SPARE PARTS 84
C801 SPARE PARTS LIST 84
C000 CONTRACT MANAGEMENT
C001 GENERAL DESCRIPTION OF WORK
A. GENERAL
The work required by this Contract consists of the modification of the Dredge HURLEY, a USACE Dustpan dredge.
These specifications call for the replacement of the three (3) main diesel generator sets and modifications to the associated auxiliary equipment.
Replacement of the main generator sets requires extensive structural, mechanical, and electrical removal and renewal.
Prospective offerors are strongly urged to visit the vessel prior to submitting a bid in order to gauge the condition of the vessel and the scope of temporary removals for access that must be performed by the Contractor. Pre-Bid Vessel Inspections shall be conducted prior to offers in accordance with Contract Section H21.
The planning, coordination, and performance of all work for the ultimate completion of all specification requirements contained herein shall be the responsibility of the Contractor. All labor and materials necessary to accomplish the specified work shall be furnished by the Contractor except where explicitly stated as being Government Furnished Materials (GFM) or Government Furnished Equipment (GFE). GFM/GFE listing is included in Section H16 of this contract.
B. VESSEL CHARACTERISTICS
Characteristics of the vessel, as it currently exists and as it shall be upon re-delivery, are tabulated below. Existing dimensions and characteristics are approximate and are provided for descriptive purposes only.
LOA: ...................................................................................... 348-ft, 6-in
Beam (overall) ............................................................................... .. 58-ft
Draft (static hull borne) ...................................................................... 7-ft
Depth (molded amidships) ............................................................. .. 11-ft
Lightship Displacement .............................................................. 2865 LT
Diesel Electric Powerplant Engines:
Current ............ 3 x General Electric Model 7FDM16 diesel engines New ....................... 3 x Wabtec Model 12V250MDC diesel engines
Diesel Electric Powerplant Alternators:
Current ........................ 3 x General Electric Model 5ATI generators New ............................... 3 x AvK Model DSG 125 M2/8 generators
Total Installed Propulsion HP ......................................................5850-hp
Total Dredge Pump HP: ..............................................................4400-hp
Hull Construction ................................................................ Welded Steel
The above tabulations shall not in any way limit the responsibility of the Contractor to perform all work and furnish all plant, labor, and materials required by these Specifications, the Government Furnished Drawings, and other documents referenced within these Specifications.
C003 DESIGN & INSTALLATION STANDARDS
The design, modification, repair, and outfitting of this vessel shall comply with all applicable rules, in the following publications, of current issue, in effect on the date the Contractor submits their offer, including any revisions published in the federal register prior to that date.:
• U.S. Army Corps of Engineers (USACE), Publication No. EM 385-1-1; "Safety and Health Requirements
Manual."
• American Bureau of Shipping (ABS) – "Rules for Building and Classing Marine Vessels"
• International Association of Classification Societies (IACS) No. 47 “Shipbuilding and Repair Quality
Standard”.
• U.S. Coast Guard Regulations (USCG) 33 CFR, Subchapter P, Part 164 – Navigation Safety Regulation
• U.S. Coast Guard Regulations (USCG) 40 CFR, Subchapter C, Part 89 – Protection of Environment:
Control of Emissions from New and In-Use Nonroad Compression Ignition Engines
• U.S. Coast Guard Regulations (USCG) 40 CFR, Subchapter C, Part 94 – Control of Emissions from
Marine Compression Ignition Engines
• U.S. Coast Guard Regulations (USCG) 46 CFR, Subchapter I – Cargo and Miscellaneous Vessels
• U.S. Coast Guard Regulations (USCG) 46 CFR Subchapter J – Electrical Engineering
• U.S. Coast Guard Regulations (USCG) 46 CFR Subchapter F, Part 62 – Vital System Automation
• U.S. Coast Guard, Navigation Rules and Regulations, International and Inland, COMDTINST M16672.2D
• U.S. Coast Guard, Navigation and Vessel Inspection Circular (NVIC) No. 7-68, “Notes on Inspection and
Repair of Steel Hulls”
• U.S. Maritime Administration Schedule for Pipes, Joints, Valves and Fittings
• United States Public Health Service (USPHS) Publication No. 393 "Handbook on Sanitation of
Vessel Construction"
• Institute of Electrical and Electronic Engineers Standards, Publication No. IEEE-45
"Recommended Practice for Electrical Installations on Shipboard"
• Institute of Electrical and Electronic Engineers Standards, Publication No. IEEE-519
"Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems"
• National Electrical Code (NEC)
• SNAME Technical & Research Bulletin 2-25 Ship Vibration and Noise Guidelines
• American Welding Society (AWS) "Guide for Steel Hull Welding", ANSI/AWS D3.5-85
All electrical equipment and material installations shall comply with applicable IEC, IEEE, NEMA, ANSI and NEC standards and codes. All equipment and material furnished shall bear the approval of the Underwriters Laboratories where applicable.
C004 CLASSING & CERTIFICATION
A. GOVERNMENT FURNISHED ABS DRAWINGS
As part of this solicitation, the Government has submitted to ABS the drawings for the structural modifications, generator engine foundation modifications, auxiliary system modifications, and electrical system modifications for review for the purpose of obtaining an issuance of a Statement of Fact that the modifications meet ABS requirements.
The Contractor is not responsible for any changes to the design as a result of ABS comments on the drawings provided to the Contractor. The Government will resolve all “technical” ABS comments. The Contractor shall be responsible to clear all “surveyor” ABS comments during the repowering work.
B. CONTRACTOR’S ABS DRAWING APPROVAL RESPONSIBILITY
Any drawings and/or design documents developed and performed by the Contractor due to deviations from the Contract Design approved by the COR as detailed in Contract Clause C040.F shall be submitted to ABS to obtain a Statement of Fact that they meet ABS requirements.
The recommended ABS point of contact is Mr. Rich Delpizzo, who can be reached by phone, email or mail, at: (703) 201-5489, RDelpizzo@eagle.org, or 1525 Wilson Blvd, Suite 625, Arlington, VA 22209.
The HURLEY’s ABS Identification Number is H-9302332.
C. ABS STATEMENT OF FACT LETTERS
The Contractor shall provide all labor and services required for an ABS Statement of Fact Letter, documenting that all work has been performed in accordance with the ABS approved drawings for this contract.
The Statement of Fact Letter shall document the following:
• All vessel modifications are adequate for river service and are in accordance with the approved construction drawings and all standards listed in C003.
D. ABS SUBMITTAL PROCESS AND CORRESPONDENCE
The Marine Design Center (CEMDC) will be the “Owner’s Representative” on this project and all correspondence with ABS shall be made available to the COR. In order to facilitate the communication process and reduce the paperwork burden on all parties, the Contractor, and all sub-contractors, shall utilize the ABS Eagle Construct Engineering Manager Portal (02E) for all drawing submittals and correspondence. The Contractor and all sub-contractors shall make the necessary arrangements with ABS to ensure that the Marine Design Center is granted the following Oversight Permissions for this Contract:
• View project and drawing status
• View comments
• View transmittals
• Download approved drawings and review letters
• E-Mail notification of approval
• E-Mail notification of transmittal
• Status
• Disclaimer
The Marine Design Center’s ID/WCN number is 615255 and the point of contact with respect to the ABS Coordination/Engineering Manager Portal (O2E) is Mr. Tim Keyser, Timothy.J.Keyser@usace.army.mil, phone:
(215) 656-6171.
At the completion of the ABS review process, the Contractor shall download all ABS “Eagle Stamped” drawings and provide them electronically as a set to the Government in .pdf format. This set shall only contain drawings that the Contractor developed and submitted to ABS.
The MDC shall be copied on all correspondences with ABS that are not transmitted through the O2E portal.
C005 VESSEL IDENTIFICATION
The following hull numbers have previously been established:
MDC Hull Number MDC Project Number ABS Identification Number ...................... H-9302332
The Contractor shall use the MDC Hull Number and MDC Project Number for identification of all project documents being submitted to the Government. The ABS Identification Number is provided to facilitate coordination with ABS.
mailto:RDelpizzo@eagle.org mailto:Timothy.J.Keyser@usace.army.mil
C010 DEFINITIONS
The following definitions are applicable to phrases and acronyms used throughout this contract:
• ABS – Acronym for American Bureau of Shipping
• BSR – Acronym for BRUCE S. ROSENBLATT & ASSOCIATES, LLC, the Governments’ AE Contractor responsible for the Contract drawings and other surveys and reports.
• CFR – Acronym for Code of Federal Regulations - a codification of the general and permanent rules published in the Federal Register by the Executive departments and agencies of the Federal Government.
• CONTRACT DESIGN – The Contract Drawings and Specification present the configuration and functionality of the diesel generator set replacements and auxiliary systems modifications. They do not depict a detailed design from which a Contractor would be able to build directly from the drawings.
• CONTRACT DRAWINGS – Drawings that, along with the specification, define the scope of work using a final level of design. The Contract Drawings are intended to be used as the starting point for completing the design development detail of the detailed design.
• CONTRACTOR – A firm holding a prime Contract with the Government for execution of the work called for in these Specifications.
• COR – Acronym for Contracting Officer’s Representative - a member of the Contract management and quality assurance team authorized by the Contracting Officer to perform certain administrative and managerial duties.
A copy of the COR’s authority letter is furnished to the Contractor.
• DAY – All mentions of “days” in this contract specification refers to calendar days.
• DETAILED DESIGN – A design package developed from the provided Contract Design that includes the following:
• Drawings developed from Contract Drawings with a level of detail suitable for construction
• Equipment selections based on the sizing defined in the Contract Design
• Supporting calculations to verify that each system design and selected equipment meet the contract requirements
• K.O. – Acronym for Contracting Officer - A person with the authority to enter into, administer and/or terminate Contracts and make related determinations and findings.
• ECR – Acronym for Engine Control Room
• EDG – Acronym for Emergency Diesel Generator Set
• EGR – Acronym for Exhaust Gas Recirculation
• Genset – Abbreviation for Diesel Generator Set
• GE EGR – Acronym for General Electric Engine Generator Regulator – The control system currently installed controls for the existing GE Gensets.
• GFE – Acronym for Government Furnished Equipment - Equipment or components furnished by the Government to the Contractor for installation aboard the vessel.
• GFM – Acronym for Government Furnished Material - Material furnished by the Government to the Contractor for processing or fabrication, and eventual installation aboard the vessel.
• GOVERNMENT – The United States Government.
• ICMS – Acronym for Integrated Control and Monitoring System
• MAJOR COMPONENT – Any component that is not available “off-the-shelf”, significant in cost, and/or may require a long lead time.
• MCC – Main Control Console
• MDC – Acronym for the Marine Design Center; US Army Corps of Engineers; Philadelphia, Pennsylvania.
• MVM – Acronym for Memphis District; US Army Corps of Engineers; Memphis, Tennessee
• NCE – Acronym for Noise Control Engineering, a subcontractor of BSR responsible for noise and vibration surveys and reports during this project.
• NTP - Acronym for Notice to Proceed. Authorization from the KO to initiate work which is issued after Award of Contract and receipt of bonding.
• P/S - Acronym for Port and Starboard.
• REFERENCE DRAWINGS – Drawings, reports, calculations, manuals, and other documentation provided to the Contractor for correlative information only. The Government assumes no responsibility for the accuracy of the reference drawings, and all work shall be measured or templated from the ship by the Contractor.
• UPS – Acronym for Uninterruptible Power Supply
• USACE - Acronym for United States Army Corps of Engineers.
• VFD – Acronym for Variable Frequency Drive
C025 CONTRACTOR QUALITY STANDARDS
The Contractor shall be responsible for the completion of a functioning vessel. The Contractor shall be responsible for the quality of all work performed. Inspection by the Marine Design Center is for the purpose of verifying the proper function of the Contractor's quality control measures and is not to be used as a substitute for control of quality by the Contractor.
B. STANDARD PARTS AND MATERIALS
All articles, fittings, equipment, machinery, supplies, and materials used in the construction and outfitting of the vessels shall be new, of the highest grade, free from defects and imperfections, and be the standard product of reputable manufacturers, to the maximum extent practicable. Any material not specified shall be the best of their kind for the purpose intended. All items shall be suitable for workboat application and meet the latest requirements of standard specifications published by national authorities. No salvaged materials shall be used in the works. Spare parts and service shall be readily obtainable.
C. WORKMANSHIP
All labor shall be especially skilled for the type of work they are performing. Work shall be thorough and complete, and shall be performed under competent direction. Where work of one trade joins, passes through, or is integral with other work, there shall be no discrepancy or misfit when completed. When engaging one kind of work with another, marring or damaging of previously acceptable construction shall be cause for rejection of previously accepted work.
All parts of work intended to join or bear upon others shall be complete and solid surface contact and fit together neatly without excessive cold work during erection.
All faying surfaces shall be painted and shall be clean and smooth before bolting up. Shims or liners shall not be used for the purpose of overcoming a bad fit.
Ends of outstanding flanges shall be cropped. Lightening holes may be punched or flame-cut. All edges shall have burrs removed.
All holes for machinery mounting bolts shall be drilled or punched; burning is not acceptable. Holes in members having sharp curvature shall be avoided.
The Contractor shall be responsible for all damages caused by their employees and subcontractors while performing all work required in this specification. The Contractor shall repair and/or replace all damaged equipment, parts, or structures without any cost or charge to the government.
D. WELDERS
All welding under this contract shall be done only by welders who have successfully passed qualification tests accepted by the American Bureau of Shipping (ABS) or other regulatory agency acceptable to ABS. The Contractor shall bear the expense of conducting these tests and shall certify by name to the Contracting Officer welders who have successfully passed the prescribed tests and hold current, valid certifications.
The list of certified welders shall be submitted during Phase I of the Contract. The list shall include the employee’s name, certification(s), and date(s) of the most recent tests for each certification(s). This list shall be named and numbered 368-F025-01 LIST OF CERTIFIED WELDERS.
The Contractor shall require any welder to repeat these tests when, in the opinion of the COR, the work of the welder indicates a reasonable doubt of their proficiency. In such cases, the welder shall be re-certified as above if they successfully passed the retest; otherwise, they shall be disqualified until they have successfully passed the retest.
The Contractor shall maintain records of the individual welder’s certification for the duration of the Contract. The records shall be available for examination upon request of the Contracting Officer or their representative.
E. WELDING
All welding shall be in accordance with the current rules of the American Bureau of Shipping (ABS) and American Welding Society (AWS), except where otherwise stated. All welding equipment used for the contract work shall be of a modern type subject to close control. The electrodes used throughout the work shall be suitable for use with the parent metal at each weld and shall be approved by ABS.
Welding procedures, as to direction, length, numbers, and sequence of beads, shall be carefully planned to minimize lock-up stresses. Care shall be exercised to produce smooth even beads, especially on all exposed plating and fittings.
Beads shall be ground where directed by the Contracting Officer or their authorized representative.
The Contractor shall employ appropriate welding procedures and grounding connections to preclude the possibility of anodic erosion of the hull after launching.
A detailed description of all welding procedures being employed in the construction shall be available to the Contracting Officer or their authorized representative.
F. INSTALLATION
Materials and equipment shall be installed in accordance with the approved recommendations of the manufacturer, and in compliance with the contract documents. The installation shall be accomplished by workmen skilled in their specific trade.
G. THREADED FASTENERS
Where the material, size, and type of fastener is specified on the Contract Drawings, that type, size, and material shall be used. For all other conditions the following requirements apply:
Bolts and machine screws of 3/8 inch in diameter or greater shall be used for structural applications. Bolt hole diameters shall not exceed bolt diameters by more than 1/32 inch for bolts up to and including 3/4 inch in diameter and 1/16 inch for bolts over 3/4 inch in diameter. Bolt ends shall protrude from the nuts not less than one (1) nor more than three (3) threads. The excess bolt length shall be removed without damaging the bolt threads.
One washer shall be used under each nut.
Where hardware (such as joiner hardware and hinges) is pre-drilled for fastenings sized less than 3/8 inch diameter, the size of fastenings used shall match the size of the pre-drilled holes in the part.
Fastenings for metal parts shall be of a similar material as the part except that:
1. Fastenings in aluminum parts shall be corrosion resistant steel.
2. Brass fastenings shall not be used.
Stainless steel fasteners shall be provided with insulating bushings and grommets for connections where dissimilar metals are attached to aluminum.
Where nuts will become inaccessible after modification of the vessel, nuts shall be prick-punched or peened to prevent backing off. All other nuts shall be self-locking.
Countersinking for fasteners shall be as specified by the fastener manufacturer. Fastening patterns shall be well arranged and consistent.
H. PLATE FAIRNESS
Steel plating shall be installed using proper welding procedures and sequences to insure fair plating panels with minimum distortion. The use of filler materials to surface unfair areas is not acceptable. Maximum allowable plating distortion is depicted in the “Shipbuilding and Repair Quality Standard” from IACS. Distortion shall not exceed the amounts in this guide.
I. CONSTRUCTION STANDARDS
All material, machinery and equipment shall be new, of current manufacture, and suitable for the marine service intended. Spare parts and service shall be readily obtainable.
All material, unless otherwise specified in this specification or in the drawings, shall be of commercial quality to ASTM, ANSI, or SAE specifications.
During modification and before delivery, the Contractor shall be responsible for protection of all material, equipment, etc., intended for the vessel.
The overweight tolerance of members shall be within the limits defined by the specifications of the American Society for Testing and Materials (ASTM).
All materials shall be free of imperfections due to manufacturing processes and from defects which adversely affect appearance or serviceability.
All plating shall be neatly cut, fitted, and welded. All sharp edges or projections which constitute a personnel hazard shall be removed or ground smooth. All notches shall have a radius to prevent stress concentrations.
Where aluminum must be attached to dissimilar metals or between dissimilar alloys of aluminum, fasteners shall be stainless steel of an approved design with insulation as required to eliminate metal to metal contact.
All galvanizing shall be done after fabrication by the hot dip process, and the zinc shall be not less than 98% pure. In instances where some types of metals cannot be hot dip galvanized, zinc silicate coating may be substituted.
C040 SCOPE OF WORK
A. CONTRACT INTENT
These specifications, in conjunction with the Contract Drawings listed in Contract Section J01 “Contract & Reference Drawings”, contain the requirements for the modification of the Dredge HURLEY, and describe the essential features, functions, and arrangements of the design.
These specifications and Contract Drawings form a “Contract Design” for the subject vessel. The design package provides the Contractor with enough information to bid on the solicitation, and develop a final design for vessel modification, and minimize uncertainly and risk.
The Contract Design package also includes ABS review and approval of drawings as described in Clause C004.A.
B. CONTRACT PHASES
After the Contract is awarded, the services to be provided by the Contractor shall be structured and managed by the Marine Design Center, in the two phases as follows:
Phase I ...................................................... Shipyard Preparation Phase II ............... Repower Execution, Installation, and Testing
During all phases of this Contract, the Contractor is authorized to use the services of Subcontractors performing under their direction and supervision. However, the Contractor shall assume the full responsibility for the Subcontractors’ work.
1. Phase 1 Shipyard Preparation
During Phase I of the Contract, the Contractor shall conduct a ship check, develop a Detailed Design for the diesel generator set replacements and auxiliary systems modifications, order long lead equipment and materials, conduct production engineering, prepare to receive and store GFE, and prepare to receive and drydock the vessel for the execution of the repower work.
The Detailed Design shall be based on this specification and the Contract Drawings listed in Contract Section J01 “Contract & Reference Drawings”.
The Contractor shall perform a ship check during phase I for the purpose of gathering information from the vessel and its crew necessary to aid in the development of the Detailed Design. See Contract Section C043 for details of the ship check.
2. Phase 2 Repower Execution, Installation, and Testing
During Phase II of the Contract, the Contractor shall modify the vessel, prepare "As-Built" drawings of the affected areas of the vessel, and test the vessel.
Please refer to Contract Section H03 “Contract Submittals” of this Contract for an outline of the deliverables required in each phase of the Contract.
C. DESIGN DEVELOPMENT
These specifications and Contract Drawings form a “Contract Design” for the vessel modification. All Contract Drawings enclosed herein detailing the arrangements, structure, outfitting, mechanical and electrical systems of the vessel have been submitted to ABS for review.
The arrangements, structural modifications, mechanical systems modifications, and electrical systems modifications have been engineered to a contract level design that meets the performance and operational requirements of the U.S.
Army Corps of Engineers.
This package has been engineered to the degree shown based on commercially available equipment.
The level of development is intended to limit the Contractor’s uncertainty and risk. This package is not a detailed design and is not intended to be substituted as detailed design drawings and documents.
D. CONTRACTOR’S RESPONSIBILITY
The Contractor shall be required to complete a detailed design as described herein to satisfy the requirements of this Contract.
Should the Contractor find any issues with the engineering and design of the vessel modification as it relates to this solicitation and Contract Drawing package, the Contractor shall bring it to the attention of the COR for resolution. If necessary, an appropriate contract modification will be developed to address the issue.
The Contractor shall be required to perform engineering and design such as development of secondary structure and foundations, piping and cable routings, miscellaneous details, complete materials lists, purchase specifications, shop drawings, construction details, “As-Built” drawings, and other engineering and technical development necessary to support their administration, operation, and production practices.
The Contractor assumes complete responsibility for modifying the vessel to meet the intent and requirements of this Contract. Should the Contractor determine at any time that they are unable to fulfill those design responsibilities, they shall notify the COR immediately of the problem experienced and their proposed manner of correction.
The Contractor’s price shall include all costs associated with the complete design and the cost to provide a fully functional integrated product in accordance with the Contract Design, including its plans, specifications, and drawings.
E. DRAWINGS
1. Contract and Reference Drawings
Contract Drawings and Reference Drawings that are part of this solicitation are listed in Contract Section J01 “Contract & Reference Drawings”. All Contract and Reference Drawings will be available to the successful bidder in CAD format.
Contract Drawings are provided with the specifications for bid purposes as well as to develop the detailed design. All features of the Contract Drawings must be complied with. The Contract Drawings have been designed in accordance with ABS Rules as per Contract Clause C004 and the performance specification of this solicitation. These drawings have previously been submitted to ABS for review. Where necessary, the Government has made revisions to the Contract Drawings in response to ABS technical comments. The drawing revisions provided in this package are either the revisions submitted to and reviewed by ABS, or they have been revised in response to a technical comment.
The Reference Drawings that are part of this solicitation are provided to the Contractor for correlative information only. The Contractor shall not build from any Reference Drawing. It is the responsibility of the Contractor to use this written specification, the Contract Drawings, and measurements from the vessel to properly develop the detailed drawings and modify the vessel. The Government assumes no responsibility for the accuracy of the reference drawings, and all work shall be measured or templated from the ship by the Contractor.
2. Drawings Required
Contract Section J, Clause J01, Contract & Reference Drawings, provides a complete list of Contract Drawings and Reference Drawings.
Contract Section H, Clause H21, Engineering and Drawings, contains a list with the minimum drawings required to be finalized and/or developed during the Phase I of the Contract in order to complete the final design. The requirements for developing the final design drawings are also delineated in Clause H21 with any specific requirements for structural, mechanical, or electrical changes defined in their relevant Contract Clauses.
For clarification purposes, the list in Contract Clause H20 details the drawings by action groups. The action groups distinguish between separate categories based upon the engineering requirements to be completed by the Contractor.
The following is a description/definition of these categories:
• Drawings To Be Finalized: As part of the scope of work for this effort, the Contractor shall be required to finalize a certain number of Contract Drawings to achieve a Final Design as defined above. These drawings have been included as Contract Drawings. The scope and extent of the necessary finalization has been explained in detail in each WBS section.
• Drawings To Be Developed: The Contractor shall also be required to develop a certain number of drawings to achieve a Final Design to conform to the requirements of this solicitation. These drawings have been identified on the drawing index but do not currently exist. These drawings shall be submitted to the Government for review and approval.
• “As-Built” Drawings: The Contractor shall be required to provide updated “As-Built” drawings of the affected areas of the vessel. The requirements for the “As-Built” drawings are defined in Contract Clause H21.
F. DEVIATIONS FROM THE CONTRACT DESIGN
Should the Contractor desire to deviate from the Contract Design, they shall submit their request in writing to the COR. The proposed deviation shall keep the intent of the general description of work as described in Contract Clause C001.A and the rest of these specifications.
Each proposed deviation request shall be accompanied with a detailed analysis and comparison of the equipment, material, or arrangement specified, and the equipment, material, or arrangement proposed, including features, dimensions, performance characteristics, benefit to the Government, and compelling reason why the deviation should be made. The request shall include at a minimum:
• Desired deviation
• Reason for the deviation
• Detailed analysis (as stated above)
• Impact on schedule
• Impact on cost
• Impact on weight, draft, and trim.
• Impact of regulatory review
• Supporting documentation (i.e. cut sheets, engineering drawings, photos, etc)
In the absence of compelling reasons for making the deviation, the Contractor’s proposal may be denied.
The Government will review the request and render a decision within 10 days of receipt. If approved, the Contractor shall be responsible for any cascading effects on the design, drawings, or scientific reports as determined by the Government. The Contractor shall be responsible for integrating the deviation into the design at no increase in contract cost and no extension of contract completion.
The Contractor bears ultimate responsibility for satisfactory performance of all systems and arrangements affected by approved deviations as well as the operation of the completed vessel, as affected by the deviation.
No work deviation shall commence without a written approval from the KO.
If a deviation is approved by the Government, it is the sole responsibility of the Contractor to coordinate with ABS and provide any additional engineering effort to meet the conditions of classifications and this specification.
The Contractor shall bear all costs associated with any requested and/or approved deviations, including engineering, estimating, administrative and overhead, regulatory review and approval, vessel modification, and test and trials.
G. COMPONENTS, SYSTEMS, AND MATERIALS
1. Components
These Specifications in conjunction with the Contract Drawings indicate the quantity of and each major component required to be provided by the Contractor and each major component that will be Government Furnished Equipment.
The Contractor shall provide all components except for those components specifically designated as Government Furnished.
Requirements for Contractor receiving, handling, and care of Government Property, which includes both Government Furnished and Contractor Furnished equipment and components, are contained elsewhere within these Specifications and in Contract Section H.
The quantity of each major component to be provided by the Contractor, together with such data as size, capacity, rating or power, and applicable Government specifications or other technical requirements, can be determined using these Specifications in conjunction with the Contract Drawings. The Contractor shall select equipment and components required to form complete systems based on the performance characteristics provided on the Contract Drawings and as described in this specification. The Contractor shall be responsible for ensuring that each system’s performance is maintained.
The Contractor shall submit cut sheets and details of selected equipment and components to the Government for review and approval during Phase I of the Contract. The Contractor shall submit a Material & Equipment Schedule (M&E) as required in Contract Clause H18.
2. Systems
These Specifications, in conjunction with the Contract Drawings, define the characteristics of each system to be modified or newly installed. They contain additional data such as system capacities and the flexibility and segregation requirements, which will enable the Contractor to prepare construction drawings and build or modify the systems.
3. Pipe and Pipe Fittings.
The Contractor shall provide and install the total number each type of pipe fitting (such as elbows, reducers, etc.) and the length of each type of pipe required to complete the vessel modifications. The numbers of these items will be defined by the Contractor's methods of construction and/or Final Design. Piping system components such as valves, hose connectors, and filters are identified and can be tabulated by the Contractor.
4. Cable and Cable Connectors
The total number of each type of cable, cable connector, and the length of each type of cable to be procured and installed will be defined by the Contractor's methods of construction and/or Final Design.
5. Materials
These Specifications and the Contract Drawings contain requirements for materials of construction and items of machinery, equipment, and outfit, which by their nature may be manufactured or procured as distinct items. These Specifications contain only the requirements and information that pertain to selection, installation, on-board performance, on-board inspection and tests. Requirements such as physical or chemical properties, manufacturer test and inspection requirements, or other requirements applicable only to manufacturers, are contained in other specifications or standards referenced and invoked herein.
The Contractor shall provide all materials required for completion of the work, except for those materials specifically designated as Government Furnished.
The quantity of each type of; structural plate and shape; deck covering; and paint to be procured and installed or applied will be defined by the Contractor's methods of construction and/or Final Design. However, the required material is identified and can be tabulated by the Contractor.
Material quantities shown in the Contract Drawings are based on estimates of the net installed material. No provisions or margins are made to account for material processing, milling, fit up, or temporary jigs.
Requirements for Contractor receiving, handling, and care of Government Property, which includes both Government Furnished and Contractor Furnished material, are contained elsewhere within these Specifications.
6. Other Requirements
The Contractor shall not install materials or components aboard the vessel that contain asbestos.
H. ADDITIONAL ENGINEERING SERVICES
As a minimum, the Contractor shall obtain the services of manufacturer’s representatives to the extent required by these specifications.
The Contractor shall obtain additional engineering services if required for the installation of Government Furnished Equipment and Material, performance of noise surveys, installation and integration of the Integrated Controls and Monitoring System (ICMS), and application of new coatings to the extent necessary to complete the work required by the Contract.
I. OSHA REQUIREMENTS
In addition to any state and local laws and regulations, the Contractor shall satisfy and adhere to occupational safety and health standards for shipyard employment contained in 29 CFR 1915 for all applicable aspects of the modification of the vessel.
J. EPA REQUIREMENTS
In addition to any state and local laws and regulations pertaining to protection of the environment, the Contractor shall satisfy and adhere to federal environmental protection standards.
C041 CARE OF VESSEL
All parts of the vessel including, but not limited to, structure, deck coverings, fittings, equipage, outfit, furniture, insulation, paint work, machinery, auxiliaries, systems, appliances, and apparatus shall be maintained in a satisfactory condition during the entire period the vessel is in the Contractor's possession. During modification, all chips, shavings, refuse, dirt, and water shall be removed weekly, or more often if directed by the COR, including such debris aboard at the time the Contractor takes possession of the vessel.
Rubbish shall be removed from places that are to be permanently closed or which may become inaccessible.
Appropriate measures shall be taken, where necessary, or if directed by the COR, to keep to a minimum wear and damage incident to modification, and to prevent corrosion or other deterioration, especially to unpainted, polished, and moving parts.
The Contractor shall be responsible for freeze prevention of fluids in piping, machinery, and equipment.
The Contractor shall be responsible for preventing condensation on electrical components.
B. VESSEL OUTFIT
The Contractor shall be responsible for the care of all vessel outfit and equipment aboard the vessel starting at the time of vessel delivery to the Contractor’s facility.
The Contractor shall replace, or repair as applicable, all items whose condition has deteriorated during the Contract due to improper care or handling, any items which are damaged during conversion and modification of the vessel, or any items which cannot be located at the conclusion of work. The KO shall be the ultimate arbiter as to gauging the condition of inventoried items.
The Contractor shall submit, for approval, details of components that will be provided as replacements in the event that identical items cannot be procured. Details shall include engineering information and catalog cut-sheets. The KO shall be the ultimate arbiter as to the suitability of Contractor proposed replacement items.
C. MACHINERY AND EQUIPMENT
The Contractor is responsible for the care of all machinery and equipment at their facility, whether furnished by them or by the Government. All parts, especially those having working surfaces or passages or piping for lubricating oil, shall be kept clean and protected during manufacturing, storing, assembly, and after installation. Electric and electronic equipment and machinery shall at all times be protected against dust, moisture, or other foreign matter, electro-static discharge, and shall not be subjected to rapid temperature changes or extremes in temperature. Any item allowed to deteriorate due to lack of care in storage as indicated above, shall, at the discretion of the COR, be subjected to tests, at the Contractor's expense, to determine its condition and, if necessary, replaced at the Contractor's expense.
All preservative applied by the manufacturer shall be left intact (or replaced if necessary) until installation of the machinery or equipment on the vessel. If removal of the preservative is necessary for testing the machinery or equipment prior to installation, the Contractor shall reapply the preservative and protect the machinery or equipment until installed. All preservatives on working parts shall be thoroughly removed prior to operation of the machinery or equipment. Any scarred paint shall be repaired.
Additional storage and handling requirements for GFE and GFM are contained in Section H of this Contract.
D. TANK CLEANING AND GAS-FREEING
Prior to performing any work on the vessel the Contractor shall drain, degrease, clean and gas-free all affected engineering spaces, voids, tanks, and pump rooms in accordance with Sections 06.I and 19.A.08 of EM 385-1-1, "Safety and Health Requirements Manual". All testing and certification shall be performed by a licensed marine chemist who shall furnish the COR with a chemist’s gas-free certificate. Further requirements for gas-freeing are detailed in Contract Clause H05.A.
All waste products removed during the performance of the work above shall become the property of the Contractor and shall be disposed of by the Contractor in an environmentally sound manner.
The Contractor shall maintain safe atmospheres in all spaces for the entire duration of the modification process.
After the completion of modifications, affected tanks and voids shall be cleaned and pass Government inspection before being closed.
At the end of contract work, the Contractor shall reinstall all hatches with new gaskets and bolts as required. Gasket and bolt material shall be similar to the existing.
E. PROTECTION FROM THE ELEMENTS
The Contractor shall provide and maintain complete protection from the elements. Tarpaulins or other suitable coverings shall be utilized to preclude the entrance of rain or snow into all interior portions of the vessel. Protection shall be provided to the satisfaction of the COR. Any repairs required due to failure of the Contractor to adequately preclude entrance of weather into the vessel shall be at no expense to the government. Repairs shall include but not be limited to equipment, furniture, furnishings, deck coverings, joinery, and ceilings.
At all times when the vessel is in the custody of the Contractor and the temperature is below 35 degrees F, the Contractor shall keep all pipelines, fixtures, traps, tanks, all auxiliary pumps, and other receptacles on the vessel from freezing and causing damage. This shall be done by either draining or heating the area.
F. PROTECTION IN WAY OF OPENINGS
The Contractor shall provide and maintain complete protection for personnel around the periphery of deck openings and around openings through the hull. The degree of protection to be provided shall satisfy USACE Safety Regulation EM 385-1-1 requirements, 29 CFR 1915, as well as other applicable safety regulations.
G. ACCESSIBILITY FOR INSPECTIONS
The Contractor shall arrange the distribution of welding cables, temporary electric cables, temporary compressed air hoses, etc., in a manner that will prevent tripping or headroom problems. When not in use, Contractor cables and hoses shall be neatly coiled and stored out of the way of construction and passages, to the satisfaction of the COR.
C043 VESSEL SHIP CHECK AND INSPECTION
The Contractor shall visit the HURLEY during Phase I “Shipyard Preparation” of the contract in order to gather information, take measurements, and perform any other inspections of the vessel required to complete their Detailed Design. The Contractor shall perform at a minimum one (1) ship check. For bidding purposes, the Offeror can assume a ship check will be 7 days (5 days aboard the vessel and 2 travel days) and will require 5 Contractor personnel. Ship checks will be scheduled by MDC and MVM with the coordination of the Contractor.
Additional ship checks are highly encouraged in order to complete the detailed design. The Contractor shall coordinate additional ship checks with MDC and MVM as needed by notifying the COR at least 21 days prior to the requested trip.
C045 ACCESS TO EQUIPMENT & MACHINERY
The locations for installation of equipment and machinery items not specifically dimensioned on the Contract Drawings or considered in these Specifications shall be designed and installed to facilitate access for purposes of maintenance, adjustment, and repair. Permanent field-run fittings shall be kept clear of routes required for the removal of such items, and passageways. The space behind certain items may be inaccessible after installation of the equipment. This factor shall be considered in providing proper preservation in way of such equipment and in selecting the location of pipes, ducts, wireways, and other permanent field-run fittings behind such equipment.
Operational and maintenance efficiency shall be a primary consideration in the installation of equipment and machinery not specifically located on the Contract Drawings or considered in these Specifications.
Shipping and unshipping arrangements for field-fit equipment with components requiring maintenance shall be demonstrated to the COR to assure their adequacy.
C100 SCIENTIFIC
C115 WEIGHT ESTIMATE & INCLINING EXPERIMENT
A. CONTRACT DRAWINGS
368-F115-01 CHANGES TO VESSEL WEIGHT ESTIMATE
368-F115-02 RESULTS OF DEADWEIGHT SURVEY
B. REFERENCE DRAWINGS
C. WEIGHT ESTIMATE & INCLINING EXPERIMENT
The Contractor shall update contract drawing 368-F115-01 CHANGES TO VESSEL WEIGHT ESTIMATE as required to match the actual vessel removals and installations associated with this project and including all modifications to the Contract. This updated drawing shall be submitted to the COR monthly for review and approval.
D. INCLINING AND DEADWEIGHT SURVEY
Upon completion of all work and after the new generator sets have been installed, and with the vessel in the lightship condition, the Contractor shall conduct an inclining test and deadweight survey under the direction of the Government.
The inclining test shall be carried out in accordance with ASTM F 1321-21. The Contractor shall be responsible for providing all inclining weights, pendulum setups, support equipment and personnel. The Government will direct the inclining experiment, record all data, and complete the inclining test report. Details of the inclining procedure can be found in Contract Section E05.
The Government will perform stability revisions per the inclining and deadweight survey results.
C170 BERTHING, DRYDOCKING, AND SERVICES
368-D170-01 DOCKING PLAN
C. GENERAL
The Contractor shall be responsible to drydock the vessel for such time as may be necessary to complete all underwater work and hull modifications specified herein and refloat the vessel upon completion of all work.
The Contractor shall develop a detailed blocking plan and supporting calculations to submit to the COR for review and approval within 30 days of contract award. BSR will use the Contractor’s docking plan to revise their structural removal calculations which are vital to the successful execution of the project.
Blocks shall be positioned to properly support the hull and allow for a minimum of 4 feet of clearance between the bottom of the vessel and the drydock floor.
Tapered wood plugs shall be fabricated and installed in all overboard discharges. Plywood sealing devices for all toilets, urinals, sinks, and showers shall be fabricated and installed.
Remove all plugs prior to undocking.
Prior to undocking, the COR or their designated representative and the Contractor shall survey the hull. All damaged paint or plugged hull openings shall be repaired.
Prior to undocking, provide a new blocking plan showing each of the vessel’s blocking positions to the COR for review and approval.
Drydocking and undocking shall include the service of tugboats, line-handlers, a qualified pilot, and a qualified dockmaster.
The bid price for this item shall include all that is described above as well as; demurrage, or other drydock costs, including weekends and holidays necessary to the performance of all modification work.
C180 NOISE AND VIBRATION
368-F180-01 NOISE AND VIBRATION PREDICTION REPORT
368-F180-02 NOISE AND VIBRATION SURVEY REPORT
During the development of the Contract Design, the Government retained the services of Noise Control Engineering, Inc. (NCE) (www.noise-control.com) to prepare a noise prediction analysis.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .