W912BU23B0002-AM0001-Specs.pdf

PDF 2 MB Posted

Attached to
Beach Nourishment: Brigantine Inlet to Great Egg Harbor Inlet, Brigantine Island, Atlantic County, NJ
Solicitation number
W912BU23B0002
Issued by

About this file

This solicitation is for a firm fixed-price contract for beach nourishment work in Brigantine, New Jersey. The scope of work includes placing approximately 200,000 cubic yards of beachfill along the Atlantic coastline, with options to add additional quantities up to 300,000 cubic yards total. Additional requirements are reconstructing pedestrian crossovers, planting dune grass, and installing sand fencing. The period of performance for the base work is 90 calendar days. The estimated value of the contract is between $10 million and $25 million. The solicitation is available electronically via SAM.gov and questions may be directed to the specified contracting officer by email.

View the file

Other files

File Type Posted
W912BU23B0002_FY23 Periodic Nourishment Brigantine_Abstract-SAM.gov.pdf PDF
W912BU23B0002-AM0003-Dwgs.pdf PDF
W912BU23B0002-AM0003-Specs.pdf PDF
W912BU23B0002-AM0002-Dwgs.pdf PDF
W912BU23B0002-AM0002-Specs.pdf PDF
W912BU23B0002-AM0001-Dwgs.pdf PDF
Brigantine_Inlet_BA_2022_9column.txt TXT text file
GDN-NJ202300046-01062023.txt TXT text file
GDS-NJ20230003-01062023.txt TXT text file
W912BU23B0002-Specs.pdf PDF
W912BU23B0002-DWGS.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is as follow s:

The Base Quantity changed from 200,000 to 700,000 under "Product Description." The options remain unchanged. The Period of Performance under Clause 52.211-10 increased from 90 to 150 calendar days. Options information updated, but NOT changed under Clause 52.52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM, Address change for bid opening, and RFI Questions and answers also attached.

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BU23B0002

X 9B. DATED (SEE ITEM 11)

31-Mar-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3.EFFECTIVE DATE

18-Apr-2023

CODE

US ARMY ENGINEER DISTRICT, PHILADELPHIA

POC: ZAQUETTE EVERETT /

1650 ARCH STREET PHILADELPHIA PA

19103-2004

W912BU 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912BU23B0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The Issued By organization has changed from

US ARMY ENGINEER DISTRICT, PHILADELPHIA

POC: ZAQUETTE EVERETT USACE, PHI

WANAMAKER BUILDING 100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

to

US ARMY ENGINEER DISTRICT, PHILADELPHIA

POC: ZAQUETTE EVERETT / 1650 ARCH STREET

PHILADELPHIA PA 19103-2004

SECTION 00 21 00 - INSTRUCTIONS

The following were previously included by reference and are now included by full text:

52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)

(a) Definitions. As used in this provision--

Administrative proceeding means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.

Federal contracts and grants with total value greater than $10,000,000 means--

(1) The total value of all current, active contracts and grants, including all priced options; and

(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).

Principal means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).

(b) The offeror ( ) has ( ) does not have current active Federal contracts and grants with total value greater than $10,000,000.

(c) If the offeror checked “has” in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:

(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:

(i) In a criminal proceeding, a conviction.

(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.

(iii) In an administrative proceeding, a finding of fault and liability that results in--

(A) The payment of a monetary fine or penalty of $5,000 or more; or

(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.

(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.

(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.

(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).

(End of provision)

SECTION 00 45 00 - REPRESENTATIONS AND CERTIFICATIONS

The following have been modified:

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 21 days after the approval by the government of Pre-placement condition surveys.

Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

Options 1 through 5, if exercised will provide additional calendar days as follows:

Option 1 (25,000 cy): 4 calendar days Option 2 (50,000 cy): 5 calendar days Option 3 (75,000 cy): 6 calendar days Option 4 (150,000 cy): 9 calendar days Option 5 (300,000 cy): 16 calendar days

(End of clause)

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

*The Contracting Officer has the right to exercise any or all options within 21 calendar days after the approval by the Government of the Pre-Placement Condition Surveys. The time slated for completion shall include final cleanup of the premises.

(End of clause)

(End of Summary of Changes)

Amendment No. 0001

IFB W912BU23B0002

14. DESCRIPTION OF AMENDMENT (continued)

a. REQUESTS FOR INFORMATION (RFI) WITH RESPONSES: RFI’s with responses, annotated Amendment No. 0001, attached hereto.

b. TECHNICAL SPECIFICATIONS:

(1) BIDDING SCHEDULE: Please delete the Bid Schedule in its entirety and substitute the revised Bid Schedule, annotated as Amendment No. 0001, attached hereto.

(2) SECTION 01 11 00 – SUMMARY OF WORK: Please delete this section in its entirety and substitute the revised Section 01 11 00, annotated as Amendment No. 0001, attached hereto.

(3) SECTION 01 30 00 – ADMINISTRATIVE REQUIREMENTS: Please delete this section in its entirety and substitute the revised Section 01 30 00, annotated as Amendment No. 0001, attached hereto.

(4) SECTION 01 50 00 – TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS:

Please delete this section in its entirety and substitute the revised Section 01 50 00, annotated as Amendment No. 0001, attached hereto.

(5) SECTION 01 57 19 – SUMMARY OF WORK: Please delete pages 1 through 22 of this section in their entirety and substitute revised pages 1 through 22 of this section, annotated Amendment No. 0001, attached hereto.

c. CONTRACT DRAWINGS: Please delete the following drawings in their entirety and substitute the revised drawings of the same numbers, with the latest revision date of 17 April 2023, attached hereto:

G-002 C-102 C-302

C-001 C-103 C-401

C-101 C-301 C-402

d. Please indicate receipt of this amendment on Standard Form 1442 (SOLICITATION, OFFER, AND AWARD) as Amendment No. 0001. Failure to acknowledge all amendments may be cause for rejection of the bid.

This page was intentionally left blank for duplex printing.

Requests for Information and Responses

1. In Section 01 30 00, 1.5 Physical Data L., states the estimated value of the contract is $5,000,000 to $10,000,000. Section 00 00 00 – Procurement and

Contracting Requirements, states the estimated value of the proposed work is

$10M to $25M. Please clarify which is the correct magnitude of the project.

Answer: See Amendment No. 0001.

2. The contractor requests the Request for Information deadline be extended until April 15th, 2023, to allow for any more question that may arise to be submitted for clarification.

Answer: Request for Information deadline extended until 11:00am 20 April

2023.

3. Will the contractor be allowed to dig in the access corridor to allow for flotation in to the borrow area? Pumping the material from the access corridor on to the beach.

Answer: The access corridor is now designated as part of the borrow area.

Please see amendment No. 001.

4. The contours of the borrow area shown on C-402 are not labeled. Please provide a drawing of the borrow area with the contours labeled. Please provide the XYZ file of the survey data for the borrow area.

Answer: See Amendment No. 0001 and Paragraph 1.2 of Section 01 11 00. XYZ

Data posted on SAM.gov.

5. Options – Additional Beachfill, Section 01 11 00, paragraph 1.2.d states

“Where Options for additional beachfill are awarded, the additional beachfill material shall be placed immediately after the initial Base Bid quantity has been placed in the area(s) to be covered by the awarded Option”.

Questions: The total option beachfill is three times the quantity of the base bid. The Base Bid beachfill is to placed between Stations 0+00 to 40+00.

Between which beachfill stations will the Option beachfill be placed? Why is the Option beachfill quantity larger than the Base Bid quantity? Will any of the options be placed outside of Stations 0+00 to 40+00?

Answer: See Amendment No. 0001, Sheet C-001 Note 4, and Paragraph 1.2 of

Section 01 11 00.

6. Can the RFI deadline be extended to April 17th?

Answer: Request for Information deadline extended until 11:00am 20 April

2023.

7. Plan Sheet C-101 references the base bid. Where are Options 1-5 Beachfill locations? Can they be referenced on the planset?

Answer: See Amendment No. 0001, Sheet C-001 Note 4, and Paragraph 1.2 of

Section 01 11 00.

8. Spec Section 01 57 19 Temporary Environmental Controls - Is there any known presence of Plover/Knot/Amaranth in the contractor work limits?

Answer: Seabeach Amaranth has been located on Brigantine Island. Piping

Plover and Red Knot have utilized Brigantine Island in the past. USACE will complete a Seabeach Amaranth survey prior to construction and bird monitoring will be required as part of the contract.

9. Spec Section 01 57 19 Temporary Environmental Controls - Will the contractor be allowed to work in these areas as long as said monitors are employed?

Answer: See Section 01 57 19 Paragraph 3.4.2 and subparagraphs regarding restrictions Piping Plover Protection. Dredging of Material is limited from

July 1st through February 28th.

10. Spec Section 01 57 19 Temporary Environmental Controls - Will the contractor be allowed to work in work limits/plover areas during the nesting season from March 15th to August 15th?

Answer: See Section 01 57 19 Paragraph 3.4.2 and subparagraphs regarding restrictions Piping Plover Protection. Dredging of Material is limited from

July 1st through February 28th.

11. Is there an anticipated notice to proceed date?

Answer: NTP is expected to be issued as soon as possible following contract award.

00 10 00-3

BIDDING SCHEDULE

(To be attached to SF 1442)

Item Estimated Unit Estimated

No. Description Quantity Unit Price Amount

BASE BID:

1. Mobilization and

Demobilization 1 JOB LS $____________

2. Structures Monitoring 1 JOB LS $____________

3. Beachfill 700,000 CY $______ $____________

4. Reconstruct Pedestrian

Dune Crossover 2,580 SF $______ $____________

5. Split Rail Fence 495 LF $______ $____________

6. Sand Fence 1,505 LF $______ $____________

7. Dune Grass 5,395 SY $______ $____________

8. MEC Modifications and Monitoring 1 JOB LS $____________

9. Name the State of New Jersey and the City of Brigantine as “Additional Insured” under

General Liability Insurance 1 JOB LS $____________

TOTAL ESTIMATED BASE BID AMOUNT $_________________

OPTIONS:

10. Option 1 – Beachfill 25,000 CY $______ $____________

11. Option 2 – Beachfill 50,000 CY $______ $____________

12. Option 3 – Beachfill 75,000 CY $______ $____________

13. Option 4 – Beachfill 150,000 CY $______ $____________

14. Option 5 – Beachfill 300,000 CY $______ $____________

TOTAL ESTIMATED BASE BID AND OPTIONS AMOUNT $_________________

00 10 00-4

NOTES:

1. Bidders must bid on all items.

2. Bidders shall list the cost of additional premium, if any, to name the

State of New Jersey and the City of Brigantine as “Additional Insured” under General Liability Insurance as noted in Section 01 30 00, Paragraph titled “INSURANCE REQUIREMENTS”.

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SCOPE OF SECTION

This section presents a general description of the work to be accomplished under this contract on Brigantine Island, between Absecon Inlet and Brigantine Inlet located in Atlantic County, New Jersey.

1.2 DESCRIPTION OF WORK

a. The contract work consists of a Base Bid to place approximately 700,000 cubic yards of beachfill material along the Atlantic Ocean coastline in the northern portion of Brigantine Island. The beachfill work shall commence in the north end of the project and proceed south.

b. The Base Bid work includes, in addition to beachfill: structures monitoring, the reconstruction of pedestrian crossovers; planting of dune grass on exposed and reconstructed dune sections within the project area;

and providing sand fence, split rail fence, and signs, as indicated.

c. The contract work also consists of option work to place additional quantities of beachfill material; 5 separate options, if awarded, to place additional beachfill material.

d. Pre-placement condition surveys, as specified in Section 01 71 23 SURVEY REQUIREMENTS, will determine the exact location and quantity of beachfill material required within the limits indicated, and will be a determining factor in the award of Options for additional quantities of beachfill.

Where Options for additional beachfill are awarded, the additional beachfill material shall be placed immediately after the initial Base Bid quantity has been placed in the area(s) to be covered by the awarded Option. The intent is to complete the beachfill template in a given Base-plus-Option area, before proceeding with work further along the construction baseline.

e. The borrow area that will be available for the beachfill material is located northeast of the project location, adjacent to the northern tip of Brigantine Island in the Brigantine Inlet. See the Contract drawings for the exact location. All material for beachfill work performed under this contract shall be obtained from this borrow area. Beachfill material from any other source, including trucking from upland sources, will not be considered under this contract.

1.3 CONTRACTOR ACCESS

a. Access to the work site is available by land and water. Access to the beach for land based equipment is as shown on the contract drawings. Any materials required to establish or stabilize access points for vehicle use shall be approved by the COR and provided and removed by the Contractor.

Any additional parking that the Contractor requires, outside the work limits, shall be coordinated directly with the appropriate local officials. Access to the approved borrow area is by water only.

Section 01 11 00 Page 1

b. Document the original conditions of the access area and route by taking detailed photographs of those areas prior to starting work. See Section 01 32 33 CONSTRUCTION PHOTOGRAPHY for additional requirements.

c. Access areas shall be restored to the original or better condition upon completion of work. Any damage to the roads due to truck traffic or other Contractor operations shall be repaired, subject to the Contracting Officer's approval, at no additional cost to the Government.

1.4 CONTRACTOR'S WORK LIMIT

The Contractor's work limit is as shown on the contract drawings. The Contractor is prohibited from operating landward of the Contractor's work limit. The Contractor shall not enter upon, affect, or damage, in any way, areas and structures outside that limit of work.

1.5 WORK HOURS

The Contractor may work 24 hours per day, 7 days per week, to complete the contract work. However, the Contractor shall be required to comply with local codes regarding noise at all times during the contract period. The Contractor shall be required to equip his land-based equipment with noise suppression equipment if so directed by the COR.

1.6 DREDGING RESTRICTIONS

Dredging of material will only be allowed from 1 July through 28 February.

1.7 ENVIRONMENTAL RESTRICTIONS

See Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS for Piping Plover and Colonial Nesting Birds restrictions for beachfill operations.

1.8 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer.

1.9 EXISTING UTILITIES

The existing utility locations shown on the drawings are approximate and not complete. The Contractor is responsible for field verifying all existing utility locations, including those not shown on the drawings. For marking underground utility lines, call for free markouts a minimum of 3 work days before you dig at 800-272-1000.

Section 01 11 00 Page 2

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

Section 01 11 00 Page 3

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

33 CFR 88 Pilot Rules

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Evidence Of Insurance

SD-11 Closeout Submittals

Certified Labor Payrolls

1.3 SUPERVISION

1.3.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

1.3.2 Superintendent Qualifications

The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as

Section 01 30 00 Page 1 for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.

1.3.2.1 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.3.3 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.4 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, clear expectations of the "Interim DD Form 1354" Submittal, and the processes for joint risk management between the Contractor and Government. Major subcontractors who will engage in the work must also attend.

1.5 PHYSICAL DATA (APR 1984)

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (FAR 52.236-4)

a. The indications of physical conditions on the sketches and in the specifications are the result of site investigations by surveys.

b. Tide Data. As indicated on drawings.

c. Weather Conditions. The climate of the area is referred to as "continental" by climatologists, characterized by cold winters and moderately hot summers. The site of the work is in the open ocean and is exposed to storms. It is believed that work can be performed during all seasons of the year except during winter months when ice and storm conditions may interfere with dredging operations. Complete weather records and reports may be obtained from the local U.S. Weather Bureau

Section 01 30 00 Page 2

Office nearest to the work site. The Contractor shall satisfy himself as to the hazards likely to arise from weather conditions during the construction period.

d. Channel Traffic. Traffic in the work area consists of ocean going and commercial fishing, sport fishing vessels, U.S. Coast Guard vessels, and recreational craft. The traffic and vessels using Brigantine Inlet may interfere with dredging operations.

e. Obstruction of Channel. The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. The Contractor shall request the U.S. Coast Guard to issue a Notice to Mariners advising navigation interests that the Contractor's dredging plant will be operating in the project waterway. The Contractor shall submit this request, at least 2 weeks prior to start date, to: Commander (OAN), Fifth Coast Guard District, Federal Building, 431 Crawford Street, Portsmouth, VA 23705 or e-mail cgd5waterways@uscg.mil.

The Contractor shall furnish a copy of each request to the Contracting Officer not less than five days prior to the start of dredging. Each request shall contain the approximate time required for completion of dredging. Upon completion of dredging, the Contractor shall promptly remove his plant, including ranges, buoys, piles and other marks placed by him under the contract in navigable waters and on shore.

f. Navigation Aids. Do not relocate or move aids to navigation that have been established by the U.S. Coast Guard. If it becomes necessary to have an aid to navigation moved in order to complete dredging operations under this contract, the Contractor shall notify the Fifth Coast Guard District (dpw) at least 45 days prior to the desired date for movement of the aid.

To request a relocation, Contractors shall contact Waterways Management Section, Assistant Section Chief/NJ, DE, PA at (757)398-6371 or e-mail cgd5waterways@uscg.mil at least 45 days before the desired date for movement of the aid. When making a request by telephone, Contractors must speak to the designated points of contact. The leaving of voicemail messages will not be acceptable. The Fifth CG District (dpw) will coordinate all temporary relocations or discontinuances. A copy of each request to the USCG for Movement of Navigation Aids (including records of telephone conversations) shall be furnished to the Contracting Officer.

g. Transportation Facilities. The work site is accessible from the New Jersey Garden State Parkway and the Atlantic City Expressway. The Contractor shall be responsible for all investigations of load carrying capacities of bridges and roadways.

h. Location. Brigantine Island is located on the Atlantic Ocean coast of New Jersey in Atlantic County.

i. Laying of Submerged Pipelines and Obstruction of Channel. Should it become necessary in the performance of this contract to use a submerged pipeline, the Contractor shall notify the Contracting Officer in advance of the schedule for placement of the pipeline. If the submerged line is to be placed across a navigable channel, the Contractor shall submit a request

Section 01 30 00 Page 3 for approval at least ten working days (Saturdays, Sundays, and holidays excluded) prior to the desired closure date, to the U.S. Coast Guard, Sector Delaware Bay, 1 Washington Avenue, Philadelphia, PA 19147-4395. A copy of each request shall be furnished to the Contracting Officer. This request shall contain the following information:

(1) Location (Channel Centerline Stationing) and depth (over the top of the pipeline) at which the submerged line will be placed;

(2) The desired length of time the channel is to be closed;

(3) The date and hour placement or removal will commence;

(4) The date and hour of anticipated completion; and

(5) The name and telephone number of the person to be contacted for information and response to emergency condition.

The Coast Guard has indicated that the requirements of navigation may make it necessary to establish times other then those requested. Coordinate the work with the Coast Guard sufficiently in advance of the planned closing to prevent delay to the dredging operations and comply with the Coast Guard requirements.

j. Bridge to Bridge Radio Telephone Equipment. In order that radio telephone communication may be made with passing vessels, all dredges engaged in work under the contract shall be equipped with and operate bridge-to-bridge radio telephone equipment. The radio telephone equipment shall operate on VHF Channel 13 (156.65 MHz) with low power output having a communication range of approximately ten miles. The frequency has been approved by the Federal Communication Commission.

k. Survey control description sheets are included as Appendix A30.

l. Magnitude of the Contract Work. The estimated value of the contract is $10,000,000 to $25,000,000.

m. Vibracore logs and sieve curves representative of the material to be dredged under this contract are included as Appendix B41 and B42, respectively.

n. New Jersey Shore Protection Study, Brigantine Inlet to Great Egg Harbor Inlet, Brigantine Island, Final Feasibility Report and Final Environmental Impact Statement, dated August 1998, are available for inspection.

Arrangements for inspection of these documents shall be made by contacting Mr. Keith Watson, Engineering Management Branch, telephone number (215) 656-6287.

o. Inspection of the Site. Prospective bidders are invited to visit the site of the work to acquaint themselves with the site conditions and problems incident to the prosecution of the work.

1.6 CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING

DAVIS-BACON ACT CERTIFIED PAYROLLS

a. The contractor will use a commercially available electronic system to process and submit certified payrolls electronically to the Government. The Davis-Bacon Act establishes the requirements for preparing, processing, and providing certified labor payrolls.

Section 01 30 00 Page 4

b. The contractor shall be responsible for obtaining and providing access for all licenses and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis-Bacon Act and related statutes. When the contractor uses an electronic Davis-Bacon Act payroll service, it shall be used to prepare, process, and maintain the relevant payrolls and basic records for all work under the construction contract. The electronic payroll service shall be capable of preserving the payroll and related basic records for the required three years after contract completion. The contractor shall obtain and provide electronic system access including electronic review to the Government, as required to comply with the Davis- Bacon Act and related statutes through the duration of the construction contract.

c. The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:

(1) commercially available;

(2) compliant with appropriate Davis-Bacon Act payroll provisions in the FAR;

(3) able to accommodate the required number of employees and subcontractors that will be employed under the contract;

(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export into an Excel spreadsheet to be imported into the contractor's mode of Resident Management System 3.0;

(5) demonstrated security of data and data entry rights;

(6) able to produce contractor-certified electronic versions of weekly payroll data;

(7) able to identify erroneous entries and track the date/time of all versions of the certified Davis-Bacon Act payrolls submitted to the government over the life of the contract; and

(8) capable of generating a durable record copy in a Compact Disc (CD) or Digital Versatile Disc (DVD) and Portable Document Format (PDF) file record of data from the system database at the end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during contract closeout.

d. All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract.(UAI 3 Jun 2019; Update 2 - 30 Nov 2021)

1.7 DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in the clause of the contract entitled "Permits and Responsibilities". However, if, in the judgement of the Contracting

Section 01 30 00 Page 5

Officer, any part of the permanent work performed by the Contractor is damaged by flood or hurricane, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such work, and equitable adjustment pursuant to Contract Clause entitled "Changes," will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damages to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense regardless of the cause of such damage. (CENAP)

1.8 CERTIFICATES OF COMPLIANCE

Certificates required for demonstrating proof of compliance of materials with specifications requirements shall be executed in triplicate copies.

Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements. (CENAP)

1.9 PERFORMANCE EVALUATION OF CONTRACTOR (MAR 2014)

a. As a minimum, the Contractor's performance will be evaluated upon final acceptance of the work for contracts less than one year in duration.

Contracts in excess of one year will receive at a minimum, an annual interim evaluation in addition to the final evaluation. However, interim evaluation may be prepared at any time during contract performance when determined to be in the best interest of the Government. The evaluation will be entered into the Contractor Performance Assessment Reporting System

(CPARS).

b. CPARS is a web-enabled application that supports the completion, distribution, and retrieval of construction contract performance evaluations. CPARS is for UNCLASSIFIED use only. An evaluation assesses Contractor performance and provides a record, both positive and negative, on a given contract. Each evaluation is based on objective facts and supported by contract management data, such as contract performance elements that evaluate quality, timely performance, effectiveness of management, and compliance with contract terms, labor standards, and safety requirements. The Contractor will be rated either outstanding, above average, satisfactory, marginal, or unsatisfactory in the areas of Contractor Quality Control, Timely Performance, Effectiveness of Management, Compliance with Labor Standards, and Compliance with Safety Standards. The Contractor will be advised of any unsatisfactory rating, either in an individual element or in the overall rating, prior to completing the evaluation, and all Contractor comments will be made a part of the official record. Performance Evaluation Reports will be available

Section 01 30 00 Page 6 to all DOD Contracting offices for their future use in determining Contractor responsibility, in compliance with ER 415-1-17.

c. Upon successful award of the contract, the Contractor will be notified by CPARS via email that access has been granted to a contract within the system. The email will contain instructions of how to log into the system.

(CENAP)

1.10 SIGNAL LIGHTS (FEB 1983)

The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working navigable channels, as approved by the Commandant, U.S. Coast Guard with respect to vessels in inland waters (33 CFR 88), as applicable. (CENAP)

1.11 ACCOMMODATIONS AND MEALS FOR GOVERNMENT INSPECTORS (1965 APR OCE)

a. The Contractor shall furnish regularly to Government inspectors on board the dredge a suitable separate area for an office. A separate trailer on the dredge may be supplied in lieu of a room. The trailer must be securely lashed to the dredge and enclosed by railings. The room or trailer shall be fully equipped and maintained to the satisfaction of the Contracting Officer; it shall be properly heated, ventilated, lighted and insulated from noise, and shall have a desk which can be locked, a chair for each inspector, and washing conveniences. The entire cost to the Contractor for furnishing, equipping and maintaining the foregoing accommodations shall be included in the cost of all bid items. If the Contractor fails to meet these requirements, the facilities referred to above will be secured by the Contracting Officer, and the cost thereof will be deducted from payments to the Contractor.

b. If the Contractor maintains on this work an establishment for the subsistence of his own employees, he shall, when requested, furnish to inspectors employed on the work, and to all Government agents who may visit the work on official business, meals of a quality satisfactory to the Contracting Officer. The meals furnished will be paid for by the Government at a rate of $5.00 per person for each meal. (CENAP)

1.12 REQUIREMENT TO NOTIFY COAST GUARD OF RELEASE OF OBJECTS INTO THE

NAVIGABLE WATERS OF THE UNITED STATES

a. Requirement: As soon as a person has knowledge of any release from a vessel or facility into the navigable waters of the United States of any object that creates an obstruction prohibited under section 403 of this title, such person shall notify the Secretary and the Secretary of the Army, and the COR of such release.

b. Restriction on use of notification: Notification provided by an individual in accordance with subsection (a) of this section may not be used against such individual in any criminal case, except a prosecution for perjury or for giving a false statement.

(Pub. L. 92–340, §15, as added Pub. L. 109–241, title VI, §602, July 11, 2006, 120 Stat. 553.)

Section 01 30 00 Page 7

1.13 INSURANCE REQUIREMENTS

Evidence of Insurance: Evidence of the following insurance shall be submitted to the Contracting Officer prior to commencement of work.

Insurance shall be maintained throughout the period of performance:

a. General Liability Insurance (Comprehensive form of policy): Bodily Injury Liability - $500,000 per occurrence.

b. Automobile Liability Insurance (Comprehensive form of policy): Bodily Injury Liability - $200,000 per person and $500,000 per accident. Property Damage Liability - $20,000 per accident.

c. Workmen's Compensation and Employer's Liability Insurance: Compliance with applicable workmen's compensation and occupational disease statutes is required. Employer's liability coverage in the minimum amount of $100,000 is also required."

d. Applicable Marine Casualty and Marine Workmen's Compensation Insurance:

As appropriate for this contract.

1.14 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that includes joint risk management, is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.

1.14.1 Informal Partnering

The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.

The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the Resident Engineer office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to 6 month intervals.

1.15 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the

Section 01 30 00 Page 8 capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.

Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of changes to this email address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Section 01 30 00 Page 9

SECTION 01 50 00

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2022; ERTA 1 2021) Standard for Portable Fire Extinguishers

NFPA 70 (2020; TIA 22-1; ERTA 1 2022) National Electrical Code

NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

EP 310-1-6a (2006; 2019 Change 2) Project Operation -- Sign Standards Manual, VOL 1

EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices

U.S. FEDERAL AVIATION ADMINISTRATION (FAA)

FAA AC 70/7460-1 (2016; Rev L; Change 2) Obstruction Marking and Lighting

U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)

MUTCD (2009; Rev 2012) Manual on Uniform Traffic Control Devices

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Site Plan; G, COR

Section 01 50 00 Page 1

Traffic Control Plan; G, COR

Sign Legend Orders; G

1.3 CONSTRUCTION SITE PLAN

Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.

1.4 PUBLIC ACCESS

The Contractor shall provide the public with access to all private and commercial properties within the limits of work.

1.5 CONTRACTOR ACCESS

Access to the work areas is only permitted at the locations shown. Provide materials required to establish or stabilize access points for vehicle use and remove upon project completion. Protect all existing structures from damage throughout the entire contract, and maintain all access points in accordance with Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.

1.6 LOCAL POLICE NOTIFICATION

Notify the local police department at least 24 hours prior to starting work to obtain approval for temporary parking and placement of any required signs.

PART 2 PRODUCTS

2.1 TEMPORARY SIGNAGE

2.1.1 Bulletin Board

Within one calendar days of mobilization on site and prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 Section 01 and other information approved by the Contracting Officer. Coordinate requirements herein with

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.

2.1.2 Project Identification Signs

a. The construction project sign package consists of three signs:

(1) Project Identification sign.

(2) On-the-job safety performance of the Contractor sign.

(3) Investing in America Sign.

Section 01 50 00 Page 2

The package shall conform to the requirements of EP 310-1-6a and EP 310-1-6b, specifically Section 16 (attached to this section). Submit the sign legend orders as described in Section 16 of EP 310-1-6a prior to erecting the signs.

b. Additional Project Identification sign requirements:

(1) Include the Army Star as shown on the attached sheets.

(2) Include the following on the project sign: "Include "The State of New Jersey" and the "NJDEP Office of Coastal Engineering" as the project sponsors. In addition, include the Philadelphia District's website address on the project sign, list the respective city officials, and state that part of the funding for the project is being provided for by the respective city, all in a manner as directed by the Contracting Officer.