This solicitation and amendment seek proposals for a new telescopic crane to replace the existing crane aboard the DCV HAYWARD. The New York District of the Corps of Engineers requires a marine deck crane and diesel-powered hydraulic power unit to be ABS classed and built to API 2C, ABS, and EM385-1-1 standards. The crane must operate on the main deck and replace an existing Pettibone Model 130 Krane. The HPU is to be mounted below deck and replace the existing unit. Offerors must be registered in SAM and VetBiz, as applicable. Questions were due by January 15th and must be submitted to the specified emails. Proposals are due by 4:30 PM EST on January 21st to the same emails. The amendment extends the deadline 5 days to January 27th at 4:30 PM EST and clarifies that only the six-part block is required, not a two-part block.

View the file

Other files for this federal contract opportunity

Other files attached to MDC 3230 HAYWARD CRANE PURCHASE, newest first.
File Type Posted
3230 HAYWARD CRANE Solicitation_Amendment 2.pdf PDF
3230 Crane Procurement Specification SOW (updated) Amendment 2.pdf PDF
3230 HAYWARD CRANE Solicitation_Amendment 1.pdf PDF
3230 HAYWARD Combined Drawings Amendment 1.pdf PDF
3230 Crane Procurement Specification SOW.pdf PDF
3230 HAYWARD CRANE Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0003 hereby incorporates changes provides in the SF 30 Continuation Page and extends solicitation.

All other terms and conditions remain unchanged.

Only a w arranted Contracting Officer (either a Procuring Contracting Officer (PCO), or an Administrative Contracting Officer (ACO)), acting w ithin their delegated limits, has the authority to issue modifications or otherw ise change the terms and conditions of this contract. If an individual other than the Contracting Off icer attempts to make changes to the terms and conditions of this contract you shall not proceed w ith the change and shall immediately notify the Contracting Officer.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BU21R0010

X 9B. DATED (SEE ITEM 11)

23-Dec-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Jan-2021

CODE

US ARMY ENGINEER DISTRICT, PHILADELPHIA

CONTRACTING DIVISION

WANAMAKER BUILDING

100 PENN SQUARE EAST

PHILADELPHIA PA 19107-3390

W912BU 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912BU21R0010

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

CHANGES AMEND NO 3

Revisions as follow:

1. Solicitation has been extended an additional 5 days from 21 January 2021 to 27 January

2021 4:30 PM EST.

Questions and Answers:

Q6) Please confirm whether only the two (2) part block or the six (6) part block are required, and which one.

A6) Only the six (6) part block is required.

Q7) If the inclusion of both a two (2) part block and a six (6) part block is an absolute requirement, could you please provide as much definition as possible regarding every aspect of each of the 2 sets of conditions of both the two (2) part block and the six(6) part block, including at a minimum:

Minimum single line speed for each in what reeving conditions maximum loads are to be lifted (and the loads);

whether a common wire rope is to be used for both blocks, and if not, please confirm that we are to provide 2 ropes

A7) Only the six (6) part block is required.