This bid sheet and related federal contract opportunity are for drainage and earthwork preparation services at the Pedricktown Disposal Area Complex in Salem County, New Jersey. The U.S. Army Corps of Engineers, Philadelphia District intends to award a firm fixed price contract consisting of two phases. Phase 1 involves amphibious excavation to excavate drainage ditches and construct additional ditches to aid drainage and drying of materials. Phase 2 requires the contractor to move, shape, place and compact dredged materials within designated areas to raise elevations and prepare the site. The contract work will provide all equipment, labor, and materials necessary to perform the drainage and earthwork preparation from August 2021 to January 2023. The bid sheet specifies rates for equipment like amphibious excavators, dozers, excavators and dump trucks. It also includes line items for labor, plans, and overhead costs. The total estimated cost range for the project is between $5-10 million.

View the file

Other files

File Type Posted
C.04.01 - 21B0009+ Formal Bid Abstract signed.pdf PDF
Amendment 0002.pdf PDF
FY21 WP PWS PTown_Ammend2.pdf PDF
21B0009_RFI Responses.pdf PDF
PTown_Site_Map_Revised.pdf PDF
Amendment 0001.pdf PDF
21B0009 - Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SHEET FOR DREDGED MATERIAL DISPOSABLE SITE DRAINAGE AND EARTHWORK PREPARATION SERVICES

CONTRACT FOR THE PEDRICKTOWN DISPOSAL AREA COMPLEX.

ITEM UNIT QUANTITY UNIT PRICE TOTAL

Amphibious Excavator

Mobilization/Demobilization Each 4 ___________ _____________

Daily Rate Work Days 960 ___________ _____________

Operator Daily Rate Work Days 1004 ___________ _____________

Widetrack Bulldozer

Mobilization/Demobilization Each 4 ___________ _____________

Daily Rate Work Days 360 ___________ _____________

Operator Daily Rate Work Days 388 ___________ _____________

Crawler Excavator

Mobilization/Demobilization Each 2 ___________ _____________

Daily Rate Work Days 180 ___________ _____________

Operator Daily Rate Work Days 194 ___________ _____________

Articulated Dump Truck

Mobilization/Demobilization Each 8 ___________ _____________

Daily Rate Work Days 720 ___________ _____________

Operator Daily Rate Work Days 776 ___________ _____________

HASP/AAP, QC & Work Plans Each 4 ___________ _____________

Mechanic Labor Work Days 348 ___________ _____________

Safety/QA Labor Work Days 348 ___________ _____________

Sub Total for Equipment & Labor _____________

G&A ___________% _____________

Sub Total with G&A _____________

Profit ___________% _____________

Total Contract Cost with Profit _____________

Daily rate per piece of equipment includes all costs, to include, but not limited to: rental, taxes, fuel, oil, maintenance, parts, repairs and insurance to ensure each piece of equipment is fully capable of executing the requirements of this contract every work day, as appropriate for each Phase of work. Mechanic Labor includes manpower efforts to support equipment maintenance. Labor workdays include an estimated 11 paid holidays during anticipated period of performance for Phase 1 and 7 paid holidays for Phase 2.