12R0040-SPECS-AM1.pdf
PDF 42 KB Posted
- Solicitation number
- W912BU-12-R-0040
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0006.pdf | ||
| 12R0040-SPECS-AM5.pdf | ||
| Amendment 0004.pdf | ||
| SITE VISIT .pdf | ||
| 12R0040-SPECS-AM3.pdf | ||
| 12R0040-SPECS-AM2.pdf | ||
| 12R0040-SPECS.pdf | ||
| 12R0040-DWGS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
W912BU
Waste Water Treatment Plant Upgrade, Tobyhanna Army Depot, Tobyhanna, Pennsylvania
THIS AMENDMENT DOES NOT EXTEND THE PROPOSAL DUE DATE OF 28 AUGUST 2012 AT 2:00PM EST.
(CONTINUED)
E5CTCMNE
U.S. Army Engineer District, Philadelphia Contracting Division-Room 643 Wanamaker Building, 100 Penn Square East Philadelphia, Pennsylvania 19107-3390
U.S. Army Engineer District, Philadelphia POC: Michele Evans Wanamaker Building, 100 Penn Square East Philadelphia, Pennsylvania 19107-3390
W912BU-12-R-0040
08/08/2012
07/27/2012
This page was intentionally left blank for duplex printing.
Amendment No. 0001
RFP W912BU-12-R-0040
14. DESCRIPTION OF AMENDMENT (continued)
a. REQUESTS FOR INFORMATION (RFI) PROCEDURE: Requests for Information (RFI) Procedure form, annotated Amendment No. 0001, attached hereto.
b. Please indicate receipt of this amendment on Standard Form 1442(SOLICITATION, OFFER, AND AWARD) as Amendment No. 0001.
Failure to acknowledge all amendments may be cause for rejection of the bid.
Amendment No. 0001
RFP W912BU-12-R-0040
RFI – Page 1
Requests for Information (RFI) Procedure
The Government requests that all bidders follow the instructions below when submitting Requests for Information (RFI’s).
Please do not submit an RFI more than once. Subsequent questions shall be submitted separately as a new RFI.
Please submit all RFI’s by 3:00 pm Eastern time, 14 August 2012.
RFI’s received after this deadline may not be addressed. All RFI’s received by the deadline will be reviewed by the Government. Changes to plans and specifications resulting from a RFI evaluation will be issued by amendment. It is important that bidders review all amendments as direct responses to RFI’s may not be provided.
The following is the preferred format for submitting RFI’s. Questions submitted in this standard format will enable the Government to evaluate responses in a timelier manner.
Requests for information shall be submitted using a spreadsheet style method as shown below. A file with this format may also be downloaded from www.fbo.gov along with the plans and specs files for this project. Please attach the spreadsheet file as an attachment to an email message to Michele.N.Evans@USACE.army.mil. Please include the Solicitation Number (W912BU-12-R-0040) in the subject line.
The spreadsheet shall contain the following columns: 1) RFI Number, 2) Reference to applicable Spec Section or Drawing Sheet Number, 3) applicable discipline involved (Mechanical, Electrical, Civil, etc…), and 4) a Clear and concise statement of the problem or clarification requested.
Example:
RFI# Discipline
Spec Sect/ Drawing Description
1 Mechanical 15 22 00 Para. 2.5.1 specifies 4-inch pipe, however Dwg P2.01 shows piping is 8-inch in size.
2 Architectural A5.1.2 Unable to locate the specifications for the Grab Bars shown in the Toilet rooms.
| SF30 |
| AMENDMENT DESCRIPTION |
| RFI PROCEDURE |
File details come from the government source that posted it. Updated .