RFI_Responses_W9128F25QA056_Basin Mining Area Road Repair_4June2025_1239PM.pdf
PDF 245 KB Posted
- Attached to
- Basin Mining Area Road Repair
- Solicitation number
- W9128F25QA056
About this file
This document is a Request for Information (RFI) Responses for the Basin Mining Area Road Repair project in Basin, Montana, dated 4 June 2025. The RFI addresses several key questions from potential contractors, including bid bond requirements, project timeline, and cost estimates. Notably, no bid bond is required for quotation submission, but the winner must provide a payment bond or irrevocable letter of credit. The project has a compressed timeline, requiring work to commence within 10 calendar days of the purchase order and be completed within 180 days.
The estimated project cost range is between $25,000 and $100,000, and it is a new requirement with no incumbent contractor. The project involves road repair services at the Basin Mining Area, specifically for Operable Units 5 and 6. Contractors are allowed to visit the site at their own convenience, and the project is set aside 100% for Service-Disabled Veteran-Owned Small Business. The solicitation is being managed by the U.S. Army Corps of Engineers, Omaha District, with the primary NAICS code 237310 for Highway, Street, and Bridge Construction.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information Responses
W9128F25QA056
Basin Mining Area Road Repair Basin, MT
As of 4 June 2025
Q: Is a bid bond required for quotation submission?
A: No, a bid bond is not required for quotation submission.
Note: The winner will be required to submit one of the following payment protections: Payment bond, or Irrevocable Letter of Credit (Per 52.228-13 Alternative Payment Protection).
Q: Could the project be completed next year in 2026?
A: No, the project needs to be completed as soon as possible and cannot wait until 2026.
Q: What is the current anticipated start date?
A: Once the purchase order is awarded, a notice to proceed will be issued by the Government which requires work to commence within ten (10) calendar days and work to be completed within180 days after receiving the notice to proceed (IAW 52.211-10 Commencement, Prosecution and Completion of Work).
Q: Do you have a magnitude or estimated project cost range for this project?
A: Disclosure of Magnitude (IAW FAR 36.204): The estimated cost range for this project is between $25,000 and $100,000.
Q: Will there be a site visit, or may we visit the area at our convenience?
A: The contractor may visit the area at their own convenience. There will be no Government-organized site visit. Please reference, page 7 of the PWS.
Q: Is this new requirement or is there an incumbent performing these services?
A: This is a new requirement.