This Request for Information (RFI) provides responses to key questions about the Basin Mining Area Road Repair project (Solicitation W9128F25QA056) in Basin, Montana. The project requires urgent completion, with work expected to commence within 10 calendar days of the purchase order award and be completed within 180 days. The estimated project cost range is between $25,000 and $100,000. Potential contractors may visit the site at their own convenience, and there is no government-organized site visit. This is a new requirement with no incumbent contractor currently performing the services. The responses are dated 29 May 2025 and provide critical operational details for interested bidders about project timeline, scope, and expectations.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information Responses
W9128F25QA056
Basin Mining Area Road Repair Basin, MT
As of 29 May 2025
Q: Could the project be completed next year in 2026?
A: No, the project needs to be completed as soon as possible and cannot wait until 2026.
Q: What is the current anticipated start date?
A: Once the purchase order is awarded, a notice to proceed will be issued by the Government which requires work to commence within ten (10) calendar days and work to be completed within180 days after receiving the notice to proceed (IAW 52.211-10 Commencement, Prosecution and Completion of Work).
Q: Do you have a magnitude or estimated project cost range for this project?
A: Disclosure of Magnitude (IAW FAR 36.204): The estimated cost range for this project is between $25,000 and $100,000.
Q: Will there be a site visit, or may we visit the area at our convenience?
A: The contractor may visit the area at their own convenience. There will be no Government-organized site visit. Please reference, page 7 of the PWS.
Q: Is this new requirement or is there an incumbent performing these services?
A: This is a new requirement.