J.2_Tooele Tank 5129B Final Report 2020.pdf
PDF 910 KB Posted
- Attached to
- STI External Tank Inspection Tooele Depot Utah
- Solicitation number
- W9128F25QA009
About this file
This document is an STI (Steel Tank Institute) In-Service Inspection Report for Diesel Tank 5129B located at Tooele Depot in Utah, conducted by the US Army Corps of Engineers Omaha District on July 27, 2020. The inspection focused on evaluating the 12,000-gallon horizontal, double-wall, welded steel tank manufactured by Perkins Welding Works in 1996, which currently stores diesel fuel.
The comprehensive report includes detailed assessments of the tank's construction, foundation, appurtenances, coating, piping system, and overall condition. Key findings include approximately 20% coating failures and the need to install facility number labeling and a manual gauge. The tank is equipped with a Ronan automatic tank gauge, a submersible turbine pump, and 2-inch primary and 8-inch emergency venting. While no mandatory repairs were identified, the report recommends recoating the tank to slow corrosion and adding the required labeling to comply with UFC 3-460-01 standards. The next recommended in-service external inspection is scheduled for July 27, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J.4_Toolele-Fac 512T2 (Tank 512-A1)-FINAL-2015.pdf | ||
| J.1_Tooele Tank 5129A Final Report 2020.pdf | ||
| J.3_Tooele Tank 5129C Final Report 2020.pdf | ||
| J.5_Toolele-Fac 512T1 (Tank 512-A2)-FINAL-2015.pdf | ||
| Attachment E - Inspection Telecon Briefing Template.docx | DOCX document | |
| Attachment B_TOD.xlsx | XLSX spreadsheet | |
| Solicitation - W9128F25QA009.pdf | ||
| SCA WD 2015 5489_Tooele Utah REV 25.gov.pdf | ||
| Attachment H - STI External Inspection Template.docx | DOCX document | |
| Attachment C - Tank Data Sheet.xlsx | XLSX spreadsheet | |
| Attachment D - Monthly Contractors Progress Management and Status Report.xlsx | XLSX spreadsheet | |
| SP-POL-CMP-INSPECT-FY25-TOD_PWS.pdf | ||
| Attachment A - General Installation Security Requirements.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers
| Omaha | District |
| STI | In‐Service |
Inspection Report
| Tooele | Depot | |
| Diesel | Tank | 5129B |
US Army Corps of Engineers Center of Expertise for Petroleum, Oils and Lubricants
| USACE | POL‐MCX | |
| 27 | July | 2020 |
STI In-Service Inspection Report Tooele Depot, Tooele UT
Table of Contents
ACRONYMS AND ABBREVIATIONS
GENERAL SUMMARY
INSPECTION DATE
STATE REGULATIONS
PREVIOUS INSPECTION DATES
RECOMMENDED FUTURE INSPECTION DATES
GENERAL TANK INFORMATION
A. GENERAL PROJECT INFORMATION
1. STI SP001 Inspection
2. Site Information
B. TANK INSPECTION COMMENTS
1. Tank Construction
2. Tank Foundation
3. Tank Appurtenances
4. Tank Coating
5. Tank Piping System
6. Fire Protection System
7. Secondary Containment
C. FINDINGS AND RECOMMENDATIONS
1. MANDATORY REPAIRS per STI SP001, UFC 3-460-01, NFPA 30, or NFPA 30A
2. REQUIRED REPAIRS to Fully Comply with STI SP001, UFC 3-460-01, NFPA 30, or NFPA 30A
3. RECOMMENDED REPAIRS as Part of Regular Maintenance
APPENDIX A: ENGINEERING CALCULATIONS AND DRAWINGS
TANK CONFIGURATION DIAGRAM
APPENDIX B: STI SP001 FORMAL EXTERNAL INSPECTION CHECKLIST
TANK ID Diesel Tank
1.0 Tank Containment
2.0 Tank Foundation and Supports
3.0 Cathodic Protection
4.0 Tank Shell, Heads, Roof
5.0 Tank Equipment
6.0 Insulated Tanks
APPENDIX C: STI SP001 MONTHLY INSPECTION CHECKLIST
1.0 Tank Containment
2.0 Leak Detection
3.0 Tank Equipment
4.0 Tank Attachments and Appurtenances
5.0 Other Conditions
APPENDIX E: PHOTOGRAPHS
ACRONYMS AND ABBREVIATIONS
API American Petroleum Institute
ASME American Society of Mechanical Engineers
ASNT American Society of Non-Destructive Testing
ATG Automatic Tank Gauge
BBL Barrel
CFR Code of Federal Regulations
CP Cathodic Protection
DFT Dry Film Thickness
HLA High Level Alarm
HLCS High Level Control Shutoff
HHLA High-High Level Alarm
LLA Low Level Alarm
LLLA Low-Low Level Alarm
MFL Magnetic Flux Leakage
MT Magnetic Particle Testing
NACE National Association of Corrosion Engineers
NDT Non-Destructive Testing
NFPA National Fire Protection Association
PSI Pounds per Square Inch
PT Penetrant Testing
P/V Pressure/Vacuum
RP Recommended Practice
PST Product Saver Tank
RT Radiography Testing
STI Steel Tank Institute
TML Thickness Measurement Location
TRV Thermal Relief Valve
UFC Unified Facilities Criteria
UFGS Unified Facilities Guide Specifications
ULS Ultra Low Sulfur
UT Ultrasonic Testing
VT Visual Testing
GENERAL SUMMARY
Tank 5129B is located at Tooele Depot in Tooele, UT and is a welded, steel, horizontal UL 2085 tank for flammable liquids which currently stores Diesel. The Tank Manufacture is Perkins Welding Works. The installation date is 1996. The in-service inspection was performed July 27, 2020. The results of this inspection will provide recommendations for repairs and upgrades which are required to comply with applicable industry and military standards. The testing and inspection was performed in accordance with the applicable sections of the Fifth Edition of SP001. Contained in this report is a detailed account of the tank inspection, a summary of the non-destructive testing, and the conclusions derived from the inspection and testing.
INSPECTION DATE
Inspection Date: 27 July 2020 Equipment Used:
Manufacturer: Dakota Ultrasonic’ s Model Number: CMX DL Calibration Method: Zeroing Procedure, Multi-step Thickness gauge
Inspector(s):
John Hester API 653/STI SP 001/NDE Level II
STATE REGULATIONS
State Regulation for STI In-Service Tank Inspections N/A State Regulation for STI Out-of-Service Tank Inspections N/A
NOTE: If there are no state regulations for tank inspections then N/A shall reside in-place of the number of years between inspections. If state regulations reside, the recommended future inspections dates shall be based on whichever is more stringent between the STI inspector’s calculations and the State regulations.
PREVIOUS INSPECTION DATES
Inspection Date: 28 August 2009
RECOMMENDED FUTURE INSPECTION DATES
STI Out-of-Service (Internal) Inspection Date: N/A (Per STI OOS is not required for Category 1 AST) STI In-Service (External) Inspection Date: 27 July 2025
John Hester Robert and Company API 653 No. 88616 SP001 STI No. AST 2092 ASNT NDT Level II No. 164397
GENERAL TANK INFORMATION
ITEM DESCRIPTION
Owner US Army
Location Tooele Depot
Facility Number 5129B
Tank Number Diesel Tank
State / Country Utah
City Tooele
Inspection Date 27 July 2020
Tank Manufacturer Perkins Welding Works
Design Standard UL 2085
Date of Construction 1996
Tank Contents Diesel
Tank Serial Number M170018
Tank Diameter 9’
Tank Length 33’
Product Height 9’
Tank Capacity 12,000 gallons
Tank Foundation Carbon steel saddles on Concrete slab
Tank Construction Double wall welded carbon steel
Interior Coating System Epoxy Coating
Exterior Coating System Epoxy Coating
Level Gauging Ronan ATG
Venting 2‐ inch primary and 8‐inch primary emergency and 8‐inch interstice
Strapping Charts 1/16th inch
Overfill Protection High Level shut off
Piping (Size and Material)
Receipt 3‐inch Carbon steel
Issue 3‐inch Carbon steel
Water Draw‐Off 1‐inch Carbon steel port only
Level Alarms LLA, HLA, HHLA
Secondary Containment Coated Welded Steel 110% capacity
A. GENERAL PROJECT INFORMATION
1. STI SP001 Inspection STI Standard SP001 In-Service inspection of Diesel Tank was completed on July 27, 2020 to evaluate the tank’s integrity, collect data, and establish a data base for future inspections and evaluations.
2. Site Information Tooele ground product facility consists of three 12,000-gal fuel tanks storing Mogas and Diesel. The facility is supplied by commercial truck.
B. TANK INSPECTION COMMENTS
1. Tank Construction The Diesel Tank is a 12,000-gallon aboveground horizontal, double wall, steel storage tank 33’ and long 9’ in diameter.
2. Tank Foundation Poured concrete slab
3. Tank Appurtenances
a. Venting
The Diesel Tank has a primary 2-inch pressure/vacuum vent.
b. Emergency Venting
8-inch emergency vent for primary and 8-inch interstice vent.
c. Manways
1 36-inch manway
d. Water Draw‐Off
1 inch water draw port with hand pump installed.
e. High Level Shutoff Valve
Magnatrol solenoid operated high-level shutoff.
f. Level Alarms
High Level, High High level, Low Level
g. Gauging
Ronan tank monitor system
h. Pumps
Submersible turbine pump.
i. Stairs and Platforms
Coated Carbon steel for support frame and platform treads with ladder access
j. Grounding and Bonding
Tank has a ground on saddle
4. Tank Coating Epoxy coated interior and exterior
5. Tank Piping System All pipes are coated carbon steel and in good condition
6. Fire Protection System None
7. Secondary Containment Coated welded carbon Steel with no containment drain valve installed
C. FINDINGS AND RECOMMENDATIONS
1. MANDATORY REPAIRS per STI SP001, UFC 3‐460‐01, NFPA 30, or NFPA 30A Mandatory repairs represent items that require immediate attention, in order to prevent imminent risk to system operators, equipment integrity, or the adjacent environment. The tank should remain out of service until these repairs are completed.
No Mandatory repairs at this time
2. REQUIRED REPAIRS to Fully Comply with STI SP001, UFC 3‐460‐01, NFPA 30, or NFPA 30A Recommended repairs represent items that should be addressed in a timely manner in order to prevent future potential risks to system operators, equipment integrity, or the adjacent environment. These items may be required by Federal, State and Local Codes or by Military Criteria.
| a. Title: | Apply | Facility | Number | Labeling | |
| OBSERVATION: | The tank does not have all the required labeling mandated by UFC 3-460-1. UFC 3- |
460-1 2-18 states each tank shall be marked with the following: "per MIL-STD-161 Tank number, Facility number, No smoking on class 1 tanks. And “confined Space” on roof manhole/ladder hach".
| REFERENCE: | UFC | 3‐460‐1 | SECTION | 2‐17 | ||
| RECOMMENDATION: | INSTALL | LABELING | TO | INCLUDE | FACILITY | NUMBER |
| b. Title: | Manual | Gauge | ||
| OBSERVATION: | The tank does not have a clock gauge installed. | |||
| REFERENCE: | UFC | 3‐460‐01 | ||
| RECOMMENDATION: | ADD | MANUAL | GAUGE |
3. RECOMMENDED REPAIRS as Part of Regular Maintenance Recommended repairs represent items that should be addressed in a timely manner in order to prevent future potential risks to system operators, equipment integrity, or the adjacent environment.
| a. Title: | Coating | failures | |||||||
| OBSERVATION: | The tank ha approximately 20% coating failures | ||||||||
| REFERENCE: | UFC | 3‐460‐01 | |||||||
| RECOMMENDATION: | RECOAT | TANK | AS | NEEDED | TO | SLOW | CORROSION | RATE |
APPENDIX A: ENGINEERING CALCULATIONS AND DRAWINGS
TANK CONFIGURATION DIAGRAM
APPENDIX B: STI SP001 FORMAL EXTERNAL INSPECTION CHECKLIST
OWNER INFORMATION
FACILITY INFORMATION
INSTALLER INFORMATION
Tooele Depot, UT Tooele Depot, UT Unknown
Name Name Name
Unknown
Number and Street Number and Street Number and Street
Tooele Depot Tooele Depot Unknown
City, State, Zip Code City, State, Zip Code City, State, Zip Code
TANK ID Diesel Tank
SPECIFICATION:
Design: UL SWRI Horizontal Vertical Rectangular
API Other
Unknown
Manufacturer: Pekins Contents: Diesel Construction Date: 1996 Last Repair/Reconstruction Date: unknown
Dimensions: 9’ D 33’ L Capacity: 12,000 Gallons Last Change of Service Date: N/A
Construction: Bare Steel Catholically Protected (Check one: A. Galvanic or B. Impressed Current)Date Installed: _______________
Coated Steel Concrete Plastic/Fiberglass Other
Double-Bottom Double-Wall Lined Date Installed: _______________
Containment: Earthen Dike Steel Dike Concrete Synthetic Liner Other Coated
CRDM: Date Installed: unknown Type: Elevated AST
Release Prevention Barrier: Date Installed: unknown Type: Coated Steel Containment
Inspection Date: July 27, 2020 Retain Until Date: July 27, 2023 (36 months from inspection date)
Prior Inspection Date: N/A Inspector Name: John Hester STI Cert# AST 2092, ASNT Level II Cert # 164397
Tanks Inspected (ID #’s): Tank 5129B
Inspection Guidance:
For equipment not included in this Standard, follow the manufacturer recommended inspection/testing schedules and procedures.
The periodic AST Inspection is intended for monitoring the external AST condition and its containment structure. This visual inspection does not require a Certified Inspector. It shall be performed by an owner’s inspector who is familiar with the site and can identify changes and developing problems.
Remove promptly upon discovery standing water or liquid in the primary tank, secondary containment area, interstice, or spill container.
Before discharge to the environment, inspect the liquid for regulated products or other contaminants and disposed of it properly.
In order to comply with EPA SPCC (Spill Prevention, Control and Countermeasure) rules, a facility must regularly test liquid level sensing devices to ensure proper operation (40 CFR 112.8(c)(8)(v)).
(*) designates an item in a non‐conformance status. This indicates that action is required to address a problem.
Non‐conforming items important to tank or containment integrity require evaluation by an engineer experienced in AST design, a Certified
Inspector, or a tank manufacturer who will determine the corrective action. Note the non‐conformance and corresponding corrective action in the comment section.
Retain the completed checklists for 36 months.
Complete this checklist on an annual basis supplemental to the owner monthly‐performed inspection checklists.
Note: If a change has occurred to the tank system or containment that may affect the SPCC plan, the condition should be evaluated against the current plan requirement by a Professional Engineer knowledgeable in SPCC development and implementation.
| Item Task Status | Comments | |
| 1.0 | Tank | Containment |
1.1Containment structure
Check for:
Holes or cracks in containment wall or floor
Washout Liner degradation Corrosion Leakage Paint failure Tank settling
Yes* No
N/A
2.0 Tank Foundation and Supports
2.1 Foundation
Settlement or foundation washout?
Yes* No
N/A
Concrete Slab
2.2 Concrete
pad or ring wall
Cracking or spalling?
2.3 Supports Check for
corrosion, paint failure, etc.
2.4 Water
drainage
Water drains away from tank?
Yes No
Item Task Status Comments
2.5 Tank
grounding
Strap secured and in good condition?
Yes No
N/A
One grounding strap
3.0 Cathodic Protection
3.1 Gavlvanic
cathodic protection system
Confirm system is functional, includes the wire connections for galvanic systems
3.2 Impressed
current system
a. Inspect the operational components (power switch, meters, and alarms).
b. Record hour meter, ammeter and voltmeter readings.
4.0 Tank Shell, Heads, Roof
4.1 Coating Check for coating
failure
Yes No
N/A
Minor coating failure
4.2 Steel
condition
Check for:
Dents Buckling Bulging Corrosion Cracking
4.3 Roof slope Check for low
points and standing water
5.0 Tank Equipment
5.1 Vents Verify that
components are moving freely and vent passageways are not obstructed for:
Emergency vent covers Pressure/vacuum vent poppets Other moving vent components
Item Task Status Comments
5.2 Valves Check the
condition of all valves for leaks, corrosion and damage.
5.2.1 Anti-
siphon, check and gate valves
Cycle the valve open and closed and check for proper operation.
5.2.2 Pressure
regulator valve
Check for proper operation. (Note that there may be small, 1/4 inch drain plugs in the bottom of the valve that are not visible by looking from above only)
5.2.3 Expansion
relief valve
Check that the valve is in the proper orientation.
(Note that fuel must be discharged back to the tank via a separate pipe or tubing.)
5.2.4 Solenoid
valves
Cycle power to valve to check operation.
(Electrical solenoids can be verified by listening to the plunger opening and closing. If no audible confirmation, the valve should be inspected for the presence and operation of the plunger.)
Item Task Status Comments
5.2.5 Fire and
shear valves
a. Manually cycle the valve to ensure components are moving freely and that the valve handle or lever has clearance to allow valve to close completely.
Tank does not have a fire or shear valve
b. Valves must not be wired in open position.
N/A
c. Make sure fusible element is in place and correctly positioned.
N/A
d. Be sure test ports are sealed with plug after testing is complete and no temporary test fixture or component remains connected to valve.
5.3 Interstitial
leak detection equipment
Check condition of equipment, including:
The window is clean and clear in sight leak gauges.
The wire connections of electronic gauges for tightness and corrosion
Activate the test button, if applicable.
Item Task Status Comments
5.4 Spill
containmen t boxes on fill pipe
a. If corrosion, damage, or wear has compromised the ability of the unit to perform spill containment functions, replace the unit.
b. Inspect the connections to the AST for tightness, as well as the bolts,nuts, washers for condition and replace if necessary.
N/A
c. Drain valves must be operable and closed
5.5 Strainer a. Check that the
strainer is clean and in good condition.
5.5 Strainer b. Access strainer
basket and check cap and gasket seal as well as bolts.
5.6 Filter a. Check that the
filter is in good condition and is within the manufacturer’s expected service life. Replace, if necessary.
Tank uses a filter at the dispensers
b. Check for leaks and decreased fuel flow
5.7 Flame
arrestors
Follow manufacturer’s instructions. Check for corrosion and blockage of air passages.
Item Task Status Comments
5.8 Leak
detector for submersible pump systems
Test according to manufacturer's instructions and authority having jurisdiction (AHJ).
Verify leak detectors are suited and properly installed for aboveground use.
5.9 Liquid level
equipment
a. Has equipment been tested to ensure proper operation?
Yes No
N/A
Tank does not have a manual guage
b. Does equipment operate as required?
Yes No
N/A
c. Follow manufacturer’s instructions
Yes No
N/A
5.10 Overfill
equipment
a. Follow manufacturer’s instructions and regulatory requirements for inspection and functionality verification.
b. Confirm device is suited for above ground use by the manufacturer
6.0 Insulated Tanks
6.1 Insulation
Check condition of insulation for:
Missing sections
Areas of moisture
Mold Damage
6.2 Insulation
cover or jacket
Check for damage that will allow water intrusion
Item Task Status Comments
7.0 Miscellaneous
7.1 Electrical
wiring and boxes
Are they in good condition?
7.2 Labels and
tags
Ensure that all labels and tags are intact and readable.
Tank needs facility number labeling installed.
APPENDIX C: STI SP001 MONTHLY INSPECTION CHECKLIST
Inspection Date: July 27 2020 Retain Until Date: July 27 2023 (36 months from inspection date)
Prior Inspection Date: N/A Inspector Name: John Hester STI Cert# AST 2092, ASNT Level II Cert # 164397
Tanks Inspected (ID #’s): Tank 5129B
Inspection Guidance:
For equipment not included in this Standard, follow the manufacturer recommended inspection/testing schedules and procedures.
The periodic AST Inspection is intended for monitoring the external AST condition and its containment structure. This visual inspection does not require a Certified Inspector. It shall be performed by an owner’s inspector who is familiar with the site and can identify changes and developing problems.
Upon discovery of water in the primary tank, secondary containment area, interstice, or spill container, remove promptly or take other corrective action. Before discharge to the environment, inspect the liquid for regulated products or other contaminants and disposed of it properly.
(*) designates an item in a non‐conformance status. This indicates that action is required to address a problem.
Non‐conforming items important to tank or containment integrity require evaluation by an engineer experienced in AST design, a Certified
Inspector, or a tank manufacturer who will determine the corrective action. Note the non‐conformance and corresponding corrective action in the comment section.
Retain the completed checklists for 36 months.
In the event of severe weather (snow, ice, wind storms) or maintenance (such as painting) that could affect the operation of critical components (normal and emergency vents, valves), an inspection of these components is required as soon as the equipment is safely accessible after the event.
| Item Task Status | Comments | |
| 1.0 | Tank | Containment |
1.1 Containment
structure
Check for water, debris, cracks or fire hazard
Yes No
Vegetation growth in containment
1.2 Primary tank Check for water
1.3 Containment
drain valves
Operable and in a closed position
1.4 Pathways
and entry
Clear and gates/doors operable
2.0 Leak Detection
2.1 Tank Visible signs of
leakage
2.2 Secondary
Containment
Visible signs of leakage from tank into secondary containment
Item Task Status Comments
2.3 Surrounding
soil
Visible signs of leakage
2.4 Interstice Visible signs of
leakage
3.0 Tank Equipment
3.1 Valves a. Check for leaks.
Yes No
N/A
Issue control valve
b. Tank drain valves must be kept locked.
Yes No
N/A
3.2 Spill
containment boxes on fill pipe
a. Inspect for debris, residue, and water in the box and remove.
N/A
b. Drain valves must be operable and closed.
Yes No
N/A
3.3 Liquid level
equipment
a. Both visual and mechanical devices must be inspected for physical damage.
b. Check that the device is easily readable
Yes No
N/A
3.4 Overfill
equipment
a. If equipped with a "test" button, activate the audible horn or light to confirm operation. This could be battery powered.
Replace the battery if needed
N/A
Item Task Status Comments
b. If overfill valve is equipped with a mechanical test mechanism;
actuate the mechanism to confirm operation.
N/A
3.5 Piping
connections
Check for leaks, corrosion and damage
N/A
4.0 Tank Attachments and Appurtenances
4.1 Ladder and
platform structure
Secure with no sign of severe corrosion or damage?
Yes No
N/A
Coated carbon steel support structure and platform
5.0 Other Conditions
5.1 Are there other conditions that
should be addressed for continued safe operation or that may affect the site spill prevention plan?
APPENDIX E: PHOTOGRAPHS
E.1: Tank North View E.2: Tank South View
E.3: Tank East View E.4: Tank West View
E.5: Tank Saddle E.6: Tank Water Draw
E.7: Grounding Strap E.8: Name Plate
E.9: Fill Stand E.10: Issue Piping
E.11: Top Viewing West E.12: Pump
E.13: 36‐inch Manway E.14: Primary Vent
E.15: 8” Interstice Emergency Vent E.16: 8” Emergency Vent
E.17: Interstice Probe E.18: Receipt Line
E.19: Coating Failure E.20: Gauging Hatch
E.21: ATG E.22: Dispenser