This is a Questions and Answers document for solicitation W9128F25Q0009 for janitorial services at the Williston, ND project office, issued by the Army Corps of Engineers Omaha District. The document includes responses to nine contractor questions updated through January 30, 2025.
Key details revealed include: the procurement is a 100% small business set-aside, there is no incumbent contractor or current contract amount, and the facility contains two bathrooms with tiled floors and rugs. The government declined to provide specific square footage or budget information. A site visit was conducted on January 30th at 9am with no additional visits planned before quotes are due. Any subcontracting must comply with the small business set-aside requirements and all solicitation terms.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Government Responses to Contractor Questions
Solicitation W9128F25Q0009
Updated 27 January 2025 & 29 January 2025 & 30 January 2025
1. Will there be a site visit? Response: Amendment 1 has been posted containing the site visit information.
2. Square Footage of location(s)? Response: As stated in the site visit provision added with Amendment 0001, the site visit is provided for your company to review the area. The specific square footage will not be added to the solicitation.
3. Who is the current contractor? Response: There is no current contractor.
4. What is the current contract amount? Response: There is no current contract amount.
5. If you are unable to provide current contract amount, what is the current budget your agency gas for this project? Response: The budget for this service will not be provided.
6. How many bathrooms are in the facility? Response: Two (2) bathrooms are in the Williston Project O ice.
7. Is the main area carpet or tile? Response: The areas listed within the PWS are tiled with rugs.
8. Is subcontracting permitted for this project? Response: The solicitation is 100% small business set-aside and any subcontracting approach by the prime contractor must ensure compliance with this set-aside. Additionally, the prime contractor shall comply with all requirements of the solicitation and resulting award.
9. Will a second site visit be conducted? Response: The site visit is being conducting today January 30th at 9 am., the team cannot conduct another site prior to the quote due date.