This document is a Firm Fixed Price (FFP) Spreadsheet for a federal contract opportunity related to a $249M Indefinite Delivery, Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) for Environmental Remediation Services (ERS) - Small Business Set-Aside.

The FFP Spreadsheet provides detailed pricing information for the base years (1-5) and option years (1-2) of the contract, as well as a 6-month extension. The pricing includes direct labor, other direct costs such as equipment/materials, travel, and subcontracted laboratory analysis. The spreadsheet specifies that certain costs are government-provided and cannot be changed by the offeror. The contract opportunity is solicitation number W9128F24R0012, issued by the U.S. Army Corps of Engineers (USACE) Omaha District, with proposals due on October 4, 2024. The contract will be a small business set-aside, with up to 8 IDIQ contracts awarded.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FFP Spreadsheet - BASE PER YR 1

TAB 6 (TABLE 6) - Firm Fixed Price Spreadsheet - W9128F24R0012 - $249M SB ERS MATOC
Reference Section L
Sample Project Price Proposal - Base Year 1
Direct LaborBurdened Rate (See Note 5 Below)UnitsQuantitySubtotal
Program Managerhrs30$ - 0
Project Managerhrs380$ - 0
Senior Contract Managerhrs140$ - 0
Procurement Specialisthrs230$ - 0
Contractor Quality Control Supervisorhrs140$ - 0
Safety and Health Managerhrs140$ - 0
Clericalhrs140$ - 0
Site Superintendent/ Construction Managerhrs300$ - 0
Civil Engineerhrs300$ - 0
Chemisthrs270$ - 0
Site Safety & Health Officerhrs300$ - 0
Regulatory Specialisthrs300$ - 0
Hazardous Materials/ Waste Specialisthrs300$ - 0
Process Engineerhrs230$ - 0
Senior UXO Supervisorhrs220$ - 0
UXO Quality Control Supervisorhrs220$ - 0
UXO Safety Officerhrs220$ - 0
Direct Labor Total, excluding profit$ - 0
C. Other Direct CostsRateUnitsQuantitySubtotal
Equipment and Material Costs:
Materials, supplies, equipment, and Other Direct Costs (ODCs) (Government provided number) (NOTE 1)$ 24,000.00ls1$ 24,000.00
$ - 0$ - 0
$ - 0$ - 0
Subtotal (Equipment and Materials):$ 24,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Equipment & Materials Total, excluding profit:$ 24,000.00
Travel Costs:RateUnitsQuantity
Airfare (NOTE 1)$700.00Trip4$ 2,800.00
Private Auto Travel (NOTE 1)$0.625miles800$ 500.00
Lodging (NOTE 1)$120.00days88$ 10,560.00
Meals and I&E (travel days) (NOTE 1)$48.00days10$ 480.00
Meals and I&E (work days) (NOTE 1)$64.00days80$ 5,120.00
$ - 0
Subtotal (Travel)$ 19,460.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Travel Cost Total, excluding profit$ 19,460.00
Subcontract Costs:RateUnitsQuantity
Subcontract Effort - Lab Analysis (Government provided number) (NOTE 1)$20,000.00each1$ 20,000.00
Subtotal (Subcontracts)$ 20,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Subcontract Total, excluding profit:$ 20,000.00
Total
Project Cost subject to Profit:$ 63,460.00
Project Cost NOT subject to Profit (See Note 3):$ - 0
Total Cost:$ 63,460.00
Fixed Fee
Maximum Profit Rate:
Profit Amount:$ - 0
Total Term Cost
YEAR 1 - Total Price:$ 63,460.00
Notes:

1. The following Government-provided costs shall not be changed by the Offeror: Materials, supplies, equipment, and other ODCs, Travel, and Subcontractor costs. Offerors should only provide numbers/percentages in highlighted (yellow) cells.

2. The escalation shown for ODC, Travel, and Subcontractor costs are for sample project calculations only. The actual escalation for travel costs, if any, are set annually by General Services Administration (GSA).

3. Please provide a description of what is not subject to fixed fee (if applicable) in the space provided at the bottom of this form.

4. Markup rates for indirect costs shall not be discounted from the rate(s) submitted for Section B – Table.

5. All markup rates utilized in the Cost Spreadsheet shall be included in Table 5 with the required supporting information. If a firm applies multiple indirect rates to any of the cost other than direct labor, the submission shall account for all the rates.

6. Rate should be the Burdened Labor Rate from the appropriate Year in Table 1 - Binding Maximum Hourly Labor Rate Schedule without discount.

Description of what is NOT subject to fixed fee (if applicable). A continuation sheet may be used if needed. :

Notes:

1. The following Government-provided costs shall not be changed by the Offeror: Materials, supplies, equipment, and other ODCs, Travel, and Subcontractor costs. Offerors should only provide numbers/percentages in highlighted (yellow) cells.

2. Please provide a description of what is not subject to application of profit or fixed fee (if applicable) in the space provided at the bottom of this form.

3. Markup rates for indirect costs shall not be discounted from the rate(s) submitted for Section B – Table.

4. All markup rates utilized in the Firm Fixed Price Spreadsheet shall be included in Table 5 with the required supporting information. If a firm applies multiple indirect rates to any of the cost other than direct labor, the submission shall account for all the rates.

5. Rate should be the Burdened Labor Rate from Table 1 - Maximum Binding Hourly Labor Rate Schedule without discount.

6. This Table is a view of Year 1 only.

Description of what is NOT subject to profit (if applicable):

FFP Spreadsheet - BASE PER YR 2

TAB 6 (TABLE 6) - Firm Fixed Price Spreadsheet - W9128F24R0012 - $249M SB ERS MATOC
Reference Section L
Sample Project Price Proposal - Base Year 2
Direct LaborBurdened Rate (See Note 5 Below)UnitsQuantitySubtotal
Program Managerhrs30$ - 0
Project Managerhrs380$ - 0
Senior Contract Managerhrs140$ - 0
Procurement Specialisthrs230$ - 0
Contractor Quality Control Supervisorhrs140$ - 0
Safety and Health Managerhrs140$ - 0
Clericalhrs140$ - 0
Site Superintendent/ Construction Managerhrs300$ - 0
Civil Engineerhrs300$ - 0
Chemisthrs270$ - 0
Site Safety & Health Officerhrs300$ - 0
Regulatory Specialisthrs300$ - 0
Hazardous Materials/ Waste Specialisthrs300$ - 0
Process Engineerhrs230$ - 0
Senior UXO Supervisorhrs220$ - 0
UXO Quality Control Supervisorhrs220$ - 0
UXO Safety Officerhrs220$ - 0
Direct Labor Total, excluding profit$ - 0
C. Other Direct CostsRateUnitsQuantitySubtotal
Equipment and Material Costs:
Materials, supplies, equipment, and Other Direct Costs (ODCs) (Government provided number) (NOTE 1)$ 24,000.00ls1$ 24,000.00
$ - 0$ - 0
$ - 0$ - 0
Subtotal (Equipment and Materials):$ 24,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Equipment & Materials Total, excluding profit:$ 24,000.00
Travel Costs:RateUnitsQuantity
Airfare (NOTE 1)$700.00Trip4$ 2,800.00
Private Auto Travel (NOTE 1)$0.625miles800$ 500.00
Lodging (NOTE 1)$120.00days88$ 10,560.00
Meals and I&E (travel days) (NOTE 1)$48.00days10$ 480.00
Meals and I&E (work days) (NOTE 1)$64.00days80$ 5,120.00
$ - 0
Subtotal (Travel)$ 19,460.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Travel Cost Total, excluding profit$ 19,460.00
Subcontract Costs:RateUnitsQuantity
Subcontract Effort - Lab Analysis (Government provided number) (NOTE 1)$20,000.00each1$ 20,000.00
Subtotal (Subcontracts)$ 20,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Subcontract Total, excluding profit:$ 20,000.00
Total
Project Cost subject to Profit:$ 63,460.00
Project Cost NOT subject to Profit (See Note 3):$ - 0
Total Cost:$ 63,460.00
Fixed Fee
Maximum Profit Rate:
Profit Amount:$ - 0
Total Term Cost
YEAR 2 - Total Price:$ 63,460.00
Notes:

1. The following Government-provided costs shall not be changed by the Offeror: Materials, supplies, equipment, and other ODCs, Travel, and Subcontractor costs. Offerors should only provide numbers/percentages in highlighted (yellow) cells.

2. Please provide a description of what is not subject to fixed fee (if applicable) in the space provided at the bottom of this form.

3. Markup rates for indirect costs shall not be discounted from the rate(s) submitted for Section B – Table.

4. All markup rates utilized in the Cost Spreadsheet shall be included in Table 5 with the required supporting information. If a firm applies multiple indirect rates to any of the cost other than direct labor, the submission shall account for all the rates.

5. Rate should be the Burdened Labor Rate from the appropriate Year in Table 1 - Binding Maximum Hourly Labor Rate Schedule without discount. 6. This Table is a view of Year 2 only.

Description of what is NOT subject to fixed fee (if applicable). A continuation sheet may be used if needed. :

FFP Spreadsheet - BASE PER YR 3

TAB 6 (TABLE 6) - Firm Fixed Price Spreadsheet - W9128F24R0012 - $249M SB ERS MATOC
Reference Section L
Sample Project Price Proposal - Base Year 3
Direct LaborBurdened Rate (See Note 5 Below)UnitsQuantitySubtotal
Program Managerhrs30$ - 0
Project Managerhrs380$ - 0
Senior Contract Managerhrs140$ - 0
Procurement Specialisthrs230$ - 0
Contractor Quality Control Supervisorhrs140$ - 0
Safety and Health Managerhrs140$ - 0
Clericalhrs140$ - 0
Site Superintendent/ Construction Managerhrs300$ - 0
Civil Engineerhrs300$ - 0
Chemisthrs270$ - 0
Site Safety & Health Officerhrs300$ - 0
Regulatory Specialisthrs300$ - 0
Hazardous Materials/ Waste Specialisthrs300$ - 0
Process Engineerhrs230$ - 0
Senior UXO Supervisorhrs220$ - 0
UXO Quality Control Supervisorhrs220$ - 0
UXO Safety Officerhrs220$ - 0
Direct Labor Total, excluding profit$ - 0
C. Other Direct CostsRateUnitsQuantitySubtotal
Equipment and Material Costs:
Materials, supplies, equipment, and Other Direct Costs (ODCs) (Government provided number) (NOTE 1)$ 24,000.00ls1$ 24,000.00
$ - 0$ - 0
$ - 0$ - 0
Subtotal (Equipment and Materials):$ 24,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Equipment & Materials Total, excluding profit:$ 24,000.00
Travel Costs:RateUnitsQuantity
Airfare (NOTE 1)$700.00Trip4$ 2,800.00
Private Auto Travel (NOTE 1)$0.625miles800$ 500.00
Lodging (NOTE 1)$120.00days88$ 10,560.00
Meals and I&E (travel days) (NOTE 1)$48.00days10$ 480.00
Meals and I&E (work days) (NOTE 1)$64.00days80$ 5,120.00
$ - 0
Subtotal (Travel)$ 19,460.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Travel Cost Total, excluding profit$ 19,460.00
Subcontract Costs:RateUnitsQuantity
Subcontract Effort - Lab Analysis (Government provided number) (NOTE 1)$20,000.00each1$ 20,000.00
Subtotal (Subcontracts)$ 20,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Subcontract Total, excluding profit:$ 20,000.00
Total
Project Cost subject to Profit:$ 63,460.00
Project Cost NOT subject to Profit (See Note 3):$ - 0
Total Cost:$ 63,460.00
Fixed Fee
Maximum Profit Rate:
Profit Amount:$ - 0
Total Term Cost
YEAR 3 - Total Price:$ 63,460.00

Notes:

1. The following Government-provided costs shall not be changed by the Offeror: Materials, supplies, equipment, and other ODCs, Travel, and Subcontractor costs. Offerors should only provide numbers/percentages in highlighted (yellow) cells.

2. Please provide a description of what is not subject to application of profit or fixed fee (if applicable) in the space provided at the bottom of this form.

3. Markup rates for indirect costs shall not be discounted from the rate(s) submitted for Section B – Table.

4. All markup rates utilized in the Firm Fixed Price Spreadsheet shall be included in Table 5 with the required supporting information. If a firm applies multiple indirect rates to any of the cost other than direct labor, the submission shall account for all the rates.

5. Rate should be the Burdened Labor Rate from Table 1 - Maximum Binding Hourly Labor Rate Schedule without discount.

6. This Table is a view of Year 3 only.

Description of what is NOT subject to profit (if applicable):

FFP Spreadsheet - BASE YR 4

TAB 6 (TABLE 6) - Firm Fixed Price Spreadsheet - W9128F24R0012 - $249M SB ERS MATOC
Reference Section L
Sample Project Price Proposal - Base Year 4
Direct LaborBurdened Rate (See Note 5 Below)UnitsQuantitySubtotal
Program Managerhrs30$ - 0
Project Managerhrs380$ - 0
Senior Contract Managerhrs140$ - 0
Procurement Specialisthrs230$ - 0
Contractor Quality Control Supervisorhrs140$ - 0
Safety and Health Managerhrs140$ - 0
Clericalhrs140$ - 0
Site Superintendent/ Construction Managerhrs300$ - 0
Civil Engineerhrs300$ - 0
Chemisthrs270$ - 0
Site Safety & Health Officerhrs300$ - 0
Regulatory Specialisthrs300$ - 0
Hazardous Materials/ Waste Specialisthrs300$ - 0
Process Engineerhrs230$ - 0
Senior UXO Supervisorhrs220$ - 0
UXO Quality Control Supervisorhrs220$ - 0
UXO Safety Officerhrs220$ - 0
Direct Labor Total, excluding profit$ - 0
C. Other Direct CostsRateUnitsQuantitySubtotal
Equipment and Material Costs:
Materials, supplies, equipment, and Other Direct Costs (ODCs) (Government provided number) (NOTE 1)$ 24,000.00ls1$ 24,000.00
$ - 0$ - 0
$ - 0$ - 0
Subtotal (Equipment and Materials):$ 24,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Equipment & Materials Total, excluding profit:$ 24,000.00
Travel Costs:RateUnitsQuantity
Airfare (NOTE 1)$700.00Trip4$ 2,800.00
Private Auto Travel (NOTE 1)$0.625miles800$ 500.00
Lodging (NOTE 1)$120.00days88$ 10,560.00
Meals and I&E (travel days) (NOTE 1)$48.00days10$ 480.00
Meals and I&E (work days) (NOTE 1)$64.00days80$ 5,120.00
$ - 0
Subtotal (Travel)$ 19,460.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Travel Cost Total, excluding profit$ 19,460.00
Subcontract Costs:RateUnitsQuantity
Subcontract Effort - Lab Analysis (Government provided number) (NOTE 1)$20,000.00each1$ 20,000.00
Subtotal (Subcontracts)$ 20,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Subcontract Total, excluding profit:$ 20,000.00
Total
Project Cost subject to Profit:$ 63,460.00
Project Cost NOT subject to Profit (See Note 3):$ - 0
Total Cost:$ 63,460.00
Fixed Fee
Maximum Profit Rate:
Profit Amount:$ - 0
Total Term Cost
YEAR 4 - Total Price:$ 63,460.00

Notes:

1. The following Government-provided costs shall not be changed by the Offeror: Materials, supplies, equipment, and other ODCs, Travel, and Subcontractor costs. Offerors should only provide numbers/percentages in highlighted (yellow) cells.

2. Please provide a description of what is not subject to application of profit or fixed fee (if applicable) in the space provided at the bottom of this form.

3. Markup rates for indirect costs shall not be discounted from the rate(s) submitted for Section B – Table.

4. All markup rates utilized in the Firm Fixed Price Spreadsheet shall be included in Table 5 with the required supporting information. If a firm applies multiple indirect rates to any of the cost other than direct labor, the submission shall account for all the rates.

5. Rate should be the Burdened Labor Rate from Table 1 - Maximum Binding Hourly Labor Rate Schedule without discount.

6. This Table is a view of Year 4 only.

Description of what is NOT subject to profit (if applicable):

FFP Spreadsheet - BASE YR 5

TAB 6 (TABLE 6) - Firm Fixed Price Spreadsheet - W9128F24R0012 - $249M SB ERS MATOC
Reference Section L
Sample Project Price Proposal - Base Year 5
Direct LaborBurdened Rate (See Note 5 Below)UnitsQuantitySubtotal
Program Managerhrs30$ - 0
Project Managerhrs380$ - 0
Senior Contract Managerhrs140$ - 0
Procurement Specialisthrs230$ - 0
Contractor Quality Control Supervisorhrs140$ - 0
Safety and Health Managerhrs140$ - 0
Clericalhrs140$ - 0
Site Superintendent/ Construction Managerhrs300$ - 0
Civil Engineerhrs300$ - 0
Chemisthrs270$ - 0
Site Safety & Health Officerhrs300$ - 0
Regulatory Specialisthrs300$ - 0
Hazardous Materials/ Waste Specialisthrs300$ - 0
Process Engineerhrs230$ - 0
Senior UXO Supervisorhrs220$ - 0
UXO Quality Control Supervisorhrs220$ - 0
UXO Safety Officerhrs220$ - 0
Direct Labor Total, excluding profit$ - 0
C. Other Direct CostsRateUnitsQuantitySubtotal
Equipment and Material Costs:
Materials, supplies, equipment, and Other Direct Costs (ODCs) (Government provided number) (NOTE 1)$ 24,000.00ls1$ 24,000.00
$ - 0$ - 0
$ - 0$ - 0
Subtotal (Equipment and Materials):$ 24,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Equipment & Materials Total, excluding profit:$ 24,000.00
Travel Costs:RateUnitsQuantity
Airfare (NOTE 1)$700.00Trip4$ 2,800.00
Private Auto Travel (NOTE 1)$0.625miles800$ 500.00
Lodging (NOTE 1)$120.00days88$ 10,560.00
Meals and I&E (travel days) (NOTE 1)$48.00days10$ 480.00
Meals and I&E (work days) (NOTE 1)$64.00days80$ 5,120.00
$ - 0
Subtotal (Travel)$ 19,460.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Travel Cost Total, excluding profit$ 19,460.00
Subcontract Costs:RateUnitsQuantity
Subcontract Effort - Lab Analysis (Government provided number) (NOTE 1)$20,000.00each1$ 20,000.00
Subtotal (Subcontracts)$ 20,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Subcontract Total, excluding profit:$ 20,000.00
Total
Project Cost subject to Profit:$ 63,460.00
Project Cost NOT subject to Profit (See Note 3):$ - 0
Total Cost:$ 63,460.00
Fixed Fee
Maximum Profit Rate:
Profit Amount:$ - 0
Total Term Cost
YEAR 5 - Total Price:$ 63,460.00

Notes:

1. The following Government-provided costs shall not be changed by the Offeror: Materials, supplies, equipment, and other ODCs, Travel, and Subcontractor costs. Offerors should only provide numbers/percentages in highlighted (yellow) cells.

2. Please provide a description of what is not subject to application of profit or fixed fee (if applicable) in the space provided at the bottom of this form.

3. Markup rates for indirect costs shall not be discounted from the rate(s) submitted for Section B – Table.

4. All markup rates utilized in the Firm Fixed Price Spreadsheet shall be included in Table 5 with the required supporting information. If a firm applies multiple indirect rates to any of the cost other than direct labor, the submission shall account for all the rates.

5. Rate should be the Burdened Labor Rate from Table 1 - Maximum Binding Hourly Labor Rate Schedule without discount.

6. This Table is a view of Year 5 only.

Description of what is NOT subject to profit (if applicable):

FFP Spreadsheet - OPT YR 1

TAB 6 (TABLE 6) - Firm Fixed Price Spreadsheet - W9128F24R0012 - $249M SB ERS MATOC
Reference Section L
Sample Project Price Proposal - Option Year 1
Direct LaborBurdened Rate (See Note 5 Below)UnitsQuantitySubtotal
Program Managerhrs30$ - 0
Project Managerhrs380$ - 0
Senior Contract Managerhrs140$ - 0
Procurement Specialisthrs230$ - 0
Contractor Quality Control Supervisorhrs140$ - 0
Safety and Health Managerhrs140$ - 0
Clericalhrs140$ - 0
Site Superintendent/ Construction Managerhrs300$ - 0
Civil Engineerhrs300$ - 0
Chemisthrs270$ - 0
Site Safety & Health Officerhrs300$ - 0
Regulatory Specialisthrs300$ - 0
Hazardous Materials/ Waste Specialisthrs300$ - 0
Process Engineerhrs230$ - 0
Senior UXO Supervisorhrs220$ - 0
UXO Quality Control Supervisorhrs220$ - 0
UXO Safety Officerhrs220$ - 0
Direct Labor Total, excluding profit$ - 0
C. Other Direct CostsRateUnitsQuantitySubtotal
Equipment and Material Costs:
Materials, supplies, equipment, and Other Direct Costs (ODCs) (Government provided number) (NOTE 1)$ 24,000.00ls1$ 24,000.00
$ - 0$ - 0
$ - 0$ - 0
Subtotal (Equipment and Materials):$ 24,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Equipment & Materials Total, excluding profit:$ 24,000.00
Travel Costs:RateUnitsQuantity
Airfare (NOTE 1)$700.00Trip4$ 2,800.00
Private Auto Travel (NOTE 1)$0.625miles800$ 500.00
Lodging (NOTE 1)$120.00days88$ 10,560.00
Meals and I&E (travel days) (NOTE 1)$48.00days10$ 480.00
Meals and I&E (work days) (NOTE 1)$64.00days80$ 5,120.00
$ - 0
Subtotal (Travel)$ 19,460.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Travel Cost Total, excluding profit$ 19,460.00
Subcontract Costs:RateUnitsQuantity
Subcontract Effort - Lab Analysis (Government provided number) (NOTE 1)$20,000.00each1$ 20,000.00
Subtotal (Subcontracts)$ 20,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Subcontract Total, excluding profit:$ 20,000.00
Total
Project Cost subject to Profit:$ 63,460.00
Project Cost NOT subject to Profit (See Note 3):$ - 0
Total Cost:$ 63,460.00
Fixed Fee
Maximum Profit Rate:
Profit Amount:$ - 0
Total Term Cost
OPTION YEAR 1 - Total Price:$ 63,460.00

Notes:

1. The following Government-provided costs shall not be changed by the Offeror: Materials, supplies, equipment, and other ODCs, Travel, and Subcontractor costs. Offerors should only provide numbers/percentages in highlighted (yellow) cells.

2. Please provide a description of what is not subject to application of profit or fixed fee (if applicable) in the space provided at the bottom of this form.

3. Markup rates for indirect costs shall not be discounted from the rate(s) submitted for Section B – Table.

4. All markup rates utilized in the Firm Fixed Price Spreadsheet shall be included in Table 5 with the required supporting information. If a firm applies multiple indirect rates to any of the cost other than direct labor, the submission shall account for all the rates.

5. Rate should be the Burdened Labor Rate from Table 1 - Maximum Binding Hourly Labor Rate Schedule without discount.

6. This Table is a view of Option Year 1 only.

Description of what is NOT subject to profit (if applicable):

FFP Spreadsheet - OPT YR 2

TAB 6 (TABLE 6) - Firm Fixed Price Spreadsheet - W9128F24R0012 - $249M SB ERS MATOC
Reference Section L
Sample Project Price Proposal - Option Year 2
Direct LaborBurdened Rate (See Note 5 Below)UnitsQuantitySubtotal
Program Managerhrs30$ - 0
Project Managerhrs380$ - 0
Senior Contract Managerhrs140$ - 0
Procurement Specialisthrs230$ - 0
Contractor Quality Control Supervisorhrs140$ - 0
Safety and Health Managerhrs140$ - 0
Clericalhrs140$ - 0
Site Superintendent/ Construction Managerhrs300$ - 0
Civil Engineerhrs300$ - 0
Chemisthrs270$ - 0
Site Safety & Health Officerhrs300$ - 0
Regulatory Specialisthrs300$ - 0
Hazardous Materials/ Waste Specialisthrs300$ - 0
Process Engineerhrs230$ - 0
Senior UXO Supervisorhrs220$ - 0
UXO Quality Control Supervisorhrs220$ - 0
UXO Safety Officerhrs220$ - 0
Direct Labor Total, excluding profit$ - 0
C. Other Direct CostsRateUnitsQuantitySubtotal
Equipment and Material Costs:
Materials, supplies, equipment, and Other Direct Costs (ODCs) (Government provided number) (NOTE 1)$ 24,000.00ls1$ 24,000.00
$ - 0$ - 0
$ - 0$ - 0
Subtotal (Equipment and Materials):$ 24,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Equipment & Materials Total, excluding profit:$ 24,000.00
Travel Costs:RateUnitsQuantity
Airfare (NOTE 1)$700.00Trip4$ 2,800.00
Private Auto Travel (NOTE 1)$0.625miles800$ 500.00
Lodging (NOTE 1)$120.00days88$ 10,560.00
Meals and I&E (travel days) (NOTE 1)$48.00days10$ 480.00
Meals and I&E (work days) (NOTE 1)$64.00days80$ 5,120.00
$ - 0
Subtotal (Travel)$ 19,460.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Travel Cost Total, excluding profit$ 19,460.00
Subcontract Costs:RateUnitsQuantity
Subcontract Effort - Lab Analysis (Government provided number) (NOTE 1)$20,000.00each1$ 20,000.00
Subtotal (Subcontracts)$ 20,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Subcontract Total, excluding profit:$ 20,000.00
Total
Project Cost subject to Profit:$ 63,460.00
Project Cost NOT subject to Profit (See Note 3):$ - 0
Total Cost:$ 63,460.00
Fixed Fee
Maximum Profit Rate:0.00%
Profit Amount:$ - 0
Total Term Cost
OPTION YEAR 2 - Total Price:$ 63,460.00

Notes:

1. The following Government-provided costs shall not be changed by the Offeror: Materials, supplies, equipment, and other ODCs, Travel, and Subcontractor costs. Offerors should only provide numbers/percentages in highlighted (yellow) cells.

2. Please provide a description of what is not subject to application of profit or fixed fee (if applicable) in the space provided at the bottom of this form.

3. Markup rates for indirect costs shall not be discounted from the rate(s) submitted for Section B – Table.

4. All markup rates utilized in the Firm Fixed Price Spreadsheet shall be included in Table 5 with the required supporting information. If a firm applies multiple indirect rates to any of the cost other than direct labor, the submission shall account for all the rates.

5. Rate should be the Burdened Labor Rate from Table 1 - Maximum Binding Hourly Labor Rate Schedule without discount.

6. This Table is a view of Option Year 2 only.

Description of what is NOT subject to profit (if applicable):

FFP Spreadsheet - 6 mo Ext.

TAB 6 (TABLE 6) - Firm Fixed Price Spreadsheet - W9128F24R0012 - $249M SB ERS MATOC
Reference Section L
Sample Project Price Proposal - 6 - Month Extension
Direct LaborBurdened Rate (See Note 5 Below)UnitsQuantitySubtotal
Program Managerhrs15$ - 0
Project Managerhrs190$ - 0
Senior Contract Managerhrs70$ - 0
Procurement Specialisthrs115$ - 0
Contractor Quality Control Supervisorhrs70$ - 0
Safety and Health Managerhrs70$ - 0
Clericalhrs70$ - 0
Site Superintendent/ Construction Managerhrs150$ - 0
Civil Engineerhrs150$ - 0
Chemisthrs135$ - 0
Site Safety & Health Officerhrs150$ - 0
Regulatory Specialisthrs150$ - 0
Hazardous Materials/ Waste Specialisthrs150$ - 0
Process Engineerhrs115$ - 0
Senior UXO Supervisorhrs110$ - 0
UXO Quality Control Supervisorhrs110$ - 0
UXO Safety Officerhrs110$ - 0
Direct Labor Total, excluding profit$ - 0
C. Other Direct CostsRateUnitsQuantitySubtotal
Equipment and Material Costs:
Materials, supplies, equipment, and Other Direct Costs (ODCs) (Government provided number) (NOTE 1)$ 12,000.00ls1$ 12,000.00
$ - 0$ - 0
$ - 0$ - 0
Subtotal (Equipment and Materials):$ 12,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Equipment & Materials Total, excluding fee:$ 12,000.00
Travel Costs:RateUnitsQuantity
Airfare (NOTE 1)$700.00Trip2$ 1,400.00
Private Auto Travel (NOTE 1)$0.625miles400$ 250.00
Lodging (NOTE 1)$120.00days44$ 5,280.00
Meals and I&E (travel days) (NOTE 1)$48.00days5$ 240.00
Meals and I&E (work days) (NOTE 1)$64.00days40$ 2,560.00
$ - 0
Subtotal (Travel)$ 9,730.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Travel Cost Total, excluding profit$ 9,730.00
Subcontract Costs:RateUnitsQuantity
Subcontract Effort - Lab Analysis (Government provided number) (NOTE 1)$10,000.00each1$ 10,000.00
Subtotal (Subcontracts)$ 10,000.00
Markup Rate (If applicable) (Note 4):
Markup Amount:$ - 0
Subcontract Total, excluding profit:$ 10,000.00
Total
Estimated Cost subject to Fixed Fee:$ 31,730.00
Estimated Cost NOT subject to Fixed Fee (See Note 3):$ - 0
Total Cost:$ 31,730.00
Fixed Fee
Maximum Profit Rate:0.00%
Profit Amount:$ - 0
Total Term Cost
6 - MONTH EXTENSION - Total Price:$ 31,730.00

Notes:

1. The following Government-provided costs shall not be changed by the Offeror: Materials, supplies, equipment, and other ODCs, Travel, and Subcontractor costs. Offerors should only provide numbers/percentages in highlighted (yellow) cells.

2. Please provide a description of what is not subject to application of profit or fixed fee (if applicable) in the space provided at the bottom of this form.

3. Markup rates for indirect costs shall not be discounted from the rate(s) submitted for Section B – Table.

4. All markup rates utilized in the Firm Fixed Price Spreadsheet shall be included in Table 5 with the required supporting information. If a firm applies multiple indirect rates to any of the cost other than direct labor, the submission shall account for all the rates.

5. Rate should be the Burdened Labor Rate from Table 1 - Maximum Binding Hourly Labor Rate Schedule without discount.

6. This Table is a view of 6 - Month Extension only.

Description of what is NOT subject to profit (if applicable):

TOTAL ALL SPREADSHEETS (BASE YEARS 1-5 AND OPTION YEARS 1-2 and 6 MONTH EXTENSION) $ 475,950.00

File details come from the government source that posted it. Updated .