This document is an amendment to a solicitation for a federal contract opportunity. The key details are:
The amendment is for the construction of a 360,000-gallon diesel fuel storage farm and ancillary facilities at Cavalier Space Force Station in North Dakota. The project will be executed using a design-bid-build delivery method and must comply with DoD antiterrorism/force protection requirements. The estimated construction cost range is $10-$25 million. The amendment revises the submission dates, adds a new contract line item for contaminated water disposal, updates the wage decision, and provides 100% drawings and specifications. Proposals are due in two volumes - Volume I (Technical) is due May 16, 2024 and Volume II (Pricing) is due June 7, 2024. The contract will be a firm-fixed-price award made on a best value tradeoff basis, with technical factors (past performance, technical approach, key personnel) approximately equal to cost/price. This is a full and open competition for both large and small businesses under NAICS code 237120.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is as follow s:
1. Addition of CLIN 0008 and updates to Sections 00 10 00 and 00 22 00 paragraph 1 w here highlighted.
2. Update to Wage Decision ND20240006 Highw ay.
3. 100% Draw ings & Specifications are posted w ith this amendment.
As part of this amendment, site visit attendee list w ill be posted to SAM.gov w ithin a couple days of its occurrence.
Date of receipt of Volume I (Technical) proposals remains 16 May 2024 at 2:00 PM CDT.
This amendment solicits Volume II (Pricing) proposals due 07 June 2024 at 2:00 PM CDT. Offerors must submit Volume I (Technical) proposals in order to submit Volume II (Pricing) proposals.
Government Point of Contact: Brandon Landis - brandon.p.landis@usace.army.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 40
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-May-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F24R0004
X 9B. DATED (SEE ITEM 11)
03-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-May-2024
CODE
ARMY CORPS OF ENGINEERS
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128F24R0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
The required response date/time has changed from 16-May-2024 02:00 PM to 07-Jun-
2024 02:00 PM.
CLIN 0008 is added as follows:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0008 60,000 Gallon OPTION Contaminated Water Disposal
FFP
Entire work complete for disposal of contaminated groundwater. (MILCON-funded)
FOB: Destination
PSC CD: Y1GC
NET AMT
The following have been modified:
CLIN SCHEDULE
PRICING NOTES:
OFFEROR'S NAME: ____________________________
TOTAL BASIC AMOUNT (CLINs 0001 – 0005): ____________________________
TOTAL OPTION AMOUNT (CLINs 0006 – 0007 0008): ___________________________
TOTAL PRICE (BASE PLUS OPTIONS): ___________________________________
NOTES:
1. See SECTION 00 21 00, INSTRUCTIONS TO OFFERORS for evaluation of options. The
Government reserves the right to exercise Option Items No. 0006 within 120 calendar days and
Nos. 0007 and 0008 within 180 days after issuance of Notice to Proceed, respectively. If any Options are awarded, the total contract duration will be increased by 100 calendar days one time.
2. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump-sum) prices and the total amount, the lump-sum prices will be considered the price submitted.
3. NoDak is the provider of electrical utility service at Cavalier Space Force Station.
Electrical connections to the project site will be constructed by NoDak as show on the project drawings. All costs associated with this work will be paid by the Contractor directly to NoDak. The Government will fully reimburse the Contractor for all costs associated with electrical connections made by NoDak, as listed in Item 0002, except for any additional costs incurred as a direct result of Contractor negligence. Remainder of electrical site work will be constructed by the Contractor under Item 0001.
4. For CLIN 0007, the Contractor shall keep a record of the amount of contaminated soil being disposed of. Upon completion, if the amount of contaminated soil disposed of is less than the estimated quantities shown for the CLIN, the Government will receive a credit based upon the unit price noted in CLIN 007. If the amount of contaminated soil disposed of is above 115% or below 85% of the estimated quantity, the equitable adjustment will be in accordance with FAR CLAUSE 52.211-18, VARIATION IN ESTIMATED QUANTITY. This CLIN can be awarded at any time during the Construction Contract period.
SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS
The following have been modified:
EVALUATION CRITERIA
SECTION 00 22 00
EVALUATION CRITERIA
1. GENERAL SCOPE OF WORK
Construct a 360,000-gallon diesel fuel storage farm with accompanying ancillary structure and equipment to operate the Emergency Power Plant at Cavalier Space Force Station, North Dakota. This project will be executed using a design-bid-build (DBB) project delivery method, which will require the contractor to provide the government with a complete facility and warranty based on the Request for Proposal (RFP).
The estimated construction cost of this project is between $10,000,000 and $25,000,000.
This project will provide a new, 360,000-gallon diesel fuel storage farm which will consist of multiple single double walled fuel tanks, with integral containment design, fuel monitoring, and leak detection.
The facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria (UFC) 1-200-01, General Building Requirements and UFC 1-200-02, High Performance and Sustainable Building Requirements. Each facility should be compatible with applicable DoD, Air Force, and base design standards. In addition, local materials and construction techniques shall be used where cost effective. This project will comply with DoD antiterrorism/force protection requirements per unified facilities criteria. All work shall be in accordance with RFP documents issued within this solicitation.
The Government reserves the right to award a contract without discussions in accordance with (IAW) FAR 52.215-1. Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a technical and cost/price standpoint. Offerors shall organize their proposals as described herein.
Proposals may be determined non-compliant for failure to follow this format and may be rejected from further consideration.
Competition for this contract will be full and open competition. The North American Industry Classification System (NAICS) code is 237120 (Oil and Gas Pipeline and Related Structures Construction), with a corresponding small business size standard of $45M.
THE OFFEROR SHOULD BE REGISTERED IN SYSTEM FOR AWARD MANAGEMENT WEBSITE
(SAM.GOV) FOR NAICS CODE 237120 PRIOR TO THE DATE PROPOSALS ARE DUE.
2. SOLICITATION SELECTION PROCEDURES
The acquisition approach for this project will be a Bifurcated Best Value RFP following FAR Part 15. It provides the advantages of a traditional Best Value Trade-off procurement method but advertises the 95% or 100% backcheck design while the 100% ready to advertise design is being developed. The Bifurcated Best Value process means that a portion of technical proposals will be due first. At that time, the Source Selection Evaluation Board (SSEB) will convene and begin to independently evaluate each proposal against the factors in the solicitation. Near the submission of Volume I proposals, the amendment for 100% ready to advertise design will be issued and offerors will have not less than 30 days to submit their price proposals (Volume II) to include Factor 4, Small Business Participation Plan and Price. Upon receipt of Volume II, the SSEB will reconvene to evaluate the remaining evaluation factors.
Price Analysis review and the Source Selection Authority review of the Best Value Trade-off will commence after Volume II submission.
Offerors must submit a Volume I (Technical) proposal in order to submit a Volume II (Pricing) proposal.
Offerors shall assume that revisions to Volume I (Technical) proposals will not be allowed, accepted, or evaluated after formal Volume I submission on the requested date – unless requested by the Government by amendment or other formal correspondence.
The Government reserves the right to award a contract without discussions in accordance with (IAW) FAR 52.215-1. Therefore, the Offeror’s initial proposal should contain the Offeror’s best terms from a technical and cost/price standpoint. Offerors shall organize their proposals as described herein.
Proposals may be determined non-compliant for failure to follow this format and may be rejected from further consideration.
3. TECHNICAL RATINGS
The evaluation ratings for Technical Factors 2 and 3 will be on an adjectival basis in conjunction with a narrative composed of the discussion of the particular strengths, weaknesses, and deficiencies of the proposal. The Source Selection Team (SST) will use a combined technical/risk rating system that includes consideration of risk in conjunction with the strengths, weaknesses, and deficiencies in determining technical ratings. Combined technical/risk evaluations shall utilize the combined technical/risk ratings listed in Table 1. The Combined technical/risk ratings will be used to evaluate Factor 2 Technical Approach and Factor 3 Key Personnel. The evaluation rating that will be used for Factor 1 Past Performance and Factor 4 Small Business Participation is described further below.
Table 1: Combined Technical/Risk Ratings Color Rating Description
Blue Outstanding Proposal demonstrates an exceptional approach and understanding of the requirements and contains multiple strengths and/or at least one significant strength, and risk of unsuccessful performance is low.
Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength or significant strength, and risk of unsuccessful performance is low to moderate.
Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Red Unacceptable Proposal does not meet requirements of the solicitation and, thus, contains one or more deficiencies and is unawardable, and/or risk of performance is unacceptably high.
RATING DEFINITIONS
Strength: is an aspect of an offeror's proposal with merit or will exceed specified performance or capability requirements to the advantage of the Government during contract performance.
Significant Strength: an aspect of an Offeror's proposal with appreciable merit or will exceed specified performance or capability requirements to the advantage of the Government during contract performance.
Weakness: a flaw in the proposal that increases the risk of unsuccessful contract performance.
Significant Weakness: a flaw that appreciably increases the risk of unsuccessful contract performance.
Deficiency: A material failure of proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level.
4. PAST PERFORMANCE RATING
The Past Performance evaluation factor assesses the degree of confidence the Government has in an Offeror’s ability to supply products and services that meet users’ needs, based on a demonstrated record of performance. The Past Performance evaluation results in an assessment of the Offeror’s probability of meeting the solicitation requirements. The Past Performance evaluation considers each Offeror's demonstrated recent and relevant record of performance in supplying products and services that meet the contract’s requirements. One performance confidence assessment rating is assigned for each Offeror after evaluating the Offeror's recent Past Performance, focusing on performance that is relevant to the contract requirements. There are three aspects of the past performance evaluation: recency, relevancy ( including context of data), and quality (including general trends in contractor performance and source of information). All three aspects must be considered for each of the contracts or requirements evaluated;
which are described below:
4.1 Recency. The first aspect is to evaluate the recency of the offeror’s past performance. Recency is generally expressed as a time period during which past performance references are considered relevant, and is critical to establishing the relevancy of past performance information. The criteria to establish what prior performance is recent shall be unique to each source selection and shall be stated in the solicitation. The recency timeframe established should be based on the acquisition and the market/industry. For example, some efforts would require longer recency periods to avoid restricting competition simply due to the lack of item production.
Recent is defined as Past Performance on contracts that had a construction completion date (otherwise known as a building occupancy date (BOD)) within the past ten (10) years from the date of this solicitation, release, or at a minimum projects shall be at least substantially complete, meaning more than 90% invoiced and paid, within the past ten (10) years from the date of this solicitation release.
4.2 Relevance. The second aspect is to determine how relevant a recent effort accomplished by the offeror is to the effort to be acquired through the source selection. The criteria to establish what prior performance is relevant shall be unique to each source selection and shall be stated in the solicitation. In establishing what is relevant for the acquisition, consideration should be given to those aspects of an offeror’s history of contract (or subcontract) performance that would provide the most context and give the greatest ability to measure whether the offeror will successfully satisfy the current requirement. Common aspects of relevancy include, but are not limited to: similarity of product/service/support, complexity, dollar value, contract type, use of key personnel (for services), and extent of subcontracting/teaming.
There are four levels of relevancy, as shown in Table 2. When source selections require a greater level of discrimination within the past performance evaluation, the SST shall use all four of the relevancy ratings identified in Table 2. The SSP shall clearly identify the treatment of relevancy within the past performance evaluation. With respect to relevancy, more relevant past performance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment than past performance of lesser relevance.
Table 2: Past Performance Relevancy Rating
Adjectival Rating Description
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
4.3 Quality of Performance. The third aspect of the past performance evaluation is to establish the overall quality of the offeror’s past performance (see FAR 15.304[c][2]). The past performance evaluation conducted in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts.
Requirements for considering history of small business utilization are outlined at FAR 15.304(c)(3)(ii) and DFARS 215.305(a)(2). The Past Performance Evaluation Team will review all past performance information collected and determine the quality of the offeror’s performance, general trends, and usefulness of the information and incorporate these into the performance confidence assessment. A separate quality assessment rating is not required; rather, the past performance rating using the confidence assessment rating based on the offeror’s overall record of recency, relevancy, and quality of performance.
After evaluating recency, relevancy and contractor performance, a Performance Confidence Assessment rating will be determined. In conducting a performance confidence assessment, each Offeror shall be assigned one of the following ratings:
Table 3: Performance Confidence Assessment Rating
Adjectival Rating Description
Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
5. SMALL BUSINESS RATING METHOD
The small business evaluation for Factor 4 will utilize the following ratings as stated in the below table for this solicitation.
Table 4: Small Business Rating Method
Color Rating Adjectival Rating Description
Blue Outstanding Proposal indicates an exceptional approach and understanding of the small business objectives.
Purple Good Proposal indicates a thorough approach and understanding of the small business objectives.
Green Acceptable Proposal indicates an adequate approach and understanding of small business objectives.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the small business objectives.
Red Unacceptable Proposal does not meet small business objectives.
6. PAST PERFORMANCE RECORDS
Past performance records may be obtainable by Offerors using one of the following methods:
(1) Accessing Past Performance information directly from Contractor Performance Assessment Reporting System (CPARS) website at https://www.cpars.gov/ for CCASS completed before 27 June 2014 and for merged CPARS completed after 1 July 2014. CPARS is an electronic repository of performance information collected by all the major federal performance reporting systems and can be accessed at the aforementioned website.
All Department of Defense (DoD) employees (military and civilian), including DoD Contractors that are working on site (military/government facilities) or contractors working offsite using Government Furnished Equipment (GFE) are required to use certificates from DoD Public Key Infrastructure (PKI) to access CPARS. If the contractor doesn't work on site or with GFE they are encouraged to obtain and use a certificate from an External Certificate Authority (ECA). For DoD users, the use of PKI Login is Mandatory.
Federal and Contractor users can use the PKI login category if they have PKI.
External Certificate Authority External Certificate Authorities (ECAs) and Interim External Certificate Authorities (IECAs) provide digital certificates to the DoD's private industry partners, contractors using their own equipment or working in non-government facilities, allied partners, and other agencies.
Additional information about the PKI certificate is at https://www.cpars.gov/pki_info.htm web page.
You will also need your Unique Entity ID (UEI) and Marketing Partner Identification Number (MPIN) to log onto CPARS. The MPIN number was selected by whoever registered your company in the System for Award Management (SAM) Registry at https://sam.gov/. If you do not know your MPIN number, you will need to contact the SAM help desk by emailing them from the email link on the SAM web page. Please be aware that they will only release the MPIN number to the person who originally registered your company. Additional instructions on locating your MPIN is located in the Frequently Asked Questions (FAQs) section under the Help tab, or -
(2) Past Performance Questionnaires (PPQs) may be used to provide or supplement a firm’s past performance with other than U.S. Governmental clients (see Attachment 2). Contact your client point of contact (POC) for the project you need a past performance record and request the POC to complete the PPQ. The PPQ included in this solicitation is provided for the Offeror to submit to the client for each project the Offeror may need a past performance record for to meet the requirements in this synopsis.
Ensure correct phone numbers and email addresses are provided for the client POC. Completed PPQs should be submitted with your proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). It is the Offeror’s responsibility to follow-up with client POCs to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Brandon Landis, Contract Specialist, via email at brandon.p.landis@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs; this does not preclude an Offeror submitting a previously completed PPQ as long as the full PPQ is submitted and completed in its entirety. This also does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If a PPQ is to be submitted for a project, the complete PPQ shall be submitted (either by the client POC or the Offeror) prior to proposal closing date.
7. RELATIVE IMPORTANCE OF EVALUATION FACTORS
Evaluation factors are listed below in descending order of importance:
Table 5: Volume I Required Submittal Items (Not Rated)
Location Description Descending Order of Importance
TAB A SF 1442 and Acknowledgements Not Rated
TAB B Representations and Certifications Not Rated
TAB C JV Agreement or Teaming Agreement (if applicable) Not Rated
Table 6: Volume I Evaluation Factors
Descending Order of Importance
TAB D Factor 1 – Past Performance 1st Most Important Factor
TAB E Factor 2 – Technical Approach 2nd Most Important Factor
TAB F Factor 3 – Key Personnel 3rd Most Important Factor
Table 7: Volume II Required Submittal Items (Not Rated)
Descending Order of Importance
TAB A SF1442 and Acknowledgement of Amendments Not Rated
TAB B (See Vol II Evaluation Factors Below)
TAB C (See Vol II Evaluation Factors Below)
TAB D Small Business Subcontracting Plan Acceptable/Unacceptable
TAB E
Any new JV Agreement or Teaming Agreement (if applicable).
Not Rated
Table 8: Volume II Evaluation Factors
Location Volume II Factors Descending Order of Importance
TAB B Factor 4 – Small Business Participation 4th Most Important Factor
TAB C Factor 5 – Section 00 10 00, Pricing Schedule
All evaluation factors other than cost or price, when combined, are approximately equal to cost or price.
8. BASIS OF AWARD & DEBRIEFING OFFERORS
The Government will evaluate proposals in accordance with the criteria described within the solicitation and will award a firm-fixed-price contract to the responsible Offeror whose proposal is determined to represent the best value to the Government utilizing the best value tradeoff process as described in FAR 15.101-1.
The award will be made based on the best overall (i.e., best value) proposal that is determined to be the most beneficial to the Government, with appropriate consideration given to the five evaluation factors:
Past Performance, Technical Approach, Key Personnel, Small Business Participation and Price. To receive consideration for award, a rating of no less than “Acceptable” must be achieved for Factors 2-4.
Offerors will be cautioned that the award may not necessarily be made to the lowest cost offered. NOTE:
ALL NON-PRICED FACTORS COMBINED ARE APPROXIMATELY EQUAL TO COST/PRICE.
The Government intends to evaluate proposals and award contracts without conducting discussions with Offerors. However, in the event the Procuring Contracting Officer (PCO) concludes conducting discussions are in the best interest of the Government, the PCO will document the rationale for the competitive range determination. If the PCO determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the PCO may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals. Therefore, the Offeror’s initial proposal should contain the Offeror’s best terms from a price and technical standpoint.
Offerors may request a debriefing in accordance with FAR 15.505 Preaward Debriefing of Offerors or FAR 15.506 Post award Debriefing of Offerors.
EVALUATION OF OPTIONS. Per FAR 52.217-5, except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
9. PROPOSAL CHARACTERISTICS
9.1. PROPOSAL SUBMISSION, PAGE LIMITATIONS, AND FORMAT
Proposals shall be submitted by the time and date as specified in Section 00 10 00, Page 1. All submissions shall be in Adobe PDF format with Optical Character Recognition (OCR) applied to all documents that will enable word searches to be conducted using Adobe-compatible PDF software. The two (2) volumes listed below shall be submitted as “SEPARATE” single files. Due to heightened security at Government installations, the proposal shall be emailed to the following. If the proposal is too large for email, Offers may be submitted electronically via DOD Safe Access File Exchange (SAFE) at https://safe.apps.mil/ to the following recipients:
1. Brandon Landis, brandon.p.landis@usace.army.mil
2. Brittany Gull, brittany.c.gull@usace.army.mil
**Offerors accessing the DOD SAFE site as a GUEST (a “Guest” is defined as a user who is not assigned a CAC) must request a package invitation from the Contract Specialist listed in Section 00 22 00 a minimum of 48-business hours prior to the close of the RFP.**
For the purposes of determining whether the proposal was received "late" in accordance with FAR 15.208, the date and time the file(s) are received by the USACE Outlook Server or uploaded into the DOD SAFE website as identified in the DOD SAFE notification e-mail sent to the Contract Specialist(s)/ Contracting Officer will be the time and date the Government received the proposal. Do not assume that electronic communication is instantaneous. Please make allowances for delays in transmittal.
Page limitations for Volumes I & II (Evaluation Factors 1 through 4) are identified within the instructions for each factor where applicable. Title Sheets, Tables of Content, Dividers, and blank pages are not included in the page limitations and will not be counted as such. A one-page cover letter or title sheet is recommended as the first page of each file identifying your firm’s name, the file’s title, and describing any applicable contractor team arrangements as defined in Tab C below. Any extraneous information or cover letters that provide additional information about your firm that is not requested by this solicitation will not be reviewed or evaluated.
Pages for each factor should be separately and sequentially numbered (i.e., the first page submitted for evaluation for each factor should be “1”). All text shall be at least 10 pt. font and easily read (Arial, Times New Roman, or Calibri). All text shall be typed and single-spaced. Each page shall be 8-1/2” x 11” (organizational chart, risk assessment and project schedule are the only documents that may be submitted on an 11” x 17”). Margins should be no less than 1” (right, left, top, and bottom).
Pages that exceed the page limitations for any factor will not be reviewed and the information contained on those pages will not be considered for evaluation. Page limitations are per factor, i.e., an Offeror may not reduce the page count for one factor in order to submit additional pages for another factor.
9.2 COMPONENT REQUIREMENTS
a. Title Sheet: The title sheet shall contain:
Solicitation number Name, title, address, email, and telephone number of the Offeror.
Offeror’s tax identification number (TIN) Names, titles, emails, and telephone numbers of persons authorized to negotiate on the
Offeror’s behalf with the Government in connection with this RFP.
Name, title, and signature of the person authorized to sign the proposal.
A statement specifying agreement with all terms, conditions and provisions included in the
RFP.
b. SF 1442: The SF 1442 shall be completed and signed by a person authorized by the Offeror.
Include the UEI number and CAGE code in Block 14 of the SF1442 along with the Offeror’s name and address.
c. Contractor Team Arrangement Requirements: For Contractor Team Arrangements, including Joint Ventures, submit the information required by “Contractor Team Arrangements” paragraph, below.
10. PROPOSAL SUBMISSION INSTRUCTIONS
Reference Section 00 21 00 Instructions to Offerors.
11. CONTRACTOR TEAM ARRANGEMENTS
11.1 CONTRACTOR TEAM ARRANGMENTS OTHER THAN JOINT VENTURE/ MENTOR-PROTÉGÉ
All Offerors proposing a team arrangement other than a Joint Venture/Mentor-Protégé, shall submit the following information in the Required Documents file:
a. A listing of each team arrangement member’s corporate name (no abbreviations), address, point of contact, phone number, UEI Number, and CAGE Code.
b. A copy of the signed team arrangement agreement or binding letter of commitment between each team member. All team arrangement agreements and letters of commitment shall:
(1) Clearly identify the expected relationship, role and responsibility between the firms, Prime Contractor, and of the subcontractor or other entity (type and proportion of work to be performed);
and
(2) Be signed by the appropriate individual(s) of each company.
11.2 JOINT VENTURE TEAM ARRANGEMENTS (INCLUDING MENTOR-PROTÉGÉS)
No contract may be awarded to a Joint Venture/Mentor-Protégé that is not registered in the System for Award Management (SAM) database. The Joint Venture/Mentor-Protégé must have its own registered Data Universal Numbering System (DUNS) number. Any Joint Venture/Mentor-Protégé agreement that is required to be approved by the Small Business Administration (SBA) shall be approved in accordance to the applicable Code of Federal Regulations (CFR). If the applicable requirements are not met prior to the due date for proposals, the proposal will be rendered unawardable.
a. In the cover letter of your proposal, provide the complete names, addresses, and phone number of the firms comprising the Joint Venture/Mentor-Protégé.
b. A copy of the Joint Venture/Mentor-Protégé agreement.
c. Signature requirements: SF 1442, SOLICITATION, OFFER, AND AWARD, Block 20, requires that the name and title of a person authorized to sign the offer for the Joint Venture/Mentor- Protégé be provided. In the case of a Joint Venture/Mentor-Protégé, subject Standard Form shall be signed by the principal representative of the Joint Venture/ Mentor-Protégé (or the alternate principal representative, if the principal representative is unavailable).
d. In addition to the requirements stated above, and to assure a single point of contact for resolution of contractual matters and payments, the Offeror shall submit a certificate signed by each participant in the Joint Venture containing the following statement:
“The parties hereto expressly understand and agree as follows:
1. (Name, title, and company) is the principal representative of the Joint Venture. As such, all communications regarding the administration of the contract and the performance of the work thereunder may be directed to him or her. In the absence of (same name, title, and company), (enter name, title, and company of alternate) is the alternate principal representative of the Joint Venture/Mentor-Protégé. These individuals have authority to sign on behalf of the Joint Venture/Mentor-Protégé.
2. Direction, approvals, required notices, and all other communications from the Government to the Joint Venture/Mentor-Protégé, including transmittal of payments by the Government, shall be directed to (enter name, title, and company of principal), principal representative of the Joint Venture/Mentor-Protégé.”
NOTE: Provide telephone numbers and email addresses for the points of contact listed in the above statement.
e. A small business joint venture offeror must submit, with its offer, the representation required in paragraph (c) of FAR solicitation provision 52.212-3, Offeror Representations and Certifications- Commercial Products and Commercial Services, and paragraph (c) of FAR solicitation provision 52.219-1, Small Business Program Representations, in accordance with 52.204-8(d) and 52.212- 3(b) for the following categories:
(A) Small business;
(B) Service-disabled veteran-owned small business;
(C) Women-owned small business (WOSB) under the WOSB Program;
(D) Economically disadvantaged women-owned small business under the WOSB Program; or
(E) Historically underutilized business zone small business.
11.3 INTEGRITY AND VALIDITY OF CONTRACTOR TEAM ARRANGEMENTS
The Contracting Officer will recognize the integrity and validity of contractor team arrangements; provided that the arrangements are identified and company relationships are fully disclosed and validation of formal agreements and relationships (i.e., Mentor-Protégé agreements, Joint Ventures, partnerships, etc.)
are provided in the offer and submitted with the proposal responding to the solicitation. Nothing in the solicitation authorizes contractor team arrangements in violation of antitrust statutes or limits the Government’s rights to:
a. Require consent to subcontracts (see FAR Subpart 44.2);
b. Determine, based on the stated contractor team arrangement, the responsibilities of the Prime
Contractor (see FAR Subpart 9.1);
c. Provide to the Prime Contractor data rights owned or controlled by the Government;
d. Pursue its policies on competitive contracting, subcontracting, and component breakout initial production or an any other time; and
e. Hold the Prime Contractor fully responsible for contract performance, regardless of team arrangement between the Prime Contractor and its subcontractors.
12. VOLUME I FACTORS
12.1 TAB D – VOLUME I – FACTOR 1 – PAST PERFORMANCE
12.1.1 SUBMISSION REQUIREMENTS (Page limitations: no more than a three (3) page narrative per project example submitted; no more than a two (2) page narrative to describe any past teaming experience; no page limitations on official past performance records such as PPQs and/or CPARS)
There are three aspects of the performance confidence evaluations: recency, relevancy, and quality of past performance. In accordance with FAR 15.305(a)(2), the recency and relevance of the information, source of the information, context of the data, and general trends in contractor’s performance shall be considered.
Relevance and quality of performance will be combined to establish one performance confidence assessment rating for each Offeror. The project examples requested within this factor must be of relevant scope and complexity to the solicited project.
CONSTRUCTION PROJECT EXAMPLES: The Offeror should submit three (3) projects similar in project size, scope, and complexity to this project to be performed by the Prime Offeror. Offeror should limit each project example to three (3) narrative pages per project submitted. If more than three (3) narrative pages are submitted per project, only the first three pages will be evaluated. In addition to the three (3) project examples, the Offeror may submit a two (2) page narrative to describe any past teaming experience between current team members as it relates to any or all of the three (3) submitted project examples. The page limitation for Factor 1 shall be a maximum of eleven (11) pages, plus past performance evaluations for each project (described below). Any information presented beyond the page limit will not be evaluated. All project examples submitted should have a completion date (or BOD) no greater than the past ten (10) years from the advertisement of this solicitation. Projects should be substantially complete, meaning more than 90% invoiced and paid.
Each project example submitted shall meet the following criteria:
1. Past project examples submitted for this factor shall have been awarded to the Offeror (either singly or one of the participants in a JV named on the SF1442 for this solicitation (W9128F24R0004)). The company shall have been the Prime Contractor for the past project, either singly or as a member of the Joint Venture to which it was awarded.
The table below provides example scenarios based on the requirements above:
Scenario Examples
Project Examples Qualify for Evaluation for Factor 1 (if all other requirements are met)
1 Past project was awarded to Company X only. Company X is proposing as a Prime Contractor for W9128F24R0004) and has signed the SF 1442 for W9128F24R0004).
Yes
2 Company Y has formed a JV with Company Z (forming Company “YZ”). Past project was awarded to Company Y only. Company YZ is proposing as a Prime Contractor for W9128F24R0004) and has signed the SF 1442 for W9128F24R0004).
Yes
3 Company Y has formed a JV with Company Z (forming Company “YZ”). Past project was awarded to JV Company YZ. Company YZ is proposing as a Prime Contractor for W9128F24R0004) and has signed the SF 1442 for W9128F24R0004).
Yes
4 Past Project was awarded to Company “AY,” a JV composed of Company A (not Prime Offeror for RFP W9128F24R0004) and Company Y. Company Y has formed a JV with Company Z (forming Company “YZ”). JV Company YZ is proposing as a Prime Contractor and has signed the SF 1442 for W9128F24R0004).
Yes
5 Company Y has formed a JV with Company Z (forming Company “YZ”).
Company YZ is proposing as a Prime Contractor for W9128F24R0004) and has signed the SF 1442 for W9128F24R0004). Company Y performed work on the past project but was not the Prime Contractor for the past project (either singly or as a member of a JV).
Yes
6 Company X is proposing as a Prime Contractor for W9128F24R0004) and has signed the SF 1442 for W9128F24R0004). Company X will use Company R as a teaming member/subcontractor, but Company R is not part of a JV with Company X for W9128F24R0004). The past project was awarded to Company R as a Prime Contractor (singly or as a member of a JV), but not Company X (singly or as a member of a JV).
7 Company Y has formed a JV with Company Z (forming Company “YZ”).
Company YZ is proposing as a Prime Contractor for W9128F24R0004) and has signed the SF 1442 for W9128F24R0004). Company YZ will use Company R as a teaming member/subcontractor, but Company R is not part of the JV.
The past project was awarded to Company R as a Prime Contractor (singly or as a member of a JV), but not to Companies Y or Z (singly or as a member of a JV).
PROJECT INFORMATION: The projects submitted should demonstrate experience on similar projects of similar or greater value to this project. If the Offeror is a joint venture, each firm shall provide information, demonstrating experience relevant to their role on this project. If the Offeror has multiple functions or division, limit the project examples to those performed by the division or unit submitting the offer or by the team members. If projects were design-build, indicate as such.
Project examples submitted should demonstrate experience on similar building and site improvement projects and minimum value at the time of contract award of $20M $5M. At least one project submitted shall demonstrate experience constructing underground storage fuel tanks with associated piping.
Project information per project example should CLEARLY include:
Summaries for each project submitted to include the name, address, telephone and email of a representative of the owner (as well as one alternate individual not affiliated with your firm) familiar with your firm’s experience on the project that can verify the experience cited.
Original contract award amount and final construction cost.
Location of project.
Original contract completion date and actual completion date (Month/Year).
Identify if the project was a construction project or a design-build project.
Percentage (%) performed by the Prime Offeror; and Percentage (%) and type of work subcontracted out.
Do not include extraneous information that is not requested.
The Offeror should demonstrate recent, relevant construction experience on similar building projects using Attachment 1, ‘Construction – Specialized Experience Form’. Offerors may identify other federal, state, or local government and private contracts that are similar to the Government’s requirements set forth in the solicitation. If the Offeror has multiple functions or divisions, limit the project examples to those performed by the division or unit submitting the offer or by the team member. Offerors may list government, private or commercial customers.
In addition, the Offeror should submit past performance evaluations and ratings for each project the Offeror included in its proposal this factor. Reference Paragraph 5 above for obtaining a past performance record.
There are no page limitations on official past performance records such as PPQs and/or CPARS. No other past performance records shall be submitted other than those related to the three (3) projects submitted for this factor.
If available, submit the respective CPARS record for the project. For projects which were designed and/or constructed for other government entities, submit the performance appraisal sheets used by that government entity if available. For projects submitted that are not covered in the CPARS database or other Government Performance Rating System, submit a PPQ. A PPQ form is attached to this solicitation for convenience (see Attachment 2).
A CPARS record or a complete PPQ should be submitted for each project submitted under this factor prior to proposal closing date.
The Government reserves the right to contact any persons who may be knowledgeable about the project or projects (this is not limited to contracts identified by the Offeror) submitted in an Offeror’s proposal. In addition, the Government may review and take into consideration other sources of information pertinent to the evaluation of the Offeror’s Past Performance, including both the previous experience projects and other similar projects performed by the Offeror. Other sources may include, but are not limited to, Past Performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), using all Commercial and Government Entity (CAGE)/Unique Entity ID (EID) numbers of team members (partnership, Joint Venture, teaming arrangement, or parent firm/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
While the Government may elect to consider data from other sources, the burden of ensuring detailed, current, accurate and complete Past Performance information rests with the Offeror.
Note: The Government reserves the right to verify the experience record of cited projects or other recent projects by reviewing DoD or Government appraisal systems, or through interviewing owners or references. The Government may check any or all cited references to very supplied information.
Although the SSEB may not rate an offeror that lacks recent, relevant past performance favorably or unfavorably regarding past performance, the SSA may determine that a “Substantial Confidence” or “Satisfactory Confidence” past performance rating is worth more than a “Neutral Confidence” past performance rating in the best value tradeoff as long as the determination is consistent with stated solicitation criteria.
12.1.2 EVALUATION CRITERIA
The Government’s overall confidence level for this factor will be based on the Offeror’s Past Performance to include recency and relevancy of the projects submitted and the quality of performance.
Past Performance on projects will examine how well an Offeror has performed on relevant projects considering such criteria as: cost growth and adherence to budget; time growth, timeliness and adherence to schedule; quality and quality control measures; management of personnel and subcontractors; compliance with safety standards/safety plan; overall customer satisfaction;
responsiveness to customer concerns.
CPARS/CCASS records will be given more weight than PPQs. The Government may, at its discretion, contact individuals other than those identified by the Offeror as references in order to verify the information contained therein. The Government reserves the right to consider all aspects of an Offeror's performance history but may attribute more importance to work that is similar to the scope contemplated for this project.
The Government may, at its discretion, contact individuals other than those identified by the Offeror as references in order to verify the information contained therein. The Government reserves the right to consider all aspects of an Offeror's performance history but may attribute more importance to work that is similar to the scope contemplated for this project.
In the case of offerors for which there is no information on past contract performance or where past contract performance information is not available, the offeror may not be evaluated favorably or unfavorably on the factor of past contract performance (see FAR 15.305(a)(2)(iv).) In this case, the offeror’s past performance is unknown and assigned a performance confidence rating of “neutral.” Although the SSEB may not rate an offeror that lacks recent, relevant past performance favorably or unfavorably with regard to past performance, the SSAC may recommend and the SSA may determine, that a “Substantial Confidence” or “Satisfactory Confidence” past performance rating is worth more than a “Neutral Confidence” past performance rating in a best value tradeoff as long as the determination is consistent with stated solicitation criteria.
12.2 TAB E – VOLUME I – FACTOR 2 – TECHNICAL APPROACH
12.2.1 SUBMISSION REQUIREMENTS (The page limit for this factor is twenty (20) pages total including organizational approach, technical approach, proposed duration, and schedule).
The offeror shall provide a narrative that describes the Offeror’s Project Management approach to executing the contract pursuant to the following requirements.