This document is a Solicitation Amendment to contract W9128F24Q0060 for janitorial services at the U.S. Army Corps of Engineers' F.E. Warren Resident Office in Cheyenne, Wyoming.
The amendment updates the Performance Work Statement and the terms of FAR 52.212-2 Evaluation - Commercial Items. It outlines the requirements for the contractor to provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform janitorial services at the two office buildings, except for government-furnished utilities and materials. The work includes weekly, bi-weekly, monthly, quarterly, and semi-annual cleaning tasks with defined performance standards and quality assurance methods. The period of performance is a one-year base period from June 1, 2024 to May 31, 2025, with three 12-month option years. Past performance, quality control, and price are the evaluation factors, with past performance and quality control being more important than price.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation QA W9128F24Q0060 4.docx | DOCX document | |
| Solicitation QA W9128F24Q0060 3.docx | DOCX document | |
| Solicitation QA W9128F24Q0060 2.docx | DOCX document | |
| Solicitation QA W9128F24Q0060.docx | DOCX document | |
| W9128F24Q0060 Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to update the Performance Work Statement, as w ell as the terms of FAR 52.212-2. All other terms and conditions remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-May-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9128F24Q0060
X 9B. DATED (SEE ITEM 11)
30-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-May-2024
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128F24Q0060
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
PERFORMANCE WORK STATEMENT
PERFORMANCE WORK STATEMENT (PWS)
JANITORIAL SERVICE
US ARMY CORPS OF ENGINEERS
(F.E. WARREN RESIDENT OFFICE)
5607 5TH CAVALRY AVE, BLDG 305 & 306
F.E. WARREN AFB, WYOMING 82005
1.0 General Information. This is a non-personal services contract to provide janitorial service at F.E. Warren AFB
Resident Office. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor, who in turn is responsible to the Government.
1.1 Description of Services/Introduction. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision and other items to include non-personal services necessary to perform janitorial services as defined in this Performance Work Statement (PWS) except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.
1.2 Background. The Corps of Engineers manages/maintains F.E. Warren AFB Resident Office in Cheyenne, Wy.
These 2 offices house fifteen employees. This requires that we have the areas cleaned on a scheduled basis to provide a quality work environment.
1.3 Objectives. Contractor shall provide for the safe, careful and efficient operation of all equipment and protection of Government funds and property under the direction of the COR.
1.4 Scope of Work. This is a non-personal services contract to provide janitorial services at U.S. Army Corps of
Engineers, F.E. Warren Resident Office. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform janitorial services for the Corps of
Engineers as defined in this Performance Work Statement except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract. The government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the contractor who, in turn is responsible to the government. This is a fixed priced, performance-based service contract where the government defines and measures desired outcomes, while contractor methods are generally not constrained or directed.
1.4.1 Buildings Description.
Bldg 305 is a 1-story building with approximately 1,100 sf comprising of approximately 1,000 sf of carpeted area and approximately 100 sf of tiled area. There is 1 bathroom and 1 kitchenette that are tiled floors. This building is occupied by 5 full time employees. This building has large, elevated windows which will require ladders or long reach equipment for cleaning.
Bldg 306 is a 1-story building with a full basement. The basement area is excluded from this contract. The 1st floor is approximately 2,200 sf comprising of approximately 2,000 sf of carpeted area and approximately 200 sf of tiled area. There are 2 bathrooms that are tiled flooring and 1 kitchenette with carpet flooring. This building is occupied by 10 full time employees. This building has large windows which may require ladders or long reach equipment for cleaning.
The cleaning requirements for each building, areas, and seasonal cleanings are described in Section 5.0 of this
Performance Work Statement.
1.5 Period of Performance. The period of performance shall be for one (1) Base Year of 12 months and three (3)
12-month option years. Active performance period will be 01 June through 31 May. The Period of Performance reads as follows:
Base Year: 01 June 2024 through 31 May 2025
Option Year 1: 01 June 2025 through 31 May 2026
Option Year 2: 01 June 2026 through 31 May 2027
Option Year 3: 01 June 2027 through 31 May 2028
1.6 Contractor Personnel
1.6.1 The contractor shall perform all work under this contract using his or her own forces except as provided in
Paragraph 1.4.2 Subcontracting. Employees who perform this work shall be qualified persons on the contractor’s own payroll.
1.6.1.1 The contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the CO and the COR as a potential threat to health, safety, security, general well-being or operational mission of the facility and its population. List of dispatch personnel shall be made available in writing to the
Government at the start of the contract.
1.6.1.2 All contractor personnel shall be fully clothed at all times, including enclosed shoes, while performing these services. Clothing shall be clean and neat in appearance.
1.6.1.3 Contractor personnel shall utilize tact, diplomacy and courtesy at all times during contact with the public.
1.6.1.4 The contractor shall make sure employees have valid driver license(s) before starting work under this contract and throughout the term of the contract.
1.6.2 Subcontracting. The contractor shall not subcontract any work without written approval of the Contracting
Officer. Compliance with the provisions of this contract by subcontractors shall be the responsibility of the contractor.
1.7 Quality Control
1.7.1 The contractor shall designate, in writing, an employee who shall serve as the contact for matters involving quality and performance or nonperformance of the required work stated in this PWS. The employee(s) shall be qualified and fully competent with full authority to act for, and on behalf of, the contractor as necessary to ensure that the required work is performed in accordance with the standards contained herein. The contractor shall furnish the above written designation to the Contracting Officer’s Representative (COR) no later than the first day of work. The contractor shall include the name(s), address(s), telephone number(s) and email(s) of the responsible individual(s).
The contractor’s quality control employee shall provide written verification that all required weekly and monthly cleaning activities have satisfactorily performed. This documentation will be submitted with the monthly invoice.
1.7.2 The Contracting Officer reserves the right to disapprove any individual whom he considers incompetent to perform the work required. The Contracting Officer will provide a written notice of any disapproval to the contractor.
1.8 Quality Assurance. The government will periodically evaluate the contractor’s performance under this contract using quality assurance procedures developed by the Government in accordance with typical procedures that might include periodic sampling, checklists, and customer complaints. This should not be considered an exhaustive list. A primary objective of Government Quality Assurance will be to ensure that the Contractor is performing the services required by this PWS in an acceptable manner. The Government may use Quality Assurance Evaluators (QAE(s)) to assist with the quality assurance methods.
1.8.1 The government has the right to inspect all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The government shall perform inspections in a manner that will not delay the work.
1.8.2 If any of the services do not conform to contract requirements, the government may require the contractor to perform the services in conformity with contract requirements and at no increase in cost. If the contract requirements are not met after a second attempt the government may (1) require the contractor to take necessary action to ensure that future performance conforms to contract requirements and (2) reduce the contract price to reflect the reduced value of the services performed.
1.8.2.1 Upon verification of a validated customer complaint or corrective action report, the COR will notify the contractor that they are required to re-perform specific services. Re-performance will take place within one (1) business day of the contractor being notified and the COR will be notified when service has been completed for inspection.
1.8.3 The government may take necessary action, if the contractor fails to perform the services again or to take the necessary action to ensure future performance is in conformity with the contract requirements. The government may
(1) by contract, or otherwise, perform the services and charge to the contractor any cost incurred by the government that related to the performance of such service or (2) terminate the contract in whole or in part.
1.8.4 The contractor is responsible to replace/repair any damage to government property due to negligence, at his or her own cost. The government may take necessary action, if the contractor fails to replace/repair any damage to government property. The government may (1) by contract, or otherwise, replace/repair damaged government property and charge to the contractor any cost incurred by the government to replace/repair any damage.
1.9 Hours of Operation. The contractor is responsible for conducting business Monday thru Friday (hours of cleaning service will be agreed to by both parties) except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Should a scheduled service time fall during these circumstances the contractor will provide services the following business day. The Contractor must maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.9.1 Place of Performance. The work to be performed under this contract will be performed at Bldg 305 and Bldg
306, 5607 5th Cavalry Ave, F.E. Warren AFB, WY.
1.10 Pre-Work Meeting. Prior to commencing any activities, the contractor shall arrange a Pre-work Meeting with the COR. The Meeting shall discuss the work requirements, scheduling, submittal process, review of the Activity
Hazard Analysis (AHA), and Abbreviated Accident Prevention Plan (AAP). At least one (1) week prior to commencing work, the Contractor shall coordinate their proposed work schedule with the COR.
1.11 Submittals. Prior to commencement of services, the Contractor shall submit the following documents to the
COR for review and approval:
Activity Hazard Analysis (AHA)
Abbreviated Accident Prevention Plan (AAP)
Insurance: All required insurance certificate(s).
Employee and vehicle ID: A list of all employees that will be working on this contract and their vehicle identification.
Non-US Citizens: List of any non-US citizens who will be performing work on this contract.
1.12 Standards and Regulations. The Contractor shall perform to the standards in the contract and comply with all
Local, State, and Federal Regulations during the services performed. The Contractor is responsible for ascertaining the extent to which these regulations affect the operations resulting from this contract. The Contractor shall comply will all applicable regulations. Applicable regulations include, but are not limited to the following:
a. Engineering Manual (EM) 385-1-1 (USACE – Safety and Health Requirements Manual), dated 15 March
2024.
b. Occupational Safety and Health Standards (29 CFR 1910).
1.12.1 Activity Hazard Analysis (AHA). The contractor shall prepare the AHA in accordance with Paragraph 1-6 of the EM 385-1-1.
Note: Contractors and other individual employer’s typically use Job Safety Analyses (JSAs), Job Hazard Analyses
(JHAs), or similar Risk Management assessment tools. The government considers equivalent to, and acceptable substitutes for, the USACE’s AHA provided the data collected is the same as that required by the AHA, commensurate with the type of services the contractor is performing.
1.12.2 Abbreviated Accident Prevention Plan (APP). EM 385-1-1 in its entirety may be too complex for the type of work performed under these contracts; contractors may reference Appendix A, for abbreviated Accident Prevention
Plan (APP). The contractor shall only need to submit items in Appendix A that are pertinent to the contract. The contractor shall use a qualified person to prepare the site-specific abbreviated Accident Prevention Plan (APP). The contractor shall prepare the APP in accordance with the format and requirements of the EM 385-1-1 and supplemented herein. The contractor shall sign and submit the APP for approval prior to the start of work onsite.
1.13 Physical Security
1.13.1 The contractor shall be responsible for safeguarding all government facilities, property, and materials provided for contractor use. The contractor shall always secure all government facilities, property, and materials. Specific security conditions may change based on threats to national defense and based on the risk of specific facilities to these threats. The contractor shall always abide by these changing conditions, as applicable.
1.13.2 Key Control. The contractor shall ensure all keys issued by the government are not lost, stolen, duplicated, or used by unauthorized persons.
1.13.2.1 The Contractor shall immediately report to the COR any occurrences of lost or stolen keys.
1.13.2.2 In the event keys, other than master keys are lost or stolen, the contractor may be required, upon written direction of the COR, to re-key or replace the affected lock or locks without cost to the government. The government may, however, at its option, replace the affected lock or locks or perform re-keying and deduct the cost of such from the monthly payment due the contractor. If a master key is lost or stolen, the government may need to replace all locks and keys for that system. The government will deduct the total cost to replace the locks and keys from the contractor’s monthly invoice.
1.13.2.3 The contractor shall prohibit the use of keys issued by the government by any persons other than the contractor’s employees. The contractor shall not facilitate access of secured areas to persons other than contractor personnel or subcontractors engaged in performance of contract work requirements.
1.14 Antiterrorism/Operation Security Requirements
1.14.1 Access and General Protection/Security Policy and Procedures. All contractor and all associated sub-contractor employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, or Security Office.
Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition
(FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
1.14.1.1 For contractors who do not require Common Access Card (CAC), but require access to a DoD facility or installation. Contractor and all associated sub-contractor employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.14.2 Pre-screen candidates using E-Verify Program. The Contractor must pre‐screen candidates using the E‐ verify Program (http://www.dhs.gov/E‐Verify) website to meet the established employment eligibility requirements.
The vendor must ensure that the candidate has two valid forms of government issued identification to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible candidates must be provided to the COR no later than three (3) business days after the initial contract award.
1.15 Payment
1.15.1 The government will make payment monthly, after the government has inspected and accepted the services, and the government has reviewed, approved, and processed the contractor’s invoice. The contractor shall submit the invoice to the COR and/or any other person that has been designated in the contract to receive the invoice.
1.15.2 The contractor must provide the contractor’s name, address, contract number, period of services completed
(i.e., for the month of January or for the period of performance of January 1 through February 23), CLIN number and specific quantities of work performed (i.e., 1 Month, 40 days, 100 acres, etc.), and total requested, for an invoice to be considered proper. The contractor shall submit the invoice by the fifth (5 th) of the month for services completed the previous month or submit the invoice upon completion of all services, in accordance with the period of performance stated in the CLIN.
2.0 Definitions. The following definitions and descriptions apply wherever the word(s) or phrase(s) is/are stated in this PWS:
Acceptable Level of Performance (ALP): The maximum percent defective, the maximum number of defects per hundred units, or the number of defects in a lot considered satisfactory on the average. The allowable leeway or variance from a standard before the government will reject the specific service.
Contracting Officer’s Representative (COR): means an individual designated an authorized in writing by the Contracting Officer to perform specific technical or administrative functions.
Performance-Based Contract (FAR 2.101): Structuring all aspects of an acquisition around the purpose of the work to be performed with the contract requirements set forth in clear, specific, and objective terms with measurable outcomes as opposed to either the manner by which the work is to be performed or broad and imprecise.
Performance Requirements Summary (PRS): The PRS shows contract requirements, the component requirements related to each contract requirement, the price of each work requirement as a percentage of the associated contract requirement (Fixed Price Contracts), the standard of performance, and the acceptable level of performance (ALP) for each work requirement.
http://www.ecfr.gov/cgi-bin/text-idx?rgn=div8&node=48:2.0.1.1.1.2.1.28 http://www.ecfr.gov/cgi-bin/text-idx?rgn=div8&node=48:2.0.1.1.1.2.1.28
Quality Assurance Surveillance Plan (QASP): An organized written document used by the Government for quality assurance surveillance. Document contains sampling/evaluation guides, checklists, and the performance requirements summary (PRS).
3.0 Government Furnished Items and Services
3.1 Services. N/A
3.2 Facilities. N/A
3.3 Utilities. (Electrical power, water services, and restroom facilities) required in the performance of the contract are available from Government sources within the contract areas or from other sources approved by the COR. These utilities are available as is.
3.4 Equipment. N/A
3.5 Materials. N/A
4.0 Contractor Furnished Items and Responsibilities
4.1 General. The Contractor shall furnish all supplies, equipment, tools and services required to perform work under this contract that are not listed under Section 3 of this PWS.
4.2 Materials. The Contractor shall furnish all materials, supplies, and equipment necessary to meet the requirements under this PWS to include but not limited to parts for repair of equipment.
4.3 Equipment. The Contractor shall furnish all equipment to meet the requirements under this PWS. Equipment used by the contractor shall maintain compliance with OSHA, EPA and other DOD Directives.
5.0 Specific Tasks
5.1 Basic Services. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform janitorial services at F.E. Warren AFB Resident Office as defined in this Performance Work Statement (PWS) except for those items specified as government furnished property and services. The work shall be performed at the Government owned facility and the contractor shall perform to the standards in this contract.
5.2 Janitorial Requirements.
5.2.1 The contractor shall provide and necessary labor, material, equipment, and supervision to perform the work as indicated below. All cleaning chemicals shall be non-scented. Cleaning supplies, i.e. disposable trash can liners, all purpose cleaner, glass cleaner, and disposable cleaning rags shall remain in the kitchen cabinets below the sink.
Location to be cleaned: F.E. Warren AFB Resident Office, Bldg 305 and Bldg 306, 5607 5 th Cavalry Ave, F.E.
Warren AFB, WY.
5.2.2 Frequency and Service to be performed:
a. One day a week
(1) Vacuum carpeting, dust mop tile, damp mop floors as needed. Includes use of crevice attachment to vacuum corners and edges of carpet.
(2) Dust all desk surfaces that are free of work papers; clean, vacuum or dust other office furniture and dust reachable horizontal areas and equipment as needed.
(3) Empty and clean all wastebaskets and provide disposable plastic liners
(4) Remove and dispose of trash from building and premises
(5) Clean floor and wipe down sink and countertops, and clean microwave and toaster ovens in two kitchenettes.
Provide hand soap (maintain 1 bottle on kitchen counter and 1 extra bottle backup in each kitchenette) and paper towels (maintain the inventory of 1 roll on each dispenser and 4 extra rolls in each kitchenette).
(6) Scrub floor and wipe down toilet and sink in three bathrooms (Bldg 305 – 1 bathroom, Bldg 306 – 2 bathroom).
Provide spray air fresheners, hand soap, toilet paper, and paper towels.
(7) Inventory requirements for each building
• Paper Towels – 1 roll on each dispenser and 4 extra rolls per building
• Toilet Paper – 1 roll on each dispenser and 6 extra rolls per building
• Hand Soap – 1 bottle beside each sink and 1 extra bottle per bathroom and kitchenette
• Air Freshener – 2 cans per bathroom
• Disposable Trash Can Liners – 1 full box per size in each building
• Disposable Cleaning Rags – 1 box per kitchen
• All Purpose Cleaner – 1 full bottle per kitchen
• Glass Cleaner – 1 full bottle/can per kitchen
b. Twice Monthly – 2nd and 4th Weeks
(1) Dust all surfaces to include windowsills, baseboards, woodwork, radiator/vents, Venetian blinds and light fixtures
(2) Spot wash all partitions to remove finger marks and smudges
c. Monthly – 4th Week
(1) Vinyl furniture will be cleaned with appropriate cleaner – not soap and water
(2) Polish metals parts of furniture
(3) Clean wood furniture with wood cleaner or polish
(4) Vacuum upholstered furniture to remove dust or other particles
d. Quarterly – 1st week of December, March, June & September
(1) Damp clean fixtures and shields
(2) Office partitions will be completely cleaned and dried without leaving streaks
(3) Wood paneling will be cleaned with wood cleaner or polish (if applicable)
e. Semi-Annually – 1st week of October & April
(1) Wash windows, inside and out, including window ventilators
(2) Shampoo all carpets, removing all dirt and non-permanent spots or stains (steam clean if required)
(3) Non-wax vinyl floors will be treated with a sealer after being stripped (if applicable)
f. As needed
(1) Spot clean carpets to prevent permanent stains
5.3 Disposal: The contractor shall transport and dispose of all waste collected during the performance of services off-base.
6.0 Performance Requirements Summary. The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance
Objective
Performance Standard Performance
Threshold
Method of
Assessment
PRS #1
Submitting of Quality
Control Plan in accordance with PWS
Part 1, paragraph 1.61.
The contractor provides certificate a minimum of five working days prior to beginning work on site.
The certificate is submitted on time with the proper insurance coverage per contract
100 Percent
Inspection by COR
PRS #2
Schedule
The Contractor provides a work schedule
The Contractor is required to schedule all work. At a minimum the schedule will include days of work, work to be accomplished, location of work, time of arrival for all required work.
Annual & Semi‐Annual requirements will be noted on schedule as
*Tentative per COR approval.
100 Percent
PRS #3
Weekly cleaning in accordance with: PWS
5.2.2(a)
The Contractor shall be required to complete weekly cleanings per noted contract requirements
The Contractor is required to clean all locations as noted. The
Government COR will inspect as noted. Five or more missed cleaning requirements within a
30-day period can be the cause for contract termination. Re‐ performance for all missed cleanings shall be accomplished within 8 hours of notification.
Random Sampling
Surveillance by the
Government
PRS #4
Twice monthly cleaning in accordance with:
PWS 5.2.2(b)
The Contractor shall be required to complete twice monthly cleanings per noted contract requirements
The Contractor is required to clean all locations as noted. The
Government COR will inspect as noted. Five or more missed cleaning requirements within a
30-day period can be the cause for contract termination. Re‐ performance for all missed cleanings shall be accomplished within 8 hours of notification.
Random Sampling
Surveillance by the
Government
PRS #5
Monthly Cleaning in accordance with: PWS
5.2.2(c)
The Contractor shall be required to complete monthly cleanings per noted contract requirements.
The Contractor is required to clean all locations as noted. The
Government COR will inspect as noted. Five or more missed cleaning requirements within a
30-day period can be the cause for contract termination. Re‐ performance for all missed cleanings shall be accomplished within 8 hours of notification.
Periodic
Surveillance by the
Government
PRS #6
Quarterly Cleaning in accordance with: PWS
5.2.2(d)
The Contractor shall be required to complete Semi‐
Annual cleanings per noted contract requirements.
The Contractor is required to clean all locations as noted. The
Government COR will inspect as noted. Five or more missed cleaning requirements within can be the cause for contract termination. Re‐performance for all missed cleanings shall be accomplished within 8 hours of notification.
PRS #7
Semi‐Annual Cleaning in accordance with:
PWS 5.2.2(e).
The Contractor shall be required to complete
Annual cleanings per noted contract requirements.
The Contractor is required to clean all locations as noted. The
Government COR will inspect as noted. Five or more missed cleaning requirements within can be the cause for contract termination. Re‐performance for all missed cleanings shall be accomplished within 8 hours of notification.
7.0 Attachments
N/A
52.212-2 EVALUATION--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:
1. Past Performance – The quoter shall provide three (3) references of projects completed within the past five
(5) years. Experience consists of projects completed as a prime contractor or projects of qualified subcontractors that have the capabilities to perform this work. These references need to be equal to or similar in scope of this requirement. The contractor shall provide dates and pertinent information to demonstrate how they are comparable to this requirement in size and complexity. The contractor shall include points of contact, titles, telephone numbers, and email addresses (if available) for all references.
The quoter will receive a rating of exceptional for past performance that demonstrates successful completion of similar purchases on all references and the additional information retrieved from Contractor
Performance Assessment Reporting System (CPARS) and from the Contracting Officer is favorable. The quoter will receive a rating of satisfactory for past performance that has at least one reference that demonstrates successful completion of similar purchases and the information from CPARS and the
Contracting Officer is favorable. The quoter will receive a rating of unsatisfactory for past performance that does not demonstrate any successfully completed similar purchases on the references and the additional information from CPARS and the Contracting Officer is not favorable.
2. Quality Control – Describe how you will ensure you will perform on site quality control.
3. Price - The quote shall be inclusive of all costs to perform the work specified in the PWS.
Past Performance and Quality Control, when combined, is more important than Price in the award decision.
(b) Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).
(c) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
(End of provision)
The following have been deleted:
PERFORMANCE WORK STATEMENT
52.212-2 Evaluation - Commercial Items NOV 2021
(End of Summary of Changes)