This document is a section of a performance specification for Advanced Modeling (BIM/CIM/GIS/CAD) requirements on a federal construction contract. The specification outlines the requirements for Building Information Modeling (BIM), Computer-Aided Design (CAD), and Geographic Information Systems (GIS) during the design and construction phases of the project. Key details include:
The contractor must develop an Advanced Modeling Project Execution Plan (PxP) that documents the BIM uses, analysis technologies, and workflows for the project. The PxP must be demonstrated and accepted by the government before any design or construction work can begin. The contractor must provide Advanced Modeling submittals throughout the project, including interim construction submittals and a final record submittal. Submittals must include the PxP, electronic files, interactive 3D models, IFC coordination views, and quality control reports. The government will provide some BIM and CAD files as government-furnished materials, but the contractor is responsible for completing and verifying the models and data to represent the as-built conditions. The models and drawings must comply with the USACE BIM/CIM and CAD standards.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 33 39.00 10
ADVANCED MODELING (BIM/CIM/GIS/CAD) REQUIREMENTS
10/24
PART 1 GENERAL
This project includes BIM and CAD requirements during the Design and
Construction phases of the project.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)
ISO 19005-3 (2012) Document Management -- Electronic
Document File Format for Long-Term
Preservation -- Part 3: Use of ISO 32000-1 with Support for Embedded Files (PDF/A-3)
ISO 19115-1 (2014) Geographic Information -- Metadata
-- Part 1: Fundamentals
ISO 32000-1 (2008) Document Management -- Portable
Document Format -- Part 1: PDF 1.7
NATIONAL INSTITUTE OF BUILDING SCIENCES (NIBS)
NBIMS-US (V3) National BIM Standard - United States
NCS (V6) United States National CAD Standard
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-1-2909 (2012) Engineering and Design --
Geospatial Data and Systems
ERDC/ITL TR-19-6 (2023) A/E/C Graphics Standard, Release 2.2
ERDC/ITL TR-19-7 (2019) A/E/C CAD Standard - Release 6.1
1.2 DEFINITIONS
1.2.1 Advanced Modeling
A subset of geospatial technologies as defined EM 1110-1-2909 GEOSPATIAL
DATA AND SYSTEMS to include BIM, CIM, GIS, and CAD. Models and drawings that form a digital representation of the project, or part thereof, comprised of "Model Elements" with "Facility/Site Data."
1.2.2 Model Element
A self-contained element with a unique identification, whose behavior and properties are defined by Facility/Site Data and software processes. Model
Elements can represent a physical entity, such as a pump, a concrete wall, or a utility vault and range from the simple to the complex.
1.2.3 Facility/Site Data
The non-graphical information attached to objects in the Model that defines various characteristics of the object. Facility/Site Data can include properties such as parametric values that drive physical sizes, material definitions and characteristics (e.g. wood, metal), manufacturer data, industry standards (e.g. AISC steel properties), and project identification numbers. Facility/Site Data can also define supplementary physical entities that are not shown graphically in the Model, such as the system of a duct, hardware on a door, content of conduit, or transformer properties.
1.2.4 USACE BIM/CIM Platform Configuration Standards - Templates, Workspaces, Catalogs, and Environments
a. Bentley AECOsim and Openroads Workspace:
The Workspace is contained within the A/E/C Work Structure. It is comprised of a collection of content libraries and supporting files that define and embody a CAD/BIM standard. The Workspace also contains sheet libraries such as print/plot configurations, font and text style libraries, and sheet borders and title blocks.
The Workspace includes pre-defined datagroup parameters.
b. USACE Revit Templates:
The USACE has developed Revit Templates specific to USACE BIM standards; these templates are Revit version specific. The USACE
Revit templates are discipline specific and include family content pertinent to that discipline. The Templates share standard symbology such as annotation families, line styles, and text styles. The Templates include pre-defined shared parameters.
1.2.5 IFC
Industry Foundation Class, a standard and file format used for the exchange of BIM data; see www.iai-tech.org. For this specification, IFC does not mean "Issued For Construction."
1.2.6 Model Uses
Reference NBIMS-US A Model Use is a method or strategy of applying modeling during a facility's life cycle to achieve one or more specific objectives.
1.2.7 USACE CAD/BIM Technology Center
The USACE CAD/BIM Technology Center hosts all standard content for USACE.
This content can be accessed through the CAD/BIM Technology Center website, https://cadbimcenter.erdc.dren.mil/.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Advanced Modeling Project Execution Plan (PxP); G, DO
PxP Demonstration; G
SD-03 Product Data
Interim Construction Advanced Modeling Submittal; G, RO
SD-11 Closeout Submittals
Record Advanced Modeling Submittal; G, RO
As-built Drawings; G, DO
1.4 QUALITY ASSURANCE
1.4.1 Advanced Modeling Project Execution Plan (PxP)
Develop an Advanced Modeling Project Execution Plan ("Plan" or "PxP") documenting mandatory and Contractor-elected BIM Uses, analysis technologies and workflows.
Submit the PxP within forty-five (45) days after Notice to Proceed.
Contractors shall use the USACE ADVANCED MODELING (BIM) PROJECT EXECUTION
PLAN (PxP) Template located at the USACE CAD/BIM Technology Center website to develop an acceptable Plan and update to include platforms and processes to meet the requirements of the project.
1.4.1.1 USACE Minimum Modeling Matrix (M3)
The USACE Minimum Modeling Matrix (M3) describes the minimum modeling and data requirements by defining the Level of Development ("LOD") and Element
Grade. Contractors shall use the M3 Template located at https://cadbimcenter.erdc.dren.mil/ and submit as part of the PxP.
Per instructions in the M3, Contractor is to identify elements included in the project scope and provide any applicable comments
1.4.2 PxP Demonstration
Within thirty (30) days after the acceptance of the PxP and M3, conduct a demonstration to review the Plan for clarification, and to verify the functionality of planned Model technology workflow and processes. If modifications are required, the Contractor shall complete the modifications and resubmit the PxP performing a subsequent demonstration for Government acceptance. There will be no payment for design or construction until the
PxP is completed and accepted by the Government. The Government may also withhold payment for unacceptable performance in executing the accepted PxP.
1.4.3 Advanced Modeling Submittals
For each Advanced Modeling Submittal, provide the following:
1.4.3.1 Approved PxP
The most recent approved PxP.
1.4.3.2 List of Submitted Files
A list of all submitted electronic files including a description, directory, and file name for each file submitted. Identify which files have been produced from the Model and Facility/Site Data. For all Sheet files, include a list of the sheet titles and sheet numbers.
1.4.3.3 Model Submittal Checklist
Complete the USACE BIM/CIM Submittal Checklist and submit with each submittal. Contractor can download the Checklist from the USACE CAD/BIM
Technology Center.
1.4.3.4 Advanced Modeling Electronic Files
Include all Advanced Modeling files associated with the scope of work to be provided under this Contract. The Model(s) shall be developed, updated and maintained using Building Information Modeling (BIM), and Computer Aided
Design (CAD) supplemented with drawing content as necessary to produce a complete set of Construction Documents.
1.4.3.5 3D Interactive Review Model
A copy of each BIM Model in an approved interactive review format.
1.4.3.6 IFC Coordination View
Provide an IFC Coordination View for all deliverables. Provide exported property set data for all IFC supported named building elements.
1.4.3.7 QC Reports
QC Reports will include the following:
1.4.3.7.1 Model Standards Checks and Reports
Provide QC checks demonstrating adherence to the NCS "BIM Implementation" section. Verify that the Project Facility/Site Data set has no undefined, incorrectly defined or duplicated elements. Identify and report non-compliant elements and submit a corrective action plan. Provide the
Government with detailed justification and request Government acceptance for any non-compliant element that the Contractor proposes to be allowed to remain in the Model.
a. No errors when opening.
b. No broken Links, References, or X-References.
c. Minimized extraneous information.
d. Content uses the coordinate system defined in the approved
PxP.
e. Models share a common alignment point.
f. Each discipline identified in the approved PxP is represented.
1.4.3.7.2 Graphics Standards Checks and Report
Provide QC checks on all graphic deliverables demonstrating that the fonts, dimensions, symbology and other construction document formatting are compliant with the requirements of this specification. Identify and report non-compliant content.
1.4.3.7.3 CAD Standards Checks and Report
Provide QC checks on CAD Output demonstrating that filenames, sheet borders, layer/level names, and symbology are compliant with the requirements of this specification. Identify and report non-compliant content. Identify and report non-compliant content.
1.4.3.7.4 Other Parameters
Develop such other QC parameters as Contractor deems appropriate for the
Project and provide to the Government for acceptance
1.4.3.8 PDF Documents
Provide one PDF file per discipline and one additional PDF file combining all disciplines, following the A/E/C CAD Standard discipline and drawing order.
1.4.4 Advanced Modeling Re-Submittals
For each Advanced Modeling Re-Submittal, provide the following:
1.4.4.1 Government Comments and Contractor Responses
Provide a response to each Government comment for backcheck.
1.4.5 Meetings
1.4.5.1 Pre-Construction Meeting
At minimum discuss the following during the meeting:
a. The requirement for Advanced Modeling deliverables under this
Contract.
b. Primary roles and responsibilities associated with the development and delivery of the Advanced Modeling submittals under this Contract.
c. Identify and agree upon a date and attendance list for the meetings described below:
1.4.5.2 Advanced Modeling Kick-Off Meeting
Conduct an Advanced Modeling Kick-Off Meeting prior to submission of the
PxP, within forty-five (45) days after Notice to Proceed. This meeting must include, at a minimum, the Contractor and the Geographic District BIM
Manager or delegate.
The intent of this meeting is to coordinate the Government's and the
Contractor's expectations for the PxP.
1.4.5.3 PxP Demonstration Meeting
Within thirty (30) days after the acceptance of the PxP and M3, conduct a demonstration to review the Plan for clarification, and to verify the functionality of planned Model technology workflow and processes. If modifications are required, the Contractor shall complete the modifications and resubmit the PxP performing a subsequent demonstration for Government acceptance. There will be no payment for design or construction until the
PxP is completed and accepted by the Government. The Government may also withhold payment for unacceptable performance in executing the accepted PxP.
1.5 OWNERSHIP AND RIGHTS OF DATA
The Government has ownership of and rights at the date of Closeout
Submittal to all CAD files, BIM/CIM Model(s), and Facility/Site Data developed for the Project in accordance with FAR Part 27, clauses incorporated in the contract and (DFARS) 252.227-7022, Government Rights
(Unlimited). The Government may make use of this data following any deliverable.
1.6 DELIVERY, STORAGE, AND HANDLING
Deliver Advanced Modeling submittals in an organized and legible manner.
Provide submittals adhering to the requirements described below.
1.6.1 Number of Copies
Provide three identical copies of disks for approval, for each submittal and each facility required. Provide on approved electronic media (one copy per disk or set of disks) as defined below. Provide submittal files on electronic storage media in compliance with the quality requirements identified in this specification.
1.6.2 Malicious Content
Scan all files for malicious viruses using commercially available scanning program that is routinely updated to identify and remove current virus threats.
1.6.3 Storage Media
Provide facility data on disk-based (DVD-R/RW) media. Any deviations from the required storage media must be approved by the Government. Select and apply technology used for electronic data transmission to ensure that the full submittal is provided on one single disk, whenever possible. When separation of the submittal is required separate the each site or facility onto separate media. Any further divisions must be documented in the PxP and approved by the Government.
1.6.3.1 Disk-Based Media
a. Apply a label directly printed to storage media. Do not provide adhesive, paper-based labels. List the name of the facility, project, project location, Contract number, Designer of Record firm/Prime
Contractor company's name, title of submission, and security classification (in accordance with the appropriate security classification labeling regulations) on the label. If multiple disks are provided, clearly document the contents of each disk on the label.
b. Include the name and contact information of the individual who produced the final data disk to ensure that any problems with the data or media can be easily resolved.
c. When browsed on any computer, the disk must display the following folders and their associated content:
(1) Submittal XXXXXX-X.X (Containing all submittal data)
(2) PxP (Containing 1 PxP per contract)
(3) Readme (Containing 1 TXT, PDF, or HTML file with general use information, organizational instructions, and basic preparer contact information. Include all information included on the storage media label.
PART 2 PRODUCTS
2.1 GOVERNMENT FURNISHED MATERIALS
The Government will provide Advanced Modeling files as Government Furnished
Material (GFM) for the Contractor's use. The information and level of detail contained in the GFM shall be maintained in the Record Models and
Record CAD files.
The Contractor has the option of preparing their own BIM/CIM models and CAD drawings as a basis for record model(s), record CAD drawings, and interim submittals. If so, the models must incorporate the same level of detail, properties, and functionality that is included in the GFM.
2.1.1 GFM Handover
The Government will provide the GFM at the Advanced Modeling Kick-Off
Meeting.
2.1.2 GFM File Formats
GFM will be provided in the following file formats:
2.1.2.1 Government Furnished BIM
The GFM will include Autodesk Revit 2021.
2.1.2.2 Government Furnished CAD
The GFM will include Bentley Systems Openroads 2022 Release 2 (version
10.12.01.59).
2.1.3 Variation with Contract Drawings
The Government makes no warranty that any of the GFM are complete or fully consistent with the contract drawings. The digital files provided are not part of the contract documents. If there is any discrepancy between the
BIM/CIM models, the CAD drawings, and the contract drawings, the contract drawings shall govern. The Government has no responsibility to modify any
GFMs due to changes in the design that occur after award.
2.1.4 Model Completion and Quality
The Government makes no guarantee that the BIM/CIM models and CAD files provide the level of completeness or quality required for closeout submittal. It is the Contractor's responsibility to complete the models and facility data to completely and correctly represent the as-built conditions of the facility and the site.
2.1.5 Data Loss, Corruption, and Error
Transfer of GFM files to the Contractor may result in corrupted files resulting in data loss and/or errors. Use of GFM files is at the
Contractor's risk. Verify data integrity upon receipt and request a replacement if necessary.
Any adjustment of file structure, format, or software version required to make GFM compatible with the Contractor's computer systems and/or software is the responsibility of the Contractor.
2.2 SYSTEM PLATFORM AND FILE FORMATS
The Contractor shall use the application(s), software version(s), and file format(s) matching or compatible with the GFM.
PART 3 EXECUTION
3.1 ADVANCED MODELING REQUIREMENTS
3.1.1 BIM and CIM
All BIM and CIM content authoring, model coordination, content delivery and all other activities and products shall comply with the NCS BIM
Implementation section, part "3.0 Basic BIM Guidelines."
All CAD content produced within the BIM and CIM authoring platforms shall comply with the NCS BIM Implementation section, part "2.0 Clarifications."
3.1.1.1 Minimum Modeling Requirements
Model to the requirements of the USACE M3 with the following modifications.
3.1.1.2 USACE Software Configuration Standards
a. USACE Bentley Workspace. Utilize the most recent version at the time of Contract award.
b. USACE Revit Templates. Utilize the most recent version at the time of Contract award.
3.1.1.3 Classification
All modeled elements shall include Facility/Site Data referencing one or more classification system(s) indentified in the M3.
3.1.1.4 Space/Room Data
The Model shall include spatial data defining actual net square footage and data to develop the room finish schedule, including room names and numbers. Include program information to verify design space against programmed space, using this information to validate area quantities.
3.1.1.5 Coordinate System
Coordinate systems used shall match those noted on the contract drawings.
3.1.1.6 Schedules
Schedules shall comply with the NCS BIM Implementation section, part "2.4
Schedules." Schedules shall be produced from, and remain linked to, the
Facility/Site Data within the Model. Any exceptions must be documented in the PxP and submitted to the Geographic BIM Manager, or delegate, for review.
3.1.1.7 Details and Enlarged Sections
Details and enlarged sections shall comply with the NCS BIM Implementation section, part "3.2 Model Coordination and Delivery." All details and enlarged sections necessary for construction shall be derived from the
Model when possible. For those details and enlarged sections not derived directly from the Model, Contractor must verify that geometry and data depicting the details and enlarged sections are consistent with Model elements. Details with significant drafted content such as 'standard' and
'typical' details shall not contradict the model and shall utilize the model as an underlay when possible for the purposes of verification and coordination. Three dimensional, isometric, and section isometric details derived from the model are preferred. Details and enlarged sections that are not derived from the Model must created using native authoring tools within the Model or be embedded within the Model.
3.1.1.8 Drawing Indices
Drawing indices shall comply with the NCS BIM Implementation section, part
"2.3 Sheet Organization." Where BIM authoring platform supports it, drawing indices should be derived from a model-driven schedule.
3.1.1.9 CAD Export
CAD content exported form a BIM or CIM modeling platform shall comply with the NCS BIM Implementation section, part "2.0 Clarifications."
3.1.2 CAD
All CAD content produced through native CAD authoring software outside of any BIM or CIM platform shall be compliant with ERDC/ITL TR-19-7 A/E/C CAD
Standard and ERDC/ITL TR-19-6 A/E/C Graphic Standard.
3.1.2.1 USACE Software Standards
a. Bentley MicroStation Seed Files . Download from the CAD/BIM
Technology Center website as part of the A/E/C Work Structure.
3.2 FINAL DESIGN AND FINAL RECORD SUBMITTAL REQUIREMENTS
Follow requirements for Content Delivery from the NCS BIM Implementation section, part "3.0 Basic BIM Guidelines."
3.3 PDF REQUIREMENTS
3.3.1 PDF Bookmarks
3.3.1.1 Construction Document Boookmarks
Bookmark construction document PDF sets to include one Parent Bookmark per
Discipline and one Child Bookmark per sheet within each Discipline. Format
Parent Bookmarks as "<Discipline>" (i.e. Architectural). Format Child
Bookmarks as "<Sheet ID> <Sheet Title>" (i.e. A-101 First Floor Plan).
3.4 MODEL USES
Include all of the following Model Uses in the Project Execution Plan (PxP).
3.4.1 Mandatory Model Uses
The following Model Uses are mandatory:
3.4.1.1 Design Phase Mandatory Model Uses
a. Design Authoring
b. 3D Coordination
c. Progress Review
3.4.1.2 Construction Phase Mandatory Model Uses
a. 3D Coordination
b. Record Modeling
3.4.2 Optional Model Uses
Contractor may use other Model Uses as desired.
3.5 AS-BUILT REQUIREMENTS
See Section 01 78 39.00.24 AS-BUILT DRAWINGS for additional as-built and record model quality and deliverable requirements.
-- End of Section --