Am-0002_W9128F22R0086_Attachments.pdf

PDF 1 MB Posted

Attached to
SOF Tactical Equipment Maintenance Facility Federal contract opportunity
Solicitation number
W9128F22R0086
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

This document describes a federal contract solicitation for the construction of a SOF Tactical Equipment Maintenance Facility at Fort Carson, Colorado. Key details include:

  • The project scope includes construction of an oil storage building, vehicle component storage building, organizational equipment parking, administration and shop control office, equipment maintenance systems office, weapons vault, shop stock listing room, repair exchange/tech support room, tool issuing/storage room, restrooms, janitorial closet, break/training/conference room, telecommunications room, utility rooms, organizational storage bays, maintenance and repair areas, fluid distribution room, and compressor room. A standalone prefabricated POL/hazardous waste storage building will also be provided.

  • The maintenance facilities will include bridge cranes, maintenance bays including pits and vehicle lifts, administrative space, and tool storage areas. Construction will consist of concrete foundation and floor slab with metal frame structure. Built-in building systems will include fire, energy, communications, security, and IT infrastructure.

  • The estimated construction cost is between $10-25 million. The solicitation number is W9128F22R0086 and it is located on the SAM website. A site visit will be held on October 6th at 11:00am MST at the provided address. Inquiries should be submitted through Bidder Inquiry in ProjNet by the deadline specified.

View the file

Other files for this federal contract opportunity

Other files attached to SOF Tactical Equipment Maintenance Facility, newest first.
File Type Posted
Am-0008_Solicitation_SOF-TEMF.pdf PDF
Am-0007_Solicitation_SOF-TEMF.pdf PDF
Am-0006_Solicitation_SOF-TEMF.pdf PDF
Am-0005_Solicitation_SOF-TEMF.pdf PDF
Am-0004_Attachments_SOF-TEMF.pdf PDF
Am-0004_Solicitation_SOF-TEMF.pdf PDF
Am-0003_W9128F22R0086_Attachments.pdf PDF
Am-0003_Solicitation_SOF-TEMF.pdf PDF
Am-0002_Solicitation_SOF-TEMF.pdf PDF
Am-0001_Solicitation_SOF-TEMF.pdf PDF
Am-0001_W9128F22R0086_Attachments.pdf PDF
Site-Visit_Sign-In-Sheet_10.06.2022.pdf PDF
Solicitation_SOF-TEMF.pdf PDF
Solicitation_SOF-TEMF.pdf PDF
SPECS_W9218F22R0086.pdf PDF
DRAWINGS_W9128F22R0086.pdf PDF
Solicitation_SOF-TEMF.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOF Tactical Equipment Maintenance Facility - Fort Carson, CO FCDC

SECTION TABLE OF CONTENTS

DIVISION 31 - EARTHWORK

SECTION 31 63 29

DRILLED CONCRETE PIERS AND SHAFTS

11/14

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 QUALITY CONTROL

1.3.1 General

1.3.2 Sequencing and Scheduling

1.3.3 Inspection Criteria

1.3.4 Qualification of Excavation Contractor

1.3.5 Qualification of Professional Engineer

1.3.6 Welding Qualifications

1.3.7 Pre-Construction Conference

1.4 PROJECT CONDITIONS

1.4.1 Existing Conditions

1.4.2 Interruption of Existing Utilities

1.4.3 Weather Limitations

PART 2 PRODUCTS

2.1 DESIGN REQUIREMENTS

2.1.1 Assembly

2.2 EQUIPMENT

2.2.1 Drilling and Excavation Equipment

2.3 MATERIALS

2.3.1 Steel Reinforcement

2.3.1.1 Deformed Steel Bars

2.3.1.2 Epoxy Coated Steel Wire

2.3.2 Ready-Mix Concrete

PART 3 EXECUTION

3.1 PREPARATION

3.2 INSTALLATION

3.2.1 Construction Criteria

3.2.2 Excavation

3.2.3 Steel Reinforcement

3.2.4 Concrete Placement

3.3 FIELD QUALITY CONTROL

3.3.1 Test Reports

-- End of Section Table of Contents --

SECTION 31 63 29 Page 1Am #0002

SECTION 31 63 29

DRILLED CONCRETE PIERS AND SHAFTS

11/14

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONCRETE INSTITUTE (ACI)

ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary

ACI 301 (2016) Specifications for Structural Concrete

ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete

ACI 305R (2020) Guide to Hot Weather Concreting

ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting

ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;

Errata 6 2016; Errata 7-9 2017) Building Code Requirements for Structural Concrete (ACI 318-14) and Commentary (ACI 318R-14)

ACI 336.1 (2001) Specification for the Construction of Drilled Piers

ACI SP-66 (2004) ACI Detailing Manual

AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)

ASCE 7 (2017) Minimum Design Loads for Buildings and Other Structures

AMERICAN WELDING SOCIETY (AWS)

AWS A5.1/A5.1M (2012) Specification for Carbon Steel Electrodes for Shielded Metal Arc Welding

AWS D1.1/D1.1M (2020) Structural Welding Code - Steel

AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel

SECTION 31 63 29 Page 2Am #0002

ASTM INTERNATIONAL (ASTM)

ASTM A615/A615M (2016) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement

ASTM A775/A775M (2017) Standard Specification for Epoxy-Coated Steel Reinforcing Bars

ASTM A884/A884M (2014) Standard Specification for Epoxy-Coated Steel Wire and Welded Wire Reinforcement

ASTM C143/C143M (2015) Standard Test Method for Slump of Hydraulic-Cement Concrete

ASTM C150/C150M (2018) Standard Specification for Portland Cement

ASTM C172 (2010) Standard Practice for Sampling Freshly Mixed Concrete

ASTM C31/C31M (2019) Standard Practice for Making and Curing Concrete Test Specimens in the Field

ASTM C39/C39M (2018) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens

ASTM C94/C94M (2017a) Standard Specification for Ready-Mixed Concrete

CONCRETE REINFORCING STEEL INSTITUTE (CRSI)

CRSI 10MSP (2009; 28th Ed; Errata) Manual of Standard Practice

U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)

FHWA NHI-10-016 (2010) Drilled Shafts: Construction Procedures and LRFD Design Methods

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926.501 Duty to Have Fall Protection

29 CFR 1926.502 Fall Protection Systems Criteria and Practices

29 CFR 1926.651 Specific Excavation Requirements

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SECTION 31 63 29 Page 3Am #0002

SD-02 Shop Drawings

Drilled Shaft Diameters; G-DO

Top and Bottom of Shaft Elevations; G-DO

Steel Reinforcement; G-DO

Accessories; G-DO

Anchor Bolt Locations; G-DO

SD-05 Design Data

Mix Design Data; G-DO

SD-06 Test Reports

Soils Report; G-DO

Ground Water Conditions; G-DO

Penetration Test; G-DO

Slump; G-DO

Concrete; G-DO

Compressive Strength; G-DO

SD-07 Certificates

Bill of Lading for Ready-Mix Concrete Deliveries; G-RO

Steel Reinforcement; G-DO

Excavation and Drilling Equipment; G-DO

Qualifications of Excavator; G-DO

Qualifications of Engineer; G-DO

Welding Certificates; G-RO

1.3 QUALITY CONTROL

1.3.1 General

Install drilled shaft foundations in accordance with applicable requirements as described by ACI 336.1, and FHWA NHI-10-016

1.3.2 Sequencing and Scheduling

Submit a detailed installation plan describing the schedule for drilling and/or excavation, installation of steel reinforcement and concrete placement with anticipated site conditions so that each excavated shaft is poured the same day that the drilling is performed.

SECTION 31 63 29 Page 4Am #0002

1.3.3 Inspection Criteria

Inspection activities should be designed to minimize delays while insuring the intent of the Industry Standard Specifications.

1.3.4 Qualification of Excavation Contractor

An experienced excavator with five (5) years experience and licensed in the State of Colorado specialized in excavating and installing work similar in material, design, and extent to that indicated for this Project. Submit certificates substantiating the Qualifications of Excavator.

1.3.5 Qualification of Professional Engineer

Provide engineering services by an authorized engineer currently licensed in the State of Colorado having a minimum of four (4) years experience as an engineer knowledgeable in drilled shaft foundation design analysis, protocols and procedures for the ACI 336.1, FHWA NHI-10-016, and ASCE 7.

Submit certificates substantiating the Qualifications of Engineer.

1.3.6 Welding Qualifications

Provide and maintain qualified procedures and personnel according to AWS D1.1/D1.1M, AWS D1.4/D1.4M, and AWS A5.1/A5.1M. Submit Welding Certificates to the Contracting Officer.

1.3.7 Pre-Construction Conference

After submittals are received and approved but before drilled shaft excavation and foundation work, including associated work, is performed, the Contracting Officer will hold a pre-construction conference to review the following:

a. The drawings, specifications and the geotechnical report.

b. Finalize construction schedule and verify availability of materials, Excavator's personnel, equipment, and facilities needed to make progress and avoid delays.

c. Methods and procedures related to drilled shaft foundation installation, including engineer's written instructions.

d. Support conditions for compliance with requirements, including alignment between foundation system and erection of structural members.

e. Governing regulations and requirements for, certificates, insurance, tests and inspections if applicable.

f. Temporary protection requirements for foundation assembly during and after installation.

1.4 PROJECT CONDITIONS

1.4.1 Existing Conditions

Locate existing underground utilities before excavating drilled shaft foundations. If existing utilities are to remain in place, provide protection during drilled shaft operations.

SECTION 31 63 29 Page 5Am #0002

1.4.2 Interruption of Existing Utilities

Do not interrupt any utility to occupied facilities unless directed in writing by the Contracting Officer.

1.4.3 Weather Limitations

Proceed with installation preparation only when existing and forecasted weather conditions permit work to proceed without water entering into the area of excavation.

PART 2 PRODUCTS

2.1 DESIGN REQUIREMENTS

2.1.1 Assembly

Installation drawings are to include, but not limited to, the following items indicating a completely dimensioned layout and location of drilled shafts and concrete placement for foundation system. Submit detailed shop drawings for the following:

a. Drilled shaft diameters

b. Top and bottom of shaft elevations

c. Steel reinforcement

d. Anchor bolt locations

e. Accessories

EQUIPMENT

2.2 EQUIPMENT

2.2.1 Drilling and Excavation Equipment

Provide drilling and excavation equipment having adequate capacity, including but not limited to, power, torque and down thrust to excavate a hole of diameter and depth indicated. Also provide excavation and over-reaming tools of adequate design, size and strength to perform the work indicated.

Provide special drilling equipment including, but not limited to, rock core barrels, rock tools, air tools and other equipment as necessary to construct the shaft excavation to the size and depth indicated when materials encountered can not be drilled using earth augers and/or over-reaming tools.

Submit certificates substantiating appropriate selection of excavation and drilling equipment.

SECTION 31 63 29 Page 6Am #0002

2.3 MATERIALS

2.3.1 Steel Reinforcement

2.3.1.1 Deformed Steel Bars

Steel bars conforming to ASTM A615/A615M and coated in accordance with ASTM A775/A775M, Grade 60 ksi and ACI 318.

2.3.1.2 Epoxy Coated Steel Wire

Steel wire conforming to ASTM A884/A884M.

2.3.2 Ready-Mix Concrete

Ready-Mix concrete and mix design conforming to ACI 117, ACI 301, and ACI 304R, minimum compressive strength [*Am-2] 4,500 psi at 28 days. See Section 03 30 00.00 10 CAST-IN-PLACE CONCRETE. [**Am-2]

Portland cements conforming to ASTM C150/C150M, Type II. Provide one brand and type of cement for formed concrete having exposed-to-view finished surfaces.

Potable water conforming to ASTM C94/C94M.

Measure, batch, mix and deliver concrete according to ASTM C94/C94M and furnish batch ticket information.

PART 3 EXECUTION

3.1 PREPARATION

Protect existing structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, vibration, and other hazards created by drilled shaft foundation operations.

Provide Fall Protection as required by 29 CFR 1926.501, 29 CFR 1926.502 and 29 CFR 1926.651.

3.2 INSTALLATION

3.2.1 Construction Criteria

Provide equipment for checking the dimensions and alignment of each shaft excavation. Determine dimensions and alignment jointly with the contractor and engineer. Measure final shaft depths with appropriate weighted tape measure or other approved method after cleaning.

Provide and install monolithically cast-in-place concrete drilled shaft foundation to the sizes indicated.

Provide and install straight cylindrical shaft foundation of the type indicated.

Tolerances:

a. Maximum variation of the center of any shaft foundation from the required location: 3 inches, measured at the ground surface.

SECTION 31 63 29 Page 7Am #0002

[*Am-2] 4,500 psi at 28 days. See Section 03 30 00.00 10 CAST-IN-PLACE CONCRETE. [**Am-2]

b. Bottom Diameter: Minus zero, plus 6 inches, measured in any direction.

c. Maximum variation from plumb: 1:40.

d. Maximum bottom level: Plus or minus 2 inches.

3.2.2 Excavation

Accomplish excavation of shaft foundations by standard excavation methods including, but not limited to, conventional augers fitted with soil and/or rock teeth, or under-reaming tools attached to drilling equipment of adequate size, power, torque and down thrust necessary for the work.

Perform excavation through whatever materials that are encountered to the dimensions, depths and applicable ACI 336.1 tolerances.

Protect excavated walls with temporary watertight steel casings of sufficient length to prevent water intrusion, cave-ins, displacement of surrounding earth, and injury to personnel and damage to construction operations.

Excavate shafts for drilled foundations to indicated elevations. Remove loose debris, materials and/or muck to make bottom surfaces level within ACI 336.1 tolerances.

Remove water from excavated shaft prior to concrete placement.

3.2.3 Steel Reinforcement

Comply with recommendations in the CRSI "Manual of Standard Practice" CRSI 10MSP for fabricating, placing and supporting reinforcement. Shop fabricate steel reinforcement in accordance with ACI SP-66.

When practicable to deliver the reinforcement cage assembly to the jobsite as a complete unit ready for installation, should it not be possible make remaining connections and/or splices, as indicated on the approved shop drawings, at-grade level prior to lowering the complete assembly into the hole.

Clean reinforcement of loose rust, mill scale, earth and other foreign materials. Do not tack weld crossing reinforcing bars. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.

Lower reinforcement steel into the hole in such a manner as to prevent damage to the walls of the excavation. Place, tie and/or clip cage symmetrically about the axis of the shaft. Use centering devices securely attached to the cage to clear the shaft walls and maintain the cage in place throughout the concrete placement operations.

Cooperate with other trades in setting of anchor bolts, inserts, and other embedded items. Where conflicts occur between reinforcing and embedded items, notify the Contracting Officer so that conflicts may be reconciled before concrete placement. Position and support anchors and embedded items with appropriate accessories.

Use templates to set anchor bolts, leveling plates and other accessories required for structure erection. Provide blocking and/or holding devices to maintain required anchoring positions during final concrete placement.

SECTION 31 63 29 Page 8Am #0002

3.2.4 Concrete Placement

Keep all equipment, including but not limited to, mixers, pumps, hoses, tools and screeds clean and free of set concrete throughout the placement operation.

Convey concrete from the mixer to place of deposit by best industry methods that prevents segregation and loss of material. Size and design the equipment for conveying concrete to ensure uniform, continuous placement of concrete.

Place concrete in accordance with ACI 318.

Place concrete in a continuous operation and without segregation into dry excavations whenever possible after inspection and written approval by the Contracting Officer. Use all practicable means to obtain a dry excavation before and during concrete placement.

Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. When hot weather conditions exist that would impair quality and strength of placed concrete, comply with ACI 305R. Comply with ACI 306.1 for cold-weather protection.

A minimum of 50 percent of the base for each shaft is to be less than 1/2 inch of sediment at the time of concrete placement. Maximum depth of sediment or debris at any place on the base of the shaft is not to exceed 1-1/2 inches. Shaft cleanliness is to be determined by the engineer by visual inspection.

3.3 FIELD QUALITY CONTROL

3.3.1 Test Reports

As a minimum, submit the following test reports and data.

a. Soils Report

b. Ground Water conditions

c. Penetration Test

d. Slump

e. Concrete

f. Compressive Strength

Sample and test concrete for quality control during placement. Quality control testing is provided by the contract.

Sample freshly placed concrete for testing in accordance with ASTM C172.

Make concrete test specimens for compressive strength at 7 and 28 days for each design mix conforming to ASTM C31/C31M. Compression test concrete in accordance with ASTM C39/C39M.

SECTION 31 63 29 Page 9Am #0002

Test Slump at plant for each design mix in accordance with ASTM C143/C143M.

-- End of Section --

SECTION 31 63 29 Page 10Am #0002

DIVISION 33 - UTILITIES

SECTION 33 40 00

STORM DRAINAGE UTILITIES

02/10

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 DELIVERY, STORAGE, AND HANDLING

1.3.1 Delivery and Storage

1.3.2 Handling

PART 2 PRODUCTS

2.1 PIPE FOR CULVERTS AND STORM DRAINS

2.1.1 Concrete Pipe

2.1.2 Ductile Iron Culvert Pipe

2.1.3 Poly Vinyl Chloride (PVC) Pipe

2.1.3.1 Type PSM PVC Pipe

2.1.3.2 Profile PVC Pipe

2.1.3.3 Smooth Wall PVC Pipe

2.1.3.4 Corrugated PVC Pipe

2.1.4 Polyethylene (PE) Pipe

2.1.4.1 Smooth Wall PE Pipe

2.1.4.2 Corrugated PE Pipe

2.1.4.3 Profile Wall PE Pipe

2.1.5 Steel Reinforced Polyethylene (SRPE) Pipe

2.2 PERFORATED PIPING

2.2.1 Polyvinyl Chloride (PVC) Pipe

2.3 DRAINAGE STRUCTURES

2.3.1 Flared End Sections

2.4 MISCELLANEOUS MATERIALS

2.4.1 Concrete

2.4.2 Mortar

2.4.3 Precast Concrete Segmental Blocks

2.4.4 Brick

2.4.5 Precast Reinforced Concrete Manholes

2.4.6 Frame and Cover for Gratings

2.4.7 Joints

2.4.7.1 Flexible Watertight Joints

2.4.7.2 External Sealing Bands

2.4.7.3 PVC Plastic Pipes

2.4.7.4 Smooth Wall PE Plastic Pipe

2.4.7.5 Corrugated PE Plastic Pipe

2.4.7.6 Profile Wall PE Plastic Pipe

2.4.7.7 Ductile Iron Pipe

2.4.7.8 Steel Reinforced Polyethylene (SRPE) Pipe

2.5 RESILIENT CONNECTORS

2.6 EROSION CONTROL RIP RAP

SECTION 33 40 00 Page 1Am #0002

PART 3 EXECUTION

3.1 INSTALLATION OF PIPE CULVERTS, STORM DRAINS, AND DRAINAGE

STRUCTURES

3.1.1 Trenching

3.1.2 Removal of Rock

3.1.3 Removal of Unstable Material

3.2 BEDDING

3.2.1 Concrete Pipe Requirements

3.2.2 Ductile Iron Pipe

3.2.3 Plastic Pipe

3.3 PLACING PIPE

3.3.1 Concrete, Clay, PVC, Ribbed PVC, Ductile Iron and Cast-Iron

Pipe

3.3.2 Elliptical and Elliptical Reinforced Concrete Pipe

3.3.3 PE, SRPE, and Dual Wall and Triple Wall PP Pipe

3.3.4 Multiple Culverts

3.3.5 Jacking Pipe Through Fills

3.4 JOINTING

3.4.1 Concrete and Clay Pipe

3.4.1.1 Cement-Mortar Bell-and-Spigot Joint

3.4.1.2 Cement-Mortar Oakum Joint for Bell-and-Spigot Pipe

3.4.1.3 Cement-Mortar Diaper Joint for Bell-and-Spigot Pipe

3.4.1.4 Cement-Mortar Tongue-and-Groove Joint

3.4.1.5 Cement-Mortar Diaper Joint for Tongue-and-Groove Pipe

3.4.1.6 Plastic Sealing Compound Joints for Tongue-and-Grooved Pipe

3.4.1.7 Flexible Watertight Joints

3.4.1.8 External Sealing Band Joint for Noncircular Pipe

3.5 DRAINAGE STRUCTURES

3.5.1 Manholes and Inlets

3.5.2 Walls and Headwalls

3.6 BACKFILLING

3.6.1 Backfilling Pipe in Trenches

3.6.2 Backfilling Pipe in Fill Sections

3.6.3 Movement of Construction Machinery

3.6.4 Compaction

3.6.4.1 General Requirements

3.6.4.2 Minimum Density

3.7 FIELD PAINTING

3.7.1 Cast-Iron Covers, Frames, Gratings, And Steps

3.7.2 Steel Covers And Frames Or Concrete Frames

3.8 FIELD QUALITY CONTROL

3.8.1 Tests

3.8.1.1 [*Am-2] NOT USED [**Am-2]

3.8.1.2 Determination of Density

3.8.1.3 Deflection Testing

3.8.1.3.1 Laser Profiler

3.8.1.3.2 Mandrel

3.8.2 Inspection

3.8.2.1 Post-Installation Inspection

3.8.2.1.1 Concrete

3.8.2.1.2 Flexible Pipe

3.8.2.1.3 Post-Installation Inspection Report

3.8.3 Repair Of Defects

3.8.3.1 Leakage Test

3.8.3.2 Deflection Testing

3.8.3.3 Inspection

3.8.3.3.1 Concrete

3.8.3.3.2 Flexible Pipe

SECTION 33 40 00 Page 2Am #0002

[*Am-2] NOT USED [**Am-2]

3.9 PROTECTION

3.10 WARRANTY PERIOD

SECTION 33 40 00 Page 3Am #0002

SECTION 33 40 00

STORM DRAINAGE UTILITIES

02/10

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO M 294 (2017) Standard Specification for Corrugated Polyethylene Pipe, 300- to 1500-mm (12- to 60-in.) Diameter

AASHTO MP 20 (2013; R 2017) Standard Specification for Steel-Reinforced Polyethylene (PE) Ribbed Pipe, 300- to 1500-mm (12- to 60-in) Diameter

AMERICAN RAILWAY ENGINEERING AND MAINTENANCE-OF-WAY ASSOCIATION

(AREMA)

AREMA Eng Man (2017) Manual for Railway Engineering

ASTM INTERNATIONAL (ASTM)

ASTM A48/A48M (2003; R 2016) Standard Specification for Gray Iron Castings

ASTM A536 (1984; R 2019; E 2019) Standard Specification for Ductile Iron Castings

ASTM A716 (2018) Standard Specification for Ductile Iron Culvert Pipe

ASTM A929/A929M (2018) Standard Specification for Steel Sheet, Metallic-Coated by the Hot-Dip Process for Corrugated Steel Pipe

ASTM B26/B26M (2014; E 2015) Standard Specification for Aluminum-Alloy Sand Castings

ASTM C32 (2013; R 2017) Standard Specification for Sewer and Manhole Brick (Made from Clay or Shale)

ASTM C55 (2017) Standard Specification for Concrete Building Brick

ASTM C62 (2017) Standard Specification for Building

SECTION 33 40 00 Page 4Am #0002

Brick (Solid Masonry Units Made from Clay or Shale)

ASTM C76 (2019) Standard Specification for Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe

ASTM C139 (2017) Standard Specification for Concrete Masonry Units for Construction of Catch Basins and Manholes

ASTM C231/C231M (2017a) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method

ASTM C270 (2019) Standard Specification for Mortar for Unit Masonry

ASTM C425 (2004; R 2013) Standard Specification for Compression Joints for Vitrified Clay Pipe and Fittings

ASTM C443 (2020) Standard Specification for Joints for Concrete Pipe and Manholes, Using Rubber Gaskets

ASTM C478 (2018) Standard Specification for Circular Precast Reinforced Concrete Manhole Sections

ASTM C877 (2008) External Sealing Bands for Concrete Pipe, Manholes, and Precast Box Sections

ASTM C923 (2008; R 2013; E 2016) Standard Specification for Resilient Connectors Between Reinforced Concrete Manhole Structures, Pipes and Laterals

ASTM C990 (2009; R 2014) Standard Specification for Joints for Concrete Pipe, Manholes and Precast Box Sections Using Preformed Flexible Joint Sealants

ASTM D1557 (2012; E 2015) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)

ASTM D1751 (2004; E 2013; R 2013) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)

ASTM D1752 (2018) Standard Specification for Preformed Sponge Rubber, Cork and Recycled PVC Expansion Joint Fillers for Concrete Paving and Structural Construction

SECTION 33 40 00 Page 5Am #0002

ASTM D1784 (2020) Standard Specification for Rigid Poly(Vinyl Chloride) (PVC) Compounds and Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds

ASTM D2167 (2015) Density and Unit Weight of Soil in Place by the Rubber Balloon Method

ASTM D2321 (2020) Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications

ASTM D2729 (2017) Standard Specification for Poly(Vinyl Chloride) (PVC) Sewer Pipe and Fittings

ASTM D3034 (2016) Standard Specification for Type PSM Poly(Vinyl Chloride) (PVC) Sewer Pipe and Fittings

ASTM D3212 (2007; R 2020) Standard Specification for Joints for Drain and Sewer Plastic Pipes Using Flexible Elastomeric Seals

ASTM D3350 (2012) Polyethylene Plastics Pipe and Fittings Materials

ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

ASTM F477 (2014) Standard Specification for Elastomeric Seals (Gaskets) for Joining Plastic Pipe

ASTM F679 (2016) Standard Specification for Poly(Vinyl Chloride) (PVC) Large-Diameter Plastic Gravity Sewer Pipe and Fittings

ASTM F714 (2013; R 2019) Standard Specification for Polyethylene (PE) Plastic Pipe (DR-PR) Based on Outside Diameter

ASTM F794 (2003; R 2014) Standard Specification for Poly(Vinyl Chloride) (PVC) Profile Gravity Sewer Pipe and Fittings Based on Controlled Inside Diameter

ASTM F894 (2019) Standard Specification for Polyethylene (PE) Large Diameter Profile Wall Sewer and Drain Pipe

ASTM F949 (2020) Standard Specification for Poly(Vinyl Chloride) (PVC) Corrugated Sewer Pipe with a Smooth Interior and Fittings

ASTM F2562/F2562M (2015) Specification for Steel Reinforced

SECTION 33 40 00 Page 6Am #0002

Thermoplastic Ribbed Pipe and Fittings for Non-Pressure Drainage and Sewerage

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-04 Samples

Pipe for Culverts and Storm Drains

SD-07 Certificates

Resin Certification

Oil Resistant Gasket

[*Am-2] <submittal deleted> [**Am-2]

Determination of Density

Frame and Cover for Gratings

Post-Installation Inspection Report

SD-08 Manufacturer's Instructions

Placing Pipe

1.3 DELIVERY, STORAGE, AND HANDLING

1.3.1 Delivery and Storage

Materials delivered to site shall be inspected for damage, unloaded, and stored with a minimum of handling. Materials shall not be stored directly on the ground. The inside of pipes and fittings shall be kept free of dirt and debris. Before, during, and after installation, plastic pipe and fittings shall be protected from any environment that would result in damage or deterioration to the material. Keep a copy of the manufacturer's instructions available at the construction site at all times and follow these instructions unless directed otherwise by the Contracting Officer. Solvents, solvent compounds, lubricants, elastomeric gaskets, and any similar materials required to install plastic pipe shall be stored in accordance with the manufacturer's recommendations and shall be discarded if the storage period exceeds the recommended shelf life.

Solvents in use shall be discarded when the recommended pot life is exceeded.

1.3.2 Handling

Materials shall be handled in a manner that ensures delivery to the trench in sound, undamaged condition. Pipe shall be carried to the trench, not dragged.

SECTION 33 40 00 Page 7Am #0002

[*Am-2] <submittal deleted> [**Am-2]

PART 2 PRODUCTS

2.1 PIPE FOR CULVERTS AND STORM DRAINS

Pipe for culverts and storm drains shall be of the sizes indicated and shall conform to the requirements specified.

2.1.1 Concrete Pipe

Manufactured in accordance with and conforming to ASTM C76, Class III or IV, as indicated on Drawings.

2.1.2 Ductile Iron Culvert Pipe

ASTM A716.

2.1.3 Poly Vinyl Chloride (PVC) Pipe

Submit the pipe manufacturer's resin certification, indicating the cell classification of PVC used to manufacture the pipe, prior to installation of the pipe.

2.1.3.1 Type PSM PVC Pipe

ASTM D3034, Type PSM, maximum SDR 35, produced from PVC certified by the Manufacturer as meeting the requirements of ASTM D1784, minimum cell class 12454-B.

2.1.3.2 Profile PVC Pipe

ASTM F794, Series 46, produced from PVC certified by the Manufacturer as meeting the requirements of ASTM D1784, minimum cell class 12454-B.

2.1.3.3 Smooth Wall PVC Pipe

ASTM F679 produced from PVC certified by the Manufacturer as meeting the requirements of ASTM D1784, minimum cell class 12454-B.

2.1.3.4 Corrugated PVC Pipe

ASTM F949 produced from PVC certified by the Manufacturer as meeting the requirements of ASTM D1784, minimum cell class 12454-B.

2.1.4 Polyethylene (PE) Pipe

Submit the pipe manufacturer's resin certification, indicating the cell classification of PE used to manufacture the pipe, prior to installation of the pipe. The minimum cell classification for polyethylene plastic shall apply to each of the seven primary properties of the cell classification limits in accordance with ASTM D3350.

2.1.4.1 Smooth Wall PE Pipe

ASTM F714, maximum DR of 21 for pipes 3 to 24 inches in diameter and maximum DR of 26 for pipes 26 to 48 inches in diameter. Pipe shall be produced from PE certified by the resin producer as meeting the requirements of ASTM D3350, minimum cell class 335434C.

SECTION 33 40 00 Page 8Am #0002

2.1.4.2 Corrugated PE Pipe

AASHTO M 294, Type S . For slow crack growth resistance, acceptance of resins shall be determined by using the notched constant ligament-stress (NCLS) test meeting the requirements of AASHTO M 294. Pipe walls shall have the following properties:

Nominal Size (inch)) Minimum Wall Area (square in/ft)

Minimum Moment of Inertia of Wall Section (in. to the

4th/in.)

12 1.5 0.024

15 1.91 0.053

18 2.34 0.062

24 3.14 0.116

30 3.92 0.163

36 4.50 0.222

42 4.69 0.543

48 5.15 0.543

54 5.67 0.800

60 6.45 0.800

2.1.4.3 Profile Wall PE Pipe

ASTM F894, RSC 160, produced from PE certified by the resin producer as meeting the requirements of ASTM D3350, minimum cell class 334433C. Pipe walls shall have the following properties:

Nominal Size (inch) Minimum Wall Area (square in/ft)

Minimum Moment of Inertia of Wall Section (in to the 4th/in)

Cell Class 334433C Cell Class 335434C

18 2.96 0.052 0.038

21 4.15 0.070 0.051

24 4.66 0.081 0.059

27 5.91 0.125 0.091

30 5.91 0.125 0.091

33 6.99 0.161 0.132

SECTION 33 40 00 Page 9Am #0002

Nominal Size (inch) Minimum Wall Area (square in/ft)

Minimum Moment of Inertia of Wall Section (in to the 4th/in)

Cell Class 334433C Cell Class 335434C

36 7.81 0.202 0.165

42 8.08 0.277 0.227

48 8.82 0.338 0.277

2.1.5 Steel Reinforced Polyethylene (SRPE) Pipe

SRPE pipe will meet the requirements of ASTM F2562/F2562M 8 - 120 inch diameter pipe and AASHTO MP 20 (12 - 60 inch diameter pipe).

2.2 PERFORATED PIPING

2.2.1 Polyvinyl Chloride (PVC) Pipe

ASTM D2729.

2.3 DRAINAGE STRUCTURES

2.3.1 Flared End Sections

Sections shall be of a standard design fabricated from zinc coated steel sheets meeting requirements of ASTM A929/A929M.

2.4 MISCELLANEOUS MATERIALS

2.4.1 Concrete

Unless otherwise specified, concrete and reinforced concrete shall conform to the requirements for 4,500 psi concrete under Section 03 30 00.00 10 CAST-IN-PLACE CONCRETE. The concrete mixture shall have air content by volume of concrete, based on measurements made immediately after discharge from the mixer, of 5 to 7 percent when maximum size of coarse aggregate exceeds 1-1/2 inches. Air content shall be determined in accordance with ASTM C231/C231M. The concrete covering over steel reinforcing shall not be less than 1 inch thick for covers and not less than 1-1/2 inches thick for walls and flooring. Concrete covering deposited directly against the ground shall have a thickness of at least 3 inches between steel and ground. Expansion-joint filler material shall conform to ASTM D1751, or ASTM D1752, or shall be resin-impregnated fiberboard conforming to the physical requirements of ASTM D1752.

2.4.2 Mortar

Mortar for pipe joints, connections to other drainage structures, and brick or block construction shall conform to ASTM C270, Type M, except that the maximum placement time shall be 1 hour. The quantity of water in the mixture shall be sufficient to produce a stiff workable mortar but in no case shall exceed 5 gallons of water per sack of cement. Water shall be clean and free of harmful acids, alkalis, and organic impurities. The

SECTION 33 40 00 Page 10Am #0002 mortar shall be used within 30 minutes after the ingredients are mixed with water. The inside of the joint shall be wiped clean and finished smooth. The mortar head on the outside shall be protected from air and sun with a proper covering until satisfactorily cured.

2.4.3 Precast Concrete Segmental Blocks

Precast concrete segmental block shall conform to ASTM C139, not more than 8 inches thick, not less than 8 inches long, and of such shape that joints can be sealed effectively and bonded with cement mortar.

2.4.4 Brick

Brick shall conform to ASTM C62, Grade SW; ASTM C55, Grade S-I or S-II; or ASTM C32, Grade MS. Mortar for jointing and plastering shall consist of one part portland cement and two parts fine sand. Lime may be added to the mortar in a quantity not more than 25 percent of the volume of cement. The joints shall be filled completely and shall be smooth and free from surplus mortar on the inside of the structure. Brick structures shall be plastered with 1/2 inch of mortar over the entire outside surface of the walls. For square or rectangular structures, brick shall be laid in stretcher courses with a header course every sixth course. For round structures, brick shall be laid radially with every sixth course a stretcher course.

2.4.5 Precast Reinforced Concrete Manholes

Conform to ASTM C478. Joints between precast concrete risers and tops shall be full-bedded in cement mortar and shall be smoothed to a uniform surface on both interior and exterior of the structure. No ladders or steps are to be included or installed in Manholes at Ft. Carson.

2.4.6 Frame and Cover for Gratings

Submit certification on the ability of frame and cover or gratings to carry the imposed live load. Frame and cover for gratings shall be cast gray iron, ASTM A48/A48M, Class 35B; cast ductile iron, ASTM A536, Grade 65-45-12; or cast aluminum, ASTM B26/B26M, Alloy 356.O-T6. Weight, shape, size, and waterway openings for grates and curb inlets shall be as indicated on the plans. The word "Storm Sewer" shall be stamped or cast into covers so that it is plainly visible.

2.4.7 Joints

2.4.7.1 Flexible Watertight Joints

a. Flexible watertight joints shall be made with plastic or rubber-type gaskets for concrete pipe and with factory-fabricated resilient materials for clay pipe. The design of joints and the physical requirements for preformed flexible joint sealants shall conform to ASTM C990, and rubber-type gaskets shall conform to ASTM C443.

Factory-fabricated resilient joint materials shall conform to ASTM C425.

Gaskets shall have not more than one factory-fabricated splice, except that two factory-fabricated splices of the rubber-type gasket are permitted if the nominal diameter of the pipe being gasketed exceeds 54 inches.

b. Rubber gaskets shall comply with the oil resistant gasket requirements of ASTM C443. Certified copies of test results shall be delivered to

SECTION 33 40 00 Page 11Am #0002 the Contracting Officer before gaskets or jointing materials are installed. Alternate types of watertight joint may be furnished, if specifically approved.

2.4.7.2 External Sealing Bands

Requirements for external sealing bands shall conform to ASTM C877.

2.4.7.3 PVC Plastic Pipes

Joints shall be solvent cement or elastomeric gasket type in accordance with the specification for the pipe and as recommended by the pipe manufacturer.

2.4.7.4 Smooth Wall PE Plastic Pipe

Pipe shall be joined using butt fusion method as recommended by the pipe manufacturer.

2.4.7.5 Corrugated PE Plastic Pipe

Pipe joints shall be water tight and shall conform to the requirements in AASHTO M 294. Water tight joints shall be made using a PE coupling and rubber gaskets as recommended by the pipe manufacturer. Rubber gaskets shall conform to ASTM F477.

2.4.7.6 Profile Wall PE Plastic Pipe

Joints shall be gasketed or thermal weld type with integral bell in accordance with ASTM F894.

2.4.7.7 Ductile Iron Pipe

Couplings and fittings shall be as recommended by the pipe manufacturer.

2.4.7.8 Steel Reinforced Polyethylene (SRPE) Pipe

SRPE joints shall meet the requirements of ASTM D3212.

2.5 RESILIENT CONNECTORS

Flexible, watertight connectors used for connecting pipe to manholes and inlets shall conform to ASTM C923.

2.6 EROSION CONTROL RIP RAP

Provide non-erodible rock not exceeding 15 inches in its greatest dimension and choked with sufficient small rocks to provide a dense mass with a minimum thickness ofas indicated.

PART 3 EXECUTION

3.1 INSTALLATION OF PIPE CULVERTS, STORM DRAINS, AND DRAINAGE STRUCTURES

Excavation of trenches, and for appurtenances and backfilling for culverts and storm drains, shall be in accordance with the applicable portions of Section 31 00 00 EARTHWORK, and the requirements specified below.

SECTION 33 40 00 Page 12Am #0002

3.1.1 Trenching

The width of trenches at any point below the top of the pipe shall be not greater than the outside diameter of the pipe plus 24 inches to permit satisfactory jointing and thorough tamping of the bedding material under and around the pipe. Sheeting and bracing, where required, shall be placed within the trench width as specified, without any overexcavation.

Where trench widths are exceeded, redesign with a resultant increase in cost of stronger pipe or special installation procedures will be necessary. Cost of this redesign and increased cost of pipe or installation shall be borne by the Contractor without additional cost to the Government.

3.1.2 Removal of Rock

Rock in either ledge or boulder formation shall be replaced with suitable materials to provide a compacted earth cushion having a thickness between unremoved rock and the pipe of at least 8 inches or 1/2 inch for each foot of fill over the top of the pipe, whichever is greater, but not more than three-fourths the nominal diameter of the pipe. Where bell-and-spigot pipe is used, the cushion shall be maintained under the bell as well as under the straight portion of the pipe. Rock excavation shall be as specified and defined in Section 31 00 00 EARTHWORK .

3.1.3 Removal of Unstable Material

Where wet or otherwise unstable soil incapable of properly supporting the pipe, as determined by the Contracting Officer, is unexpectedly encountered in the bottom of a trench, such material shall be removed to the depth required and replaced to the proper grade with select granular material, compacted as provided in paragraph BACKFILLING. When removal of unstable material is due to the fault or neglect of the Contractor while performing shoring and sheeting, water removal, or other specified requirements, such removal and replacement shall be performed at no additional cost to the Government.

3.2 BEDDING

The bedding surface for the pipe shall provide a firm foundation of uniform density throughout the entire length of the pipe.

3.2.1 Concrete Pipe Requirements

When no bedding class is specified or detailed on the drawings, concrete pipe shall be bedded in granular material minimum 4 inch in depth in trenches with soil foundation. Depth of granular bedding in trenches with rock foundation shall be 1/2 inch in depth per foot of depth of fill, minimum depth of bedding shall be 8 inch up to maximum depth of 24 inches.

The middle third of the granular bedding shall be loosely placed. Bell holes and depressions for joints shall be removed and formed so entire barrel of pipe is uniformly supported. The bell hole and depressions for the joints shall be not more than the length, depth, and width required for properly making the particular type of joint.

3.2.2 Ductile Iron Pipe

Bedding for ductile iron pipe shall be as shown on the drawings.

SECTION 33 40 00 Page 13Am #0002

3.2.3 Plastic Pipe

Bedding for PVC, PE, SRPE and PP pipe shall meet the requirements of ASTM D2321. Use Class IB or II material for bedding, haunching, and initial backfill.

3.3 PLACING PIPE

Each pipe shall be thoroughly examined before being laid; defective or damaged pipe shall not be used. Plastic pipe, excluding SRPE pipe shall be protected from exposure to direct sunlight prior to laying, if necessary to maintain adequate pipe stiffness and meet installation deflection requirements. Pipelines shall be laid to the grades and alignment indicated. Proper facilities shall be provided for lowering sections of pipe into trenches. Lifting lugs in vertically elongated pipe shall be placed in the same vertical plane as the major axis of the pipe.

Pipe shall not be laid in water, and pipe shall not be laid when trench conditions or weather are unsuitable for such work. Diversion of drainage or dewatering of trenches during construction shall be provided as necessary. Deflection of installed flexible pipe shall not exceed the following limits:

TYPE OF PIPE MAXIMUM ALLOWABLE

DEFLECTION (percent)

Plastic (PVC, PE, SRPE, and PP) 5

Note post installation requirements of paragraph DEFLECTION TESTING in PART 3 of this specification for all pipe products including deflection testing requirements for flexible pipe.

3.3.1 Concrete, Clay, PVC, Ribbed PVC, Ductile Iron and Cast-Iron Pipe

Laying shall proceed upgrade with spigot ends of bell-and-spigot pipe and tongue ends of tongue-and-groove pipe pointing in the direction of the flow.

3.3.2 Elliptical and Elliptical Reinforced Concrete Pipe

The manufacturer's reference lines, designating the top of the pipe, shall be within 5 degrees of a vertical plane through the longitudinal axis of the pipe, during placement. Damage to or misalignment of the pipe shall be prevented in all backfilling operations.

3.3.3 PE, SRPE, and Dual Wall and Triple Wall PP Pipe

Laying shall be with the separate sections joined firmly on a bed shaped to line and grade and shall follow manufacturer's guidelines.

3.3.4 Multiple Culverts

Where multiple lines of pipe are installed, adjacent sides of pipe shall be at least half the nominal pipe diameter or 3 feet apart, whichever is

SECTION 33 40 00 Page 14Am #0002 less.

3.3.5 Jacking Pipe Through Fills

Methods of operation and installation for jacking pipe through fills shall conform to requirements specified in Volume 1, Chapter 1, Part 4 of AREMA Eng Man.

3.4 JOINTING

3.4.1 Concrete and Clay Pipe

3.4.1.1 Cement-Mortar Bell-and-Spigot Joint

The first pipe shall be bedded to the established grade line, with the bell end placed upstream. The interior surface of the bell shall be thoroughly cleaned with a wet brush and the lower portion of the bell filled with mortar as required to bring inner surfaces of abutting pipes flush and even. The spigot end of each subsequent pipe shall be cleaned with a wet brush and uniformly matched into a bell so that sections are closely fitted. After each section is laid, the remainder of the joint shall be filled with mortar, and a bead shall be formed around the outside of the joint with sufficient additional mortar. If mortar is not sufficiently stiff to prevent appreciable slump before setting, the outside of the joint shall be wrapped or bandaged with cheesecloth to hold mortar in place.

3.4.1.2 Cement-Mortar Oakum Joint for Bell-and-Spigot Pipe

A closely twisted gasket shall be made of jute or oakum of the diameter required to support the spigot end of the pipe at the proper grade and to make the joint concentric. Joint packing shall be in one piece of sufficient length to pass around the pipe and lap at top. This gasket shall be thoroughly saturated with neat cement grout. The bell of the pipe shall be thoroughly cleaned with a wet brush, and the gasket shall be laid in the bell for the lower third of the circumference and covered with mortar. The spigot of the pipe shall be thoroughly cleaned with a wet brush, inserted in the bell, and carefully driven home. A small amount of mortar shall be inserted in the annular space for the upper two-thirds of the circumference. The gasket shall be lapped at the top of the pipe and driven home in the annular space with a caulking tool. The remainder of the annular space shall be filled completely with mortar and beveled at an angle of approximately 45 degrees with the outside of the bell. If mortar is not sufficiently stiff to prevent appreciable slump before setting, the outside of the joint thus made shall be wrapped with cheesecloth. Placing of this type of joint shall be kept at least five joints behind laying operations.

3.4.1.3 Cement-Mortar Diaper Joint for Bell-and-Spigot Pipe

The pipe shall be centered so that the annular space is uniform. The annular space shall be caulked with jute or oakum. Before caulking, the inside of the bell and the outside of the spigot shall be cleaned.

a. Diaper Bands: Diaper bands shall consist of heavy cloth fabric to hold grout in place at joints and shall be cut in lengths that extend one-eighth of the circumference of pipe above the spring line on one side of the pipe and up to the spring line on the other side of the pipe. Longitudinal edges of fabric bands shall be rolled and stitched

SECTION 33 40 00 Page 15Am #0002 around two pieces of wire. Width of fabric bands shall be such that after fabric has been securely stitched around both edges on wires, the wires will be uniformly spaced not less than 8 inches apart.

Wires shall be cut into lengths to pass around pipe with sufficient extra length for the ends to be twisted at top of pipe to hold the band securely in place; bands shall be accurately centered around lower portion of joint.

b. Grout: Grout shall be poured between band and pipe from the high side of band only, until grout rises to the top of band at the spring line of pipe, or as nearly so as possible, on the opposite side of pipe, to ensure a thorough sealing of joint around the portion of pipe covered by the band. Silt, slush, water, or polluted mortar grout forced up on the lower side shall be forced out by pouring, and removed.

c. Remainder of Joint: The remaining unfilled upper portion of the joint shall be filled with mortar and a bead formed around the outside of this upper portion of the joint with a sufficient amount of additional mortar. The diaper shall be left in place. Placing of this type of joint shall be kept at least five joints behind actual laying of pipe. No backfilling around joints shall be done until joints have been fully inspected and approved.

3.4.1.4 Cement-Mortar Tongue-and-Groove Joint

The first pipe shall be bedded carefully to the established grade line with the groove upstream. A shallow excavation shall be made underneath the pipe at the joint and filled with mortar to provide a bed for the pipe. The grooved end of the first pipe shall be thoroughly cleaned with a wet brush, and a layer of soft mortar applied to the lower half of the groove. The tongue of the second pipe shall be cleaned with a wet brush;

while in horizontal position, a layer of soft mortar shall be applied to the upper half of the tongue. The tongue end of the second pipe shall be inserted in the grooved end of the first pipe until mortar is squeezed out on interior and exterior surfaces. Sufficient mortar shall be used to fill the joint completely and to form a bead on the outside.

3.4.1.5 Cement-Mortar Diaper Joint for Tongue-and-Groove Pipe

The joint shall be of the type described for cement-mortar tongue-and-groove joint in this paragraph, except that the shallow excavation directly beneath the joint shall not be filled with mortar until after a gauze or cheesecloth band dipped in cement mortar has been wrapped around the outside of the joint. The cement-mortar bead at the joint shall be at least 1/2 inch, thick and the width of the diaper band shall be at least 8 inches. The diaper shall be left in place. Placing of this type of joint shall be kept at least five joints behind the actual laying of the pipe. Backfilling around the joints shall not be done until the joints have been fully inspected and approved.

3.4.1.6 Plastic Sealing Compound Joints for Tongue-and-Grooved Pipe

Sealing compounds shall follow the recommendation of the particular manufacturer in regard to special installation requirements. Surfaces to receive lubricants, primers, or adhesives shall be dry and clean. Sealing compounds shall be affixed to the pipe not more than 3 hours prior to installation of the pipe, and shall be protected from the sun, blowing dust, and other deleterious agents at all times. Sealing compounds shall be inspected before installation of the pipe, and any loose or improperly

SECTION 33 40 00 Page 16Am #0002 affixed sealing compound shall be removed and replaced. The pipe shall be aligned with the previously installed pipe, and the joint pulled together. If, while making the joint with mastic-type sealant, a slight protrusion of the material is not visible along the entire inner and outer circumference of the joint when the joint is pulled up, the pipe shall be removed and the joint remade. After the joint is made, all inner protrusions shall be cut off flush with the inner surface of the pipe. If non-mastic-type sealant material is used, the "Squeeze-Out" requirement above will be waived.

3.4.1.7 Flexible Watertight Joints

Gaskets and jointing materials shall be as recommended by the particular manufacturer in regard to use of lubricants, cements, adhesives, and other special installation requirements. Surfaces to receive lubricants, cements, or adhesives shall be clean and dry. Gaskets and jointing materials shall be affixed to the pipe not more than 24 hours prior to the installation of the pipe, and shall be protected from the sun, blowing dust, and other deleterious agents at all times. Gaskets and jointing materials shall be inspected before installing the pipe; any loose or improperly affixed gaskets and jointing materials shall be removed and replaced. The pipe shall be aligned with the previously installed pipe, and the joint pushed home. If, while the joint is being made the gasket becomes visibly dislocated the pipe shall be removed and the joint remade.

3.4.1.8 External Sealing Band Joint for Noncircular Pipe

Surfaces to receive sealing bands shall be dry and clean. Bands shall be installed in accordance with manufacturer's recommendations.

3.5 DRAINAGE STRUCTURES

3.5.1 Manholes and Inlets

Construction shall be of reinforced concrete, plain concrete, brick, precast reinforced concrete, precast concrete segmental blocks, prefabricated corrugated metal, or bituminous coated corrugated metal;

complete with frames and covers or gratings. Pipe studs and junction chambers of prefabricated corrugated metal manholes shall be fully bituminous-coated and paved when the connecting branch lines are so treated. Pipe connections to concrete manholes and inlets shall be made with flexible, watertight connectors.

3.5.2 Walls and Headwalls

Construction shall be as indicated.

3.6 BACKFILLING

3.6.1 Backfilling Pipe in Trenches

After the pipe has been properly bedded, selected material from excavation or borrow, at a moisture content that will facilitate compaction, shall be placed along both sides of pipe in layers not exceeding 6 inches in compacted depth. The backfill shall be brought up evenly on both sides of pipe for the full length of pipe. The fill shall be thoroughly compacted under the haunches of the pipe. Each layer shall be thoroughly compacted with mechanical tampers or rammers. This method of filling and compacting shall continue until the fill has reached an elevation equal to the

SECTION 33 40 00 Page 17Am #0002 midpoint (spring line) of concrete pipe or has reached an elevation of at least 12 inches above the top of the pipe for flexible pipe. The remainder of the trench shall be backfilled and compacted by spreading and rolling or compacted by mechanical rammers or tampers in layers not exceeding 6 inches. Tests for density shall be made as necessary to ensure conformance to the compaction requirements specified below.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .