RELEASED_AM0002_W9128F22R0011.pdf

PDF 482 KB Posted

Attached to
Gavins Point Tailrace Bulkheads Federal contract opportunity
Solicitation number
W9128F22R0011
Issued by
Department of the Army Corps of Engineers Engineering District Omaha

About this file

This document contains an amendment to a solicitation and the related federal contract opportunity. The amendment modifies the solicitation by extending the proposal due date to July 18, 2022 and revising the specifications section regarding project work windows. The opportunity is for construction of replacement tailrace bulkheads at Gavins Point Dam in Crofton, Nebraska. Services required include fabrication of six new draft tube bulkheads with rubber seals, field verification of dimensions, installation and functionality testing, removal and disposal of existing bulkheads, and provision of inspection reports and as-built drawings. The estimated cost range for construction is $1-5 million. The primary NAICS code is 237990. The performance period was increased from 480 to 660 days. The solicitation is available through SAM.gov and proposals are due to the U.S. Army Corps of Engineers Omaha District by the extended July date.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate Amendment No. 0002. See AM0002 in SF30 Block 14 Continuation Page for description of amendment changes. The date proposals are due has been extended to 18 July 2022 at 2:00pm. All other terms and conditions remain the same.

Gavins Point Bulkhead Tailrace, Gavins Point Dam, South Dakota

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-Jul-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F22R0011

X 9B. DATED (SEE ITEM 11)

24-May-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Jul-2022

CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9128F22R0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0002

06 July 2022 Solicitation No. W9128F22R0011

Date of Issue: 24 May 2022 [New] Date of Receiving Proposals: 18 July 2022

SUBJECT: Amendment No. 0002 to Request for Proposal Solicitation Package for Construction of Tailrace Bulkhead Replacement, Gavin’s Point Dam.

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

(1) Section 01 12 00 Page 4, paragraph 1.8 In the first sentence of the third subparagraph delete “April to May” and replace with “September to October”.

2. This amendment is a part of the proposal papers and its receipt shall be acknowledged. All other conditions and requirements of the specifications remain unchanged.

3. See Section 00 21 00, on how to submit electronic offers.

4. Electronic Offers will be received until 2:00 p.m., local time at place of receiving proposals, 18 July 2022, as stated in the Request For Proposal.

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901

05 July 2022

JAC/[2100]

SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

The contractor period of performance end date has increased by 180 days from 480 days to 660 days.

W9128F22R0011

(End of Summary of Changes)