This document summarizes an amendment to a solicitation and the related federal contract opportunity. The amendment modifies the specifications for a construction contract to build a stepped roller compacted concrete spillway chute structure, approach walls, and stilling basin for Pipestem Dam in North Dakota. Only galvanized steel sheets will be allowed for contraction joints between concrete sections. Electronic bids are due by 2:00pm on June 13th for the two-step sealed bid procurement, with an estimated construction value between $100 million and $250 million. Under the two-step process, offerors must first submit technical proposals for evaluation, with only acceptable proposals advancing to the second step of priced bid submission. The U.S. Army Corps of Engineers district office in Omaha, Nebraska issued this amendment and opportunity for dam spillway modification work.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

6 Jun 22: AM0003: Jessica Jackson, Contracting Officer, 402.995.2052

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Jun-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F22B0002

X 9B. DATED (SEE ITEM 11)

02-May-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Jun-2022

CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9128F22B0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AM0003 DESCRIPTIVE CHANGES

06 June 2022 Solicitation No. W9128F22B0003

Date of Issue: 02 May 2022 Date of Opening: 13 June 2022

SUBJECT: Amendment No. 0003 to Specifications and Drawings for Construction of Pipestem Spillway Modification Project, Pipestem Dam, ND.

TO: Prospective Bidders and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

(1) Section 03 37 23 Page 21, paragraph 2.2.6

Replace Paragraph:

”Material for vertical contraction joints between the RCC blocks/monoliths shall consist of either a heavy-duty woven geotextile sheet or a galvanized steel ASTM A653/A653M sheet metal, minimum 14 gauge thickness, for the embedded plates. The woven geotextile shall be flexible. Rigid PVC or plastic sheet contraction joint materials may be substituted; however, the material proposed will be evaluated by the Contracting Officer for adequacy during construction of the test section.”

With:

“Material for vertical contraction joints between the RCC blocks/monoliths shall consist of a galvanized steel ASTM A653/A653M sheet metal, minimum 14 gauge thickness, for the embedded plates. Rigid HDPE or plastic sheet contraction joint materials may be substituted; however, the material proposed will be evaluated by the Contracting Officer for adequacy during construction of the test section.”

2. This amendment is a part of the bidding papers and its receipt shall be acknowledged. All other conditions and requirements of the specifications remain unchanged.

a. See Section 00 21 00, paragraph: Instructions to Bidders, on how to submit electronic bids.

W9128F22B0002

3. Electronic Step 1 technical proposals will be received until 2:00 p.m., local time at place of bid opening, 13 June 2022.

Attachments:

U.S. Army Engineer District, Omaha Corps of Engineers 1616 Capitol Avenue Omaha, Nebraska 68102-4901 06 June 2022

JAC/[2100]

(End of Summary of Changes)

File details come from the government source that posted it. Updated .