Pipestem Dam Pre Bid Walk Sign-In.pdf
PDF 96 KB Posted
- Attached to
- STEP-ONE IFB - Pipestem Dam Spillway Modification Project, Pipestem Creek, Jamestown, ND.
- Solicitation number
- W9128F22B0002
About this file
This document provides details for a two-step sealed bid solicitation for the Pipestem Dam Spillway Modification Project. The U.S. Army Corps of Engineers Omaha District is seeking a firm fixed-price contract between $100-250 million to construct a stepped roller compacted concrete spillway chute with an integrated three-stage labyrinth crest control structure, approach walls, and stilling basin. The scope also includes lowering the upstream and approach channels. Interested offerors must attend a pre-bid meeting on May 10th and have an active SAM registration. The two-step process will begin with an evaluation of technical proposals, with only technically acceptable offerors invited to submit priced bids in step two along with the final specifications. Payment and performance bonds will be required at time of award.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
10 May 2022 at 10:00 am
Name Company Position Email Phone Number Darin Larson USACE Resident Engineer darin.w.larson@usace.army.mil 701-531-0217 Bob Worden USACE Lead Engineer robert.j.worden@usace.army.mil 402-995-2250 Chris Fasserro USACE Project Manager christopher.a.fassero@usace.army.mil 402-889-8183 Duston Marlow Rizzo International Geologist duston.marlow@rizzointl.com 916-757-7278 Tim Howe Barnard Const Superintendent tim.howe@barnard-inc.com 813-731-4744 Mike Killian Barnard Const Lead Estimator Mike.Killian@barnard-inc.com 406-581-7342 Cody Gordanier Shimmick Construction Pursuit Manager cody.gordanier@shimmick.com 303-547-8122 Mike DeMarte Shimmick Construction Director of Estimating mike.demarte@shimmick.com 303-513-7290 Chad Erickson Strata Corp GM Concrete Operations chad.erickson@stratacorporation.com 701-775-4205 Sarah Griesbach Jensen Brothers Construction, Inc. Office Manager sarah@jensenbrothersconstruction.com 701-866-6363 Taylor Terpstra Park Construction Company Estimator tterpstra@parkconstructionco.com 701-690-0559 Michael Nottestad Park Construction Company VP mnottestad@parkconstructionco.Com 701-741-3092 Marc Montplaisir Rain for Rent Sales mmontplaisir@rainforrent.com 701-509-2583 Jim Ouldhouse Martin Construction Inc Sr Project Manager jouldhouse@martinnd.com 701-456-2546 Ben Herden Ames Construction Area Project Manager benherden@amesco.com 612-741-0086 Nicholas Glass Ames Construction Project Manager nicholasglass@amesco.com 612-360-8222 Josh Skluzacek American Engineering Testing, Inc. Senior Engineer Business Development jskluzacek@teamaet.com 701-590-3294
Pipestem Dam Pre-Bid Walk - Met at Project Office mailto:darin.w.larson@usace.army.mil mailto:robert.j.worden@usace.army.mil mailto:christopher.a.fassero@usace.army.mil mailto:duston.marlow@rizzointl.com mailto:tim.howe@barnard-inc.com mailto:Mike.Killian@barnard-inc.com mailto:cody.gordanier@shimmick.com mailto:mike.demarte@shimmick.com mailto:chad.erickson@stratacorporation.com mailto:sarah@jensenbrothersconstruction.com mailto:tterpstra@parkconstructionco.com mailto:mnottestad@parkconstructionco.Com mailto:mmontplaisir@rainforrent.com mailto:jouldhouse@martinnd.com mailto:benherden@amesco.com mailto:nicholasglass@amesco.com mailto:jskluzacek@teamaet.com
Sheet1
File details come from the government source that posted it. Updated .