This abstract of offers is for a construction project to complete flood risk management work along the Middle Logan Creek in Randolph, Nebraska. The project requires furnishing all plant, labor, materials, and equipment to perform work including earthwork and grading for a realigned and widened creek channel, bridge replacements, drainage structures, erosion controls, fencing and road work. Estimated costs range from $5-10 million. Six bids were received by the August 14th deadline ranging from $5.7-11.9 million. The Army Corps of Engineers will award a contract from this solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Middle Logan Creek Flood Risk Management Project, newest first.
File Type Posted
Middle Logan Creek ProjNet Question and Answers.pdf PDF
Am0002.pdf PDF
AM0002 Drawings.pdf PDF
SIte Visit Vendor List 7.23.20.pdf PDF
SIte Visit7.23.20.pdf PDF
Am0001_Drawings.pdf PDF
Am0001.pdf PDF
Randolph Drawings 2 of 3.pdf PDF
W9128F20B0027 Randolph Specs.pdf PDF
Randolph Drawings 3 of 3.pdf PDF
Randolph Drawings 1 of 3.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. DATE ISSUED 3. DATE OPENED

I CERTIFY THAT I HAVE OPENED, READ AND

AND RECORDED ON THIS ABSTRACT

ALL OFFERS RECEIVED IN RESPONSE DATE SIGNED

X C. REASONABLE CONTRACT

7A. 7B. 7C. 7D. 7E. 7F. 7E. F. E. F.

ITEM # DESCRIPTION EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Basic Items

0001 Entire work complete for Bridge Street Bridge, exclusive of the Steel H-piles and associated work (Items 0007 thru 0009).

1 JOB 1,142,000.00$ 1,142,000.00$ 1,555,875.00$ 1,555,875.00$ 1,499,900.00$ 1,499,900.00$

0002 Entire work complete for Sholes Road Bridge exclusive of the Steel H-piles and associated work (Items 0007 thru 0009).

JOB

831,000.00$ 831,000.00$ 1,276,772.00$ 1,276,772.00$ 1,352,500.00$ 1,352,500.00$

0003 All plant, material, and labor required for Earth Excavation. 120,000 CY 3.61$ 433,200.00$ 12.50$ 1,500,000.00$ 3.20$ 384,000.00$

0004 All plant, material, and labor required for on project site placement of Compacted Earthen Fill.

24,000 CY 3.50$ 84,000.00$ 4.00$ 96,000.00$ 4.00$ 96,000.00$

0005 All plant, material, and labor required for off project site placement of surplus Earthen Spoil.

96,000 CY 5.18$ 497,280.00$ 3.50$ 336,000.00$ 5.10$ 489,600.00$

0006 All plant, material, and labor required for Riprap. 11,750 TON 97.84$ 1,149,620.00$ 88.00$ 1,034,000.00$ 49.00$ 575,750.00$

0007 All plant, material, and labor required for furnishing and delivering Steel H-piles

5,690 LF 49.21$ 280,004.90$ 32.85$ 186,916.50$ 30.20$ 171,838.00$

0008 All plant, materials, and labor required for Driving Steel H-Piles 5,690 LF 15.78$ 89,788.20$ 43.90$ 249,791.00$ 14.60$ 83,074.00$

0009 All plant, materials, and labor requrired for Driving Test for Steel H-piles 4 EA 8,700.00$ 34,800.00$ 12,000.00$ 48,000.00$ 41,600.00$ 166,400.00$

0010 All Remaining Work 1 JOB 1,087,200.00$ 1,087,200.00$ 3,408,649.00$ 3,408,649.00$ 3,679,000.00$ 3,679,000.00$

Total 5,628,893.10$ 9,692,003.50$ 8,498,062.00$

RANDOLPH, NE

MIDDLE LOGAN CREEK

(Without Profit)

6. NUMBER OF AMENDMENTS ISSUED

Bid Bond & 20% B. BID SECURITY (Type & Amount)

Bid Bond & 20%/$3 million

C. AMENDMENTS ACKNOWLEDGED

C. AMENDMENTS ACKNOWLEDGED

Lincoln, NE 68501 Harvey, SD 58341 B. BID SECURITY (Type & Amount)B. REASONABLE CONTRACT

(Including Profit)

A. OFFEROR A. OFFEROR

PO Box 81036 PO Box 213

A. HIRED LABOR

GOVERNMENT ESTIMATE CCEI HSG Park Joint Venture, LLC

NO. 1 NO. 2

ABSTRACT OF OFFERS - CONSTRUCTION

1. SOLICITATION NUMBER

W9128F20B0027

4. ISSUING OFFICE

8. GOVERNMENT ESTIMATE

(Check A, B or C AND COMPLETE D, E AND F)

5. PROJECT TITLE 9. OFFERS

TO THIS SOLICITATION

SIGNATURE

NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

OMAHA, NE 68102-1618

1616 CAPITOL AVENUE

CONTRACTING DIVISION (CENWO-CT)

US ARMY CORPS OF ENGINEERS

l PAGES

14 August 2020

7A. 7B. 7C. 7D. 7E. F. E. F. E. F. E. F.

ITEM # DESCRIPTION EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMO UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Basic Item

0001 Entire work complete for Bridge Street Bridge, exclusive of the Steel H-piles and associated work (Items 0007 thru 0009).

1 JOB 1,609,650.00$ 1,609,650.00$ 1,228,427.00$ 1,228,427.00$ 1,980,600.00$ 1,980,600.00$ 1,600,000.00$ 1,600,000.00$

Entire work complete for Sholes Road Bridge exclusive of the Steel H-piles and associated work (Items 0007 thru 0009). 1 JOB $ 1,282,610.00 1,282,610.00$ 914,974.00$ 914,974.00$ $ 1,826,700.00 1,826,700.00$ 1,400,000.00$ 1,400,000.00$

0003 All plant, material, and labor required for Earth Excavation. 120,000 CY $ 2.30 276,000.00$ 2.90$ 348,000.00$ $ 6.40 768,000.00$ 7.00$ 840,000.00$

0004 All plant, material, and labor required for on project site placement of Compacted Earthen Fill.

24,000 CY 4.85$ 116,400.00$ 4.80$ 115,200.00$ 4.20$ 100,800.00$ 9.00$ 216,000.00$

0005 All plant, material, and labor required for off project site placement of surplus Earthen Spoil.

96,000 CY 7.15$ 686,400.00$ 3.60$ 345,600.00$ 2.90$ 278,400.00$ 5.50$ 528,000.00$

0006 All plant, material, and labor required for Riprap. 11,750 TON 48.70$ 572,225.00$ 97.75$ 1,148,562.50$ 113.00$ 1,327,750.00$ 84.00$ 987,000.00$

0007 All plant, material, and labor required for furnishing and delivering Steel H-piles

5,690 LF 44.97$ 255,879.30$ 34.75$ 197,727.50$ 33.00$ 187,770.00$ 35.00$ 199,150.00$

0008 All plant, materials, and labor required for Driving Steel H-Piles 5,690 LF 12.26$ 69,759.40$ 24.00$ 136,560.00$ 33.00$ 187,770.00$ 44.00$ 250,360.00$

0009 All plant, materials, and labor requrired for Driving Test for Steel 4 EA 9,709.00$ 38,836.00$ 19,009.00$ 76,036.00$ 12,100.00$ 48,400.00$ 14,000.00$ 56,000.00$

0010 All Remaining Work 1 JOB 2,897,923.00$ 2,897,923.00$ 1,266,376.00$ 1,266,376.00$ 3,925,486.00$ 3,925,486.00$ 2,500,000.00$ 2,500,000.00$

Total 7,805,682.70$ 5,777,463.00$ 10,631,676.00$ 8,576,510.00$

C. AMENDMENTS ACKNOWLEDGED

PO Box 610 Nebraska City, NE 68410

B. BID SECURITY (Type & Amount) Bid Bond & 20%

B. BID SECURITY (Type & Amount)

BID BOND & 20%

C. AMENDMENTS ACKNOWLEDGED

MIDDLE LOGAN CREEK

3. CONTRACT ITEMS

RANDOLPH, NE

4. OFFERS (Continued)

NO. 3

A. OFFEROR

ABSTRACT OF OFFERS -

CONTINUATION SHEET

SERVICES

2. PROJECT TITLE

INSTRUCTIONS: Attach this form to Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation l PAGES

1. SOLICITATION NUMBER

W9128F20B0027 sheet will accommodate 24 contract items to conform the number of items which can be entered . Use additional forms and continuation sheets as needed.

NO. 6

A. OFFEROR -

NO. 4

Shinn Kellogg, LLC Midwest Construction Company

A. OFFEROR

Centennial, CO 80112 Watlhill, NE 68067

7307 160 St.

NO. 5

A. OFFEROR

Albia, IA 52531

ME Collins Contracting Co., INC>Iron Mike Construction, LLC PO Box 83 Wahoo, NE 68066

B. BID SECURITY (Type & Amount) Bid Bond & 20%

C. AMENDMENTS ACKNOWLEDGED

Bid Bond & 20%

C. AMENDMENTS ACKNOWLEDGED

B. BID SECURITY (Type & Amount)

7A. 7B. 7C. 7D. 7E. F. E. F. E. F. E. F.

ITEM # DESCRIPTION EST. QTY UNIT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT UNIT PRICE ESTIMATED AMOUNT

Basic Item

0001 Entire work complete for Bridge Street Bridge, exclusive of the Steel H-piles and associated work (Items 0007 thru 0009).

1 JOB

1,622,000.00$ 1,622,000.00$ 2,264,705.88$ 2,264,705.88$

Entire work complete for Sholes Road Bridge exclusive of the Steel H-piles and associated work (Items 0007 thru 0009).

JOB $ 1,292,650.00 1,292,650.00$ 1,895,882.35$ 1,895,882.35$

0003 All plant, material, and labor required for Earth Excavation. 120,000 CY $ 3.00 360,000.00$ 10.35$ 1,242,000.00$

0004 All plant, material, and labor required for on project site placement of Compacted Earthen Fill.

24,000 CY

2.55$ 61,200.00$ 15.53$ 372,720.00$

0005 All plant, material, and labor required for off project site placement of surplus Earthen Spoil.

96,000 CY

2.55$ 244,800.00$ 12.94$ 1,242,240.00$

0006 All plant, material, and labor required for Riprap. 11,750 TON 93.00$ 1,092,750.00$ 97.06$ 1,140,455.00$

0007 All plant, material, and labor required for furnishing and delivering Steel H-piles 5,690 LF 45.50$ 258,895.00$ 45.29$ 257,700.10$

0008 All plant, materials, and labor required for Driving Steel H-Piles 5,690 LF 12.50$ 71,125.00$ 45.29$ 257,700.10$

0009 All plant, materials, and labor requrired for Driving Test for Steel H-piles 4 EA 10,000.00$ 40,000.00$ 14,235.29$ 56,941.16$

0010 All Remaining Work 1 JOB 2,451,185.74$ 2,451,185.74$ 3,235,294.12$ 3,235,294.12$

Total 7,494,605.74$ 11,965,638.71$ -$ -$

3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED 2 2

B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount) B. BID SECURITY (Type & Amount) Bid Bond & 20% Bid Bond & 20%

RANDOLPH, NE 648 A. Road 5100 Hwy PP Dodge, NE 68633 Poplar Bluff, MO 63901

A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR -

MIDDLE LOGAN CREEK Pruss Excavation Co. Young General Contracting, Inc

CONTINUATION SHEET sheet will accommodate 24 contract items to conform the number of items which can be entered . Use additional forms and continuation sheets as needed.

2. PROJECT TITLE 4. OFFERS (Continued)

NO. 3 NO. 4 NO. 5 NO. 6

ABSTRACT OF OFFERS -

1. SOLICITATION NUMBER PAGE 2 OF 3

W9128F20B0027 l PAGES SERVICES INSTRUCTIONS: Attach this form to Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation

PAGE 1
PAGE 2
PAGE 3
2020-08-14T10:00:07-0500
David Neal, Contracting Officer

File details come from the government source that posted it. Updated .