This document contains a cost spreadsheet and related solicitation for an 8(a) Indefinite Delivery, Indefinite Quantity (IDIQ) Single Award Task Order Contract (SATOC) for Rapid Response/Immediate Response (RR/IR), Environmental Remediation (ERS) Services and Other Mission Related Support Services. The cost spreadsheet outlines annual estimated costs for base years 1 through 3 and option years 4 through 5, with total estimated annual costs of $110,000. The solicitation is for a $35 million IDIQ contract to provide emergency, immediate, or rapid response environmental remediation services at contaminated sites within the United States for the U.S. Army Corps of Engineers and its customers. The successful offeror will be required to maintain regulatory compliance, restore property from environmental spills or releases, mitigate unstable situations, and prevent or minimize future releases to protect human life, public health, and the environment.

Cost Spreadsheet

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RR5 8(a) Cost Spreadsheet

Attachment 1 - Cost Spreadsheet - W9128F19R0016 - Rapid Response 5 IDIQ SATOC, 8(a)
Reference Section L, Paragraph 5.3.4
YEAR 1 (BASE YEAR 1)
A. Home Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Operations Manager$ - 0hrs150$ - 0
Program Chemist$ - 0hrs50$ - 0
Engineer$ - 0hrs55$ - 0
Senior Contracts Manager$ - 0hrs120$ - 0
Procurement Specialist$ - 0hrs150$ - 0
Senior UXO Supervisor$ - 0hrs35$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Home Office Overhead Rate (Base Period):0.00%
Total Home Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
B. Field Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Site Safety and Health Officer$ - 0hrs200$ - 0
Regulatory Specialist$ - 0hrs125$ - 0
Contractor Quality Control Supervisor$ - 0hrs200$ - 0
Site Superintendent / Site Manager$ - 0hrs150$ - 0
Professional Industrial Hygienist$ - 0hrs125$ - 0
Project Manager$ - 0hrs125$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Field Office Overhead Rate (Base Period):0.00%
Total Field Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
C. Other Direct CostsUnitsQuantitySubtotal
Materials, supplies, equipment, and other ODCs (plugged number)each10,000$ 10,000.00
Markup Rate (If applicable) (Base Period - Year 1):0.00%
Markup Amount (Base Period - Year 1):$ - 0
Subtotal:$ 10,000.00
Subcontract Effort (plugged number)each100,000$ 100,000.00
Markup Rate (If applicable) (Base Period - Year 1):0.00%
Markup Amount (Base Period):$ - 0
Subtotal:$ 100,000.00
Total (A+B+C)
Total Estimated Cost$ 110,000.00
Fixed Fee
Fixed Fee Rate:0.00%
Fixed Fee Amount:$ - 0
Total Term Cost
Year 1 Total :$ 110,000.00
YEAR 2 (BASE YEAR 2)
A. Home Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Operations Manager$ - 0hrs150$ - 0
Program Chemist$ - 0hrs50$ - 0
Engineer$ - 0hrs55$ - 0
Senior Contracts Manager$ - 0hrs120$ - 0
Procurement Specialist$ - 0hrs150$ - 0
Senior UXO Supervisor$ - 0hrs35$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Home Office Overhead Rate (Base Period):0.00%
Total Home Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
B. Field Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Site Safety and Health Officer$ - 0hrs200$ - 0
Regulatory Specialist$ - 0hrs125$ - 0
Contractor Quality Control Supervisor$ - 0hrs200$ - 0
Site Superintendent / Site Manager$ - 0hrs150$ - 0
Professional Industrial Hygienist$ - 0hrs125$ - 0
Project Manager$ - 0hrs125$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Field Office Overhead Rate (Base Period):0.00%
Total Field Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
C. Other Direct CostsUnitsQuantitySubtotal
Materials, supplies, equipment, and other ODCs (plugged number)each10,000$ 10,000.00
Markup Rate (If applicable) (Base Period - Year 2):0.00%
Markup Amount (Base Period - Year 2):$ - 0
Subtotal:$ 10,000.00
Subcontract Effort (plugged number)each100,000$ 100,000.00
Markup Rate (If applicable) (Base Period - Year 2):0.00%
Markup Amount (Base Period):$ - 0
Subtotal:$ 100,000.00
Total (A+B+C)
Total Estimated Cost$ 110,000.00
Fixed Fee
Fixed Fee Rate:0.00%
Fixed Fee Amount:$ - 0
Total Term Cost
Year 2 Total :$ 110,000.00
YEAR 3 (BASE YEAR 3)
A. Home Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Operations Manager$ - 0hrs150$ - 0
Program Chemist$ - 0hrs50$ - 0
Engineer$ - 0hrs55$ - 0
Senior Contracts Manager$ - 0hrs120$ - 0
Procurement Specialist$ - 0hrs150$ - 0
Senior UXO Supervisor$ - 0hrs35$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Home Office Overhead Rate (Base Period):0.00%
Total Home Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
B. Field Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Site Safety and Health Officer$ - 0hrs200$ - 0
Regulatory Specialist$ - 0hrs125$ - 0
Contractor Quality Control Supervisor$ - 0hrs200$ - 0
Site Superintendent / Site Manager$ - 0hrs150$ - 0
Professional Industrial Hygienist$ - 0hrs125$ - 0
Project Manager$ - 0hrs125$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Field Office Overhead Rate (Base Period):0.00%
Total Field Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
C. Other Direct CostsUnitsQuantitySubtotal
Materials, supplies, equipment, and other ODCs (plugged number)each10,000$ 10,000.00
Markup Rate (If applicable) (Base Period - Year 3):0.00%
Markup Amount (Base Period - Year 3):$ - 0
Subtotal:$ 10,000.00
Subcontract Effort (plugged number)each100,000$ 100,000.00
Markup Rate (If applicable) (Base Period - Year 3):0.00%
Markup Amount (Base Period):$ - 0
Subtotal:$ 100,000.00
Total (A+B+C)
Total Estimated Cost$ 110,000.00
Fixed Fee
Fixed Fee Rate:0.00%
Fixed Fee Amount:$ - 0
Total Term Cost
Year 3 Total :$ 110,000.00
YEAR 4 (Option Year 1)
A. Home Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Operations Manager$ - 0hrs150$ - 0
Program Chemist$ - 0hrs50$ - 0
Engineer$ - 0hrs55$ - 0
Senior Contracts Manager$ - 0hrs120$ - 0
Procurement Specialist$ - 0hrs150$ - 0
Senior UXO Supervisor$ - 0hrs35$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Home Office Overhead Rate (Base Period):0.00%
Total Home Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
B. Field Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Site Safety and Health Officer$ - 0hrs200$ - 0
Regulatory Specialist$ - 0hrs125$ - 0
Contractor Quality Control Supervisor$ - 0hrs200$ - 0
Site Superintendent / Site Manager$ - 0hrs150$ - 0
Professional Industrial Hygienist$ - 0hrs125$ - 0
Project Manager$ - 0hrs125$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Field Office Overhead Rate (Base Period):0.00%
Total Field Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
C. Other Direct CostsUnitsQuantitySubtotal
Materials, supplies, equipment, and other ODCs (plugged number)each10,000$ 10,000.00
Markup Rate (If applicable) (Base Period - Year 4):0.00%
Markup Amount (Base Period - Year 4):$ - 0
Subtotal:$ 10,000.00
Subcontract Effort (plugged number)each100,000$ 100,000.00
Markup Rate (If applicable) (Base Period - Year 4):0.00%
Markup Amount (Base Period):$ - 0
Subtotal:$ 100,000.00
Total (A+B+C)
Total Estimated Cost$ 110,000.00
Fixed Fee
Fixed Fee Rate:0.00%
Fixed Fee Amount:$ - 0
Total Term Cost
Year 4 Total :$ 110,000.00
YEAR 5 (Option Year 2)
A. Home Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Operations Manager$ - 0hrs150$ - 0
Program Chemist$ - 0hrs50$ - 0
Engineer$ - 0hrs55$ - 0
Senior Contracts Manager$ - 0hrs120$ - 0
Procurement Specialist$ - 0hrs150$ - 0
Senior UXO Supervisor$ - 0hrs35$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Home Office Overhead Rate (Base Period):0.00%
Total Home Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
B. Field Office PersonnelUnburdened Binding Cap Rate (Hourly)UnitsQuantitySubtotal
Site Safety and Health Officer$ - 0hrs200$ - 0
Regulatory Specialist$ - 0hrs125$ - 0
Contractor Quality Control Supervisor$ - 0hrs200$ - 0
Site Superintendent / Site Manager$ - 0hrs150$ - 0
Professional Industrial Hygienist$ - 0hrs125$ - 0
Project Manager$ - 0hrs125$ - 0
Subtotal:$ - 0
Applied Fringe Rate:0.00%
Total Fringes:$ - 0
Applied Field Office Overhead Rate (Base Period):0.00%
Total Field Office Overhead Amount (Base Period):$ - 0
Applied G&A Rate (Base Period):0.00%
Total G&A Amount (Base Period):$ - 0
Subtotal:$ - 0
C. Other Direct CostsUnitsQuantitySubtotal
Materials, supplies, equipment, and other ODCs (plugged number)each10,000$ 10,000.00
Markup Rate (If applicable) (Base Period - Year 5):0.00%
Markup Amount (Base Period - Year 5):$ - 0
Subtotal:$ 10,000.00
Subcontract Effort (plugged number)each100,000$ 100,000.00
Markup Rate (If applicable) (Base Period - Year 5):0.00%
Markup Amount (Base Period):$ - 0
Subtotal:$ 100,000.00
Total (A+B+C)
Total Estimated Cost$ 110,000.00
Fixed Fee
Fixed Fee Rate:0.00%
Fixed Fee Amount:$ - 0
Total Term Cost
Year 5 Total :$ 110,000.00