This document contains a cost spreadsheet and related solicitation for an 8(a) Indefinite Delivery, Indefinite Quantity (IDIQ) Single Award Task Order Contract (SATOC) for Rapid Response/Immediate Response (RR/IR), Environmental Remediation (ERS) Services and Other Mission Related Support Services under NAICS Code 562910. The cost spreadsheet outlines estimated costs for personnel, other direct costs, subcontracting efforts, and total estimated costs for the base years and option years of the contract. The solicitation is from the Department of the Army Corps of Engineers Engineering District Omaha for $35 million in ERS projects to maintain regulatory compliance, restore contaminated property, mitigate unstable situations, and prevent future releases to protect human life, public health, and the environment. The period of performance is one base year with four optional one-year extensions.
Cost Spreadsheet
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Cost_Spreadsheet_For_RR5_8(a)_-_W9128F19R0016_-_3_April_19.xlsx | XLSX spreadsheet | |
| Am_0004_-_W9128F19R0016_-_Rapid_Response_5_-_8(a).pdf | ||
| Am_0003_-__RFP_W9128F19R0016.pdf | ||
| RR5_8a_Table_1_Excel_File_-_W9128F19R0016_-_22_March_2019.xlsx | XLSX spreadsheet | |
| Am_0002_-__RFP_W9128F19R0016.pdf | ||
| Am_0001_-_RFP_W9128F19R0016.pdf | ||
| Cost_Spreadsheet_For_RR5_8(a)_-_W9128F19R0016.xlsx | XLSX spreadsheet | |
| RR5_8a_Table_1_Excel_File_-_W9128F19R0016.xlsx | XLSX spreadsheet | |
| RFP_W9128F19R0016_-_Rapid_Response_5_-_8(a)_Set-Aside.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RR5 8(a) Cost Spreadsheet
| Attachment 1 - Cost Spreadsheet - W9128F19R0016 - Rapid Response 5 IDIQ SATOC, 8(a) | ||||
| Reference Section L, Paragraph 5.3.4 | ||||
| YEAR 1 (BASE YEAR 1) | ||||
| A. Home Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Operations Manager | $ - 0 | hrs | 150 | $ - 0 |
| Program Chemist | $ - 0 | hrs | 50 | $ - 0 |
| Engineer | $ - 0 | hrs | 55 | $ - 0 |
| Senior Contracts Manager | $ - 0 | hrs | 120 | $ - 0 |
| Procurement Specialist | $ - 0 | hrs | 150 | $ - 0 |
| Senior UXO Supervisor | $ - 0 | hrs | 35 | $ - 0 |
| Subtotal: | $ - 0 | |||
| B. Field Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Site Safety and Health Officer | $ - 0 | hrs | 200 | $ - 0 |
| Regulatory Specialist | hrs | 125 | $ - 0 | |
| Contractor Quality Control Supervisor | hrs | 200 | $ - 0 | |
| Site Superintendent / Site Manager | hrs | 150 | $ - 0 | |
| Professional Industrial Hygienist | $ - 0 | hrs | 125 | $ - 0 |
| Project Manager | $ - 0 | hrs | 125 | $ - 0 |
| Subtotal: | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | each | 10,000 | $ 10,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 1): | 0.00% | |||
| Markup Amount (Base Period - Year 1): | $ - 0 | |||
| Subtotal: | $ 10,000.00 | |||
| Subcontract Effort (plugged number) | each | 100,000 | $ 100,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 1): | 0.00% | |||
| Markup Amount (Base Period): | $ - 0 | |||
| Subtotal: | $ 100,000.00 | |||
| Total (A+B+C) | ||||
| Total Estimated Cost | $ 110,000.00 | |||
| Fixed Fee | ||||
| Fixed Fee Rate: | 0.00% | |||
| Fixed Fee Amount: | $ - 0 | |||
| Total Term Cost | ||||
| Year 1 Total : | $ 110,000.00 |
| YEAR 2 (BASE YEAR 2) | ||||
| A. Home Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Operations Manager | $ - 0 | hrs | 150 | $ - 0 |
| Program Chemist | $ - 0 | hrs | 50 | $ - 0 |
| Engineer | $ - 0 | hrs | 55 | $ - 0 |
| Senior Contracts Manager | $ - 0 | hrs | 120 | $ - 0 |
| Procurement Specialist | $ - 0 | hrs | 150 | $ - 0 |
| Senior UXO Supervisor | $ - 0 | hrs | 35 | $ - 0 |
| Subtotal: | $ - 0 | |||
| B. Field Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Site Safety and Health Officer | $ - 0 | hrs | 200 | $ - 0 |
| Regulatory Specialist | $ - 0 | hrs | 125 | $ - 0 |
| Contractor Quality Control Supervisor | $ - 0 | hrs | 200 | $ - 0 |
| Site Superintendent / Site Manager | $ - 0 | hrs | 150 | $ - 0 |
| Professional Industrial Hygienist | $ - 0 | hrs | 125 | $ - 0 |
| Project Manager | $ - 0 | hrs | 125 | $ - 0 |
| Subtotal: | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | each | 10,000 | $ 10,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 2): | 0.00% | |||
| Markup Amount (Base Period - Year 2): | $ - 0 | |||
| Subtotal: | $ 10,000.00 | |||
| Subcontract Effort (plugged number) | each | 100,000 | $ 100,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 2): | 0.00% | |||
| Markup Amount (Base Period): | $ - 0 | |||
| Subtotal: | $ 100,000.00 | |||
| Total (A+B+C) | ||||
| Total Estimated Cost | $ 110,000.00 | |||
| Fixed Fee | ||||
| Fixed Fee Rate: | 0.00% | |||
| Fixed Fee Amount: | $ - 0 | |||
| Total Term Cost | ||||
| Year 2 Total : | $ 110,000.00 |
| YEAR 3 (BASE YEAR 3) | ||||
| A. Home Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Operations Manager | $ - 0 | hrs | 150 | $ - 0 |
| Program Chemist | $ - 0 | hrs | 50 | $ - 0 |
| Engineer | $ - 0 | hrs | 55 | $ - 0 |
| Senior Contracts Manager | $ - 0 | hrs | 120 | $ - 0 |
| Procurement Specialist | $ - 0 | hrs | 150 | $ - 0 |
| Senior UXO Supervisor | $ - 0 | hrs | 35 | $ - 0 |
| Subtotal: | $ - 0 | |||
| B. Field Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Site Safety and Health Officer | $ - 0 | hrs | 200 | $ - 0 |
| Regulatory Specialist | $ - 0 | hrs | 125 | $ - 0 |
| Contractor Quality Control Supervisor | $ - 0 | hrs | 200 | $ - 0 |
| Site Superintendent / Site Manager | $ - 0 | hrs | 150 | $ - 0 |
| Professional Industrial Hygienist | $ - 0 | hrs | 125 | $ - 0 |
| Project Manager | $ - 0 | hrs | 125 | $ - 0 |
| Subtotal: | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | each | 10,000 | $ 10,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 3): | 0.00% | |||
| Markup Amount (Base Period - Year 3): | $ - 0 | |||
| Subtotal: | $ 10,000.00 | |||
| Subcontract Effort (plugged number) | each | 100,000 | $ 100,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 3): | 0.00% | |||
| Markup Amount (Base Period): | $ - 0 | |||
| Subtotal: | $ 100,000.00 | |||
| Total (A+B+C) | ||||
| Total Estimated Cost | $ 110,000.00 | |||
| Fixed Fee | ||||
| Fixed Fee Rate: | 0.00% | |||
| Fixed Fee Amount: | $ - 0 | |||
| Total Term Cost | ||||
| Year 3 Total : | $ 110,000.00 |
| YEAR 4 (Option Year 1) | ||||
| A. Home Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Operations Manager | $ - 0 | hrs | 150 | $ - 0 |
| Program Chemist | $ - 0 | hrs | 50 | $ - 0 |
| Engineer | $ - 0 | hrs | 55 | $ - 0 |
| Senior Contracts Manager | $ - 0 | hrs | 120 | $ - 0 |
| Procurement Specialist | $ - 0 | hrs | 150 | $ - 0 |
| Senior UXO Supervisor | $ - 0 | hrs | 35 | $ - 0 |
| Subtotal: | $ - 0 | |||
| B. Field Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Site Safety and Health Officer | $ - 0 | hrs | 200 | $ - 0 |
| Regulatory Specialist | $ - 0 | hrs | 125 | $ - 0 |
| Contractor Quality Control Supervisor | $ - 0 | hrs | 200 | $ - 0 |
| Site Superintendent / Site Manager | $ - 0 | hrs | 150 | $ - 0 |
| Professional Industrial Hygienist | $ - 0 | hrs | 125 | $ - 0 |
| Project Manager | $ - 0 | hrs | 125 | $ - 0 |
| Subtotal: | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | each | 10,000 | $ 10,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 4): | 0.00% | |||
| Markup Amount (Base Period - Year 4): | $ - 0 | |||
| Subtotal: | $ 10,000.00 | |||
| Subcontract Effort (plugged number) | each | 100,000 | $ 100,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 4): | 0.00% | |||
| Markup Amount (Base Period): | $ - 0 | |||
| Subtotal: | $ 100,000.00 | |||
| Total (A+B+C) | ||||
| Total Estimated Cost | $ 110,000.00 | |||
| Fixed Fee | ||||
| Fixed Fee Rate: | 0.00% | |||
| Fixed Fee Amount: | $ - 0 | |||
| Total Term Cost | ||||
| Year 4 Total : | $ 110,000.00 |
| YEAR 5 (Option Year 2) | ||||
| A. Home Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Operations Manager | $ - 0 | hrs | 150 | $ - 0 |
| Program Chemist | $ - 0 | hrs | 50 | $ - 0 |
| Engineer | $ - 0 | hrs | 55 | $ - 0 |
| Senior Contracts Manager | $ - 0 | hrs | 120 | $ - 0 |
| Procurement Specialist | $ - 0 | hrs | 150 | $ - 0 |
| Senior UXO Supervisor | $ - 0 | hrs | 35 | $ - 0 |
| Subtotal: | $ - 0 | |||
| B. Field Office Personnel | Burdened Binding Cap Rate (Hourly) | Units | Quantity | Subtotal |
| Site Safety and Health Officer | $ - 0 | hrs | 200 | $ - 0 |
| Regulatory Specialist | $ - 0 | hrs | 125 | $ - 0 |
| Contractor Quality Control Supervisor | $ - 0 | hrs | 200 | $ - 0 |
| Site Superintendent / Site Manager | $ - 0 | hrs | 150 | $ - 0 |
| Professional Industrial Hygienist | $ - 0 | hrs | 125 | $ - 0 |
| Project Manager | $ - 0 | hrs | 125 | $ - 0 |
| Subtotal: | $ - 0 | |||
| C. Other Direct Costs | Units | Quantity | Subtotal | |
| Materials, supplies, equipment, and other ODCs (plugged number) | each | 10,000 | $ 10,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 5): | 0.00% | |||
| Markup Amount (Base Period - Year 5): | $ - 0 | |||
| Subtotal: | $ 10,000.00 | |||
| Subcontract Effort (plugged number) | each | 100,000 | $ 100,000.00 | |
| Markup Rate (If applicable) (Base Period - Year 5): | 0.00% | |||
| Markup Amount (Base Period): | $ - 0 | |||
| Subtotal: | $ 100,000.00 | |||
| Total (A+B+C) | ||||
| Total Estimated Cost | $ 110,000.00 | |||
| Fixed Fee | ||||
| Fixed Fee Rate: | 0.00% | |||
| Fixed Fee Amount: | $ - 0 | |||
| Total Term Cost | ||||
| Year 5 Total : | $ 110,000.00 |