W59XQG41214366
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 2, to Solicitation W9128F-15-R-0025, Digital Governors, Amendment contains response to questions and clarification of submittal requirements. See Amendment 1, RFI Questions in the clasue section and Attachement 1 - Existing Governors. Due date of proposals has been changed to 2:00 PM, 16 September 2015. All other terms and conditions of this solicitation remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Sep-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9128F-15-R-0025
X 9B. DATED (SEE ITEM 11)
10-Aug-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
04-Sep-2015
CODE
U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST
CONTRACTING OFFICE
1616 CAPITOL AVENUE
OMAHA NE 68102-4901
W9128F 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9128F-15-R-0025
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
1. Question: Clarification for submission requirements
Offerors shall submit two (2) copies on separate CDs of Binder 1- (containing Factors1-4).
Offerors will submit one (1) copy of Binder 2 – Price, on a separate CD.
All offerors are required to submit an electronic copy of Binder 1 and 2 on a CD.
The binders shall be divided as follows.
Binder No. 1 Tab 1 – Experience Tab 2 – Past Performance Tab 3 – Technical Approach Tab 4 – Utilization of Small Business Concerns (Large Business Only)
Binder No. 2 Tab 1 - Cover Letter Tab 2 - Solicitation, Offer and Award and Supplies or Services and Prices (Section B) Tab 3 - Representations, Certifications and Other Statements of Offerors (Section K) Tab 4 - Pre-Award Survey Information and Small Business Information
Both Binder 1 and Binder 2 shall contain all submission requirement information. Proposal clarity, organization (as defined in this solicitation) and cross reference is mandatory. No material (information not part of the proposal) shall be incorporated by reference.
Binder 2 shall include a cover letter stating that the proposal complies completely with all terms, conditions, and specifications contained in the solicitation. A proposal that does not comply with all terms, conditions, and specifications in the solicitation will be automatically rejected and not considered for award.
Question 2: Amendment 1, response #9 indicates that the bidders are to supply spare water level transducers for each plant, please provide specifications for those devices if they are to be supplied under the project scope of supply as the sensor types and prices vary greatly.
W9128F-15-R-0025
Government Response: The contractor does not need to provide spare water level transducers.
They can be removed from the supply contract language.
Question 3: Amendment 1, response #10 indicates that the cabinets will be indicated on each POR, since the cabinet prices vary greatly between a free standing and an actuator cabinet insertion size cabinet, in order to accurately provide the governor supply pricing, the cabinet size for each plant be provided before that time for those bidders that are not that familiar with each plants requirement as this could present an unfair advantage. Would the government be willing to modify the price sheet for a governor base price with the free standing enclosure with an adder/ deduct for an insertion size enclosure?
Government Response: No, the Contract specifies the internal and external cabinet dimensions that the contractor is to use for bidding purposes (See specification sections 48 19 00.00 26, paragraphs 2.2.1.1 and 2.2.1.2). It can be assumed that the only projects with external cabinets are Ft. Peck Powerhouse 1 and Ft. Randall.
Photos of the existing governors are attached.
Big Bend – Internal Cabinet Ft. Peck Powerhouse 1 – External Cabinet Ft. Peck Powerhouse 2 – Internal Cabinet Ft. Randall – External Cabinet Garrison – Internal Cabinet Gavins Point – Internal Cabinet Oahe – Internal Cabinet
(End of Summary of Changes)
Question 4: How would the USACE intend to provide compensation to suppliers for delays on-site outside of the suppliers control during on-site Erection Engineer, Programmer, and Commissioning Services?
Government Response: Contractor can submit a Request for Equitable Adjustment (REA) IAW applicable FAR guidelines
Question 5: Is it acceptable to the USACE for suppliers to clarify the quantity of days on-site per unit included as part of the supplier’s proposal in regards to Erection Engineer, Programmer, and Commissioning Services. Would this approach be grounds for rejection of bid?
Government Response: Contractor in their proposal can include projected number of days for commissioning, but provide price for Job. Number of days for commissioning is not an evaluated factor on its own.
Question 6: Could the USACE please confirm that the Erection Engineer, Programmer, and Commissioning Services efforts would be performed concurrently in one trip by the supplier’s on-site engineer?
Government Response: It is the Government's expectation that the services will be performed concurrently for each unit. There are 31 units so 31 commissioning/programming trips would be required, quantity of 31 jobs for the CLIN.