Updated Section - Statement of Work

View the file

Other files

File Type Posted
18Nov2009revised_33_75_19_SF6_Breakers.pdf PDF
W9128F-09-T-0096-00002.pdf PDF
01 22 00 00 26.pdf PDF
01 42 00 00 10.pdf PDF
W9128F-09-T-0096-P00001.pdf PDF
33 75 19 00 26.pdf PDF
01 33 00 00 10.pdf PDF
01 30 60 00 26.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Garrison Breakers

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 10.00 26

STATEMENT OF WORK

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

1.1.1 General

1.1.2 Location and Arrangement

1.1.3 Shipment and Installation

1.2 SPECIFICATIONS

1.3 CHANGES IN SPECIFICATIONS AND DRAWINGS

1.4 DEFINITIONS

1.4.1 Directed, Required, Ordered, Designated, Prescribed

1.4.2 As Shown, As Indicated, As Detailed

1.4.3 Contracting Officer (CO), Contracting Officer's Representative

(COR)

1.4.4 Government Quality Assurance Representative (GQAR)

1.4.5 Weekend(s)

1.4.6 Project

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 11 10.00 26 Page 1

SECTION 01 11 10.00 26

STATEMENT OF WORK

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

1.1.1 General

These specifications include the design, manufacture, fabrication, assembly, wiring, testing and delivery of the items of equipment listed in the Bid Schedule and as shown. The major items of equipment to be furnished are outdoor sulfur hexafluoride (SF6) gas circuit breakers rated 123 kV, 1,200 amperes and 245 kV, 2000 amperes.

1.1.2 Location and Arrangement

The locations and general arrangement of the circuit breakers are shown.

The circuit breakers will replace existing switchyard breakers at the Garrison Powerhouse.

1.1.3 Shipment and Installation

The equipment furnished under this contract shall be installed under seperate contract. The equipment shall be shipped as completely assembled as feasible so as to require a minimum of installation work at the powerhouse. Any instrument, relay, meter, or other device which cannot withstand the hazards of shipment when mounted in place on the circuit breakers shall be carefully packed and shipped separately. All parts shall be prepared for shipment so that slings or hooks for handling may be attached readily while the parts are in the railway car or truck.

1.2 SPECIFICATIONS

Technical specifications listed below cover the detailed requirements for the equipment and services listed in the Schedule:

SECTION TITLE

01 11 10.00 26 STATEMENT OF WORK

01 22 00.00 26 MEASUREMENT AND PAYMENT

01 30 60.00 26 OPERATIONS AND MAINTENANCE DATA

01 33 00.00 10 SUBMITTAL PROCEDURES

01 42 00.00 10 SOURCE OF REFERENCED PUBLICATIONS

33 75 19.00 26 HIGH VOLTAGE SF6 GAS CIRCUIT BREAKERS

1.3 CHANGES IN SPECIFICATIONS AND DRAWINGS

The Government reserves the right to revise or amend the specifications and/or drawings prior to the date set for opening. Copies of such amendments will be furnished to all prospective bidders. If the revisions and amendments require material changes in quantities or prices bid, or both, the date set for opening bids may be extended to enable bidders the opportunity to revise their technical proposals and/or bids. The amendment will include an announcement of the new date for opening bids.

SECTION 01 11 10.00 26 Page 2

1.4 DEFINITIONS

1.4.1 Directed, Required, Ordered, Designated, Prescribed

Wherever in the specifications or upon the drawings the words "directed," "required," "ordered," "designated," "prescribed," or words of like import are used, it shall be understood that the "direction," "requirement," "order," "designation," or "prescription" of the Contracting Officer is intended and similarly the words "approved", "acceptable," "satisfactory," or words of like import shall mean "approved by," or "acceptable to," or "satisfactory to" the Contracting Officer unless otherwise expressly stated.

1.4.2 As Shown, As Indicated, As Detailed

Where "as shown," "as indicated," "as detailed," or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word "provided" as used herein shall be understood to mean "provided complete in-place," that is "furnished and installed." (FAR 52.236-21 (b and c).)

1.4.3 Contracting Officer (CO), Contracting Officer's Representative (COR)

Wherever in these specifications or upon the drawings the words "Contracting Officer" (CO) or "Contracting Officer's Representative" (COR), are used, it shall be understood to also mean "Government" unless otherwise expressly stated.

1.4.4 Government Quality Assurance Representative (GQAR)

Wherever in these specifications the word "GQAR" is used, it shall be understood to mean "Government Quality Assurance Representative," unless otherwise stated.

1.4.5 Weekend(s)

Wherever in these specifications the word "weekend(s)" is used, it shall be understood to mean "Saturday, Sunday and Federal Holidays," unless otherwise expressly stated.

1.4.6 Project

Wherever in these specifications the word "Project" is used, it shall be understood to mean "Garrison Project".

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

NOT USED

-- End of Section --

SECTION 01 11 10.00 26 Page 3