ABSTRACT -08-B-0005.xls

XLS spreadsheet 47 KB Posted

Attached to
Antelope Creek, Phase 3, Flood Protection Project, Lincoln, NE
Solicitation number
W9128F-08-B-0005
Issued by

About this file

Bid Abstract 08-B-0005

View the file

Other files

File Type Posted
am0004.pdf PDF
DrawingsAm0004.zip ZIP file
AutoCadd Drawings.zip ZIP file
Microstation Drawings.zip ZIP file
Am0001.pdf PDF
Antelope Creek Specs.pdf PDF
Antelope Creek Drawings Part 1.zip ZIP file
Antelope Creek Drawings Part 2.zip ZIP file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE1

ABSTRACT OF OFFERS - CONSTRUCTION1. SOLICITATION NUMBER2. DATE ISSUED3. DATE OPENEDPAGE 1 OF 2
W9128F-08-B-000515-Apr-0822-May-08l PAGES
4. ISSUING OFFICEI CERTIFY THAT I HAVE OPENED, READ ANDNAME AND TITLE OF CERTIFYING OFFICIAL (Type)
US ARMY CORPS OF ENGINEERSRECORDED ON THIS ABSTRACT ALL OFFERSNEIL F. HERMAN, Contract Specialist
CONTRACTING DIVISION (CENWO-CT)RECEIVED IN RESPONSE TO THIS SOLICITATIONSIGNATUREDATE SIGNED
106 SOUTH 15TH STREET*22-May-08
OMAHA, NE 68102-1618
5. PROJECT TITLE8. GOVERNMENT ESTIMATE9. OFFERS
(Check A, B or C AND COMPLETE D, E AND F)NO. 1NO. 2
ANTELOPE CREEK, PHASE 3A. HIRED LABORA. OFFERORA. OFFEROR
FLOOD CONTROL PROJECTDOBSON BROTHERS CONSTRUCTIONHWAKINS CONSTRUCTION COMPANY
LINCOLN, NEPO BOX 814092516 DEER PARK BLVD
LINCOLN, NE 68501OMAHA, NE 68105
B. REASONABLE CONTRACTB. BID SECURITY (Type & Amount)B. BID SECURITY (Type & Amount)
X(Without Profit)20%20%
6. NUMBER OF AMENDMENTS ISSUEDC. REASONABLE CONTRACTC. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED
5(Including Profit)
7A7B7CD.E.F.E.F.E.F.
ITEM #DESCRIPTION OF OFFER ITEMEST. QUANTITYUNITUNIT PRICEESTIMATED AMOUNTUNIT PRICEESTIMATED AMOUNTUNIT PRICEESTIMATED AMOUNT
1Clearing and Grubbing1JOB$ 19,760.00$ 93,000.00$ 500,100.00
2Pavement Removal/Disposal1JOB$ 46,812.00$ 72,000.00$ 62,403.00
3Channel Lining Removal/Dis.1JOB$ 2,882.00$ 7,000.00$ 7,761.00
4Dewatering1JOB$ 17,986.00$ 1,285,000.00$ 265,387.00
5Excavation310,000CY$ 6.00$ 1,860,000.00$ 7.57$ 2,346,700.00$ 8.09$ 2,507,900.00
6Rubble Excavation/Disposal2,000CY$ 15.25$ 30,500.00$ 14.70$ 29,400.00$ 16.35$ 32,700.00
7Utility Demolition1JOB$ 224,489.00$ 89,000.00$ 99,025.00
8Clear Tract 420 North 20th St1JOB$ 1,806.00$ 18,000.00$ 19,920.00
9Lead Removal 420 N 20th St1JOB$ 877.00$ 525.00$ 584.00
10Asbestos Removal 420 N 20
10ATextured Ceiling1,700SF$ 1.45$ 2,465.00$ 4.60$ 7,820.00$ 5.14$ 8,738.00
10BFloor Mastic1,000SF$ 1.25$ 1,250.00$ 2.30$ 2,300.00$ 2.57$ 2,570.00
11Clear Tract 2218 "N" Street1JOB$ 6,348.00$ 26,000.00$ 29,093.00
12Clear Tract 2231 "N" Street1JOB$ 16,497.00$ 96,000.00$ 106,953.00
13Lead Removal 2231 "N" St1JOB$ 4,279.00$ 260.00$ 292.00
14Asbestos Removal 2231 "N"
14AInsulation60LF$ 8.45$ 507.00$ 17.30$ 1,038.00$ 19.27$ 1,156.20
14BGlazing200LF$ 0.60$ 120.00$ 5.78$ 1,156.00$ 6.42$ 1,284.00
14CCaulking250LF$ 0.60$ 150.00$ 5.78$ 1,445.00$ 6.42$ 1,605.00
15Sump/Drain 2231 "N" Street1JOB$ 317.00$ 525.00$ 584.00
16PCB/Mercury 2231 "N" St1JOB$ 2,424.00$ 525.00$ 584.00
17Clear Tract Kuklin Pool1JOB$ 17,471.00$ 40,000.00$ 44,382.00
18Asbestos Removal Kuklin100LF$ 9.65$ 965.00$ 17.33$ 1,733.00$ 19.27$ 1,927.00
19Lead Removal Kuklin Pool1JOB$ 4,966.00$ 800.00$ 376.00
20Clear Tract Old Muny Pool1JOB$ 2,171.00$ 14,000.00$ 15,596.00
21Asbestos Removal Old Muny100LF$ 9.65$ 965.00$ 17.33$ 1,733.00$ 19.27$ 1,927.00
22Asbestos Removal Muny Ext.1,200SF$ 4.85$ 5,820.00$ 1.16$ 1,392.00$ 1.28$ 1,536.00
23Lead Removal Pedestrian1JOB$ 4,484.00$ 1,050.00$ 1,168.00
24Pedestrian Bridge # 31JOB$ 224,439.00$ 229,000.00$ 144,433.00
25Irrigation Line Ped Bridge # 31JOB$ 16,008.00$ 85,000.00$ 16,188.00
26Drainage Structures
26ADrainage Structure # 301JOB$ 3,524.00$ 16,800.00$ 35,355.00
26BDrainage Structure # 311JOB$ 4,824.00$ 21,000.00$ 46,720.00
26CDrainage Structure # 321JOB$ 2,434.00$ 15,750.00$ 38,544.00
26DDrainage Structure # 331JOB$ 17,102.00$ 31,500.00$ 65,992.00
26EDrainage Structure # 341JOB$ 12,882.00$ 29,400.00$ 17,637.00
27Crushed Stone1JOB$ 99,176.00$ 368,000.00$ 408,820.00
28Compacted Backfill1JOB$ 110,861.00$ 255,000.00$ 238,447.00
29Concrete Low Flow Channel1JOB$ 149,845.00$ 357,000.00$ 234,231.00
30Concrete Channel Lining1JOB$ 942,588.00$ 652,000.00$ 324,241.00
31Cellular Concrete Mattress
31AType A13,700SY$ 105.55$ 1,446,035.00$ 130.00$ 1,781,000.00$ 94.32$ 1,292,184.00
31BType B3,200SY$ 108.35$ 346,720.00$ 187.00$ 598,400.00$ 108.62$ 347,584.00
32Concrete Bike Trail7,660SY$ 44.90$ 343,934.00$ 45.00$ 344,700.00$ 46.06$ 352,819.60
33Labyrinth Weir1JOB$ 1,330,907.00$ 2,025,000.00$ 2,394,407.00
34Conduit Extension1JOB$ 669,149.00$ 470,000.00$ 397,496.00
35"N" St Roadway & Utilities1JOB$ 688,894.00$ 1,480,000.00$ 973,377.00
36Topsoil1JOB$ 86,671.00$ 104,000.00$ 115,296.00
37Seeding and Mulching20ACRE$ 2,195.00$ 43,900.00$ 1,000.00$ 20,000.00$ 1,109.60$ 22,192.00
38Erosion Control Blanket
38AErosion Control Blanket56,000SY$ 2.40$ 134,400.00$ 1.50$ 84,000.00$ 1.65$ 92,400.00
38BTurf Reinforcement Mat16,400SY$ 5.50$ 90,200.00$ 4.30$ 70,520.00$ 4.79$ 78,556.00
39Landscaping1JOB$ 135,891.00$ 121,000.00$ 70,730.00
40All Remaining Work1JOB$ 383,363.00$ 3,400,000.00$ 3,221,111.00
Total Item 0001 thru 0040$ 9,560,058.00$ 16,697,472.00$ 14,644,311.80
OPTIONS
41Option 1 - Bent Encasement
41A"O" Street Bridge1JOB$ 295,387.00$ 340,400.00$ 163,323.00
41B"P" Street Bridge1JOB$ 211,529.00$ 212,300.00$ 145,689.00
41C"Q" Street Bridge1JOB$ 213,153.00$ 211,500.00$ 103,556.00
41D"Y" Street Bridge Staining1JOB$ 20,589.00$ 24,000.00$ 5,841.00
41EVine Street Bridge Staining1JOB$ 38,030.00$ 24,000.00$ 5,841.00
42Option 2 - Low Flow Channel1JOB$ 738,215.00$ 2,520,000.00$ 1,098,313.00
43Option 3 - Retaining Walls1JOB$ 1,025,096.00$ 1,570,000.00$ 579,108.00
44Option 4 - Retaining Walls1JOB$ 152,215.00$ 548,000.00$ 279,578.00
45Option 5 - Park Irrigation1JOB$ 82,755.00$ 543,000.00$ 115,025.00
46Option 6 - "N" Street Bridge1JOB$ 1,615,162.00$ 2,600,000.00$ 1,484,852.00
47Option 7 - Piling HP 10 x 424,335FT$ 40.35$ 174,917.25$ 39.00$ 169,065.00$ 44.00$ 190,740.00
48Option 8 - Piling HP 14 x 892,640FT$ 69.55$ 183,612.00$ 75.50$ 199,320.00$ 79.63$ 210,223.20
49Option 9 - Retaining Walls1JOB$ 144,493.00$ 409,000.00$ 204,323.00
TOTALS$ 14,455,211.25$ 26,068,057.00$ 19,230,724.00
ABSTRACT OF OFFERS -1. SOLICITATION NUMBERPAGE 2 OF 2
W9128F-08-B-0005l PAGES
CONSTRUCTIONINSTRUCTIONS: Attach this form to Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation
CONTINUATION SHEETsheet will accommodate 24 contract items to conform the number of items which can be entered . Use additional forms and continuation sheets as needed.
2. PROJECT TITLE4. OFFERS (Continued)
NO. 3NO. 4NO. 5NO. 6
ENVIRONMENTALA. OFFERORA. OFFERORA. OFFERORA. OFFEROR
RESTORATION PROJECTJUDDS BROS CONSTRUCTION COPARK CONSTRUCTION COMPANY
Sand Creek Breakwater3835 NORTH 68TH STREET23260 MAIN STREET, SUITE 6
North of Wahoo, NELINCOLN, NE 68505-5344HAMPTON, MN 55031
B. BID SECURITY (Type & Amount)B. BID SECURITY (Type & Amount)B. BID SECURITY (Type & Amount)B. BID SECURITY (Type & Amount)
20%20%20%20%
3. CONTRACT ITEMSC. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGEDC. AMENDMENTS ACKNOWLEDGED
AB$D.E.D.E.D.E.E.D.E.
ITEM #EST. QUANTITYUNITUNIT PRICEESTIMATED AMOUNTUNIT PRICEESTIMATED AMOUNTUNIT PRICEUNIT PRICEESTIMATED AMOUNTUNIT PRICEESTIMATED AMOUNT
11JOB$ 100,000.00$ 30.00$$
21JOB$ 61,000.00$ 64,800.00$$
31JOB$ 8,000.00$ 36,900.00$$
41JOB$ 240,000.00$ 184,200.00$$
5310,000CY$ 7.10$ 2,201,000.00$ 4.50$ 1,395,000.00$$
62,000CY$ 16.00$ 32,000.00$ 13.00$ 26,000.00$$
71JOB$ 100,000.00$ 140,000.00$$
81JOB$ 20,000.00$ 4,300.00$$
91JOB$ 575.00$ 533.00$$
10$$$$
10A1,700SF$ 4.50$ 7,650.00$ 4.05$ 6,885.00$$
10B1,000SF$ 2.25$ 2,250.00$ 2.00$ 2,000.00$$
111JOB$ 30,000.00$ 5,740.00
121JOB$ 105,000.00$ 10,700.00
131JOB$ 300.00$ 506.00
14
14A60LF$ 16.50$ 990.00$ 15.20$ 912.00
14B200LF$ 5.50$ 1,100.00$ 5.05$ 1,010.00
14C250LF$ 5.50$ 1,375.00$ 5.05$ 1,262.50
151JOB$ 575.00$ 2,630.00
161JOB$ 575.00$ 202.00
171JOB$ 45,000.00$ 5,580.00
18100LF$ 16.50$ 1,650.00$ 15.20$ 1,520.00
191JOB$ 750.00$ 506.00
201JOB$ 16,000.00$ 3,830.00
21100LF$ 16.50$ 1,650.00$ 15.20$ 1,520.00
221,200SF$ 1.10$ 1,320.00$ 1.00$ 1,200.00
231JOB$ 1,000.00$ 506.00
241JOB$ 221,000.00$ 156,900.00
251JOB$ 24,000.00$ 17,600.00
26
26A1JOB$ 25,000.00$ 12,200.00
26B1JOB$ 35,000.00$ 16,400.00$ - 0$ - 0
26C1JOB$ 30,000.00$ 11,600.00$$
26D1JOB$ 39,000.00$ 27,700.00
26E1JOB$ 29,000.00$ 22,100.00
271JOB$ 400,000.00$ 220,900.00
281JOB$ 280,000.00$ 89,100.00
291JOB$ 260,000.00$ 233,700.00
301JOB$ 625,000.00$ 322,900.00
31
31A13,700SY$ 94.00$ 1,287,800.00$ 111.00$ 1,520,700.00
31B3,200SY$ 100.00$ 320,000.00$ 118.00$ 377,600.00
327,660SY$ 40.00$ 310,400.00$ 61.10$ 468,026.00
331JOB$ 1,440,000.00$ 993,600.00
341JOB$ 410,000.00$ 355,500.00
351JOB$ 350,000.00$ 2,547,300.00
361JOB$ 250,000.00$ 16,400.00
3720ACRE$ 2,000.00$ 40,000.00$ 962.00$ 19,240.00
38
38A56,000SY$ 1.80$ 100,800.00$ 1.45$ 81,200.00
38B16,400SY$ 5.50$ 90,200.00$ 4.15$ 68,060.00
391JOB$ 170,000.00$ 209,700.00
401JOB$ 1,000,000.00$ 766,752.00
TOTAL BASIC$ 10,716,960.00$ 10,453,450.50
OPTIONS
41
41A1JOB$ 325,000.00$ 185,600.00
41B1JOB$ 200,000.00$ 139,500.00
41C1JOB$ 200,000.00$ 125,200.00
41D1JOB$ 24,000.00$ 24,100.00
41E1JOB$ 24,000.00$ 24,100.00
421JOB$ 1,100,000.00$ 918,700.00
431JOB$ 800,000.00$ 721,700.00
441JOB$ 230,000.00$ 271,900.00$$
451JOB$ 450,000.00$ 75,400.00$ - 0$ - 0
461JOB$ 2,350,000.00$ 2,200,900.00
474,335FT$ 40.00$ 173,400.00$ 62.20$ 269,637.00
482,640FT$ 75.00$ 198,000.00$ 109.00$ 287,760.00$ - 0$ - 0
491JOB$ 125,000.00$ 127,500.00$ - 0$ - 0
TOTALS$ 16,916,360.00$ 15,825,447.50$$