ABSTRACT -08-B-0005.xls
XLS spreadsheet 47 KB Posted
- Solicitation number
- W9128F-08-B-0005
About this file
Bid Abstract 08-B-0005
View the file
Other files
| File | Type | Posted |
|---|---|---|
| am0004.pdf | ||
| DrawingsAm0004.zip | ZIP file | |
| AutoCadd Drawings.zip | ZIP file | |
| Microstation Drawings.zip | ZIP file | |
| Am0001.pdf | ||
| Antelope Creek Specs.pdf | ||
| Antelope Creek Drawings Part 1.zip | ZIP file | |
| Antelope Creek Drawings Part 2.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE1
| ABSTRACT OF OFFERS - CONSTRUCTION | 1. SOLICITATION NUMBER | 2. DATE ISSUED | 3. DATE OPENED | PAGE 1 OF 2 | |||||
| W9128F-08-B-0005 | 15-Apr-08 | 22-May-08 | l PAGES | ||||||
| 4. ISSUING OFFICE | I CERTIFY THAT I HAVE OPENED, READ AND | NAME AND TITLE OF CERTIFYING OFFICIAL (Type) | |||||||
| US ARMY CORPS OF ENGINEERS | RECORDED ON THIS ABSTRACT ALL OFFERS | NEIL F. HERMAN, Contract Specialist | |||||||
| CONTRACTING DIVISION (CENWO-CT) | RECEIVED IN RESPONSE TO THIS SOLICITATION | SIGNATURE | DATE SIGNED | ||||||
| 106 SOUTH 15TH STREET | * | 22-May-08 | |||||||
| OMAHA, NE 68102-1618 | |||||||||
| 5. PROJECT TITLE | 8. GOVERNMENT ESTIMATE | 9. OFFERS | |||||||
| (Check A, B or C AND COMPLETE D, E AND F) | NO. 1 | NO. 2 | |||||||
| ANTELOPE CREEK, PHASE 3 | A. HIRED LABOR | A. OFFEROR | A. OFFEROR | ||||||
| FLOOD CONTROL PROJECT | DOBSON BROTHERS CONSTRUCTION | HWAKINS CONSTRUCTION COMPANY | |||||||
| LINCOLN, NE | PO BOX 81409 | 2516 DEER PARK BLVD | |||||||
| LINCOLN, NE 68501 | OMAHA, NE 68105 | ||||||||
| B. REASONABLE CONTRACT | B. BID SECURITY (Type & Amount) | B. BID SECURITY (Type & Amount) | |||||||
| X | (Without Profit) | 20% | 20% | ||||||
| 6. NUMBER OF AMENDMENTS ISSUED | C. REASONABLE CONTRACT | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | ||||||
| 5 | (Including Profit) | ||||||||
| 7A | 7B | 7C | D. | E. | F. | E. | F. | E. | F. |
| ITEM # | DESCRIPTION OF OFFER ITEM | EST. QUANTITY | UNIT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT |
| 1 | Clearing and Grubbing | 1 | JOB | $ 19,760.00 | $ 93,000.00 | $ 500,100.00 | |||
| 2 | Pavement Removal/Disposal | 1 | JOB | $ 46,812.00 | $ 72,000.00 | $ 62,403.00 | |||
| 3 | Channel Lining Removal/Dis. | 1 | JOB | $ 2,882.00 | $ 7,000.00 | $ 7,761.00 | |||
| 4 | Dewatering | 1 | JOB | $ 17,986.00 | $ 1,285,000.00 | $ 265,387.00 | |||
| 5 | Excavation | 310,000 | CY | $ 6.00 | $ 1,860,000.00 | $ 7.57 | $ 2,346,700.00 | $ 8.09 | $ 2,507,900.00 |
| 6 | Rubble Excavation/Disposal | 2,000 | CY | $ 15.25 | $ 30,500.00 | $ 14.70 | $ 29,400.00 | $ 16.35 | $ 32,700.00 |
| 7 | Utility Demolition | 1 | JOB | $ 224,489.00 | $ 89,000.00 | $ 99,025.00 | |||
| 8 | Clear Tract 420 North 20th St | 1 | JOB | $ 1,806.00 | $ 18,000.00 | $ 19,920.00 | |||
| 9 | Lead Removal 420 N 20th St | 1 | JOB | $ 877.00 | $ 525.00 | $ 584.00 | |||
| 10 | Asbestos Removal 420 N 20 | ||||||||
| 10A | Textured Ceiling | 1,700 | SF | $ 1.45 | $ 2,465.00 | $ 4.60 | $ 7,820.00 | $ 5.14 | $ 8,738.00 |
| 10B | Floor Mastic | 1,000 | SF | $ 1.25 | $ 1,250.00 | $ 2.30 | $ 2,300.00 | $ 2.57 | $ 2,570.00 |
| 11 | Clear Tract 2218 "N" Street | 1 | JOB | $ 6,348.00 | $ 26,000.00 | $ 29,093.00 | |||
| 12 | Clear Tract 2231 "N" Street | 1 | JOB | $ 16,497.00 | $ 96,000.00 | $ 106,953.00 | |||
| 13 | Lead Removal 2231 "N" St | 1 | JOB | $ 4,279.00 | $ 260.00 | $ 292.00 | |||
| 14 | Asbestos Removal 2231 "N" | ||||||||
| 14A | Insulation | 60 | LF | $ 8.45 | $ 507.00 | $ 17.30 | $ 1,038.00 | $ 19.27 | $ 1,156.20 |
| 14B | Glazing | 200 | LF | $ 0.60 | $ 120.00 | $ 5.78 | $ 1,156.00 | $ 6.42 | $ 1,284.00 |
| 14C | Caulking | 250 | LF | $ 0.60 | $ 150.00 | $ 5.78 | $ 1,445.00 | $ 6.42 | $ 1,605.00 |
| 15 | Sump/Drain 2231 "N" Street | 1 | JOB | $ 317.00 | $ 525.00 | $ 584.00 | |||
| 16 | PCB/Mercury 2231 "N" St | 1 | JOB | $ 2,424.00 | $ 525.00 | $ 584.00 | |||
| 17 | Clear Tract Kuklin Pool | 1 | JOB | $ 17,471.00 | $ 40,000.00 | $ 44,382.00 | |||
| 18 | Asbestos Removal Kuklin | 100 | LF | $ 9.65 | $ 965.00 | $ 17.33 | $ 1,733.00 | $ 19.27 | $ 1,927.00 |
| 19 | Lead Removal Kuklin Pool | 1 | JOB | $ 4,966.00 | $ 800.00 | $ 376.00 | |||
| 20 | Clear Tract Old Muny Pool | 1 | JOB | $ 2,171.00 | $ 14,000.00 | $ 15,596.00 | |||
| 21 | Asbestos Removal Old Muny | 100 | LF | $ 9.65 | $ 965.00 | $ 17.33 | $ 1,733.00 | $ 19.27 | $ 1,927.00 |
| 22 | Asbestos Removal Muny Ext. | 1,200 | SF | $ 4.85 | $ 5,820.00 | $ 1.16 | $ 1,392.00 | $ 1.28 | $ 1,536.00 |
| 23 | Lead Removal Pedestrian | 1 | JOB | $ 4,484.00 | $ 1,050.00 | $ 1,168.00 | |||
| 24 | Pedestrian Bridge # 3 | 1 | JOB | $ 224,439.00 | $ 229,000.00 | $ 144,433.00 | |||
| 25 | Irrigation Line Ped Bridge # 3 | 1 | JOB | $ 16,008.00 | $ 85,000.00 | $ 16,188.00 | |||
| 26 | Drainage Structures | ||||||||
| 26A | Drainage Structure # 30 | 1 | JOB | $ 3,524.00 | $ 16,800.00 | $ 35,355.00 | |||
| 26B | Drainage Structure # 31 | 1 | JOB | $ 4,824.00 | $ 21,000.00 | $ 46,720.00 | |||
| 26C | Drainage Structure # 32 | 1 | JOB | $ 2,434.00 | $ 15,750.00 | $ 38,544.00 | |||
| 26D | Drainage Structure # 33 | 1 | JOB | $ 17,102.00 | $ 31,500.00 | $ 65,992.00 | |||
| 26E | Drainage Structure # 34 | 1 | JOB | $ 12,882.00 | $ 29,400.00 | $ 17,637.00 | |||
| 27 | Crushed Stone | 1 | JOB | $ 99,176.00 | $ 368,000.00 | $ 408,820.00 | |||
| 28 | Compacted Backfill | 1 | JOB | $ 110,861.00 | $ 255,000.00 | $ 238,447.00 | |||
| 29 | Concrete Low Flow Channel | 1 | JOB | $ 149,845.00 | $ 357,000.00 | $ 234,231.00 | |||
| 30 | Concrete Channel Lining | 1 | JOB | $ 942,588.00 | $ 652,000.00 | $ 324,241.00 | |||
| 31 | Cellular Concrete Mattress | ||||||||
| 31A | Type A | 13,700 | SY | $ 105.55 | $ 1,446,035.00 | $ 130.00 | $ 1,781,000.00 | $ 94.32 | $ 1,292,184.00 |
| 31B | Type B | 3,200 | SY | $ 108.35 | $ 346,720.00 | $ 187.00 | $ 598,400.00 | $ 108.62 | $ 347,584.00 |
| 32 | Concrete Bike Trail | 7,660 | SY | $ 44.90 | $ 343,934.00 | $ 45.00 | $ 344,700.00 | $ 46.06 | $ 352,819.60 |
| 33 | Labyrinth Weir | 1 | JOB | $ 1,330,907.00 | $ 2,025,000.00 | $ 2,394,407.00 | |||
| 34 | Conduit Extension | 1 | JOB | $ 669,149.00 | $ 470,000.00 | $ 397,496.00 | |||
| 35 | "N" St Roadway & Utilities | 1 | JOB | $ 688,894.00 | $ 1,480,000.00 | $ 973,377.00 | |||
| 36 | Topsoil | 1 | JOB | $ 86,671.00 | $ 104,000.00 | $ 115,296.00 | |||
| 37 | Seeding and Mulching | 20 | ACRE | $ 2,195.00 | $ 43,900.00 | $ 1,000.00 | $ 20,000.00 | $ 1,109.60 | $ 22,192.00 |
| 38 | Erosion Control Blanket | ||||||||
| 38A | Erosion Control Blanket | 56,000 | SY | $ 2.40 | $ 134,400.00 | $ 1.50 | $ 84,000.00 | $ 1.65 | $ 92,400.00 |
| 38B | Turf Reinforcement Mat | 16,400 | SY | $ 5.50 | $ 90,200.00 | $ 4.30 | $ 70,520.00 | $ 4.79 | $ 78,556.00 |
| 39 | Landscaping | 1 | JOB | $ 135,891.00 | $ 121,000.00 | $ 70,730.00 | |||
| 40 | All Remaining Work | 1 | JOB | $ 383,363.00 | $ 3,400,000.00 | $ 3,221,111.00 | |||
| Total Item 0001 thru 0040 | $ 9,560,058.00 | $ 16,697,472.00 | $ 14,644,311.80 | ||||||
| OPTIONS | |||||||||
| 41 | Option 1 - Bent Encasement | ||||||||
| 41A | "O" Street Bridge | 1 | JOB | $ 295,387.00 | $ 340,400.00 | $ 163,323.00 | |||
| 41B | "P" Street Bridge | 1 | JOB | $ 211,529.00 | $ 212,300.00 | $ 145,689.00 | |||
| 41C | "Q" Street Bridge | 1 | JOB | $ 213,153.00 | $ 211,500.00 | $ 103,556.00 | |||
| 41D | "Y" Street Bridge Staining | 1 | JOB | $ 20,589.00 | $ 24,000.00 | $ 5,841.00 | |||
| 41E | Vine Street Bridge Staining | 1 | JOB | $ 38,030.00 | $ 24,000.00 | $ 5,841.00 | |||
| 42 | Option 2 - Low Flow Channel | 1 | JOB | $ 738,215.00 | $ 2,520,000.00 | $ 1,098,313.00 | |||
| 43 | Option 3 - Retaining Walls | 1 | JOB | $ 1,025,096.00 | $ 1,570,000.00 | $ 579,108.00 | |||
| 44 | Option 4 - Retaining Walls | 1 | JOB | $ 152,215.00 | $ 548,000.00 | $ 279,578.00 | |||
| 45 | Option 5 - Park Irrigation | 1 | JOB | $ 82,755.00 | $ 543,000.00 | $ 115,025.00 | |||
| 46 | Option 6 - "N" Street Bridge | 1 | JOB | $ 1,615,162.00 | $ 2,600,000.00 | $ 1,484,852.00 | |||
| 47 | Option 7 - Piling HP 10 x 42 | 4,335 | FT | $ 40.35 | $ 174,917.25 | $ 39.00 | $ 169,065.00 | $ 44.00 | $ 190,740.00 |
| 48 | Option 8 - Piling HP 14 x 89 | 2,640 | FT | $ 69.55 | $ 183,612.00 | $ 75.50 | $ 199,320.00 | $ 79.63 | $ 210,223.20 |
| 49 | Option 9 - Retaining Walls | 1 | JOB | $ 144,493.00 | $ 409,000.00 | $ 204,323.00 | |||
| TOTALS | $ 14,455,211.25 | $ 26,068,057.00 | $ 19,230,724.00 |
| ABSTRACT OF OFFERS - | 1. SOLICITATION NUMBER | PAGE 2 OF 2 | |||||||||
| W9128F-08-B-0005 | l PAGES | ||||||||||
| CONSTRUCTION | INSTRUCTIONS: Attach this form to Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation | ||||||||||
| CONTINUATION SHEET | sheet will accommodate 24 contract items to conform the number of items which can be entered . Use additional forms and continuation sheets as needed. | ||||||||||
| 2. PROJECT TITLE | 4. OFFERS (Continued) | ||||||||||
| NO. 3 | NO. 4 | NO. 5 | NO. 6 | ||||||||
| ENVIRONMENTAL | A. OFFEROR | A. OFFEROR | A. OFFEROR | A. OFFEROR | |||||||
| RESTORATION PROJECT | JUDDS BROS CONSTRUCTION CO | PARK CONSTRUCTION COMPANY | |||||||||
| Sand Creek Breakwater | 3835 NORTH 68TH STREET | 23260 MAIN STREET, SUITE 6 | |||||||||
| North of Wahoo, NE | LINCOLN, NE 68505-5344 | HAMPTON, MN 55031 | |||||||||
| B. BID SECURITY (Type & Amount) | B. BID SECURITY (Type & Amount) | B. BID SECURITY (Type & Amount) | B. BID SECURITY (Type & Amount) | ||||||||
| 20% | 20% | 20% | 20% | ||||||||
| 3. CONTRACT ITEMS | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | C. AMENDMENTS ACKNOWLEDGED | |||||||
| A | B | $ | D. | E. | D. | E. | D. | E. | E. | D. | E. |
| ITEM # | EST. QUANTITY | UNIT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | UNIT PRICE | ESTIMATED AMOUNT | UNIT PRICE | ESTIMATED AMOUNT |
| 1 | 1 | JOB | $ 100,000.00 | $ 30.00 | $ | $ | |||||
| 2 | 1 | JOB | $ 61,000.00 | $ 64,800.00 | $ | $ | |||||
| 3 | 1 | JOB | $ 8,000.00 | $ 36,900.00 | $ | $ | |||||
| 4 | 1 | JOB | $ 240,000.00 | $ 184,200.00 | $ | $ | |||||
| 5 | 310,000 | CY | $ 7.10 | $ 2,201,000.00 | $ 4.50 | $ 1,395,000.00 | $ | $ | |||
| 6 | 2,000 | CY | $ 16.00 | $ 32,000.00 | $ 13.00 | $ 26,000.00 | $ | $ | |||
| 7 | 1 | JOB | $ 100,000.00 | $ 140,000.00 | $ | $ | |||||
| 8 | 1 | JOB | $ 20,000.00 | $ 4,300.00 | $ | $ | |||||
| 9 | 1 | JOB | $ 575.00 | $ 533.00 | $ | $ | |||||
| 10 | $ | $ | $ | $ | |||||||
| 10A | 1,700 | SF | $ 4.50 | $ 7,650.00 | $ 4.05 | $ 6,885.00 | $ | $ | |||
| 10B | 1,000 | SF | $ 2.25 | $ 2,250.00 | $ 2.00 | $ 2,000.00 | $ | $ | |||
| 11 | 1 | JOB | $ 30,000.00 | $ 5,740.00 | |||||||
| 12 | 1 | JOB | $ 105,000.00 | $ 10,700.00 | |||||||
| 13 | 1 | JOB | $ 300.00 | $ 506.00 | |||||||
| 14 | |||||||||||
| 14A | 60 | LF | $ 16.50 | $ 990.00 | $ 15.20 | $ 912.00 | |||||
| 14B | 200 | LF | $ 5.50 | $ 1,100.00 | $ 5.05 | $ 1,010.00 | |||||
| 14C | 250 | LF | $ 5.50 | $ 1,375.00 | $ 5.05 | $ 1,262.50 | |||||
| 15 | 1 | JOB | $ 575.00 | $ 2,630.00 | |||||||
| 16 | 1 | JOB | $ 575.00 | $ 202.00 | |||||||
| 17 | 1 | JOB | $ 45,000.00 | $ 5,580.00 | |||||||
| 18 | 100 | LF | $ 16.50 | $ 1,650.00 | $ 15.20 | $ 1,520.00 | |||||
| 19 | 1 | JOB | $ 750.00 | $ 506.00 | |||||||
| 20 | 1 | JOB | $ 16,000.00 | $ 3,830.00 | |||||||
| 21 | 100 | LF | $ 16.50 | $ 1,650.00 | $ 15.20 | $ 1,520.00 | |||||
| 22 | 1,200 | SF | $ 1.10 | $ 1,320.00 | $ 1.00 | $ 1,200.00 | |||||
| 23 | 1 | JOB | $ 1,000.00 | $ 506.00 | |||||||
| 24 | 1 | JOB | $ 221,000.00 | $ 156,900.00 | |||||||
| 25 | 1 | JOB | $ 24,000.00 | $ 17,600.00 | |||||||
| 26 | |||||||||||
| 26A | 1 | JOB | $ 25,000.00 | $ 12,200.00 | |||||||
| 26B | 1 | JOB | $ 35,000.00 | $ 16,400.00 | $ - 0 | $ - 0 | |||||
| 26C | 1 | JOB | $ 30,000.00 | $ 11,600.00 | $ | $ | |||||
| 26D | 1 | JOB | $ 39,000.00 | $ 27,700.00 | |||||||
| 26E | 1 | JOB | $ 29,000.00 | $ 22,100.00 | |||||||
| 27 | 1 | JOB | $ 400,000.00 | $ 220,900.00 | |||||||
| 28 | 1 | JOB | $ 280,000.00 | $ 89,100.00 | |||||||
| 29 | 1 | JOB | $ 260,000.00 | $ 233,700.00 | |||||||
| 30 | 1 | JOB | $ 625,000.00 | $ 322,900.00 | |||||||
| 31 | |||||||||||
| 31A | 13,700 | SY | $ 94.00 | $ 1,287,800.00 | $ 111.00 | $ 1,520,700.00 | |||||
| 31B | 3,200 | SY | $ 100.00 | $ 320,000.00 | $ 118.00 | $ 377,600.00 | |||||
| 32 | 7,660 | SY | $ 40.00 | $ 310,400.00 | $ 61.10 | $ 468,026.00 | |||||
| 33 | 1 | JOB | $ 1,440,000.00 | $ 993,600.00 | |||||||
| 34 | 1 | JOB | $ 410,000.00 | $ 355,500.00 | |||||||
| 35 | 1 | JOB | $ 350,000.00 | $ 2,547,300.00 | |||||||
| 36 | 1 | JOB | $ 250,000.00 | $ 16,400.00 | |||||||
| 37 | 20 | ACRE | $ 2,000.00 | $ 40,000.00 | $ 962.00 | $ 19,240.00 | |||||
| 38 | |||||||||||
| 38A | 56,000 | SY | $ 1.80 | $ 100,800.00 | $ 1.45 | $ 81,200.00 | |||||
| 38B | 16,400 | SY | $ 5.50 | $ 90,200.00 | $ 4.15 | $ 68,060.00 | |||||
| 39 | 1 | JOB | $ 170,000.00 | $ 209,700.00 | |||||||
| 40 | 1 | JOB | $ 1,000,000.00 | $ 766,752.00 | |||||||
| TOTAL BASIC | $ 10,716,960.00 | $ 10,453,450.50 | |||||||||
| OPTIONS | |||||||||||
| 41 | |||||||||||
| 41A | 1 | JOB | $ 325,000.00 | $ 185,600.00 | |||||||
| 41B | 1 | JOB | $ 200,000.00 | $ 139,500.00 | |||||||
| 41C | 1 | JOB | $ 200,000.00 | $ 125,200.00 | |||||||
| 41D | 1 | JOB | $ 24,000.00 | $ 24,100.00 | |||||||
| 41E | 1 | JOB | $ 24,000.00 | $ 24,100.00 | |||||||
| 42 | 1 | JOB | $ 1,100,000.00 | $ 918,700.00 | |||||||
| 43 | 1 | JOB | $ 800,000.00 | $ 721,700.00 | |||||||
| 44 | 1 | JOB | $ 230,000.00 | $ 271,900.00 | $ | $ | |||||
| 45 | 1 | JOB | $ 450,000.00 | $ 75,400.00 | $ - 0 | $ - 0 | |||||
| 46 | 1 | JOB | $ 2,350,000.00 | $ 2,200,900.00 | |||||||
| 47 | 4,335 | FT | $ 40.00 | $ 173,400.00 | $ 62.20 | $ 269,637.00 | |||||
| 48 | 2,640 | FT | $ 75.00 | $ 198,000.00 | $ 109.00 | $ 287,760.00 | $ - 0 | $ - 0 | |||
| 49 | 1 | JOB | $ 125,000.00 | $ 127,500.00 | $ - 0 | $ - 0 | |||||
| TOTALS | $ 16,916,360.00 | $ 15,825,447.50 | $ | $ |