AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

$495M Unrestricted Multiple Aw ard Task Order Contract (MATOC) for Design-Build and Design-Bid-Build Construction Services for the State of Haw aii

See Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9128A22R0003

X 9B. DATED (SEE ITEM 11)

16-Mar-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

Am-0002

5. PROJECT NO.(If applicable)

6. ISSUED BY CODE

CONTRACTING DIVISION

BLDG 230 OTAKE ST.

FORT SHAFTER HI 96858

W9128A 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

3. EFFECTIVE DATE

31-Mar-2022

W9128A22R0003 Am-0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

1. CHANGES TO SPECIFICATIONS. Attached hereto are revised pages/paragraphs to the specifications. The revision mark “(Am-0002)” is shown on each revised page.

a. REVISED SECTIONS. The following are revised pages to the solicitation. Changes are marked in “*” asterisks.

Section 00 10 00 – Page 1 Section 00 22 10 – Pages 2-6

b. NEW SECTIONS. The following are new pages to the solicitation.

Section 00 60 00, Appendix A – Requests for Information (#8 through 15)

c. REPLACED SECTIONS. The following section from the solicitation has been deleted in its entirety and replaced with the section attached to this amendment.

Section 00 22 10, Attachment A – Experience Information Section 00 73 00, Appendix B – Offeror Questions and Comments

2. The proposal due date and time remains unchanged.

RFP No. W9128A22R0003

NOTES:

1. The Government will provide all MATOC Awardees a fair opportunity to be considered for award for every MATOC solicitation unless an exemption under FAR 16.505(b)(2) and DFARS 216.505(b)(2) applies.

2. The minimum guarantee for the pool of contractors is $2,000 per contractor for the base period only. A minimum guarantee will not be applicable to the optional periods of performance.

3. All interested prime and sub-contractors are recommended to participate in and review the Interested Vendors List available in the solicitation announcement on SAM.gov (Solicitation No. W9128A22R0003).

A contractor must be registered and signed into SAM.gov in order to access the Interested Vendors List function.

4. MEASUREMENT AND PAYMENT. Compensation for all work to be performed under this contract will be made under the payment item(s) listed in the task order. Prices(s) and payment(s) for the item(s) shall cover all work, complete and finished in accordance with the specifications, schedules, and drawings, and shall be full compensation for all work in connection therewith, including quality control and the cost of performance-and payment-bond premiums as specified in the CONTRACT CLAUSES. Price(s) and payment(s) shall constitute full and final compensation for furnishing all materials, equipment, management, supervision, labor, transportation, fuel, power, water, and all incidental items necessary to complete the work, except as otherwise specified to be furnished by the Government. For the purpose of CONTRACT CLAUSE entitled "PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS", the term "designated billing office" and "designated payment office" are as follows:

a. Billing Office

U.S. Army Corps of Engineers, Honolulu District Area Office to be determined with award of each task order

b. Payment Office

USACE Finance Center Attn: CEFC-FP 5722 Integrity Drive Millington, TN 380554-5005

5. Each Offeror must submit the following documents electronically in PDF format. Failure to submit all required documents electronically in PDF format may result in the Offeror being ineligible for award. Please refer to Section 00 73 00, Appendix A – Electronic Proposal Submissions, for further instructions.

a. SF1442 (pages 1 and 2) including acknowledging all amendments

b. Proposal Schedule

c. Section 00 45 00, Representations and Certifications

d. Section 00 45 00, Representations and Certifications, Appendix A – SF LLL Disclosure of Lobbying

Activities

e. Volume 1 in response to Section 00 22 10.

6. Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet. Please refer to Section 00 73 00, Appendix B – Offeror Questions and Comments, for further instructions.

Section 00 10 00 – 1 (Am-0002)

Section 00 22 10 – 2

5.2. Submit the Standard Form 1442, completed and signed by a person authorized to bind the company in accordance with the instructions at FAR 4.102.

5.3. Joint Venture Prime Contractors:

If the offeror is a Joint Venture, a copy of the joint venture agreement shall be submitted with the proposal. All members of the joint venture shall sign the SF 1442 unless a written agreement by the joint venture is furnished with the proposal designating one firm with the authority to bind the other member(s) of the joint venture. Failure to comply with the foregoing requirements may eliminate the proposal from further consideration.

If the Offeror is a Limited Liability Company, include a copy of the Articles of Organization and Operating Agreement.

5.4. Representations and Certifications: Submit completed provisions in Section 00 45 00.

6.0 VOLUME 1, TAB B – FACTOR 1 – PAST PERFORMANCE

There are three aspects to the performance confidence evaluation: recency, relevancy and quality of past performance. In accordance with FAR 15.305(a)(2), the currency and relevance of the information, source of the information, context of the data, and general trends in contractor's performance shall be considered. All recent projects will be evaluated for the relevance and quality of performance will be combined to establish one performance confidence assessment rating for each Offeror.

6.1 SUBMISSION REQUIREMENTS:

Submit Experience Information for Prime Construction Contractor (Section 00 22 10, Attachment 1) for each project to be submitted under Factor 1, plus 1 additional page (3 pages max per project).

Also provide performance assessment as described in paragraph 6.5 Performance Assessment.

6.2 RECENCY OF PAST EXPERIENCE:

For a project to be recent, projects shall be completed, or currently in progress with at least 80% construction completed of the current contract value, within the past ten years as of the date the solicitation was issued.

6.3 RELEVANCY OF PAST EXPERIENCE:

These projects must be of relevant scope and complexity to the solicited project. The Offeror shall submit information on at least four (4), but no more than seven (7) completed projects demonstrating the Offeror's recent and relevant experience. At least two (2) of the relevant projects must be design-build.

A relevant construction project is further defined as a construction project with a value of $20,000,000 or more performed under a single relevant task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather offerors shall submit the work performed under a task order as a project.

For purposes of this evaluation, to be considered a relevant construction project, the project must involve one of the following types of work:

(1) New construction, repair or renovation of existing multi-story administrative facilities (headquarters, operational, and administration/office buildings, etc.)

Section 00 22 10 – 3

(2) New construction, repair or renovation of existing scientific, medical and dental facilities, data centers and industrial facilities (clinics, hospitals warehouses, hangars, aircraft shelters, maintenance buildings, etc.)

(3) New construction, repair or renovation of existing educational facilities (schools, laboratories, childcare centers, training ranges or buildings, etc.)

(4) New construction, repair or renovation of existing community support facilities (multi-story, multi-unit Bachelor Enlisted Quarters (BEQ) dormitory/condominium/apartments, hotels/timeshares, living quarters, reserve centers, dining facilities, auditoriums, recreational facilities, theaters and retail, etc.)

(5) New construction, repair or renovation of shore protection or flood mitigation facilities.

Projects must have been performed by the Offeror. Projects submitted that were not performed by the Offeror will not be evaluated. If any firm has multiple functions or divisions, limit the project examples to those performed by the division or unit submitting the offer. If projects were design-build, identify them as such.

The information that is required to be supplied is identified on the form provided entitled "EXPERIENCE INFORMATION" (Attachment 1).

6.4 EVALUATION CRITERIA

The Government will review the project descriptions submitted, subject to the established quantity limitations, to ensure the past performance requirements have been met. Past performance in the following project types may be considered additional strengths.

Construction project performed as a prime contractor.

Construction project with a construction value of $50,000,000 or more Projects which were constructed within the State of Hawaii Offerors demonstrating past performance with relevant projects in a variety of different types of work (see 6.1 (1) – (5) above).

6.4.1 PHASE 2 EVALUATION

The information provided in the Offeror’s proposal for this evaluation factor will be carried over for use in evaluating of the Offeror, if selected, during Phase 2 of the solicitation. In Phase 2 of this solicitation, Offerors will not be allowed to submit revisions to its original proposal for Factor 1 – Past Performance. Any supplemental information or revisions provided for this factor during Phase 2 will not be evaluated.

6.5 PERFORMANCE ASSESSMENT

For each of the projects submitted, provide a copy of the Contractor Performance Assessment Reporting System (CPARS) report. If CPARS does not exist please provide a Past Performance Questionnaire (PPQ) (Attachment 2) to a representative of the owner. The Past Performance Questionnaire included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1, Past Performance of Construction Contractor. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment 2), which will provide contract and client information for the respective project(s).

Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact at W9128A22R0003@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past

Section 00 22 10 – 4 performance evaluation. Offerors may use previously completed PPQs and do not need to have one completed specifically for this project but must include it as a hardcopy.

In addition to the above, the Government may review any other sources of information for evaluating past performance for any project. Other sources may include, but are not limited to, past performance information retrieved through the Federal Awardee Performance and Integrity Information System (FAPIIS), Contractor Assessment Reporting System (CPARS) or other databases using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company / subsidiary/ affiliate) identified in the Offeror' s proposal; interviews with Program Managers, Contracting Officers, and Fee Determining Officials; and the Defense Contract Management Agency. The information obtained from these sources will be evaluated supplementary to the past performance questionnaires. In reference to the contracts pulled from these sources, the relevancy of the projects, completion dates, ratings and comments in the individual categories and overall ratings will be considered in making the overall confidence assessment.

While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.

6.5.1 RATING SYSTEM

Each submitted project will be assigned one of the levels of relevancy shown in Table 1.

Table 1. Past Performance Relevancy Rating Method

Adjectival Rating Definition Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this RFP requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this RFP requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this RFP requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this RFP requires.

In reviewing each past performance effort by the Offeror, the Technical Evaluation Board (TEB) will then evaluate the overall quality of the Offeror's past performance (see FAR 15.304(c)(2)) to determine the performance confidence assessment rating. The past performance evaluation conducted in support of a current source selection does not establish, create, or change the existing record and history of the Offeror's past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the Offeror performed those past contracts.

The TEB will review all past performance information collected and determine the quality of the Offeror's performance, general trends, and usefulness of the information and incorporate these into the performance confidence assessment (see Table 2 below).

The past performance confidence assessment rating is based on the Offeror's overall record of recency, relevancy, and quality of performance. At the conclusion of the assessment, the Offeror shall be assigned one of the ratings in Table 2. In the case for which there is no information on past contract performance or where past contract performance information is not available, the Offeror will not be evaluated favorably or unfavorably on the factor of past contract performance.

In this case, the Offerors' past performance is unknown and assigned a performance confidence rating of "neutral".

Section 00 22 10 – 5

Table 2. Performance Confidence Assessment

Adjectival Rating Description Substantial Confidence

Based on the offeror's recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence

Based on the offeror's recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.

Neutral Confidence No recent/relevant performance record is available or the offeror's performance report is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.

Limited Confidence Based on the offeror's recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror's recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.

7.0 VOLUME 1, TAB C – FACTOR 2 – ORGANIZATION / MANAGEMENT TEAM

7.1 SUBMISSION REQUIREMENTS

Submit an organizational chart on a page not to exceed 11”X 17” and a narrative that clearly but concisely describes the Offeror’s organization, capability and intended technical approach to project management and execution of the contract. Limit the information to 10 single sided pages.

Documentation that exceeds 10 single sided pages will not be considered by the Government.

Include the following:

Describe your resources in personnel, construction, plant and equipment. Offerors are not required to submit individual personnel resumes or qualifications; however, Offerors will be required to use qualified personnel, who meet all qualification requirements specified in the DIV 01 specifications, on a Task Order basis.

Describe the roles and responsibilities of the offeror and the designer for design build projects Describe the type of work your firm or (joint venture) would self-perform under this contract to be compliant with the requirements of FAR 52.236-1, Performance of Work by Contractor.

Describe your firm’s capability to support completing more than one project, in geographically separate and remote areas, concurrently. Provide any examples of your firm’s performance of such projects.

7.2 EVALUATION CRITERIA: The Government will review the proposal to ensure it meets the submission requirements.

Substantial ability to self-perform work required under this contract may be considered a strength.

Evidence of your firm’s ability to perform more than two concurrent projects, in geographically separate and remote areas, concurrently may be considered a strength.

7.2.1 PHASE 2 EVALUATION

The information provided in the Offeror’s proposal for this evaluation factor will be carried over for use in evaluating of the Offeror, if selected, during Phase 2 of the solicitation. In Phase 2 of this

Section 00 22 10 – 6 solicitation, Offerors will not be allowed to submit revisions to its original proposal for Factor 2 – Organization / Management Team. Any supplement information or revisions provided for this factor during Phase 2 will not be evaluated.

7.3 RATING SYSTEM: The following ratings will be used with Factor 2.

Table 3. Organization / Management Team

Adjectival Rating Description Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.

Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

Unacceptable Proposal does not meet requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.

8.0 VOLUME 1, TAB D – FACTOR 3 – BONDING CAPACITY

8.1 SUBMISSION REQUIREMENTS

Submit a letter of commitment from your insurance company or surety, signed by an authorized agent of that firm that identifies your surety and bonding capacity. The minimum single contract/task order bonding capacity must be at least $100,000,000 single bonding and $250,000,000 aggregate.

The surety must appear on the Department of Treasury Circular 570 “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and Acceptable Reinsuring Companies.” If the Offeror submits evidence from an individual Surety, the individual surety must include documentation meeting the requirements of FAR 28.203 and contract clause 52.228-11. If the joint venture involves a construction firm and an A-E firm and the construction firm intends to provide the bond, provide a complete explanation with confirmation from the insurance company or surety. The Bonding Capacity letter has no page limitation.

8.2 EVALUATION CRITERIA: The Government will review the letter of commitment to ensure the submission requirements have been met. This submission requirement will be a Go/No Go evaluation. Submissions not satisfying the bonding capacity submission requirements will not be considered.

Offerors will not be eligible to be considered for Phase 2 if it does not receive a “GO” adjectival rating.

Page 25a of 157

(Am-0002)

SECTION 00 22 10, ATTACHMENT 1

EXPERIENCE INFORMATION for Prime Construction Contractor

PRIME CONSTRUCTION CONTRACTOR PROJECT #

Project Name:

Offeror:

Project and Location:

Owner:

Owner’s Point of Contact for Reference: Telephone:

Awarded Construction Cost: Final Construction Cost:

Explain Cost Growth, if any:

Date of Award: Original Completion Date: Revised Completion Date:

Explain Time Growth, if any:

Design-Build Design-Bid-Build Other (please explain):

General Scope of Construction and Offeror’s Role:

Page 25b of 157

(Am-0002)

Work Your Company Self-Performed:

Extent and Type of Work You Subcontracted Out:

Describe extent of relevancy of the project by checking all applicable boxes below and provide any additional narrative to support relevancy assessment (in terms of scope, magnitude and complexity as compared to the scope of the RFP). Higher relevancy will be assessed based on ability to meet multiple relevancy criteria listed below.

Construction project with a construction value of at least $50,000,000

Project constructed within the State of Hawaii

Your Performance Evaluation by Owner, if known:

CPARS PPQ Is the CPARS/PPQ attached?

$495M Unrestricted Multiple Award Task Order Contract (MATOC) for Design‐Build and Design‐Bid‐Build Construction Services for the State of Hawaii

RFI # Reference Question Government Response

8 Section 00 22 10 Phase 1 of 2 Phases Design-Build/Design-Bid-Build Selection Procedures:

(Paragraph 1.2 and 6.1) defines the Offeror as the Prime Contractor or the Joint Venture Prime Contractor. Would the Government consider the qualifications in Factor 1 (Past Performance) and Factor 2 (Organization / Management Team), of one major subcontractor that can provide an "Exclusive Teaming Agreement" signed by both parties to participate in this solicitation?

Factor 1: No.

Factor 2: Yes. All page limits remain unchanged.

9 SF 1442 Section 13. A. Please clarify your response to RFI #1: It appears from your response that you are requiring a sealed hard copy to be delivered and not an electronic submittal. Please clarify if an electronic submittal via SAFE online is acceptable in compliance with Appendix A (p. 155 of 157 of the RFP).

See revised Section 00 10 00, Notes 5 and 6, per Am-0002.

10 Section 00 22 10, Attachment 1

Amendment 1 provided an updated "Section 00 22 10, Attachment 1". RFI #2's response indicated "No" with respect to allowing proposers to modify the form. Does increasing or decreasing the size of the response boxes constitute modifications to the form, or can this be done, as necessary, when responses call for less information (ie: "Design Build") or more information ("General Scope of Construction and Offeror's Role")?

Increasing or decreasing the size of the response boxes constitute modifications to the form. See revised Section 00 22 10, Paragraph 6.1 and Attachment 1, per Am-0002.

11 Section 00 22 10, Attachment 1

If altering the size of the response blocks is admissible... Amendment 1, RFI #3 asked about allowing for more than 1 page per Experience Information Form. The government responded with an updated "Section 00 22 10, Attachment 1" but did not clarify if there is a page limitation for each project write-up. Can the government confirm if the intention is to limit Project Experience Information Forms to 2 pages?

See revised Section 00 22 10, Paragraph 6.1, per Am-0002.

12 Section 00 22 10, Attachment 1

In the updated "Section 00 22 10, Attachment 1", the block that begins with "Describe extent of relevancy", the government instructs us to "provide any additional narrative to support the relevancy assessment".

Based on the current form, there is no space to provide the narrative. Can the government specify where would the government like us to address this?

See response to RFI #10.

13 ID 9660039 Per ID 9660039 (RFI #8) submitted via ProjNet on 03/26/2022, if it is acceptable for the offeror to complete a teaming agreement with a subcontractor and use that subcontractor's experience in Factor 1-Past Performance Experience, can you please include a new Attachment 1 that reflects this change?

No. See response to RFI #8.

14 00 22 10 6.3 Relevancy of Past Experience, (3)

In Section 00 22 10, 6.3 Relevancy of Past Experience, (3), can you please add "laboratory to the list of categories included in parenthesis to ensure the category meets the requirements of past experience for this

MATOC?

See revised Section 00 22 10, Paragraph 6.3(3), per Am-0002.

15 00 22 10 6.3 Relevancy of Past Experience, (4)

In Section 00 22 10, 6.3 Relevancy of Past Experience, (4), can you please add "hotel/timeshare and prison" to the list of categories included in parenthesis to ensure both categories meet the requirements of past experience for this MATOC?

See revised Section 00 22 10, Paragraph 6.3(4), per Am-0002.

Section 00 60 00, Attachment A (Am‐0002)

Section 00 73 00, Appendix B – 1

OFFEROR QUESTIONS AND COMMENTS

Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) no later than April 6, 2022, 2:00 PM Hawaii Standard Time. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment/question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team. Offerors are requested to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

All timely questions and approved answers will be made available through ProjNet. Approved answers to all timely questions will also be posted as an amendment to the solicitation in the form of a report generated from ProjNet as soon as the comment/question entering period is over and all answers are finalized.

The Solicitation Number is: W9128A22R0003

The Bidder Inquiry Key is: P55N6S-PISQVP

Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and

Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

(Am-0002) http://www.projnet.org/

22-R-0003 Am-0002
22-R-0003 00 10 00 - Page 1
22-R-0003 00 22 10 - Pages 2-6
22-R-0003 00 22 10, Attachment 1
SECTION 00 22 10, ATTACHMENT 1
22-R-0003 00 60 00, App. A (RFIs 8-15)
22-R-0003 00 73 00, App. B - Offeror Questions and Comments
Specific Instructions for ProjNet Bid Inquiry Access:
Specific Instructions for Future ProjNet Bid Inquiry Access: