2024 DHA Industry Day_Strategic Leveling Alignment Plan (SLAP).pdf
PDF 806 KB Posted
- Attached to
- 2024 DHA O&M Industry Day – San Antonio, TX – 13-15 August Estancia del Norte San Antonio
- Solicitation number
- W9127S-24-DHA-OandM_IndustryDay
About this file
This document is a Strategic Leveling Alignment Plan (SLAP) for the Defense Health Agency's (DHA) upcoming Operations & Maintenance (O&M) contracts. The key details are:
The goals of the SLAP are to establish a predictable annual workload and sustainable contracting schedule for DHA, its military treatment facilities (MTFs), and Medical Support Teams (MSTs) over the next 5 years. The plan organizes the requirements by DHA's six areas of responsibility and aims to leverage geographic task orders where possible. The plan also seeks to incorporate non-MST MTFs into the existing MST contract vehicles. The document projects 80 new solicitations from FY23-27, with a concentrated annual workload in March. It notes a Rough Order of Magnitude of 30+ medical sites remaining outside MST support. The SLAP discusses potential updates to the GSA APEX2 contract vehicle to support "large, non A-E Requirements Packages" over $250K such as HVAC and roof resurfacing projects.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DHA Operations & Maintenance (O&M) Contracts Strategic Leveling Alignment Plan (SLAP)
Marvin Hsie & Freddie Aguilar 12 August 2024
Controlled By: DHA Facility Ops Branch CUI Category: PROPIN
DISTRO/LDC: FEDCON
POC: (210) 831-7684
CUI
Improving Health and Building Readiness. Anytime, Anywhere — Always
AGENDA
• Audience: Attendees/vendors at DHA Industry Day
• Goals of DHA Leveling Plan
• Course of Actions
• Tactical View of Leveling Plan for 300 MTFs
• Parking Lot & Questions
Goals of SLAP for DHA O&M Contracts
• Establish a predictable annual workload for DHA, MTFs and MSTs for next 5 years
• Establish a sustainable battle rhythm for New Contract Awards and Option Years during the Fiscal Year of Execution
• Organize by the DHA Six Area of Responsibilities (AOR)
• Arrange by Geographic Task Orders (GTO), when possible. Task order with multiple MTF. Example JBSA Lackland/Randolph.
• Arrange by Individual Task orders (ITO), when Site to large for GTO- Example BAMC and Bethesda.
• Assign a dedicated MST to GTOs for efficiency, familiarity and standardization?
• EX: Fort Detrick Labs, RHC Europe
Goals of Leveling Plan
• Incorporate non-MST serviced MTFs into one of the four MSTs’ MATOCs/BPAs
• Rough Order of Magnitude (ROM) is 35+ Medical Sites total in DHA left
• Common Output Levels do not align w/ Med O&M
• Poses moderate to high risk to DHA for standardization and patient risk
• No onsite MTF QA program. Therefore, Gov QA/QC process fragmented
• Purposeful Non-Use of DMLSS vs Maximo
• DMLSS Mandated by DHA CC and prior Services Surgeon Generals
Projected Five Years Workload
So lic ita tio ns
New Solicitations from FY23 - FY27
FY23 FY24 FY25 FY26 FY27
January February March April May June July August September October November December
CY24 Recompete/Solicitations and Option Years All MSTs
Recompete/Solicitations Option Year Renew
95 Contract Actions in March every year
Only 12 Contract Actions in June every year
DHA O&M: MST vs Non-MST
CUI
DHA O&M Execution By Source
MST Standardized Sites
Non- MST Sites
• Huntsville: OMEE VI ending. Transition plan to New OMEE VII MATOC soon…
• MUST offload existing sites to New MATOC in the future
• Task Orders being moved to OMEE VII within the next year of award
• Mobile: Proposed new O&M MATOCs.
• Details forthcoming in future Federal announcements
• Oahu MATOC Awarded last year
• Little Rock: One new O&M MATOC starting this year
• *Capacity to support “large, Non A-E Requirements Package” > $250K
• HVAC & Roof Resurfacing…large repair projects that does not need ENG support
Proposed Course of Actions: Updates
• GSA: Need to replace expiring BPA with Apex 2 Working details:
• Key SIN: Ancillary Repair and Alterations
• Support “large, non A-E Requirements Package” > $250K?
• HVAC “in kind” Replacements and Roof resurfacing
Proposed Course of Actions: Updates
Review: Goals of SLAP for DHA O&M Contracts
• Establish annual workload for DHA, MTFs and MSTs for next 5 years
• Establish battle rhythm for New Contract Awards and Option Years during the FY
• Organize by the DHA Six Area of Responsibilities (AOR)
• Arrange by Geographic Task Orders (GTO), when possible
• Requirement still for Small Market Awards – EX: Minot AFB
• Assign a dedicated MST to GTOs for efficiency, familiarity and standardization?
• Execute when opportunities arise: Option Year or MATOCs expiring
• Incorporate non-MST serviced MTFs into one of the four MSTs MATOCs/BPAs
• Rough Order of Magnitude (ROM) is 30+ Medical Sites total in DHA
Parking Lot and Questions?
BACKUP SLIDES
• Goal: Execute 300+ DHA MTFs O&M Contract actions on time and with funds
• Show Five Year DHA Leveling Plan Spreadsheet
• Show FY23 Workload Projections
• (Briefly) show FROID O&M Section
• Discuss Capacity Ceiling now or at Contract Standardization Brief?
Create algorithm for determining “just the right amount” of corrective maintenance
• Use BUILDER Mechanical, Electrical, and Plumbing data as key variable?
Tactical Views of Leveling Plan
January February March April May June July August September October November December
CY23 Recompetes / New Solicitations Only ALL MSTs