JISCC_RFI_Log_as_of_15_Aug_16.pdf

PDF 80 KB Posted

Attached to
JISCC Garage
Solicitation number
W9127P-16-R-0001
Issued by

About this file

RFI as of 15 August 16

View the file

Other files

File Type Posted
W9127P-16-R-0001-0001.pdf PDF
W9127P-16-R-0001-0002.pdf PDF
Pre-Bid_Conference_Slides_-_JISCC.pdf PDF
MFR_-_Prebid_conference.pdf PDF
RFI_Log_as_of_18_Aug.pdf PDF
W9127P-16-R-0001-0002.pdf PDF
Question_and_Answer_-_6.pdf PDF
JISCC_RFI_Log_as_of_16_Aug_16.pdf PDF
Question_and_Answer_-_5.pdf PDF
Question_and_Answer_-_4.pdf PDF
EXHIBITS_B_ _C.doc DOC document
Question_and_Answer_-_3.pdf PDF
PREaward_Slides_-_JISCC.ppt PPT presentation
Question_and_Answer_-2.pdf PDF
W9127P-16-R-0001-0001.pdf PDF
Question_and_Answer_1.pdf PDF
EXHIBITS_B_ _C.doc DOC document
EXHIBITS_A.doc DOC document
7526.pdf PDF
7533.pdf PDF
7538.pdf PDF
7528.pdf PDF
7527.pdf PDF
7529.pdf PDF
W9127P-16-R-0001_-_Solicitation.pdf PDF
7830.pdf PDF
7531.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VING ‐ JISCC Garage Building RFI Log ‐ as of 8/15/16 Comment Number Question Jacobs Response

1 On sheet ES‐001 show the feeder #2, from PR‐1 panel to the MDP. Panel MDP are in the electric room which is on sheet E ‐111, please indicate where is located the MDP panel on sheet ES‐001?

The MDP is located just above the label "MDP" on ES‐001. Contractor will need to extend the conduit stub outs in the electrical room to the MDP per note 1.

2 Sheet ES‐001 the feeder ends with a symbol showing a continuous pipeline to the MDP panel, but I can’t see the location of the MDP panel on the drawings.

There are no outputs of voice and data in the ET‐111, but ET‐501 shown the outlet for data and voice in the details and it seems that one of the schematic says typical are 4, please confirm.

See attached revised plan ET111 showing locations.

Please clarify concrete strength for the building components mentioned in spec 03 30 00‐11. Sheet S‐111 only specifies 5,000 psi for floors.

The compressive strength of concrete is provided in Concrete General Notes on Sheet S001.

4 Could you please provide the make and model number of the Main Fire AlarmPanel that we are tying into?

VIARNG to provide photo of Main Fire Alarm Panel including make and model number.

5 Could you pleaseprovide a picture of equipment and set up in RM A‐138 and A‐ 126 to see what equipment set up looks like and in particularthe fiber patch panel they are using?

VIARNG to provide photo of equipment in Room A‐138 and A‐126.

6 Could you please provide a picture of the existing fiber patch racks? VIARNG to provide photo of existing fiber patch racks.

7 Could you please provide a schematic or picture of the path and or the stub ups of the 4" conduit from RM A‐138 to RM A‐126?

VIARNG to provide photo of stub ups for the 4" conduit from Room A‐138 to Room A‐ 126.